The invention relates to the technical field of
bridge engineering, in particular to a bottom formwork dismounting method for superaltitude cable bent
tower lower cross beam support-free method construction. Comprising the following steps that S1, an existing lower cross beam serves as a disassembling tool
supporting system, a plurality of stand columns are arranged on the top of the lower cross beam, distribution beams are erected among the stand columns in the bridge direction, and a sliding type hanging frame
system is erected on the distribution beams; s2, a
polytetrafluoroethylene sliding plate and a limiting device are arranged between a sliding beam and a distribution beam of the sliding type hanging frame
system; s3, longitudinal beams are laid on the tops of the lower cross beams, upper cross beams are transversely erected at the two ends of the longitudinal beams, and winches are arranged; s4, the bottom formwork is segmented through a sliding type hanging frame
system; and S5, after the bottom formwork is removed, the overlapped sliding type hanging frame system, the distribution beams and the stand columns are removed, and the original appearance of the top structure of the lower cross beam is recovered. The cyclic operation of positioning,
cutting and shifting of the superaltitude lower cross beam support-free method bottom formwork is achieved through the traction sliding type hanging frame system, operation is convenient and fast, and stability and safety are high.