A system and method for increasing the efficiency of tailings pond occupancy before closure
By building sub-dikes in the warehouse in the tailings pond to separate the mine and drainage areas, the problem of the need to build a new warehouse after the tailings pond is closed is solved, the capacity utilization rate is improved, and land acquisition and construction problems are avoided, and the warehouse closing project is provided. Favorable terrain conditions.
Patent Information
- Application Number
- CN202010339633.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-04-26
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-04-26
AI Technical Summary
After the existing tailings pond is closed, new tailings ponds need to be built to store subsequent tailings, resulting in land acquisition, construction and construction period problems, and insufficient storage capacity utilization.
Dry beach surface is formed in the tailings pond, and a sub-dike in the warehouse is built to separate the ore-release area and drainage area. The empty storage capacity above the dry beach surface is used to achieve potential expansion of the tailings pond and avoid the necessity of building a new tailings pond.
The capacity utilization rate of tailings ponds has been improved, land acquisition and construction problems of new tailings ponds have been avoided, favorable terrain conditions have been created, and smooth drainage and soil and water conservation have been provided for closed warehouse projects.
Smart Images

Figure CN111472365B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of tailings ponds, and in particular to a system and method for increasing the efficiency of a tailings pond before closure. Background Art
[0002] A tailings pond refers to a place constructed by building a dam to block the valley mouth or enclosing land, used to store tailings or other industrial waste discharged after ore sorting in metal or non-metal mines.
[0003] There are tens of thousands of tailings ponds in my country, and many of them have already reached the middle and late stages of their service life. According to relevant national laws, regulations and specifications, closure projects are required. Conventional tailings pond closure projects are covered with soil and greened according to the existing terrain conditions of the tailings pond, and usually spillways and other flood discharge systems are set up for flood discharge.
[0004] In order to maintain their development, mining enterprises need to build new tailings ponds to store the tailings generated by subsequent production after the existing tailings ponds are closed. However, some mines have a small amount of ore surplus in the later stage, and the corresponding amount of tailings generated is not large. If a new tailings pond is built to store tailings, it is necessary to go through land acquisition and necessary new construction procedures, which usually takes 2-3 years and requires a large investment. Summary of the invention
[0005] The embodiments of the present application provide a system and method for increasing the occupancy rate of a tailings pond before closure, thereby solving the technical problem in the prior art that the storage capacity of the tailings pond is not fully utilized, i.e., a new tailings pond needs to be built for closure. This realizes the potential expansion of the tailings pond that serves the later stage, and can meet the storage of tailings in the later stage. For mines in the later stage with small ore surplus, it can avoid the problems of land acquisition, construction, and construction period caused by the construction of a new tailings pond, and at the same time, it can also create favorable terrain conditions for the closure project.
[0006] An embodiment of the present application provides a system for increasing the efficiency of a tailings pond when it is occupied before closing the pond, the system comprising: a tailings pond having a dry beach surface formed therein; an intra-pond sub-dike constructed on the dry beach surface so that a mining area is formed in the space between the intra-pond sub-dike and the tailings dam of the tailings pond, and a drainage area is formed in the space between the intra-pond sub-dike and the tail of the tailings pond, the mining area is used to store tailings, and the drainage area is used to store water.
[0007] In some embodiments, the ore drawing area is in communication with the drainage area.
[0008] In some embodiments, a tailings drainage water channel is provided on the sub-dike within the reservoir; the ore discharge area is connected to the drainage area through the tailings drainage water channel.
[0009] In some embodiments, the tailings water discharge channel is formed between at least one end of the intra-reservoir sub-dike and the inner side of the tailings pond.
[0010] In some embodiments, the width of the tailings water channel is 1m-3m.
[0011] In some embodiments, the sub-dike in the reservoir is constructed by at least one of membrane bag stacking, earth dam stacking, and dry tailings stacking.
[0012] In some embodiments, the drainage area is connected to the internal flood discharge system of the tailings pond.
[0013] In some embodiments, a closed reservoir and flood discharge system is constructed on the tailings pond.
[0014] In some embodiments, the ore is drawn in the ore drawing area by at least one of wet alluvial drawing and dry tailings drawing.
[0015] In some embodiments, the intra-reservoir sub-dike is arranged close to the tail of the tailings pond so that the ore discharge area is larger than the drainage area.
