A node for connecting raft foundation and pile foundation casting

By using small-diameter steel rings, Y-shaped braces and steel bar brackets in the pile foundation nodes, combined with the wire mesh and positioning device, the problems of concrete waste and uneven pile mouths in the traditional method are solved. Improve the firmness and construction efficiency of the nodes.

CN109944266BActive Publication Date: 2024-11-26BEIJING JINGHONG YUNTAI TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN201910357743.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-04-30
Publication Date
2024-11-26
Estimated Expiration
2039-04-30

AI Technical Summary

Technical Problem

In the node processing of pile foundation and raft foundation, traditional methods lead to waste of concrete materials and no overlap between the steel cage and raft foundation, resulting in insufficient firmness, especially after the pile cutting, the pile mouth is uneven and difficult to deal with.

Method used

The small diameter steel ring, bottom Y-shaped bracelet, top Y-shaped bracelet, cylindrical base, wire ropeway groove, steel bar frame and other components are used to achieve the close integration of pile foundation and raft foundation through the wire mesh and positioning device. , solves the problems of concrete leakage and uneven pile mouth.

Benefits of technology

It has achieved a one-time solution to the tie-up problem between pile foundation and raft foundation, improved the firm performance of the nodes, reduced concrete leakage, and was suitable for pile mouth treatment after pile cutting, reducing material waste.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN109944266B_ABST
    Figure CN109944266B_ABST
Patent Text Reader

Abstract

The present invention relates to a node for the casting and connection of a raft foundation and a pile foundation. The bottom of the cylindrical base is welded with bottom Y-shaped support pieces at four evenly divided positions, the cylindrical base is sleeved in the cylindrical pedestal square seat and the two are fixed, and the top Y-shaped support pieces are evenly distributed at the four corners of the top of the cylindrical pedestal square seat; small-diameter steel rings are welded on the outer edges of the four bottom Y-shaped support pieces, and large-diameter steel rings are welded on the outer edges of the four top Y-shaped support pieces; the present invention adopts a small-diameter steel ring with the bottom Y-shaped support piece as the skeleton, which is fully covered with steel wire mesh; the top of the cylindrical base is mirror-symmetrically welded with a steel support frame, and the steel support frame is tied or welded together with the cast raft foundation steel cage, which solves the problem of concrete leakage in the pile foundation pipe hole at one time, solves the connection problem between the pile foundation and the raft foundation, and solves the problem of uneven pile mouth after pile cutting.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a node for pouring and connecting a raft foundation and a pile foundation. Background Art

[0002] A deep foundation (see figure) consisting of a pile and a pile cap (referred to as a cap) connected to the top of the pile, or a single pile foundation connected by a column and a pile foundation, is referred to as a pile foundation. If the pile body is completely buried in the soil and the bottom of the cap is in contact with the soil, it is called a low cap pile foundation; if the upper part of the pile body is exposed to the ground and the bottom of the cap is above the ground, it is called a high cap pile foundation. Building pile foundations are usually low cap pile foundations. And low cap pile foundations are generally set at the bottom of the raft foundation. Since the pile height of the pile may not meet the design requirements, it is generally necessary to cut the pile when pouring the raft foundation. The top surface of the pipe pile after cutting is often uneven, so it is more troublesome to deal with the node between the pile foundation and the raft foundation. The current common practice is to directly place a steel cage and then pour concrete to seal the pile hole. However, this kind of sealing often causes a large amount of concrete to leak into the pile hole, resulting in a waste of materials, and the inserted steel cage actually has no overlap with the raft foundation, so its firmness needs to be discussed. Summary of the invention

[0003] The purpose of the invention is to provide a node for connecting a raft foundation with a pile foundation.

