Deepwater double-wall steel cofferdam and sinking construction method thereof

Through the combination of floating crane and water injection device, combined with air blowing, sand blowing and mud absorption technology, the problem of difficulty in positioning and sinking control of deep water double-wall steel cofferdam is solved, and the stable sinking and efficient deviation correction of cofferdam are achieved. , improves construction safety and structural stability.

CN118911173AInactive Publication Date: 2024-11-08HANGZHOU JIANGRUN TECH LIMITED

Patent Information

Application Number
CN202411409386.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-10
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Traditional deep-water double-wall steel cofferdams are difficult to position and sink and control in deep water environments, their sealing properties are difficult to ensure, and their sinking and stability are poor due to geological conditions, which can easily overturn or move due to buoyancy, which limits its application effect. and construction safety.

Method used

The block lifting and positioning is carried out using a floating crane, combining a water injection device and a level controller to ensure smooth sinking. The bottom sediment is treated with air blowing, sand blowing and mud absorption technologies, and real-time skewing and sludge monitoring and sludge monitoring are carried out through excavation, backfill and top The push method is used to correct the deviation, and finally pour concrete to fix it to improve stability.

Benefits of technology

It improves the accuracy and stability of sinking, ensures the dry environment of the construction area and the position accuracy of the cofferdam, reduces the risk of overturning or moving, and enhances construction safety and structural stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911173A_ABST
    Figure CN118911173A_ABST
Patent Text Reader

Abstract

The invention provides a deepwater double-wall steel cofferdam and a sinking construction method thereof. The sinking construction method comprises the steps of factory prefabrication and processing of double-wall steel cofferdam blocks, field hoisting and splicing, sinking and implantation of the steel cofferdam, deviation correction and deviation correction of the steel cofferdam, concrete pouring in a wall cavity, bottom sealing concrete pouring and internal cleaning of the steel cofferdam. Precise machining of steel cofferdam components can be achieved, the difficulty during assembly is reduced, the sinking efficiency and control precision of the cofferdam are improved, the method can be suitable for the complex underwater environment, and the stability and bearing capacity of the cofferdam structure under deep water can be guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of bridge and underwater structure construction, and in particular to a deep-water double-wall steel cofferdam and a sinking construction method thereof. Background Art

[0002] Deepwater double-walled steel cofferdam is an important technology used in underwater engineering construction in deepwater environments, such as bridge foundations, underwater structures or submarine pipelines. It consists of two layers of inner and outer steel plates, connected by transverse and longitudinal support structures to form an enclosed space. There are blades at the bottom to cut into the underwater sediments to improve stability and sealing. Bulkheads may be set between the inner and outer walls to divide the space into multiple compartments to improve structural rigidity and stability and facilitate construction control. Openable covers are set at the top and bottom of the cofferdam to facilitate personnel entry and exit and equipment transportation and installation.

[0003] However, there are some problems and shortcomings in the practical application of traditional double-walled steel cofferdams. First, in deepwater environments, especially when the water flow is turbulent and the geological conditions are complex, the positioning and sinking control of the cofferdam is extremely difficult, and it is easy to deviate from the predetermined position due to the influence of hydrodynamics. Second, ensuring the good sealing of the cofferdam under the deepwater pressure and changing geological conditions is a major challenge, and any water seepage may affect the dry environment of the construction area. Third, the geological conditions in deepwater areas are diverse, such as silt, sand layers, hard rock or unstable strata, which will affect the sinking and stability of the cofferdam. Finally, the cofferdam needs to overcome the buoyancy to maintain stability during the sinking process, otherwise it may overturn or move due to unstable underwater geological conditions. These problems have limited the application effect and construction safety of traditional double-walled steel cofferdams to a certain extent.

[0004] Therefore, there is an urgent need for a deepwater double-wall steel cofferdam and a blowing-water injection-sand blowing combined sinking construction method to solve the problems existing in the prior art. Summary of the invention

[0005] The embodiment of the present invention provides a deep-water double-wall steel cofferdam and a sinking construction method thereof, which addresses the problems existing in the current technology, such as difficulty in positioning and sinking control, difficulty in ensuring sealing, sinking and stability being affected by various geological conditions, and the need to overcome buoyancy to maintain stability.

[0006] In a first aspect, the present invention provides a deepwater double-wall steel cofferdam sinking construction method, the method comprising the following steps: S00. Prefabricate and process each piece of the double-walled deepwater steel cofferdam in the factory; S10, using a floating crane to lift each piece of the double-walled steel cofferdam to a designated location, using a positioning instrument to position and temporarily assemble, and after the assembly is completed, connecting a water injection device to the cavity of the double-walled steel cofferdam; S20, using a water injection device to sink, and ensuring that the steel cofferdam sinks smoothly through a horizontal controller, and in the process from when the double-walled steel cofferdam approaches the water bottom to when it contacts the water bottom, using an air blowing bed treatment method, a cofferdam sand blowing sinking method, and a cofferdam mud suction sinking method in sequence; S30, real-time monitoring of cofferdam deflection after the double-walled steel cofferdam has been sunk; The double-walled steel cofferdam was corrected by using the centralized excavation method and backfilling sand and gravel method; The double-walled steel cofferdam is corrected by underwater jacking and mud suction methods. When the deviation is greater than the threshold, the steel cofferdam is hoisted and sunk again. S40, after the steel cofferdam is fixed at the bottom of the water, the excess water in the wall cavity of the steel cofferdam is extracted through the drainage port, and then the concrete is poured; S50, after the strength of the bottom concrete reaches the standard, drain the water inside the steel cofferdam, clean the mud and stones at the bottom, and weld the cofferdam joints; Tie up the foundation reinforcement, pour the foundation concrete, and complete the construction.

