The invention discloses a cavity type mixed
tower fan foundation formwork construction method. Comprising the steps of
cushion layer pouring, pay-off, cavity foundation slab
steel bar binding, annular
support system erecting, foundation lower inner formwork supporting and inner support frame body arranging,
cantilever anchoring end bottom formwork frame body supporting,
cantilever anchoring end bottom formwork installing, foundation upper inner formwork supporting and inner support arranging, anchor backing plate and prestressed
pipe installing,
steel bar binding and annular
support system erecting. And a foundation outer formwork is installed. Compared with the prior art, formwork erecting is formed at a time, a foundation is integrally poured, and the overall construction quality is guaranteed; the problem of leakage caused by two-time pouring of a construction joint part is avoided,
water stop steel plates are reduced, and materials are saved; the inner supporting frame bodies are radially arranged with the center of the circle and the center of the stand column as a supporting point, and
structural stress is reasonable. The supporting frame body is simple in structure, neat, attractive, reasonable in stress and easy to operate, the center stand column is recycled, and construction is efficient.