Multi-machine coordinated lifting system and technology for box girder of highway bridge over railway cutting under construction

Through the multi-machine collaborative lifting system in the deep-cut section of the railway, the cranes at the top of the railway and the roadbed station are coordinated, and combined with the cannon truck feeding beams, the problems of difficult and high risks of box beams are solved, and the safety of box beams is achieved. Economical and rapid lifting reduces construction complexity and cost.

CN111717798BActive Publication Date: 2024-12-06CHINA RAILWAY 16TH BUREAU GRP RAIL TRANSPORT ENG CO LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202010611764.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-06-30
Publication Date
2024-12-06
Estimated Expiration
2040-06-30

AI Technical Summary

Technical Problem

During the lifting of box girders on the upper span highway bridge in the railway deep-cut section, due to the long length and heavy box girder, the crane is difficult to translate and lift, and the lifting radius and height are too large, resulting in high lifting risks. In addition, the traditional bridge staging method The cast-in-place method has high cost and construction complexity.

Method used

Adopt a multi-machine collaborative lifting system, using cranes at the top station and roadbed stations to operate in coordination, combined with the cannon truck feeding beams, and through preset lifting points and wire ropes, the box beams can be moved and positioned, and the box beams can be selected. QAY200 and QAY650 cranes are used to meet lifting capacity and safety requirements.

Benefits of technology

It realizes safe and reliable lifting of box girders, reduces project costs, simplifies the construction process, improves lifting efficiency, and ensures construction safety and lifting accuracy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111717798B_ABST
    Figure CN111717798B_ABST
Patent Text Reader

Abstract

The present invention relates to a multi-machine coordinated lifting system and process for a box girder of a highway bridge over a railway cutting under construction. The method uses a cutting top workstation crane A (40) located on an existing road (8) at a bridge head and a roadbed workstation crane C (2) and a roadbed workstation crane B (3) at a bridge site lifting area. A prefabricated beam yard is set up next to the bridge site. A gun carriage (38) for transporting the box girder (1) to the lifting area is set up between the beam yard and the bridge site. A lifting point A (9) and a lifting point B (10) are preset at both ends of the box girder (1). An intermediate span (5) is preset in the middle of a bridge pier (4). Side spans (6) are provided at both ends of the intermediate span (5). The cutting top workstation is located at the top of a roadbed slope. The present invention has a reasonable design, a compact structure and is easy to use.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a multi-machine coordinated hoisting system and process for a box girder of a highway bridge that crosses a railway cutting under construction. Background Art

[0002] The railway in a certain area is a deep cutting section with a cutting slope height of 27.7m. The cutting slope is divided into four levels with a slope ratio of 1:1.25. According to the design, after the main railway cutting project is completed, a highway bridge over the railway will be built to restore the existing highway project. See the schematic diagram of the bridge site for details. Figure 1 The upper highway bridge is a simple-supported and then continuous prestressed reinforced concrete continuous box girder bridge, with a span of 3×40m and a crossing angle of 90o with the railway. The bridge is 7m wide, with two box girders arranged transversely in each span, with a beam width of 3.1m and a pier height of 25.7m. See the highway bridge type layout diagram for details. Figure 2 Two beam manufacturing sites are set up on the right side of railway DK166+800 and on the left side of DK166+900. A temporary road is built to the existing road, and the beams are transported to the top of the bridgehead cutting for erection.

[0003] Since the box girder is long and heavy, and is transported from the top of the cutting, it is a horizontal lifting operation. If the crane is operating on the top of the cutting, the lifting operation radius is too large and difficult to achieve; if the crane is operating on the roadbed, the lateral distance from the slope foot to the bridge abutment is 43m, and the vertical height is 27.7m, the crane's operating radius and lifting height are too large and difficult to achieve. In addition, since the crane is operating in a deep cutting and there are bridge piers within the operating range, and the lifting point needs to be changed during the multi-machine lifting process, there is a high risk of collision between the boom and the bridge piers, beams, and between the crane booms.

[0004] Commonly used methods for erecting simply supported box girders include the bridge erection machine method, cast-in-place method, and hoisting method. When prefabricated beams are used to cross the railway operating line, a bridge erection machine or crane is generally used to erect the beams. Based on the safety considerations of the railway operating line, the railway management department generally gives priority to the bridge erection machine method when conditions permit. When the conditions for bridge erection machine erection are not met, the crane erection method can be considered.

[0005] The bridge-erecting machine method is suitable for erecting box girders with a large number of spans. The present invention has a small number of spans, only three spans, and the transportation on the hoisting site is inconvenient. If a bridge-erecting machine is used for construction, it is necessary to build a construction access road and an assembly platform; in addition, the assembly and disassembly of the bridge-erecting machine requires the cooperation of a large-tonnage crane and a large number of professionals, and the project cost is relatively large. The cast-in-place construction method has a large amount of on-site work, and there are cross-operations with slope protection and drainage projects, which also affects the development of subsequent processes and makes it difficult to guarantee the construction period. The crane hoisting method has a small amount of on-site work and has little impact on the construction of railway projects under construction; through parallel operations, the highway can be opened as soon as possible, and the impact on local traffic is small. Therefore, the present invention adopts a crane hoisting solution, and the lifting equipment adopts an all-terrain truck crane. Summary of the invention