[0007] Furthermore, in step S00, a three-dimensional model of the side wall of the double-walled steel cofferdam is first established, and then a finite element analysis method is used to perform a mechanical analysis on the three-dimensional model to determine the arrangement of the middle supporting channel steel and the peripheral purlin; Conduct scaled tests to verify the structural reliability and anti-leakage performance of double-walled steel cofferdams in deep water environments; After the test is completed, the side walls of the double-walled steel cofferdam are virtually assembled to eliminate interference and misalignment problems in the assembly process in advance; After the virtual assembly is completed, the blocks of the double-walled steel cofferdam side walls are manufactured and assembled using the vertical formwork method.

[0008] Furthermore, in step S00, the double-walled steel cofferdam is composed of two layers of inner and outer wall panels, the two layers of wall panels are connected by transverse and longitudinal channel steel supports, and outer purlins are set at the four corners of the inner layer.

[0009] Further, in step S20, while the water injection device is injecting water to cause the double-walled steel cofferdam to sink, fasteners on the double-walled steel cofferdam are fixed and water stop strips are attached in sequence from top to bottom; During the sinking process, the water injection speed of each water injection device is dynamically adjusted through the cooperation of the horizontal controller to ensure that the double-walled steel cofferdam will not deviate during the sinking process; When the double-walled steel cofferdam of the lower layer sinks to the set value, all water injection devices are removed, and the double-walled steel cofferdam of the lower layer is hoisted to the top of the double-walled steel cofferdam of the lower layer by the floating crane for docking and assembly; After assembly, water is injected using the water injection device of the upper double-walled steel cofferdam to sink it.

[0010] Furthermore, in step S20, the air blowing bed treatment method is: The high-pressure airflow is transported to the bottom of the double-walled steel cofferdam through a pipeline, and the impact force of the high-pressure airflow is used to loosen and clean the sediment at the bottom of the double-walled steel cofferdam.

[0011] Further, in step S20, the cofferdam sand blowing and sinking method is: The mud outlet pipe is suspended in water and an air inlet pipe is installed outside the mud outlet pipe so that the bottom of the air inlet pipe is bent and enters the bottom of the mud outlet pipe; High-pressure gas is introduced into the air inlet pipe, so that mud and sand enter from the bottom of the mud outlet pipe under the action of high pressure and are ejected from the mud outlet at the top of the mud outlet pipe.

[0012] Furthermore, in step S20, the cofferdam sludge suction sinking method is: A mud suction device is installed at the bottom of the double-walled steel cofferdam at the bottom of the water. After the double-walled steel cofferdam is leveled, mud is evenly sucked in sequence around the double-walled steel cofferdam to keep the mud surface in the center of the double-walled steel cofferdam 1 to 2 meters lower than the mud surface at the blade foot of the double-walled steel cofferdam, forming a pot bottom shape.

[0013] Furthermore, in step S20, the order of sludge suction is: The mud is first sucked out in layers at the four corners of the inner cavity of the double-walled steel cofferdam. Then, after the concrete pouring of the inner cavity of the double-walled steel cofferdam is completed and the concrete strength reaches the standard, the mud is sucked out from the middle of the inner cavity of the double-walled steel cofferdam to form a bottom foundation pit for the subsequent pouring of the bottom concrete.

[0014] Furthermore, in step S50, a pebble sealing layer is piled up outside the double-walled steel cofferdam, and bagged sand and stone are placed on the pebble sealing layer to fix the bottom of the double-walled steel cofferdam.

[0015] In a second aspect, the present invention provides a deepwater double-walled steel cofferdam, which is constructed by the above-mentioned deepwater double-walled steel cofferdam sinking construction method.

[0016] The main contributions and innovations of the present invention are as follows: 1. During the prefabrication stage in the factory, the structural reliability and anti-leakage performance of the double-walled steel cofferdam are ensured by means of establishing three-dimensional models, finite element analysis, scaled tests and virtual assembly. At the same time, interference and dislocation problems in the assembly process are eliminated in advance, thereby improving construction quality and efficiency.