[0004] The present invention solves the above-mentioned technical problems by adopting the following technical solutions: a node for casting and connecting a raft foundation and a pile foundation, the main structure of which includes: a small-diameter steel ring, a large-diameter steel ring, a bottom Y-shaped support piece, a top Y-shaped support piece, a cylindrical base, a steel cableway groove, a steel support frame, a side clamping steel plate, a spring hole groove, a clamping spring seat, a cylindrical pedestal square seat, an upper strip inclined plate, a lower strip inclined plate, a support piece, a steel mesh, a steel wire, a spring seat, and a clamping pipe strip, the bottom Y-shaped support piece is welded at four evenly divided positions on the bottom of the cylindrical base, the cylindrical base is sleeved in the cylindrical pedestal square seat and the two are fixed, and the top Y-shaped support pieces are evenly distributed at the four corners of the top of the cylindrical pedestal square seat; small-diameter steel rings are welded on the outer edges of the four bottom Y-shaped support pieces, and large-diameter steel rings are welded on the outer edges of the four top Y-shaped support pieces;

[0005] The cylindrical base is hollow, and four steel cableway grooves are milled on the inner wall of the hollow pipe; a side clamping steel plate is integrally formed on one side of the outer wall of the cylindrical base, and a spring hole groove is opened in the side clamping steel plate, and a clamping spring seat is arranged in the spring hole groove;

[0006] The four steel cableway grooves are connected with the spring hole grooves, and steel wires are placed in the steel cableway grooves. The ends of the four steel wires are inserted into the spring hole grooves and bound by the clamping spring seats; the starting ends of the steel wires are fixed to the inner side of the clamping tube strip;

[0007] The upper end of the bottom Y-shaped support piece is integrally formed with a lower strip-shaped inclined plate; the lower end of the top Y-shaped support piece is integrally formed with an upper strip-shaped inclined plate; the four corners of the cylindrical support platform square seat are provided with support pieces, which penetrate the side wall of the clamping tube strip; a rectangular square groove is provided between the support piece and the lower strip-shaped inclined plate, and a spring seat is placed in the rectangular square groove;

[0008] The small diameter steel ring has a bottom Y-shaped support plate as a skeleton and is covered with wire mesh; a steel support frame is welded to the top of the cylindrical base in a mirror-symmetrical manner, and the steel support frame is tied or welded together with the cast raft foundation steel cage, and the longitudinal height of the steel support frame is in the range of 0.65-0.8 times the thickness of the raft foundation.

[0009] Furthermore, the diameter of the small diameter steel ring matches the inner diameter of the pipe pile.

[0010] Furthermore, the mesh size of the wire mesh is between 0.8 and 2.7 centimeters.

[0011] Furthermore, an anti-slip rubber strip is provided on the outer wall of the pipe clamping strip.

[0012] Furthermore, the diameter of the hollow hole in the cylindrical base is between 1.2 and 3 centimeters.

[0013] Furthermore, the upper end of the pipe clamping strip is buckled onto the upper strip-shaped inclined plate.

[0014] Furthermore, the lower end of the pipe clamping strip is buckled onto the lower strip-shaped inclined plate.

[0015] Furthermore, the horizontal expansion and contraction range of the pipe clamping strip is 2-4 cm.

[0016] Furthermore, one end of the small diameter steel ring is placed in the pipe pile of the pile foundation.

[0017] Furthermore, one end of the large diameter steel ring is cast together with the raft foundation.

[0018] The beneficial effects of the present invention are as follows: a small-diameter steel ring is used with a bottom Y-shaped support piece as a skeleton, which is covered with a steel wire mesh; a steel support frame is welded on the top of the cylindrical base in a mirror-symmetrical manner, and the steel support frame is tied or welded together with the cast raft foundation steel cage. The technical solution solves the problem of concrete leakage in the pile foundation pipe hole at one time, solves the problem of the connection between the pile foundation and the raft foundation, and solves the problem of uneven pile mouth after pile cutting. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 The present invention is a node overall structure diagram of a raft foundation and a pile foundation cast and tied.

[0020] Figure 2The present invention provides a top view of the structure of a node where a raft foundation and a pile foundation are cast and tied together.