[0006] The technical problem to be solved by the present invention is generally to provide a multi-machine collaborative lifting system and process for box girders of highway bridges that cross the railway cutting under construction. A multi-machine collaborative lifting process for box girders of highway bridges that cross the railway cutting under construction, the method uses a cutting top station crane A located at the top of the roadbed slope and a roadbed station crane C and a roadbed station crane B at the bridge site lifting area, a prefabricated beam yard is set up at the cutting top beside the bridge site, and a gun carriage for transporting the box beam to the lifting area is set up between the beam yard and the bridge site; lifting points A and B are preset at both ends of the box beam; an intermediate span is preset in the middle of the bridge pier, and side spans are provided at both ends of the intermediate span, and the cutting top station is at the top of the roadbed slope;

[0007] The method comprises the following steps:

[0008] Step 1: Execute the side span box girder hoisting plan.

[0009] As a further improvement of the above technical solution:

[0010] The roadbed crane C and the roadbed crane B are both located on the roadbed, and the top-cutting crane A is located at the top of the pad. The position is determined according to the operating conditions and crane performance parameters. Then, the box girder is delivered by a gun carriage from the existing road at the bridge head. When the left end of the beam approaches the abutment, the top-cutting crane A hooks the left end of the box girder to the A lifting point for trial lifting. After confirming that it is safe and stable, it starts lifting and the rear of the gun carriage withdraws. Secondly, the top-cutting crane A cooperates with the gun carriage to continue to deliver the box girder in translation. Thirdly, when the gun carriage approaches the abutment, the roadbed crane B and the roadbed crane C hook the left end of the box girder to the A lifting point through the balance beam, and the top-cutting crane A changes the hook and hooks the right end of the box girder to the B lifting point. After the lifting point conversion is completed, the gun carriage withdraws. Later, the roadbed cranes B, C and the top-cutting crane A work together to translate the box girder into place.

[0011] Step two, execute the lifting plan for the middle span box girder; first, use a trolley to push and deliver the box girder along the existing road at the bridge head and the erected side span box girder; then, when the left end of the hoisted box girder approaches the left end of the right span box girder in step one, the roadbed work station crane B hooks the left end of the box girder to the lifting point A, and the rear of the trolley withdraws; secondly, the roadbed work station crane B cooperates with the trolley to continue to translate and deliver the box girder; again, when the trolley approaches the left end of the right span box girder in step one, the roadbed work station crane C hooks the lifting point A at the left end of the box girder, and the roadbed work station crane B changes the hook and hooks the lifting point B at the right end of the box girder. After the lifting point conversion is completed, the trolley withdraws; later, the roadbed work station cranes B and C work together to translate the box girder into place.

[0012] Beneficial effects of the present invention: The method of using multiple cranes at multiple stations on the top of the cutting and the roadbed surface to coordinate with the gun carriage to feed the beam can solve the problem of difficulty in crane translation and lifting due to the long length and heavy weight of the beam when erecting the box beam of the highway bridge over the deep cutting of the railway under construction. The QAY200 and QAY650 cranes are selected, and the steel wire rope can meet the lifting capacity requirements and ensure the safety of the operation. The bearing capacity of the foundation must meet the lifting requirements. The anti-overturning stability of the crane meets the requirements and can ensure the safety of the construction. Practice has proved that the technical method of multi-machine collaborative lifting of large-span box beams over the deep cutting highway bridge over the railway under construction is novel, practical, safe and reliable, and has a good application effect. The present invention has a reasonable design, low cost, strong and durable, safe and reliable, simple operation, time-saving and labor-saving, money-saving, compact structure and easy use. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the bridge site overview of the present invention. Figure 2 It is the layout diagram of the highway bridge type of the present invention. Figure 3 This is a process flow chart of the three-machine coordinated gun carriage feeding beam hoisting process of the present invention. Figure 4 The cranes A, B, C and the beam transporting trolley of the present invention are in position. Figure 5 The crane A of the present invention cooperates with the gun carriage to feed the beam. Figure 6 It is the three-machine coordinated gun carriage feeding beam of the present invention. Figure 7 It is the crane A of the present invention that unhooks. Figure 8 It is that the gun carriage of the present invention is evacuated. Fig. 9 This is the three-machine coordinated translation lifting of the present invention. Fig.10 This is a process flow chart of the double-machine coordinated gun carriage feeding beam hoisting process of the present invention. Fig.11 The cranes B and C of the present invention and the beam transporting trolley are in place. Fig.12 The crane B of the present invention cooperates with the gun carriage to feed the beams. Fig.13 It is the crane B of the present invention that unhooks. Fig.14 It is that the gun carriage of the present invention is evacuated. Fig.15 This is the double-machine cooperative translation lifting of the present invention. Fig.16 It is a schematic diagram of the box girder hanging point of the present invention. Fig.17 It is a schematic diagram of the working force of the crane of the present invention. Fig.18 It is a schematic diagram of a crane of the present invention. Fig.19 It is a schematic diagram of the lifting auxiliary device of the present invention. Fig. 20 It is a schematic diagram of an explosion of the lifting auxiliary device of the present invention. Fig.21 It is a schematic diagram of a side connecting rod of the present invention. Fig. 22 It is a schematic diagram of a gun carriage of the present invention. Fig.23 It is a schematic diagram of the present invention. Fig.24 It is a calculation geometry model diagram of the side span box girder hoisting of the present invention. Fig.25 It is a calculation geometry model diagram of the side span box girder hoisting of the present invention. DETAILED DESCRIPTION

[0014] like Figure 1-25 ,like Figure 1 As shown, in this embodiment, a multi-machine collaborative lifting process for a box girder of a highway bridge over a railway cutting under construction is performed by means of a cutting top workstation crane A40 located at the top of the roadbed slope and a roadbed workstation crane C2 and a roadbed workstation crane B3 at the bridge site lifting area. A prefabricated beam yard is set at the cutting top beside the bridge site, and a gun carriage 38 for transporting the box girder 1 to the lifting area is set between the beam yard and the bridge site.