[0017] 2. Use a floating crane to lift the blocks to the designated position and position them for temporary assembly, and connect the water injection device in the cavity to sink them, and cooperate with the horizontal controller to ensure smooth sinking. At the same time, during the sinking process, the air blowing bed treatment method, the cofferdam sand blowing sinking method and the cofferdam mud suction sinking method are used in turn, which effectively solves the problems of positioning and sinking control difficulties in traditional methods and improves the accuracy and stability of sinking.

[0018] 3. After the sinking is completed, the cofferdam deflection is monitored in real time, and centralized excavation, backfilling sand and gravel, underwater jacking and mud suction methods are used to correct the deflection. When the deviation is greater than the threshold, it can be lifted and sunk again, ensuring the position accuracy and stability of the cofferdam.

[0019] 4. Pour concrete after draining excess water from the wall cavity through the drain port. After the strength of the bottom concrete reaches the standard, drain the internal water, clean the mud and stones at the bottom, weld the cofferdam joints, tie the pedestal steel bars and pour the pedestal concrete, ensuring a dry environment in the construction area and improving the sealing.

[0020] 5. A pebble sealing layer is piled up on the outside of the double-walled steel cofferdam and bagged sand and stone are placed to fix the bottom, which effectively improves the stability of the cofferdam in deep water environment, overcomes buoyancy, reduces the risk of capsizing or movement, and improves construction safety.

[0021] The details of one or more embodiments of the invention are set forth in the following drawings and description so that other features, objects, and advantages of the invention are more readily apparent. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings: Figure 1 is a flow chart of a deepwater double-wall steel cofferdam sinking construction method according to an embodiment of the present invention; Figure 2 is a schematic diagram of the lower steel cofferdam structure according to an embodiment of the present invention; Figure 3 2 is a schematic diagram of splicing an upper and lower layer of steel cofferdam according to an embodiment of the present invention; Figure 4 is a partial structural schematic diagram of a sand blasting device according to an embodiment of the present invention; Figure 5 is a floating bed ship crane arrangement diagram according to an embodiment of the present invention; Figure 6 is a sludge suction operation zoning diagram according to an embodiment of the present invention; Figure 7 Schematic diagram of fixing the bottom of the cofferdam according to an embodiment of the present invention.

[0023] In the figure, 1. side wall of steel cofferdam; 2. temporary connection parts; 3. water injection device; 4. middle supporting channel steel; 5. outer purlin; 6. level controller; 7. cofferdam lifting lug; 8. water stop; 9. bolt; 10. drain outlet; 11. blade foot; 12. mud and sand outlet direction; 13. mud outlet pipe; 14. sand blowing pipe lifting lug; 15. air inlet of air compressor; 16. air inlet pipe; 17. air inlet direction; 18. mud outlet; 19. sand blowing equipment; 20. floating crane; 21. bottom sealing concrete; 22. sand and gravel layer; 23. pebble sealing layer; 24. bagged sand, soil and stone; 25. air compressor. DETAILED DESCRIPTION

[0024] Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, the same numbers in different drawings represent the same or similar elements unless otherwise indicated. The implementations described in the following exemplary embodiments do not represent all implementations consistent with one or more embodiments of this specification. Instead, they are merely examples of devices and methods consistent with some aspects of one or more embodiments of this specification as detailed in the appended claims.

[0025] It should be noted that: in other embodiments, the steps of the corresponding method are not necessarily performed in the order shown and described in this specification. In some other embodiments, the steps included in the method may be more or less than those described in this specification. In addition, a single step described in this specification may be decomposed into multiple steps for description in other embodiments; and multiple steps described in this specification may be combined into a single step for description in other embodiments.

[0026] Embodiment 1 The present invention aims to propose a deepwater double-wall steel cofferdam sinking construction method, specifically, referring to Figure 1-7 , the method comprising: Step 1: Prefabricate the components of the double-walled deepwater steel cofferdam in the factory: Digital block division and simulated assembly technology are used in the processing of steel cofferdam blocks. CAD (computer-aided design) software is used to establish a three-dimensional model of the side wall 1 of the double-walled steel cofferdam, accurately simulating the geometric shape, size and structural details of the cofferdam. Finite element analysis (FEA) and other software are used to conduct mechanical analysis of the model, evaluate the stress, strain and stability of the cofferdam under different working conditions, ensure that the design meets the requirements of safety and durability, and finally determine the arrangement of the central support channel steel 4 and the outer purlin 5. A scaled test is also carried out to test the structural reliability and anti-leakage of the double-walled steel cofferdam in deep water environment. Using BIM (Building Information Modeling) technology and special simulation software, virtual assembly is carried out to discover and solve problems such as interference and dislocation that may occur during the assembly process in advance. In the actual manufacturing process, the vertical formwork method is used for block production. Simulating the vertical state of the cofferdam at the foundation position, a formwork-forming mold frame is set up so that the blocks can be directly hoisted to the cofferdam for assembly without turning over, which improves efficiency and reduces the risk of deformation. According to the digital design, CNC machine tools are used for precise cutting and processing, and each piece is marked with a unique code to facilitate rapid on-site positioning and assembly, as well as quality traceability. The middle support channel steel 4 is welded to the inner cavity of the cofferdam to form the cofferdam as a whole.