[0016] The embodiment of the present application also provides a method for increasing the efficiency of a tailings pond before closure, which is applicable to any of the above-mentioned systems for increasing the efficiency of a tailings pond before closure. The method for increasing the efficiency of a tailings pond before closure includes:
[0017] An internal sub-dike is constructed on the dry beach surface formed in the tailings pond, so that a mining area is formed in the space between the internal sub-dike and the tailings dam of the tailings pond, and a drainage area is formed in the space between the internal sub-dike and the tail of the tailings pond. The mining area is used to store tailings, and the drainage area is used to store water.
[0018] In some embodiments, the method for increasing the efficiency of the tailings pond before closure further comprises the steps of:
[0019] The ore drawing area is connected to the drainage area.
[0020] In some embodiments, the connecting the ore drawing area with the drainage area specifically includes:
[0021] A tailings drainage water channel is arranged on the sub-dike in the reservoir, so that the ore discharge area is connected with the drainage area through the tailings drainage water channel.
[0022] In some embodiments, when an internal sub-dike is constructed on the dry beach surface formed in the tailings pond, a tailings drainage channel is formed between at least one end of the internal sub-dike and the inner side of the tailings pond, so that the mining area is connected to the drainage area through the tailings drainage channel.
[0023] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages:
[0024] 1. A system and method for increasing the occupancy rate of a tailings pond before closure is provided in an embodiment of the present application. For a tailings pond that serves to the middle and late stages, an internal dike is constructed on the dry beach surface formed therein, so that a ore discharge area is formed in the space between the internal dike and the tailings dam of the tailings pond, and a drainage area is formed in the space between the internal dike and the tail of the tailings pond. The dry beach surface of the tailings pond usually slopes downward from the top of the tailings dam to the tail of the tailings pond, and tailings water usually flows from the direction of the tailings dam to the lower tail of the tail. In the embodiment of the present application, the construction of the internal dike forms an interception, and the formed ore discharge area can continue to be used for storing tailings, and the formed drainage area can store tailings water and serve as a reserved space in the reservoir for flood control and drainage, thereby making full use of the empty storage capacity above the dry beach surface in the tailings pond and maximizing the utilization of the tailings pond capacity. The potential of tailings ponds serving the middle and late stages has been tapped and expanded, which can meet the storage of tailings in the later stages. For mines in the later stages with small ore surplus, the problems of land acquisition, construction, and construction period caused by the construction of new tailings ponds can be avoided. From the above, it can be seen that the empty space efficiency enhancement system for the tailings pond before closure provided by the embodiment of the present application fully occupies the empty storage capacity above the dry beach surface in the tailings pond before closure, improves its storage capacity utilization rate, avoids the need for new tailings ponds in mines in the later stages with small ore surplus, and thus achieves empty space efficiency enhancement for the tailings pond before closure.
[0025] 2. After continuous ore discharge in the ore discharge area, the sub-dike in the reservoir will eventually be level with the dam crest of the tailings dam, or the top of the sub-dike in the reservoir will slope toward the dam crest of the tailings dam by about 1% to 3% of the dry beach surface when the reservoir is closed. That is, the tailings pond will eventually form a low dam crest and a slightly higher dispersion slope on the dam crest of the sub-dike in the reservoir. The terrain can be fully utilized for closure, and drainage and flood discharge can be smooth, while taking into account soil and water conservation, creating favorable terrain conditions for the closure project. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The drawings in the specification, which constitute a part of this application, are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.
[0027] In the attached picture:
[0028] Figure 1 A schematic diagram of the structure of the tailings pond occupancy efficiency enhancement system before closure provided in an embodiment of the present application;
[0029] Figure 2 A schematic cross-sectional view of a tailings pond occupancy efficiency enhancement system before closure provided in an embodiment of the present application;
[0030] Figure 3A flow chart of a method for increasing the efficiency of a tailings pond before closure provided in an embodiment of the present application.
[0031] In the figure:
[0032] 100. Tailings pond occupancy efficiency enhancement system before closure; 10. Tailings pond; 20. Sub-dike inside the pond; 11. Dry beach surface; 12. Tailings dam; 13. Reservoir tail; 101. Ore discharge area; 102. Drainage area; 201. Tailings water channel; 110. Dry beach surface when the pond is closed. DETAILED DESCRIPTION
[0033] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0034] It should be noted that, unless otherwise specified, all technical and scientific terms used in this application have the same meanings as commonly understood by ordinary technicians in the technical field to which this application belongs.