[0015] A lifting point 9 and B lifting point 10 are preset at both ends of the box beam 1; an intermediate span 5 is preset in the middle of the bridge pier 4, and side spans 6 are provided at both ends of the intermediate span 5, and the cutting top working position is at the top of the roadbed slope;

[0016] The method comprises the following steps:

[0017] Step 1: Execute the side span box girder hoisting plan.

[0018] The roadbed crane C2 and the roadbed crane B3 are both located on the roadbed, and the top-of-cut crane A40 is located at the top of the pad. The position is determined according to the operating conditions and crane performance parameters. Then, the gun carriage 38 is used to push and deliver the box girder 1 from the existing road 8 at the bridge head. When the left end of the beam approaches the abutment, the top-of-cut crane A40 hooks the left end of the box girder A lifting point 9 for trial lifting. After confirming that it is safe and stable, the lifting begins, and the tail of the gun carriage 38 is evacuated. Secondly, The top-of-cut crane A40 cooperates with the gun carriage 38 to continue to deliver the box girder; again, when the gun carriage 38 approaches the abutment, the roadbed crane B and the roadbed crane C hook the left end of the box girder A at the lifting point 9 through the balance beam, and the top-of-cut crane A changes the hook and hooks the right end of the box girder 1 at the lifting point B 10. After the lifting point conversion is completed, the gun carriage 38 withdraws; later, the roadbed cranes B, C and the top-of-cut crane A work together to move the box girder into place;

[0019] Step two, execute the lifting plan for the middle span box girder; first, use the trolley to push and deliver the box girder along the existing road at the bridge head and the erected side span box girder; then, when the left end of the hoisted box girder 1 is close to the left end of the right span box girder in step one, the roadbed station crane B hooks the left end A lifting point 9 of the box girder, and the rear of the trolley withdraws; secondly, the roadbed station crane B cooperates with the trolley to continue to translate and deliver the box girder; again, when the trolley is close to the left end of the right span box girder in step one, the roadbed station crane C hooks the left end lifting point A lifting point 9 of the box girder, and the roadbed station crane B changes the hook and hooks the right end B lifting point 10 of the box girder. After the lifting point conversion is completed, the trolley withdraws; later, the roadbed station cranes B and C work together to translate the box girder into place.

[0020] Among them, the prefabricated box beam is a simply supported component. In order to ensure that the force points and stress state of the box beam during the hoisting process are consistent with its use, parallel hoisting two-point hoisting is adopted to ensure the balanced force at the hoisting point during the hoisting of the box beam and the stability when the beam is hoisted and dropped. The distance between the hoisting point and the two ends of the object is calculated based on the moment balance of the box beam itself, that is, to ensure that the positive and negative bending moments at the hoisting point are equal. Therefore, the two hoisting points are set at 0.2L from the beam end. Fig.16 The lifting point adopts the wire rope binding hoisting method. The weight of each box beam in this project is 161.2t, and the theoretical bearing capacity of the two lifting points is 80.6t under the condition of double lifting.

[0021] Step B1, selecting roadbed crane B and roadbed crane C.

[0022] The planar relationship between the crane, beam and environment in working condition CZ3 is shown in the figure.

[0023] The lifting capacity requirements of roadbed crane B and roadbed crane C are the same, both

[0024] G jBC =K1K2G0 (3.1)

[0025] In the formula, G0 is the sum of the weight of the load, the lifting lugs and the rigging weight shared by the crane, G0 = 161.2 / 2 + 2.0 = 82.6t; K1 is the dynamic load coefficient, which is 1.1; K2 is the unbalanced coefficient of the double crane lifting, which is 1.2. The calculation results show that G jBC =109.0t.

[0026] The operating range R of crane B B Should meet Lifting height H B Should satisfy H B >33.0m. The operating range R of crane C C Should meet Lifting height H C Same as H B .

[0027] According to G jBC , R B , H B , R C , H C Considering that cranes B and C are of the same model, referring to the crane performance table, cranes B and C can use QAY500 truck cranes, with a lifting capacity of G = 118t, a working range of R = 20m, and a boom length of L = 48m. It can meet the lifting requirements.

[0028] Step B2, selection of crane A for the cutting top station

[0029] According to the performance parameters of cranes B and C, after determining the position of the lifting point conversion of working condition CB2, the performance parameter requirements of crane A are determined. The plane relationship between the crane, beam and environment of working condition CB2 is shown in the figure.