[0027] The double-walled steel cofferdam is subjected to huge water pressure load in the underwater environment. In order to ensure the structural stability of the cofferdam, the composite support technology of the ring peripheral purlin channel steel is adopted. The cofferdam structure consists of two layers of inner and outer wall panels, which must be connected in the middle by horizontal and longitudinal support structures to resist water pressure and ensure the integrity of the structure. The specific support structure is to set a middle channel steel support 4 between the inner and outer wall panels, and set peripheral purlins 5 at the four corners.

[0028] Step 2: Hoist and assemble the steel cofferdam components on site: According to the design layout, the floating crane 20 is used to lift the eight steel cofferdam side walls 1 to the designed position by hanging the cofferdam lifting ears 7. High-precision instruments such as laser centering instruments and optical theodolites are used to assist on-site workers in accurately positioning the blocks. Ensure that the bolt holes are accurately aligned and use temporary connectors 2 to preliminarily fix the blocks. After the steel cofferdam is temporarily fixed as a whole, the water injection device 3 is connected to the steel cofferdam cavity.

[0029] Step 3: Steel cofferdam sinks to the bed: Use the water injection device 3 to inject water into the cofferdam wall cavity, so that the steel cofferdam sinks steadily. During the sinking process, tighten the bolts 9 between the blocks from bottom to top, and stick the water stop 8.

[0030] Among them, in order to ensure the stability and anti-seepage and anti-impact capabilities of the steel cofferdam structure in a complex deep water environment, the waterstop 8 is made of high-performance sealing materials.

[0031] During the sinking process, the water injection speed of each water injection device is adjusted, combined with the horizontal controller 6, to ensure that the steel cofferdam will not deviate during the sinking process. When the lower steel cofferdam sinks 80% underwater, the water injection device 3 is removed. The upper steel cofferdam is transferred to the site by the floating crane 20, and the upper and lower steel cofferdams are docked and assembled. When splicing the upper and lower steel cofferdams, the side walls on the four corners are spliced ​​first, and then the four faces are spliced ​​to ensure that the cofferdam as a whole will not deviate under the condition of eight floating cranes 20. After assembly, the water injection device 3 is used to continue to sink the cofferdam until it is implanted. During the entire sinking process of the steel cofferdam, a conductivity sensor is installed at the underwater joint to monitor the conductivity change of the water. If water seepage occurs at the joint, the newly entered water may have different conductivity, thereby causing changes in the monitoring value. So that when water seepage occurs in the cofferdam, it can be repaired in time.

[0032] Air blowing landing treatment technology: When the steel cofferdam descends to a certain position and the blade foot 11 is about to contact the bottom of the water, it is necessary to reduce the friction between the steel cofferdam and the riverbed or seabed surface so that the cofferdam can sink more smoothly and evenly according to the design requirements until a stable landing state is reached. Therefore, air blowing landing treatment technology is adopted. The high-pressure airflow generated by the air compressor is transported to the bottom of the cofferdam through a pipeline, and the impact force of the airflow is used to loosen and remove the sediments under the blade foot of the cofferdam, such as silt, sand and gravel. The removal of sediments reduces the contact area and friction between the cofferdam and the riverbed or seabed, making it easier for the cofferdam to sink under its own weight. By precisely controlling the direction and intensity of the airflow, it is possible to fine-tune the sinking speed and position of the cofferdam to prevent the cofferdam from shifting or tilting due to external conditions (such as water flow).

[0033] In this embodiment, the divers carefully measure the river channel in the water beforehand, then turn on the air compressor and adjust the output pressure to a level suitable for blowing the sediments to reduce the difference in water surface height. The high-pressure airflow is released through the nozzle at the bottom of the cofferdam to impact and loosen the sediments, making them easy to be carried away or removed by the water flow.

[0034] Cofferdam sand blowing and sinking technology: When the steel cofferdam is placed at the bottom of the water or close to the bottom of the water, there is a large friction between the bottom of the cofferdam and the riverbed or seabed due to the presence of a large amount of sediment (such as sand, mud, gravel, etc.) at the bottom of the water, which hinders the sinking of the cofferdam. For this reason, the cofferdam sand blowing and sinking technology is used as an auxiliary. The basic principle of the cofferdam sand blowing and sinking technology is to use fluid dynamics to remove the sediment (such as sand, mud, gravel, etc.) at the bottom of the cofferdam through high-pressure gas or liquid, reduce the friction between the contact surface of the cofferdam and the riverbed, and enable the cofferdam to sink smoothly under the action of its own gravity.