[0035] In the present invention, unless otherwise specified, the directional words used, such as "up" and "down", usually refer to the directions shown in the drawings, or to the vertical, perpendicular or gravity directions; similarly, for ease of understanding and description, "left" and "right" usually refer to the left and right shown in the drawings; "inside" and "outside" refer to the inside and outside relative to the outline of each component itself, but the above directional words are not used to limit the present invention.
[0036] In addition, in the present invention, descriptions such as "first", "second", etc. are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.
[0037] After the tailings pond has served for the middle and late stages, it needs to be closed. However, since the mine is still in operation and tailings need to be discharged, a new tailings pond is needed to store the tailings generated by subsequent production. When some mines reach the late stage, the ore surplus is not large, and the corresponding tailings generated is not large. If a new tailings pond is built to store tailings at this time, it is necessary to go through land acquisition and necessary new construction procedures. The cycle usually takes 2-3 years, and the project investment is large. The tailings pond that needs to be closed after serving for a long time usually has a storage capacity utilization rate of about 75% to 85%, which means that the storage capacity is not fully utilized. For the tailings pond that is expected to be closed after serving for a long time, if ore is continued to be discharged into it, the artificial low-lying area near the tail of the pond will be occupied by tailings particles and there will be insufficient flood control and drainage space, which is very likely to cause accidents. Therefore, the storage capacity of the tailings pond cannot be fully utilized.
[0038] In order to solve the technical problem in the prior art that the storage capacity of the tailings pond is not fully utilized, i.e. the pond needs to be closed, resulting in the need to build a new tailings pond, the embodiment of the present application provides a system and method for increasing the occupancy rate of the tailings pond before closure.
[0039] The present invention is further described below in conjunction with the accompanying drawings.
[0040] like Figure 1 and Figure 2 As shown, an embodiment of the present application provides a tailings pond occupancy efficiency enhancement system before closure, and the tailings pond occupancy efficiency enhancement system 100 before closure includes a tailings pond 10, an inner dike 20, and a mining area 101 and a drainage area 102 formed between the inner dike 20 and the tailings pond 10.
[0041] The tailings pond 10 is a tailings pond that has been in service for a long time, that is, it needs to be closed or needs to be closed soon after it has been in service. A dry beach surface 11 (i.e., the dry beach surface before closure) is formed in the tailings pond 10. The dry beach surface 11 is the tailings deposition beach surface from the top of the tailings dam 12 of the tailings pond 10 to the water edge of the reservoir. The tailings are discharged in front of the tailings dam 12, and the larger particles are deposited in front of the dam. The tailings water flows to the lower tail end of the reservoir, and the hydraulic grading is continuously deposited to form a dry beach surface in front of the tailings dam 12 of the tailings pond 10. The dry beach surface 11 of the tailings pond 10 is usually inclined downward from the top of the tailings dam 12 to the tail of the tailings pond 10 to form a slope, and the tailings water flows from the tailings dam 12 to the lower tail of the reservoir.
[0042] The inner sub-dike 20 is constructed on the dry beach surface 11, so that the space between the inner sub-dike 20 and the tailings dam 12 of the tailings dam 10 forms a ore-discharging area 101, and the space between the inner sub-dike 20 and the tail 13 of the tailings dam 10 forms a drainage area 102. The ore-discharging area 101 is used to store tailings, and the drainage area 102 is used to store water. The drainage area 102 is mainly an artificial low-lying area, which is generally at least 1m lower than the top of the tailings dam 12 or the tailings accumulation dam.