[0030] After the lifting point conversion, the lifting capacity requirements of cranes B and C are

[0031] G jBC =K1K2G0 (3.2)

[0032] In the formula, G0 is the sum of the weight of the load, the lifting lugs and the rigging weight shared by cranes B and C, G0 = 161.2 / 2 / 2 + 2.0 = 42.3t; K1 and K2 are the dynamic load coefficient and the imbalance coefficient, which are 1.1 and 1.2 respectively. jBC =60.9t. According to the performance table of QAY500 truck crane, the operating conditions of cranes B and C are selected as lifting weight G = 69t, arm length L = 66m, and lifting height The corresponding maximum working range is R=30m.

[0033] From this calculation, it can be obtained that to realize the lifting point conversion of cranes B, C and crane A in working condition CB2, the minimum working range R of crane A is required A ≥17.64m. The lifting capacity requirement of crane A is calculated in the same way as in formula (3.1), and we can get G jA =109.0t. Refer to the crane performance table and select QAY500 truck crane, using the working conditions of lifting capacity G = 138t, operating range R = 18m, arm length L = 30m, lifting height Can meet lifting requirements.

[0034] The cranes used in this project should be of the same model as much as possible to facilitate coordinated operation.

[0035] First, determine the calculated load G of the object to be hoisted j

[0036] G j =K1K2G0(1)

[0037] In the formula, G0 is the sum of the weight of the object being hoisted, the lifting lugs and the weight of the rigging (t), which is taken as 82.6t; K1 is the dynamic load coefficient, which is taken as 1.1; K2 is the unbalanced coefficient of the double crane lifting, which is taken as 1.2. The calculation results show that G j =109.0t.

[0038] Then, according to the crane parameters, select the rated lifting capacity Q ≥ G j . Under the premise of meeting the lifting weight, select the boom length L and working radius R according to the lifting height H and site conditions. According to the lifting process, calculate the operating radius and lifting height of each crane under different working conditions.

[0039] According to the requirements of the above crane performance parameters, the performance tables of cranes of different tonnages were consulted for comparative analysis. Under the premise of meeting the lifting weight requirements, economic factors were considered. Crane A selected the QAY200 crane, and cranes B and C selected the QAY650 crane.

[0040] Wire Rope Selection

[0041] The standard for the use of thick diameter wire rope is

[0042]

[0043] In the formula, D is the minimum diameter of the hoisting wire rope (mm); Q is the weight of the crane (t); β is the load distribution coefficient, which is generally taken as 66%. Considering the unbalanced coefficient K of double crane lifting, it is generally taken as 1.2, and under the condition of multiple crane lifting, it is taken as

[0044] Q=80.6×1.2=96.7t,

[0045] According to formula (2), D min Should reach 60mm.

[0046] Force F of single-strand wire rope on one side N Calculate according to the following formula

[0047]

[0048] In the formula, 1.05 is the angle coefficient; Q is the weight of the crane sling (t), which is 97.2t. N =25.4t.

[0049] Total pulling force

[0050] Z n =K×F N (4)

[0051] In the formula, k is the safety factor of the hoisting wire rope, which is 10. The total tension Z is n =2489.2kN. The steel wire rope is a fiber core, so its breaking force needs to be converted. The conversion formula is

[0052]

[0053] In the formula, α is the conversion coefficient, which is 1.226, and the breaking tension of the wire rope is Z = 2030.3 kN. According to the literature [8], the breaking tension is

[0054]

[0055] Where, Z is the breaking force (kN); FC is the tensile strength of the wire rope, take 1670kg / mm 2 , calculation shows that D = 65mm.

[0056] After the above analysis and calculation, the steel wire rope selected is Φ65-6×19zs+FC-1670.

[0057] Outrigger foundation bearing capacity

[0058] From the lifting plan, it can be seen that the load-bearing capacity of cranes A and B is equal. The total load-bearing capacity N of the foundation of a single crane is calculated as follows:

[0059]

[0060] In the formula, γ G , γ Q is the static and dynamic load combination coefficient, which are 1.2 and 1.4 respectively; G0 is the sum of the weight of the crane, the overload counterweight, the sling and the rigging weight (kN). For cranes B and C of the same model,

[0061] G0=2855.7kN;

[0062] G L The weight of the box girder is 789.9kN.

[0063] Calculation shows that the total load-bearing capacity is N = 3979.8 kN.

[0064] Assuming that the four outriggers of the crane are evenly stressed, the average compressive stress applied by each outrigger on the foundation is

[0065]

[0066] Where A is the area of ​​the crane leg steel pad (m 2 ), the leg pad is made of 2.5m×3.0m×0.05m steel plate. It can be calculated that p=132.7kPa.

[0067] Considering the construction of beam erection over the railway, a safety factor of 1.2 is taken, and the bearing capacity requirement of the work site is f a ≥1.2p=159.2kPa. If the bearing capacity of the on-site foundation does not meet the above requirements, compaction or replacement can be used.

[0068] Lifting safety analysis

[0069] In order to ensure the stability of the crane during the lifting process, it is necessary to analyze the anti-overturning stability of the crane. The anti-overturning stability standard of the crane is

[0070] ∑M=K G ·M G +K Q ·MQ +K W ·M W ≥0 (9)

[0071] Where, ∑M is the anti-overturning moment, K G is the weighted coefficient of self-weight, which is 1; K Q K is the weighted coefficient of lifting load, which is 1.15; W is the wind load weighting coefficient, which is 1; M G 、M Q 、M W The moment (kN·m) of the crane's deadweight, lifting load, and wind load on the overturning edge. See the crane working force diagram for details. Fig.17 In the figure, G is the dead weight of the crane (kN); Q is the weight of the hoisted object (kN); W is the wind load (kN), which is considered to be 20% of the weight of the hoisted object; a is the distance from the center of gravity of the crane to the tipping fulcrum of the support leg (m); R is the operating radius of the crane (m); h is the height of the resultant point of the wind load (m).

