The invention discloses a grid following-grid construction
mode switching control method of a full-power
wind power converter, and belongs to the technical field of
wind power generation in the field of electrical
engineering. The control method comprises the steps of data sampling, calculation of control angles of two
modes, calculation of d-axis current instruction values and q-axis current instruction values of the two
modes, calculation of d-axis and q-axis modulation
voltage instruction values and
switching signal generation. According to the invention, the network following controller and the
network construction controller can be independently designed, and respective operation characteristics of a network following mode and a
network construction mode are ensured; meanwhile, the two
modes are not operated at the same time, so that the burden of the controller is reduced, and the cost is saved; according to the grid following-grid construction
mode switching control method of the full-power
wind power converter, the problems that the transient peak of direct-
current voltage is too large and the transient time is too long under high
wind speed and high power in an existing instantaneous value inheritance
mode switching scheme can be effectively solved, and the smoothness of mode switching is remarkably improved.