[0043] The technical solutions in the above embodiments of the present application have at least the following technical effects or advantages:
[0044] The embodiment of the present application provides a tailings pond occupancy efficiency enhancement system before closure, which constructs an internal dike 20 on the dry beach surface 11 formed in the tailings pond 10 that has been in service for the middle and late stages, so that the space between the internal dike 20 and the tailings dam 12 of the tailings pond 10 forms a ore discharge area 101, and the space between the internal dike 20 and the tail 13 of the tailings pond 10 forms a drainage area. The dry beach surface 11 of the tailings pond 10 is usually inclined downward from the top of the tailings dam 12 to the tail of the tailings pond 10 to form a slope, and the tailings water is usually discharged from the tailings dam 12. The water flows from the dam 12 to the lower tail of the reservoir. The construction of the sub-dike 20 in the reservoir in the embodiment of the present application forms an interception, and the formed discharge area 101 can continue to be used to store tailings. The tailings particles are intercepted and stored in the discharge area 101, and the formed drainage area 102 can store tailings water and serve as a space reserved in the reservoir for flood control and flood discharge, thereby fully occupying the empty storage capacity above the dry beach surface 11 in the tailings reservoir 10 under the condition of ensuring the safety performance of the tailings reservoir, realizing the maximization of the tailings reservoir capacity utilization, and the tailings reservoir capacity utilization rate can reach 95-98%. It realizes the potential expansion of the tailings reservoir that serves the middle and late stages, which can meet the storage of tailings in the later stages. For mines in the later stages with small ore surplus, it can avoid the problems of land acquisition, construction, and construction period caused by the construction of new tailings reservoirs, and realizes the occupancy efficiency of the tailings reservoir before closing. At the same time, after continuous discharge of ore in the discharge area 101, tailings are deposited in the discharge area 101, and eventually a dry beach surface 110 is formed when the reservoir is closed, where the sub-dike 20 in the reservoir is level with the crest of the tailings dam 12, or the top of the sub-dike 20 in the reservoir slopes toward the crest of the tailings dam 12 (the crest of the tailings dam is also called the beach top) by about 1% to 3%. That is, the tailings pond 10 eventually forms a drainage slope surface with a low crest of the tailings dam 12 and a slightly higher crest of the sub-dike 20 in the reservoir, which can make full use of the terrain for closure, achieve smooth drainage and flood discharge, and take into account soil and water conservation at the same time, creating favorable terrain conditions for the reservoir closure project.
[0045] In this embodiment, the ore-discharging area 101 is connected to the drainage area 102, so that after the ore is discharged from the ore-discharging area 101, the tailings water can flow into the drainage area 102, and the tailings particles are deposited in the ore-discharging area 101, so as to fully utilize the space of the ore-discharging area 101. Of course, it can be adjusted according to the actual application situation, and the ore-discharging area 101 and the drainage area 102 may not be connected.
[0046] A tailings discharge water channel 201 may be provided on the inner dike 20, so that the ore discharge area 101 is connected to the drainage area 102 through the tailings discharge water channel 201. The tailings discharge water channel 201 may be formed between at least one end of the inner dike 20 and the inner side of the tailings reservoir 10. The tailings discharge water channel 201 may also be directly opened on the inner dike 20, which is not limited here. The width of the tailings discharge water channel 201 may be 1m-3m.
[0047] The reservoir sub-dike 20 can be constructed by at least one of film bag stacking, earth sub-dam stacking, and dry tailings stacking. Of course, the reservoir sub-dike 20 can also be constructed by other methods. For those skilled in the art, the reservoir sub-dikes constructed by other methods under this enlightenment should be included in the scope of this application.
[0048] The drainage area 102 can be connected to the internal flood discharge system of the tailings pond 10, which is the tailings pond flood discharge system originally built by the tailings pond 10. A closed reservoir flood discharge system such as a spillway can also be built in advance on the tailings pond 10 to facilitate drainage. The closed reservoir flood discharge system is the flood discharge system built when the reservoir is closed. With the above settings, the demand for the tailings pond flood control storage capacity of the drainage area 102 can be reduced, and the area of the drainage area 102 can be reduced, thereby increasing the area of the ore discharge area 101, so as to achieve the purpose of making full use of the tailings pond volume.
[0049] Ore can be drawn in the ore drawing area 101 by at least one of wet alluvial drawing and dry tailings drawing.
[0050] The inner sub-dike 20 can be arranged close to the tail of the tailings pond 10, so that the ore discharge area 101 is larger than the drainage area 102. Thus, the volume of the tailings pond can be fully utilized to store more tailings.
[0051] The following is an introduction to the construction and operation of the tailings pond occupancy efficiency enhancement system before closure provided by the embodiment of the present application:
[0052] S1: First, a sub-dike 20 is constructed within a certain range on the dry beach surface 11 in the tailings pond 10 before closing, so that a ore discharge area 101 and a drainage area 102 are formed in the tailings pond 10. The sub-dike can be built at the dry beach position under the premise of meeting the design flood discharge requirements. The sub-dike 20 can be built by film bag stacking, earth dam stacking, dry tailings stacking, etc., and a 1-3m wide tailings water discharge channel 201 is reserved at both ends of the sub-dike 20.