[0072] QAY650 crane G = 291.4t, a = 5m, under the most unfavorable working condition R = 40m, Q = 20.7t, W = 4.14t, the wind load resultant point is the center of gravity of the hoisted object, h = 26.7m, the calculation can be obtained

[0073] ∑M=513.3kN·m>0, meets the requirements.

[0074] Similarly, for QAY200 crane, ∑M=77.3kN·m>0, which meets the requirements.

[0075] A multi-machine collaborative lifting process for box girders of a highway bridge over a railway cutting under construction, the method uses a cutting top workstation crane A located on an existing road at the bridge head and a roadbed workstation crane C and a roadbed workstation crane B at a bridge site lifting area, a prefabricated beam yard is set up next to the bridge site, and a gun carriage for transporting the box girders to the lifting area is set up between the beam yard and the bridge site;

[0076] There are A and B lifting points preset at both ends of the box girder; there is an intermediate span preset in the middle of the pier, and side spans at both ends of the intermediate span. The cutting top work station is on the existing road at the bridge head;

[0077] The method comprises the following steps:

[0078] Step 1: Execute the lifting plan for the side span box girder. First, the roadbed crane C and the roadbed crane B are both located on the roadbed, and the top-of-cut crane A is located on the existing road at the bridgehead. The position is determined according to the operating conditions and crane performance parameters. Then, the box girder is delivered by a gun carriage from the existing road at the bridgehead. When the left end of the beam approaches the top-of-cut work station of the existing road at the bridgehead, the top-of-cut crane A hooks the left end of the box girder to the A lifting point for trial lifting. After confirming that it is safe and stable, the lifting begins. , the rear of the gun carriage evacuates; secondly, the cutting top station crane A cooperates with the gun carriage to continue to deliver the box beam horizontally; thirdly, when the gun carriage approaches the cutting top to the preset position, the roadbed station crane B and the roadbed station crane C hook the left end A of the box beam through the balance beam, and the cutting top station crane A changes the hook and hooks the right end B of the box beam. After the lifting point conversion is completed, the gun carriage evacuates; later, the cutting top station crane A and the roadbed station cranes B and C work together to move the box beam horizontally into place;

[0079] Step two, execute the mid-span box girder lifting plan. First, use a trolley to push and deliver the box girder along the existing road at the bridge head and the erected box girder; then, when the left end of the hoisted box girder approaches the left end of the right span box girder in step one to the preset position, the roadbed work station crane B hooks the left end of the box girder to the lifting point A, and the rear of the trolley withdraws; secondly, the roadbed work station crane B cooperates with the trolley to continue to translate and deliver the box girder; again, when the trolley approaches the left end of the right span box girder in step one to the preset position, the roadbed work station crane C hooks the lifting point A at the left end of the box girder, and the roadbed work station crane B changes the hook and hooks the lifting point B at the right end of the box girder. After the lifting point conversion is completed, the trolley withdraws; later, the roadbed work station cranes B and C work together to translate the box girder into place.

[0080] The lifting and positioning device 11 is installed on the beam 1; secondly, the crane C and the crane B respectively hook the A lifting point 9 and the B lifting point 10 of the box beam 1, wherein the wire rope of the crane A is connected to the movable lifting lug seat 31 located at the B lifting point 10, and a trial lifting is carried out. After confirming that it is safe and stable, the lifting is started, and the angle between the monitoring side vertical frame 26 and the monitoring swing rod 28 is observed to realize the observation of the box beam 1 and determine whether it is lifted correctly.

[0081] When changing the position of the lifting lug, the movable lifting lug seat 31 is moved to the A lifting point 9 and blocked by the transverse stopper 33 at the end of the lifting lug A, so that the crane A or C hook is hung at the A lifting point 9 or the B lifting point 10;

[0082] When it is necessary to lower the installation, the auxiliary rotating shaft 35 drives the auxiliary swing arm 36 to swing upward, and the longitudinal position adjustment is achieved by pulling with a winch.

[0083] Before step one include:

[0084] Step A, determine the position of the hanging point, based on the distance between the hanging point and the two ends of the object and the box beam's own moment balance as the calculation standard, that is, to ensure that the positive and negative bending moments at the hanging points are equal, the two hanging points are respectively set at 0.2L from the beam end, and the hanging points are wire rope tied pocket hanging type;

[0085] Step B, crane selection;

[0086] First, determine the calculated load G of the object to be hoisted j

[0087] G j =K1K2G0 (1);

[0088] In the formula, G0 is the sum of the weight of the object being hoisted, the lifting lugs and the weight of the rigging; K1 is the dynamic load coefficient, which is taken as 1.1; K2 is the unbalanced coefficient of the double crane lifting, which is taken as 1.2;

[0089] Then, according to the crane parameters, select the rated lifting capacity Q ≥ G j , under the premise of meeting the lifting weight, select the boom length L and working radius R according to the lifting height H and site conditions, and calculate the operating radius and lifting height of each crane according to different working conditions according to the lifting process;