[0035] In this embodiment, the diver sinks to the bottom of the water and presses Figure 5As shown, a sand blowing device 19 is installed at the bottom of the steel cofferdam, and it is ensured that the sand blowing device is connected to the air compressor on the water surface through a pipeline without air leakage. The mud outlet pipe 13 is hoisted into the water through the sand blowing pipe hanging ear 14, and two galvanized air inlet pipes 16 are inserted outside the mud outlet pipe 13. The air compressor air inlet 15 on the floating crane 20 sends high-pressure air to the bottom of the mud outlet pipe 13 and 2-3m away from the bottom of the pipe along the air inlet direction 17, and mixes with the mud in the mud outlet pipe 13. After inflation, a low-pressure area is generated in the mud outlet pipe 13. The pressure difference between the inside and outside of the mud outlet pipe 13 is continuously increased by continuous inflation. When a certain pressure difference is reached, the balance is broken, and the mud and sand are forced to return from the mud outlet pipe 13 under the action of high pressure and spray out from the mud outlet 18 along the mud and sand outlet direction 12.

[0036] Cofferdam sludge suction sinking technology: When a steel cofferdam is placed underwater, its bottom will contact the overburden. When the cofferdam needs to pass through the overburden (such as loose sediments such as silt and sand) and sink to the hard soil or rock base, it will generate greater friction resistance, which will prevent or slow down the sinking of the cofferdam. Therefore, the cofferdam sludge suction sinking technology is used as an auxiliary. The cofferdam sludge suction sinking technology is based on the principles of fluid mechanics and soil mechanics. By removing sediments (such as silt, sand, etc.) at the bottom of the cofferdam, the friction resistance between the cofferdam and the riverbed or seabed is reduced, so that the cofferdam can sink smoothly to the designed depth under its own gravity.

[0037] In this embodiment, a diver or underwater robot installs a mud suction device at the bottom of the underwater cofferdam. When the cofferdam is leveled (the inclination rate is not greater than 1%), the twelve mud suction machines around the cofferdam and the three mud suction machines in the middle start to suck mud in the designed order, and the mud is sucked evenly to keep the mud surface at the center of the cofferdam 1-2m lower than the mud surface at the blade foot, forming a pot bottom shape, but the mud surface at the blade tip must be higher than the blade tip to prevent sand from turning over. During the mud suction process, the soil conditions around the blade foot 11 of the cofferdam should be checked regularly. If hard obstacles (such as boulders or rock formations) are encountered, local underwater loosening blasting or other treatment measures may be required.

[0038] Preferably, the mud suction sequence is: zone ①-zone ②-zone ③-zone ④-zone ⑤. When the mud is sucked and sinks, the mud is sucked in layers around the cofferdam in zones ①, ②, ③, and ④. When the concrete pouring of the cofferdam cavity is completed and the steel cofferdam is fixed and stable with the strength reaching the standard, the mud suction operation of zone ⑤ is carried out to form a bottom sealing foundation pit, and then the bottom sealing concrete 21 is poured.

[0039] Step 4: Correction of steel cofferdam deviation and inclination: After the steel cofferdam is sunk, intelligent monitoring methods are used to determine whether the cofferdam is deviated from the designed position.

[0040] In this embodiment, inclinometers and gyroscopes are used to monitor the tilt angle and rotation of the cofferdam to ensure that its verticality and direction meet the design requirements; underwater cameras and closed-circuit television systems are used to provide intuitive visual monitoring, capture the posture of the steel cofferdam and dynamically correct it to determine whether the falling position is accurate. According to the monitoring results, the centralized excavation method and backfilling sand and gravel method are used to correct the double-walled steel cofferdam.

[0041] Among them, the concentrated excavation method is to concentrate the excavation on the higher side of the cofferdam to reduce the soil pressure on that side, prompting the cofferdam to move to the lower side, thereby correcting the deviation.

[0042] Among them, the backfilling sand and gravel method is to backfill sand and gravel on the lower side of the cofferdam to increase the soil pressure on that side, so that the center of gravity of the cofferdam is biased to that side, helping the cofferdam to return to the correct position. The underwater jacking method and mud suction method are used to correct the inclination of the double-walled steel cofferdam.

[0043] Among them, the underwater jacking method is to evenly distribute the hydraulic cylinders around the cofferdam to facilitate the balanced adjustment of the position of the cofferdam. A connecting device is installed at the bottom of the cofferdam to connect the hydraulic cylinders, and the position and posture of the cofferdam are adjusted by the extension and contraction of the hydraulic cylinders.

[0044] Among them, the mud suction method is to suck mud on the inclined side of the cofferdam to reduce the soil pressure on that side, causing the cofferdam to tilt in the opposite direction, thereby gradually restoring the vertical state. If the position deviation exceeds the specifications and design requirements, the heavy water in the compartment must be pumped out to float the cofferdam, reposition the cofferdam, and fill it with water again to sink it until it meets the specifications and design requirements.

[0045] Step 5: Concrete pouring: After the double-walled steel cofferdam is lowered and placed in the bed, it is placed stably on the riverbed or seabed according to the designed position. A pump is used to pump out excess water from the drain port 10. After the pumping is completed, the drain port 10 is blocked and concrete is poured into the cavity between the double walls. During this process, a jack is arranged on the top of the double-walled steel cofferdam to prevent the steel cofferdam from floating up due to pumping. After the concrete strength in the cavity meets the standard, the conduit method is used to pour the bottom concrete 21 underwater in the double-walled steel cofferdam. After the concrete strength meets the standard, the double-walled steel cofferdam and the bottom concrete 21 have completely isolated the middle area.