[0053] S2: Alluvial discharge or dry tailing discharge is carried out in the discharge area 101, which fully occupies the area where the dry beach surface 11 does not reach the final accumulation elevation before the tailings pond 10 is closed. The discharge area 101 is the area surrounded by the top of the tailings dam 12 to the sub-dike 20 in the reservoir and the terrain on both sides of the tailings pond 10.
[0054] S3: Tailings water flows from the discharge area 101 to the drainage area 102. The drainage area 102 is a space reserved in the tailings pond for flood control and drainage. The drainage area 102 is connected to the flood discharge system in the reservoir. A closed reservoir flood discharge system such as a spillway can also be built in advance to reduce its demand for the flood control storage capacity of the tailings pond and reduce the area of the drainage area 102, thereby increasing the scope of the discharge area 101 and achieving the purpose of making full use of the volume of the tailings pond.
[0055] S4: The ore discharge finally forms a dry beach surface 110 when the reservoir is closed, in which the sub-dike 20 in the reservoir is level with the top of the tailings dam 12, or the top of the sub-dike 20 in the reservoir is inclined about 1% to 3% toward the top of the tailings dam 12, so as to obtain more effective storage capacity between the dry beach surface 110 when the reservoir is closed and the dry beach surface 11 before closing.
[0056] The inventor of this application simulated the above tailings pond occupancy efficiency enhancement system before closure. The original tailings pond adopted upstream tailings dam technology, with multi-faceted dams and a total storage capacity of about 1300×104m 3 , effective storage capacity is about 950×104m 3 By applying the technical solution of the tailings pond occupancy efficiency enhancement system before closure provided in the embodiment of the present application to expand the ore discharge capacity, an additional effective storage capacity of about 200×104m 3 It can find a way out for the remaining tailings in the later stage of the enterprise, and can create favorable terrain conditions for reservoir closure, creating huge benefits for the enterprise.
[0057] See also Figure 3 The embodiment of the present application also provides a method for increasing the efficiency of a tailings pond before closure. The method is applicable to any of the above-mentioned systems for increasing the efficiency of a tailings pond before closure, and comprises the steps of:
[0058] S100: constructing an inner dike 20 on the dry beach surface 11 formed in the tailings pond 10, so that the space between the inner dike 20 and the tailings dam 12 of the tailings pond 10 forms a ore discharge area 101, and the space between the inner dike 20 and the tail of the tailings pond 10 forms a drainage area 102; the ore discharge area 101 is used to store tailings, and the drainage area 102 is used to store water;
[0059] S200: Ore is discharged into the ore discharge area 101 , and tailings water is stored in the drainage area 102 .
[0060] Wherein, in step S100 or after step S100, the method further includes the following steps:
[0061] The ore-discharging area 101 is connected with the drainage area 102. A tailings-discharging water channel 201 may be provided on the internal dike 20, so that the ore-discharging area 101 is connected with the drainage area 102 through the tailings-discharging water channel 201. When the internal dike 20 is constructed on the dry beach surface 11 formed in the tailings pond 10, a tailings-discharging water channel 201 may be formed between at least one end of the internal dike 20 and the inner side of the tailings pond 10, so that the ore-discharging area 101 is connected with the drainage area 102 through the tailings-discharging water channel 201.
[0062] Wherein, before step S100, during step S100 or after step S100, the method further includes the following steps:
[0063] A closed reservoir flood discharge system is constructed on the tailings pond 10 to reduce the demand for the flood control storage capacity of the tailings pond in the drainage area 102, thereby reducing the area of the drainage area 102 and increasing the scope of the mining area 101, thereby achieving the purpose of more fully utilizing the tailings pond capacity.