[0090] According to the requirements of crane performance parameters, consult the performance tables of cranes of different tonnages for comparative analysis and select the crane;

[0091] Specifically, crane performance parameters include lifting height, operating radius, lifting weight, etc. Since the operating radius determines the lifting weight, the crane operating radius R is used as the lifting radius. A , R B Minimum, that is, the minimum crane tonnage is the optimization goal. The crane position is described by its distance x and y to the center line of the road, and x and y are optimization variables. As the preferred choice:

[0092] Step B1, crane B optimization model: First, based on the comprehensive analysis of the crane operating conditions, according to the mid-span box girder hoisting calculation geometry model diagram, with the position of crane B as the optimization variable, under the premise of ensuring safe hoisting, the crane operating radius is minimized, that is, the crane tonnage is minimized as the optimization goal, and the optimization mathematical model is established as follows:

[0093] min R B (3.1)

[0094]

[0095] Formulas 3.2a to 3.2c are the lifting distance, height and lifting weight conditions of crane B under working condition C1, formula 3.2d is the anti-collision condition of crane B under working condition C3, and formulas 3.2e to k are the range of the position and luffing angle of crane B under the two working conditions; xB ,y B are the lateral and longitudinal distances of the crane in the coordinate system, m; a is the center position of the left end of the mid-span box girder, m; L is the length of the box girder, m; L B is the crane boom length, m; θ CZ1 θ CZ3 is the luffing angle of the cranes in working conditions CZ1 and CZ3, °; H B H 墩 +H 绳 +H 盖 +H 梁 =33, m; G is the lifting weight of the crane, t; G0 is the load of a single crane, t; P B is the minimum distance from the crane boom to the box girder during translation and P B >0,m.

[0096] Step B2, based on the comprehensive analysis of the crane operation conditions, in accordance with the mid-span box girder hoisting calculation geometry model diagram, with the position of crane C as the optimization variable, under the premise of ensuring safe hoisting, with the minimum crane operation radius, that is, the minimum crane tonnage as the optimization goal, the optimization mathematical model is established as follows:

[0097] min R C (3-3)

[0098]

[0099] Formulas 3.2a to 3.2c are the lifting distance, height and lifting weight conditions of crane C under working condition CZ3, and formulas 3.2d to g are the range of crane C's position and luffing angle; are the lateral and longitudinal distances of the crane in the coordinate system, m; a is the center position of the left end of the mid-span box girder, m; L is the length of the box girder, m; L 臂C is the crane boom length, m; θ Z3 is the luffing angle of the crane under CZ3 working condition, °; ​​H C H 墩 +H 绳 +H 盖 +H 梁 =33, m; G is the lifting weight of the crane, t; G0 is the load of a single crane, t.

[0100] Step B3, crane B, C selection analysis; the general description of the constrained optimization problem is: Where x=[x1,x2,Λ,x n ] T, under the premise of satisfying the constraint condition G(x)≤0, the objective function f(x) is minimized. For the above crane position optimization model, the Interior Point algorithm (interior point algorithm) in the fmincon function is used to solve it. When solving the actual optimization problem, the solution formula is:

[0101] min f(x)

[0102]

[0103] In formula 4.1, Ax≤b and A1x=b1 are linear constraints, C(x)≤0 and C1(x)=0 are nonlinear constraints, and LB≤x≤UB is a bounded constraint. The basic idea of ​​the constrained optimization interior point algorithm is to convert the constrained optimization problem into an unconstrained problem by introducing the utility function, and then continuously update the utility function through the optimization iteration process to make the algorithm converge. When the iteration point is close to the boundary, the objective function increases in vain as a penalty to prevent the iteration point from crossing the boundary and ensure that the optimal solution is within the feasible domain.

[0104] Step B4, through the above-mentioned Interior Point algorithm, the optimization mathematical model established in the process of step-by-step lifting and hoisting of the side span box girder is calculated and solved, that is, the appropriate lifting weight is selected in the crane performance table, and the arm length and working radius corresponding to the lifting weight are obtained, and the optimization model is substituted for calculation to obtain the B and C crane selection and station configuration scheme as shown below:

[0105] (1) Selection of crane B

[0106] Table 4-1 Crane B model calculation results

[0107]

[0108] For the selection optimization of crane B, when the parameters of QAY 300 crane are used for calculation, the objective function has no solution, and the performance of QAY 300 crane cannot meet the working condition requirements, so this crane configuration combination is excluded; QAY 650 and QAY 500 cranes both meet the requirements. For economic considerations, crane B chooses QAY 500 crane for hoisting, and the distances x and y from crane B to the center line of the highway are 13.27m and 7m respectively.

[0109] (2) Selection of crane C

[0110] Table 4-2 Crane C model calculation results

[0111]

[0112]

[0113] For the selection optimization of crane C, when the parameters of QAY 300 crane are used for calculation, the objective function has no solution, and the performance of QAY 300 crane cannot meet the working condition requirements, so this crane configuration combination is excluded; QAY 650 and QAY 500 cranes both meet the requirements. For economic considerations, QAY 500 crane is selected for hoisting in crane C, and the distances x and y from crane C to the center line of the highway are 4.37m and 7m respectively.