[0046] Step 6: Capping construction: After the strength of the bottom concrete reaches the standard, the remaining water in the steel cofferdam is extracted, and the mud and gravel at the bottom are cleaned to expose the sand and gravel layer 22. The construction personnel weld the joints on the inside of the steel cofferdam, and use ultrasonic testing to ensure the quality of the welding to prevent water seepage in the joints caused by the high water pressure in the external environment. A pebble sealing layer 23 is piled up on the outside of the cofferdam, and bagged sand and stone 24 are placed on the pebble sealing layer 23 to fix the bottom of the cofferdam. Finally, the foundation steel bars are tied, and the foundation concrete is poured at one time, and the construction is finally completed. The foundation can be put into subsequent use. During the subsequent use, the steel cofferdam structure is regularly inspected for quality.

[0047] Embodiment 2 On the basis of the first embodiment, for step 4, in the process of steel cofferdam deviation correction and inclination correction, the operation method of using underwater camera and closed-circuit television system is as follows: 1. Equipment installation and debugging 1.1 Underwater camera installation: Underwater cameras are installed at key locations around the steel cofferdam by professional divers or using underwater robots to ensure that the camera's field of view can cover the main parts of the steel cofferdam, especially those that are prone to deflection.

[0048] During the installation process, the stability of the camera must be ensured to prevent factors such as water flow from causing the camera to shake and affect the image quality.

[0049] The camera is waterproofed to ensure that it can work normally in underwater environments.

[0050] 1.2 CCTV system connection: Connect the underwater camera to the CCTV system to ensure stable transmission of image signals.

[0051] The closed-circuit television system was debugged and parameters such as image clarity, contrast and color were adjusted so that the posture of the steel cofferdam could be clearly observed.

[0052] 2. Posture capture and monitoring 2.1 Real-time monitoring: Underwater cameras continuously capture images of the steel cofferdam and transmit the images to the CCTV system.

[0053] The operators use the closed-circuit television system to observe the posture of the steel cofferdam in real time, including its tilt angle, rotation, and relative position to the surrounding environment.

[0054] 2.2 Data Analysis: Image analysis software is used to analyze the images taken by the camera to extract key feature points of the steel cofferdam, such as the edges and corners of the steel cofferdam.

[0055] By tracking and analyzing the position changes of feature points, the inclination angle, rotation angle, displacement and other parameters of the steel cofferdam are calculated, so as to accurately determine the posture of the steel cofferdam.

[0056] 3. Dynamic deviation correction 3.1 Determine the accuracy of falling position: Based on the images captured by the camera and the steel cofferdam posture parameters obtained by analysis, it is determined whether the falling position of the steel cofferdam is accurate.

[0057] Compare the designed position and the actual position and calculate the deviation between the two. If the deviation is within the allowable range, the drop position is considered accurate; if the deviation exceeds the allowable range, correction is required.

[0058] 3.2 Corrective measures: If the steel cofferdam is found to be deflected, appropriate corrective measures shall be taken according to the degree and direction of the deflection.

[0059] For smaller deflections, fine-tuning can be done by adjusting the injection speed of the water injection device, adjusting the ballast distribution in the steel cofferdam, etc.

[0060] For larger deviations, centralized excavation, backfilling with sand and gravel, underwater jacking and mud suction can be used for correction. During the correction process, continuous monitoring is carried out through underwater cameras and closed-circuit television systems to ensure that the correction effect meets the requirements.

[0061] Embodiment 3 Based on the same concept, the present invention also proposes a deep-water double-walled steel cofferdam, which is constructed by the deep-water double-walled steel cofferdam sinking construction method of Example 1.

[0062] Among them, Figure 2 As shown, the double-walled steel cofferdam is prefabricated and assembled. Each layer is composed of eight steel cofferdam side walls 1. Each steel cofferdam side wall 1 is fixed and connected by bolts 9, and a water stop strip 8 is pasted at the joint. Before the connection, a temporary connector 2 is used to fix it. There is a blade-shaped cofferdam blade foot 11 at the bottom of the lower steel cofferdam, which is used to penetrate into the underwater riverbed or seabed when the lower layer is implanted, so that the steel cofferdam is fixed as a whole. A horizontal controller 6 is placed on the four sides of the lower steel cofferdam to monitor the level of the cofferdam at all times during the lower process of the steel cofferdam, so as to make timely adjustments. A drainage outlet 10 is opened at the lower part of the steel cofferdam side wall, and water is pumped out after sinking. A middle support channel steel 4 is set between the inner and outer wall plates of the cofferdam, and an outer purlin 5 is set at the four corners. The cofferdam outer wall is welded with a cofferdam lifting lug 7 for hoisting when the steel cofferdam sinks. A water injection device 3 is connected to the cavity of each steel cofferdam side wall 1, and water is injected when the steel cofferdam sinks.