[0021] Figure 3 This is a structural diagram of a cylindrical base of a node where a raft foundation and a pile foundation are cast and tied together according to the present invention.

[0022] Figure 4 This is a core structural diagram of a node where a raft foundation and a pile foundation are cast and tied together according to the present invention.

[0023] Figure 5 This is a core front view of a node where a raft foundation and a pile foundation are cast and tied together according to the present invention.

[0024] In the figure, 1-small diameter steel ring, 2-large diameter steel ring, 3-bottom Y-shaped support piece, 4-top Y-shaped support piece, 5-cylindrical base, 51-wire ropeway groove, 6-rebar support frame, 7-side clamping steel plate, 71-spring hole groove, 72-clamping spring seat, 8-cylindrical base square seat, 81-upper strip inclined plate, 82-lower strip inclined plate, 83-support piece, 9-wire mesh, 10-steel wire, 11-spring seat, 12-clamping pipe strip. DETAILED DESCRIPTION

[0025] The following is combined with Figure 1-5 A detailed description is given of the specific implementation modes of the present invention.

[0026] Embodiment: A node for pouring and pulling a raft foundation and a pile foundation, the main structure of which is: a small diameter steel ring 1, a large diameter steel ring 2, a bottom Y-shaped support piece 3, a top Y-shaped support piece 4, a cylindrical base 5, a steel cableway groove 51, a steel support frame 6, a side clamping steel plate 7, a spring hole groove 71, a clamping spring seat 72, a cylindrical pedestal square seat 8, an upper strip inclined plate 81, a lower strip inclined plate 82, a support piece 83, a steel mesh 9, a steel wire 10, a spring seat 11, and a clamping pipe strip 12, the bottom Y-shaped support piece 3 is welded on four evenly divided positions at the bottom of the cylindrical base 5, the cylindrical base 5 is sleeved in the cylindrical pedestal square seat 8 and the two are fixed, and the top Y-shaped support pieces 4 are evenly distributed on the four corners of the top of the cylindrical pedestal square seat 8; the small diameter steel ring 1 is welded on the outer edges of the four bottom Y-shaped support pieces 3, and the large diameter steel ring 2 is welded on the outer edges of the four top Y-shaped support pieces 4;

[0027] The cylindrical base 5 is hollow inside, and four steel cableway grooves 51 are milled on the inner wall of the hollow pipe; a side clamping steel plate 7 is integrally formed on one side of the outer wall of the cylindrical base 5, and a spring hole groove 71 is opened in the side clamping steel plate 7, and a clamping spring seat 72 is arranged in the spring hole groove 71;

[0028] The four steel cableway grooves 51 are connected with the spring hole grooves 71, and the steel cableway grooves 51 are all inserted with steel wires 10. The ends of the four steel wires 10 are all inserted into the spring hole grooves 71 and bound by the clamping spring seats 72; the starting ends of the steel wires 10 are fixed to the inner side of the clamping tube strip 12;

[0029] The bottom Y-shaped support piece 3 is integrally formed with a lower strip inclined plate 82 at the upper end; the top Y-shaped support piece 4 is integrally formed with an upper strip inclined plate 81 at the lower end; the cylindrical support platform square seat 8 is provided with support pieces 83 at the four corners, and the support pieces 83 pass through the side wall of the clamping tube strip 12; a rectangular square groove is provided between the support piece 83 and the lower strip inclined plate 82, and a spring seat 11 is inserted into the rectangular square groove;

[0030] The small diameter steel ring 1 has a bottom Y-shaped support plate 3 as a skeleton and is covered with a wire mesh 9; a steel support frame 6 is welded to the top of the cylindrical base 5 in a mirror-symmetrical manner, and the steel support frame 6 is tied or welded together with the cast raft foundation steel cage, and the longitudinal height of the steel support frame 6 is in the range of 0.65-0.8 times the thickness of the raft foundation.

[0031] Furthermore, the diameter of the small-diameter steel ring 1 matches the inner diameter of the pipe pile.