[0064] As can be seen from the above, the method for increasing the efficiency of the tailings pond before closure provided by the embodiment of the present application is to build a sub-dike 20 on the dry beach surface 11 formed in the tailings pond 10 that serves to the middle and late stages, and the construction of the sub-dike 20 in the reservoir forms an interception, and the formed ore discharge area 101 can continue to be used to store tailings, and the tailings particles are intercepted and stored in the ore discharge area 101, while the formed drainage area 102 can store tailings water and serve as a space reserved in the reservoir for flood control and flood discharge, so as to fully occupy the empty storage capacity above the dry beach surface 11 in the tailings pond 10 under the condition of ensuring the safety performance of the tailings pond, and maximize the utilization of the tailings pond capacity, and the tailings pond capacity utilization rate can reach 95-98%. It realizes the potential expansion of the tailings pond that serves to the middle and late stages, can meet the storage of tailings in the later stage, and can avoid the land acquisition, construction, and construction period problems brought by the construction of new tailings ponds for mines in the later stage with small ore surplus, and realizes the increase in the efficiency of the tailings pond before closure. At the same time, after continuous discharge of ore in the discharge area 101, tailings are deposited in the discharge area 101, and eventually a dry beach surface 110 is formed when the reservoir is closed, where the sub-dike 20 in the reservoir is level with the crest of the tailings dam 12, or the top of the sub-dike 20 in the reservoir slopes toward the crest of the tailings dam 12 (the crest of the tailings dam is also called the beach top) by about 1% to 3%. That is, the tailings pond 10 eventually forms a drainage slope surface with a low crest of the tailings dam 12 and a slightly higher crest of the sub-dike 20 in the reservoir, which can make full use of the terrain for closure, achieve smooth drainage and flood discharge, and take into account soil and water conservation at the same time, creating favorable terrain conditions for the reservoir closure project.
[0065] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that are not conceived through creative work should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope defined in the claims.
Claims
1. A tailings pond occupancy efficiency enhancement system before closure, characterized in that: The tailings pond occupancy efficiency enhancement system before closure includes: Tailings pond, in which a dry beach is formed; An inner sub-dike is constructed on the dry beach surface so that a space between the inner sub-dike and the tailings dam of the tailings pond forms a ore-discharging area in the tailings pond, and a space between the inner sub-dike and the tail of the tailings pond forms a drainage area, wherein the ore-discharging area is used to store tailings, and the drainage area is used to store water; The ore drawing area is connected to the drainage area; A tailings water discharge channel is provided on the sub-dike in the reservoir; The ore drawing area is connected to the drainage area through the tailings water channel; The tailings water discharge channel is formed between at least one end of the sub-dike in the reservoir and the inner side of the tailings reservoir.
2. The tailings pond occupancy efficiency enhancement system before closure according to claim 1 is characterized in that: The width of the tailings water channel is 1m-3m.
3. The tailings pond occupancy efficiency enhancement system before closure according to claim 1 is characterized in that: The sub-dike in the reservoir is constructed by at least one of membrane bag stacking, earth dam stacking and dry tailings stacking.
4. The tailings pond occupancy efficiency enhancement system before closure according to claim 1 is characterized in that: The drainage area is connected to the flood discharge system in the tailings pond.
5. The tailings pond occupancy efficiency enhancement system before closure according to claim 1 is characterized in that: A closed reservoir flood discharge system is constructed on the tailings pond to reduce the demand for the flood control storage capacity of the tailings pond in the drainage area.
6. The tailings pond occupancy efficiency enhancement system before closure according to claim 1 is characterized in that: The ore is drawn in the ore drawing area by at least one of wet alluvial drawing and dry tailings drawing.
7. A tailings pond occupancy efficiency enhancement system before closure according to any one of claims 1 to 6, characterized in that: The inner sub-dike is arranged close to the tail of the tailings pond so that the ore discharge area is larger than the drainage area.
8. A method for increasing the efficiency of a tailings pond before closure, applicable to the system for increasing the efficiency of a tailings pond before closure as claimed in any one of claims 1 to 7, characterized in that: The method comprises: An inner dike is constructed on the dry beach surface formed in the tailings pond, so that the space between the inner dike and the tailings dam of the tailings pond forms a ore discharge area, and the space between the inner dike and the tail of the tailings pond forms a drainage area; discharge ore into the ore discharge area, and store tailings water into the drainage area; The method further comprises: connecting the ore drawing area with the drainage area; The method of connecting the ore drawing area with the drainage area includes: A tailings drainage channel is arranged on the inner dike of the reservoir, so that the ore discharge area is connected with the drainage area through the tailings drainage channel; When constructing an inner dike on the dry beach surface formed in the tailings pond, a tailings drainage channel is formed between at least one end of the inner dike and the inner side of the tailings pond, so that the ore discharge area is connected with the drainage area through the tailings drainage channel; The method further includes: constructing a closed reservoir flood discharge system on the tailings pond to reduce the demand of the drainage area for the flood control storage capacity of the tailings pond.