[0063] like Figure 3As shown in the figure, when the lower steel cofferdam is 80% sunk into the water, the upper steel cofferdam is hoisted. The upper steel cofferdam and the lower steel cofferdam are connected with the water stop belt through bolts.

[0064] like Figure 4 As shown, when the cofferdam is sunk and landed, an air compressor and a sand blowing device 19 are used for sand blowing. The principle is to insert two galvanized air inlet pipes 16 outside the mud outlet pipe 13, and the air compressor inlet 15 is connected to the air compressor on the shore. High-pressure air is sent to the bottom of the mud outlet pipe 13 and 2-3m away from the bottom of the pipe along the air inlet direction 17, and mixed with the mud in the mud outlet pipe 13. After inflation, a low-pressure area is generated in the mud outlet pipe 13. The pressure difference inside and outside the mud outlet pipe increases continuously due to continuous inflation. When a certain pressure difference is reached, the balance is broken, and the mud and sand are forced to be ejected back from the mud outlet 18 on the mud outlet pipe 13 along the mud outlet direction 12 under the action of high pressure. Two sand blowing pipe hanging ears 14 are set above the mud outlet pipe 13 to hang the sand blowing equipment 19 into the bottom of the water.

[0065] like Figure 5 As shown, at the construction site, there are eight floating cranes 20 for sinking the double-walled steel cofferdam, and the floating cranes 20 are arranged on the four sides and four corners of the cofferdam. Six sand blowing devices 19 are installed on the inner wall of the steel cofferdam, and sand blowing and sinking are carried out at the sand blowing points. Air compressors (air compressors 25) are installed on four floating boats and connected to the sand blowing devices 19.

[0066] like Figure 6 The figure shows the zoning of the mud suction operation when the double-walled steel cofferdam is sinking by mud suction. Before starting mud suction, divers or underwater robots install mud suction devices at the bottom of the underwater cofferdam. Areas ①, ②, ③, and ④ are close to the side walls of the steel cofferdam, and three mud suction machines are arranged in each area. Three mud suction machines are hoisted into the bottom of the water by a floating crane in area ⑤. According to the design requirements, the mud suction sequence is: area ①-area ②-area ③-area ④-area ⑤. When the mud is sucked and sinking, the mud is sucked in layers around the cofferdam in areas ①, ②, ③, and ④. After the concrete pouring of the cofferdam cavity is completed and the strength of the steel cofferdam is fixed and stable, the mud suction operation in area ⑤ is carried out to form a bottom foundation pit, and then the bottom concrete is poured.

[0067] like Figure 7 As shown, the blade foot 11 of the steel cofferdam is inserted into the underwater gravel layer 22, a bottom sealing concrete layer 21 is poured inside the steel cofferdam, a pebble sealing layer 23 is piled up outside the cofferdam, and bagged sand and stone 24 is placed on the pebble sealing layer 23 to fix the bottom of the cofferdam.

[0068] Those skilled in the art should understand that the technical features of the above embodiments may be arbitrarily combined. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0069] The above embodiments only express several implementation methods of the present invention, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present invention. It should be pointed out that, for those of ordinary skill in the art, several modifications and improvements can be made without departing from the concept of the present invention, and these all belong to the protection scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the attached claims.

Claims

1. A deepwater double-wall steel cofferdam sinking construction method, characterized in that: The following steps are involved: S00. Prefabricate and process each piece of the double-walled deepwater steel cofferdam in the factory; S10, using a floating crane to lift each piece of the double-walled steel cofferdam to a designated location, using a positioning instrument to position and temporarily assemble, and after the assembly is completed, connecting a water injection device to the cavity of the double-walled steel cofferdam; S20, using a water injection device to sink, and ensuring that the steel cofferdam sinks smoothly through a horizontal controller, and in the process from when the double-walled steel cofferdam approaches the water bottom to when it contacts the water bottom, using an air blowing bed treatment method, a cofferdam sand blowing sinking method, and a cofferdam mud suction sinking method in sequence; S30, real-time monitoring of cofferdam deflection after the double-walled steel cofferdam has been sunk; The double-walled steel cofferdam was corrected by using the centralized excavation method and backfilling sand and gravel method; The double-walled steel cofferdam is corrected by underwater jacking and mud suction methods. When the deviation is greater than the threshold, the steel cofferdam is hoisted and sunk again. S40, after the steel cofferdam is fixed at the bottom of the water, the excess water in the wall cavity of the steel cofferdam is extracted through the drainage port, and then the concrete is poured; S50, after the strength of the bottom concrete reaches the standard, drain the water inside the steel cofferdam, clean the mud and stones at the bottom, and weld the cofferdam joints; Tie up the foundation reinforcement, pour the foundation concrete, and complete the construction.