[0032] Furthermore, the mesh size of the steel wire mesh 9 is between 0.8 and 2.7 centimeters.

[0033] Furthermore, an anti-slip rubber strip is provided on the outer wall of the pipe clamping strip 12 .

[0034] Furthermore, the diameter of the hollow hole in the cylindrical base 5 is between 1.2 and 3 cm.

[0035] Furthermore, the upper end of the pipe clamping strip 12 is buckled onto the upper strip-shaped inclined plate 81 .

[0036] Furthermore, the lower end of the pipe clamping strip 12 is buckled onto the lower strip-shaped inclined plate 82 .

[0037] Furthermore, the horizontal expansion and contraction range of the pipe clamping strip 12 is 2-4 cm.

[0038] Furthermore, one end of the small diameter steel ring 1 is placed in the pipe pile of the pile foundation.

[0039] Furthermore, one end of the large diameter steel ring 2 is cast together with the raft foundation.

[0040] The overall structural description of the present invention is relatively complex, but the actual manufacturing process is not complicated. Since many accessories are integrally formed and are one-time pressed components, the manufacturing cost is relatively low.

[0041] The main purpose of the patent application in this case is to overcome the shortcomings in several aspects: First, the traditional treatment of the pile foundation and raft foundation node is generally to use a steel cage directly placed in the pile hole, and then pour concrete to fill it. This method is easy to waste concrete aggregates. The concrete in the pile hole is loose and does not meet the design requirements. The design adopts two small-diameter steel rings 1 and a large-diameter steel ring 2. The small-diameter steel ring 1 is densely covered with steel mesh 9. The steel mesh 9 can hold the poured concrete aggregates, making the concrete at the top of the pile dense.

[0042] The second is that when encountering a project with cut piles, the top of the pile hole is severely damaged, and it becomes very difficult to directly pour concrete after the traditional steel cage is placed, and the broken wall on the side cannot be handled at all, resulting in the placed steel cage being tilted or overturned. In this case, a clamping device composed of an upper strip inclined plate 81, a lower strip inclined plate 82, a support plate 83, a steel wire 10, a spring seat 11, and a clamping pipe strip 12 is used to overcome the above disadvantages. Specific clamping process: In the design, the clamping pipe strip 12 is actually a metal edge strip erected between the upper strip inclined plate 81 and the lower strip inclined plate 82, and because the clamping pipe strip 12 is tied by the steel wire 10 and cooperates with the reverse action of the upper spring seat 11, the initial state of the clamping pipe strip 12 is in an energy storage state, and the structure is initially retracted, and the end of the steel wire 10 that allows it to be in an energy storage state is locked by the clamping spring seat 72.

[0043] When the bottom end of the product of this case is placed on the top of the pile hole, its small diameter steel ring 1 and the above-mentioned clamping device are all placed therein. At this time, the construction personnel only need to use a hammer to break the spring hole groove 71, and the clamping spring seat 72 therein is automatically released, thereby releasing the steel wire 10. At this time, due to the reaction force of the spring seat 11, the four pieces of the clamping strips 12 will automatically pop open and be clamped on the inner wall of the pile hole pipe to fix the entire product of this case. The fixing direction is fixed by the clamping strips 12 supported in the pipe wall, thereby solving the problem of difficult handling of the damaged pipe mouth after cutting the pile.

[0044] The two steel bar supports 6 designed on the cylindrical base 5 provide fulcrums for tying or welding the main bars of the raft foundation. Therefore, the structural product of this case can closely combine the pile foundation with the raft foundation, thereby increasing the firmness of the node.

[0045] This design is suitable for pile foundation and raft foundation engineering. Although the cost is slightly higher than the traditional steel cage production cost, its structural parts can be cold-rolled and processed in one piece at the factory. It can be made by a few metal pressing molds and a small part of welding to get the finished product. Therefore, this case has a good promotion value and meets the needs of the market.