[0114] Step B5, crane A selection analysis,

[0115] From the results of the mid-span selection analysis, it can be seen that cranes B and C both use QAY500 cranes, and the side span is selected for crane A based on the mid-span selection.

[0116] G j =K1K2G0 (4.2)

[0117] In the formula, G0 is the sum of the weight of the object being hoisted, the lifting lugs and the weight of the rigging (t), which is 42.1 t for cranes B and C and 82.6 t for crane A; K1 is the dynamic load coefficient, which is 1.1; K2 is the unbalanced coefficient of the double crane lifting, which is 1.2. The G0 of cranes B and C can be calculated as follows: j = G of 46.3t crane A j =109.0t.

[0118] Based on the crane model B and C being QAY500, refer to the crane performance table and select the rated lifting capacity Q≥G j . Under the premise of meeting the lifting weight, select the boom length L and working radius R according to the lifting height H and site conditions. Cranes B and C should meet H≥33m, G≥46.3t, and crane A should meet G≥109.0t. Analysis shows:

[0119] Cranes B and C are selected with R=38m, L=72m, G=46t>40.5t, crane A is QAY300, R=8m, L=25.7m, G=103t>101.25t.

[0120] According to the above calculation and analysis, the lifting point is transferred when the left end of the side span box girder being hoisted is 11m away from the top of the cutting.

[0121] In summary, considering the safety of construction, economy and the performance parameter requirements of cranes under various working conditions, cranes B and C choose QAY500 cranes, and crane A chooses QAY300 cranes.

[0122] Step C, wire rope selection

[0123] First of all, the use standard of thick diameter wire rope is

[0124]

[0125] In the formula, D is the minimum diameter of the hoisting wire rope; Q is the weight of the crane; β is the load distribution coefficient, which is generally taken as 66%. Considering the unbalanced coefficient K of double crane lifting, it is generally taken as 1.2, and under the condition of multiple crane lifting, it is taken as

[0126] Q=80.6×1.2=96.7t,

[0127] Then, according to formula (2), D min ;

[0128] Secondly, the force F of the single-strand wire rope on one side N Calculate according to the following formula

[0129]

[0130] In the formula, 1.05 is the angle coefficient; Q is the weight borne by the crane sling;

[0131] Total pulling force

[0132] Z n =K×F N (4)

[0133] In the formula, k is the safety factor of the hoisting wire rope, which is 10;

[0134] Secondly, the steel wire rope is a fiber core, so its breaking tension is converted. The conversion formula is:

[0135]

[0136] In the formula, α is the conversion coefficient, which is 1.226, and the breaking force is calculated as

[0137]

[0138] Where Z is the breaking force; F C is the tensile strength of the wire rope, take 1670kg / mm 2 ;

[0139] After the above analysis and calculation, the steel wire rope is selected as Φ65-6×19zs+FC-1670;

[0140] Step D, calculate the bearing capacity of the outrigger foundation,

[0141] First, it can be seen from the lifting plan that the load-bearing capacity of cranes C and B is equal. The total load-bearing capacity N of the foundation of a single crane is calculated as follows:

[0142]

[0143] In the formula, γ G , γ Q is the static and dynamic load combination coefficient, which are 1.2 and 1.4 respectively; G0 is the sum of the weight of the crane, the overload counterweight, the sling and the rigging weight. For cranes B and C of the same model, G L is the weight of the box girder;

[0144] Then, assuming that the four outriggers of the crane are evenly stressed, the average compressive stress exerted on the foundation by each outrigger is

[0145]

[0146] Where A is the area of ​​the crane leg steel pad (m 2 );

[0147] Secondly, considering the construction of beam erection over the railway, taking 1.2 times the safety factor, the bearing capacity requirement of the work site is f a ≥1.2p, if the bearing capacity of the on-site foundation does not meet the above requirements, compaction or replacement can be used;

[0148] Step E: Lifting safety analysis

[0149] First, the crane's anti-overturning stability standard is

[0150] ∑M=K G ·M G +K Q ·M Q +K W ·M W ≥0 (9);

[0151] Where, ∑M is the anti-overturning moment, K G is the weighted coefficient of self-weight, which is 1; K Q K is the weighted coefficient of lifting load, which is 1.15; W is the wind load weighting coefficient, which is 1; M G 、M Q 、M W The moments of the crane's deadweight, lifting load and wind load on the overturning edge respectively.

[0152] With the help of a multi-machine collaborative lifting system for the box girder of the highway bridge crossing the railway cutting under construction.

[0153] A multi-machine coordinated lifting system for box girders of a highway bridge that crosses a railway cutting under construction, comprising a gun carriage for transporting the box girders to a lifting area, a roadbed crane C, a roadbed crane B and a lifting auxiliary device installed on the box girders, which are arranged between a beam yard and a bridge site; and lifting points A and B are provided at both ends of the lifting auxiliary device.

[0154] Lifting auxiliary devices include:

[0155] A supporting device, used for being sleeved on the box beam;

[0156] Balance monitoring device, used to monitor whether the box girder is level during the lifting process;

[0157] Process base, used to support the box beam for easy installation;

[0158] Mobile lifting lug device, used to change the position of the lifting suspension.