2. The deepwater double-walled steel cofferdam sinking construction method according to claim 1, characterized in that: In step S00, a three-dimensional model of the double-wall steel cofferdam side wall is first established, and then a finite element analysis method is used to perform mechanical analysis on the three-dimensional model to determine the arrangement of the middle supporting channel steel and the outer purlin; Conduct scaled tests to verify the structural reliability and anti-leakage performance of double-walled steel cofferdams in deep water environments; After the test is completed, the side walls of the double-walled steel cofferdam are virtually assembled to eliminate interference and misalignment problems in the assembly process in advance; After the virtual assembly is completed, the vertical formwork method is used to manufacture and assemble the blocks of the double-walled steel cofferdam side walls.

3. The deepwater double-walled steel cofferdam sinking construction method according to claim 2, characterized in that: In step S00, the double-walled steel cofferdam is composed of two layers of inner and outer wall panels, the two layers of wall panels are connected by transverse and longitudinal channel steel supports, and outer purlins are set at the four corners of the inner layer.

4. The deepwater double-walled steel cofferdam sinking construction method according to claim 1, characterized in that: In step S20, while the water injection device is injecting water to cause the double-walled steel cofferdam to sink, fasteners on the double-walled steel cofferdam are fixed and waterstop strips are attached from top to bottom; During the sinking process, the water injection speed of each water injection device is dynamically adjusted through the cooperation of the horizontal controller to ensure that the double-walled steel cofferdam will not deviate during the sinking process; When the double-walled steel cofferdam of the lower layer sinks to the set value, all water injection devices are removed, and the double-walled steel cofferdam of the lower layer is hoisted to the top of the double-walled steel cofferdam of the lower layer by the floating crane for docking and assembly; After assembly, water is injected using the water injection device of the upper double-walled steel cofferdam to sink it.

5. The deepwater double-walled steel cofferdam sinking construction method according to claim 1, characterized in that: In step S20, the air blowing implantation treatment method is: The high-pressure airflow is transported to the bottom of the double-walled steel cofferdam through a pipeline, and the impact force of the high-pressure airflow is used to loosen and clean the sediment at the bottom of the double-walled steel cofferdam.

6. The deepwater double-walled steel cofferdam sinking construction method according to claim 1, characterized in that: In step S20, the cofferdam sand blowing and sinking method is: The mud outlet pipe is suspended in water and an air inlet pipe is installed outside the mud outlet pipe so that the bottom of the air inlet pipe is bent and enters the bottom of the mud outlet pipe; High-pressure gas is introduced into the air inlet pipe, so that mud and sand enter from the bottom of the mud outlet pipe under the action of high pressure and are ejected from the mud outlet at the top of the mud outlet pipe.

7. The deepwater double-walled steel cofferdam sinking construction method according to claim 1, characterized in that: In step S20, the cofferdam sludge suction sinking method is: A mud suction device is installed at the bottom of the double-walled steel cofferdam at the bottom of the water. After the double-walled steel cofferdam is leveled, mud is evenly sucked in sequence around the double-walled steel cofferdam to keep the mud surface in the center of the double-walled steel cofferdam 1 to 2 meters lower than the mud surface at the blade foot of the double-walled steel cofferdam, forming a pot bottom shape.

8. The deepwater double-walled steel cofferdam sinking construction method according to claim 7, characterized in that: In step S20, the order of sludge suction is: The mud is first sucked out in layers at the four corners of the inner cavity of the double-walled steel cofferdam. Then, after the concrete pouring of the inner cavity of the double-walled steel cofferdam is completed and the concrete strength reaches the standard, the mud is sucked out from the middle of the inner cavity of the double-walled steel cofferdam to form a bottom foundation pit for the subsequent pouring of the bottom concrete.

9. The deepwater double-walled steel cofferdam sinking construction method according to any one of claims 1 to 8, characterized in that: In step S50, a pebble sealing layer is piled up outside the double-walled steel cofferdam, and bagged sand and soil are placed on the pebble sealing layer to fix the bottom of the double-walled steel cofferdam.

10. A deepwater double-walled steel cofferdam, characterized in that: It is obtained by the deepwater double-walled steel cofferdam sinking construction method described in any one of claims 1-9.

Citation Information

Patent Citations

  • Double-wall steel cofferdam construction method

    CN111155540A

  • Construction method of large-scale bridge foundation deepwater foundation pit cofferdam

    CN111206606A

  • Double-wall steel hanging box cofferdam structure and construction method thereof

    CN117344766A

  • Cofferdam construction simulation test method and cofferdam construction simulation test device

    CN118410542A

  • Double-wall cofferdam and pier construction method

    WO2020114523A1

Cited By

  • A displacement monitoring system for deepwater bottomless double-walled steel cofferdam construction

    CN119245576B

  • Deepwater bare rock geology bottom-sealing-free double-wall steel cofferdam sinking construction control method

    CN119323196A

  • A method for controlling the sinking construction of double-walled steel cofferdam without bottom in deep-water bare rock geology

    CN119323196B

  • Combined sinking deepwater double-wall steel cofferdam and construction method thereof

    CN119571845A

  • Combined immersed deep-water double-wall steel cofferdam and its construction method

    CN119571845B