Claims

1. A node for connecting a raft foundation and a pile foundation, the main structure of which is: a small diameter steel ring (1), a large diameter steel ring (2), a bottom Y-shaped support piece (3), a top Y-shaped support piece (4), a cylindrical base (5), a wire ropeway groove (51), a steel bar support frame (6), a side clamping steel plate (7), a spring hole groove (71), a clamping spring seat (72), a cylindrical pedestal square seat (8), an upper strip inclined plate (81), a lower strip inclined plate (82), a support piece (83), a steel mesh (9), a steel wire (10), a spring seat (11), and a clamping pipe strip (12). Features: The bottom of the cylindrical base (5) is welded with bottom Y-shaped support pieces (3) at four evenly spaced positions. The cylindrical base (5) is sleeved in the cylindrical support platform square seat (8) and the two are fixed to each other. The top four corners of the top of the cylindrical support platform square seat (8) are evenly distributed with top Y-shaped support pieces (4); small-diameter steel rings (1) are welded on the outer edges of the four bottom Y-shaped support pieces (3), and large-diameter steel rings (2) are welded on the outer edges of the four top Y-shaped support pieces (4); The cylindrical base (5) is hollow inside, and four steel cableway grooves (51) are milled on the inner wall of the hollow pipe; a side clamping steel plate (7) is integrally formed on one side of the outer wall of the cylindrical base (5), a spring hole groove (71) is opened in the side clamping steel plate (7), and a clamping spring seat (72) is arranged in the spring hole groove (71); The four steel cableway grooves (51) are connected to the spring hole groove (71), and steel wires (10) are placed in the steel cableway grooves (51). The ends of the four steel wires (10) are inserted into the spring hole grooves (71) and are bound by the clamping spring seats (72); the starting ends of the steel wires (10) are fixed to the inner side of the clamping tube strip (12); The upper end of the bottom Y-shaped support piece (3) is integrally formed with a lower strip-shaped inclined plate (82); the lower end of the top Y-shaped support piece (4) is integrally formed with an upper strip-shaped inclined plate (81); support pieces (83) are provided at the four corners of the cylindrical support platform square seat (8), and the support pieces (83) penetrate the side wall of the tube clamping strip (12); a rectangular square groove is provided between the support piece (83) and the lower strip-shaped inclined plate (82), and a spring seat (11) is inserted into the rectangular square groove; The small diameter steel ring (1) has a bottom Y-shaped support sheet (3) as a framework and is covered with a steel mesh (9); a steel support frame (6) is welded to the top of the cylindrical base (5) in a mirror-symmetrical manner; the steel support frame (6) is tied or welded together with the cast raft foundation steel cage, and the longitudinal height of the steel support frame (6) is in the range of 0.65-0.8 times the thickness of the raft foundation; The diameter of the small diameter steel ring (1) matches the inner diameter of the pipe pile; The mesh size of the steel wire mesh (9) is between 0.8 and 2.7 cm; The outer wall of the pipe clamping strip (12) is provided with an anti-slip rubber strip; The diameter of the hollow hole in the cylindrical base (5) is between 1.2 and 3 cm.

2. A node for connecting a raft foundation and a pile foundation according to claim 1, Features The upper end of the pipe clamping strip (12) is buckled onto the upper strip-shaped inclined plate (81).

3. A node for connecting a raft foundation and a pile foundation according to claim 1, Features The lower end of the pipe clamping strip (12) is buckled onto the lower strip-shaped inclined plate (82).

4. A node for connecting a raft foundation and a pile foundation according to claim 1, Features The tube clamping strip (12) has a horizontal telescopic range of 2-4 cm.

5. A node for connecting a raft foundation and a pile foundation according to claim 1, Features One end of the small diameter steel ring (1) is placed in the pipe pile of the pile foundation.

6. A node for connecting a raft foundation and a pile foundation according to claim 1, Features One end of the large diameter steel ring (2) is cast together with the raft foundation.