[0159] The support device comprises two side support frames and an intermediate support frame between the two side support frames; the two side support frames and the intermediate support frame are connected as a whole through a side connecting rod; a side center notch corresponding to the box beam is provided on the side support frame and the intermediate support frame; a side stopper for placing the box beam to slide out longitudinally is installed on the side center notch of the side support frame through bolts, and a side fixing hanging ring is provided on both the side support frames and the intermediate support frame;

[0160] The balance monitoring device comprises a monitoring lifting guide frame vertically mounted on a supporting device; a monitoring hinge shaft is lifted and lowered in the monitoring lifting guide frame, a monitoring lower pressure head is provided at the lower end of the monitoring hinge shaft for pressing on the upper surface of the box beam, a monitoring side vertical frame is vertically provided on one side of the monitoring lower pressure head, a monitoring horizontal vertical cross bar is vertically provided on the monitoring side vertical frame, and a monitoring swing bar is swingably provided at the lower end of the monitoring horizontal vertical cross bar; a vertical marking line is provided on the monitoring side vertical frame, and whether the box beam is horizontal can be judged by observing the swing of the monitoring swing bar relative to the vertical marking line;

[0161] The movable lifting lug device comprises a lifting lug longitudinal movable frame longitudinally arranged on the supporting device; the A lifting point and the B lifting point are arranged at two ends of the lifting lug longitudinal movable frame; a movable lifting lug seat is longitudinally moved by a push rod on the lifting lug longitudinal movable frame;

[0162] A lifting eye B end limit block is provided at the B lifting point, and a lifting eye B end transverse stop bar for blocking the movement of the movable lifting eye seat is provided at the output end of the lifting eye B end limit block;

[0163] The structure of the A lifting point is the same as that of the B lifting point; a transverse stop bar at the A end of the lifting eye for blocking the movement of the movable lifting eye seat is arranged at the output end of the A lifting point.

[0164] The auxiliary positioning device comprises an auxiliary bracket arranged on the supporting device, an auxiliary rotating shaft driven by a motor is arranged on the auxiliary bracket, an auxiliary swing arm driven by the auxiliary rotating shaft to swing, and a traction rope is swingingly connected under the auxiliary swing arm;

[0165] A roller is arranged at the bottom of the supporting device;

[0166] A winch is provided on the gun carriage, and a traction rope is connected to the winch;

[0167] The winch pulls the box girder axially and approaches the adjacent connecting body through the traction rope.

[0168] The present invention realizes the construction of the box girder 1 based on the crane C2 and the crane B3, and ingeniously realizes the automatic change of the lifting point, realizes the installation of the middle span 5 and the side span 6, and realizes the installation and lifting through the ingenious design of the cutting top station 7. The existing road 8 at the bridge head is pulled into place, and the A lifting point 9 and the B lifting point 10 are lifted. The lifting auxiliary device 11 is used as the invention point to realize the support of the box girder and avoid the sinking and deformation of the box girder caused by the traditional lifting. Thus, the support device 12 frame is preferably a detachable split structure with good versatility and adjustable length. It can organize the force and avoid deformation. The balance monitoring device 13 can use swinging to realize the visual observation of the angle with the naked eye. The process base 14 is convenient for off-ground support and easy to assemble. The movable lifting ear device 15 can adjust the position of the lifting wire rope. The auxiliary positioning device 16 can realize automatic swing to avoid manual hook replacement. It is connected to the winch through a wire rope to realize the longitudinal positioning of the box beam, thereby solving the technical problem of inconvenient docking between box beams. The monitoring lifting guide frame 23 realizes guidance, and the monitoring hinge shaft 24 has good compatibility, so that the monitoring lower pressure head 25 is pressed on the upper surface of the box beam, thereby realizing the verticality of the monitoring side vertical frame 26, and the monitoring swing rod 28 (always in a vertical state) swinging on the monitoring horizontal vertical cross bar 27 is used to realize the vertical and vertical angle adjustment.

Claims

1. A multi-machine collaborative lifting process for a box girder of a highway bridge over a railway cutting under construction, characterized in that: The process uses a cutting top crane A (40) located at the top of the roadbed slope and a roadbed crane C (2) and a roadbed crane B (3) at the bridge site hoisting area. A precast beam yard is set up at the cutting top beside the bridge site, and a gun carriage (38) for transporting the box beam (1) to the hoisting area is set up between the precast beam yard and the bridge site. A lifting point (9) and a lifting point (10) are preset at both ends of the box beam (1); an intermediate span (5) is preset in the middle of the bridge pier (4), and side spans (6) are provided at both ends of the intermediate span (5), and the cutting top working position is at the top of the roadbed slope; The process comprises the following steps; Step 1: Execute the lifting plan for the side span box girder. First, the roadbed crane C (2) and the roadbed crane B (3) are both located on the roadbed, and the top-of-cut crane A (40) is located at the top of the pad. The position is determined according to the operating conditions and the performance parameters of the crane. Then, the box girder (1) is delivered by the gun carriage (38) from the existing road (8) at the bridge head. When the left end of the box girder approaches the abutment, the top-of-cut crane A (40) hooks the left end of the box girder to the lifting point A (9) for trial lifting. After confirming that it is safe and stable, the lifting begins. The gun carriage (38) is pushed back from the existing road (8) at the bridge head to deliver the box girder. 8) The tail is evacuated; secondly, the cutting top crane A (40) cooperates with the gun carriage (38) to continue to deliver the box girder in translation; thirdly, when the gun carriage (38) approaches the abutment, the roadbed crane B and the roadbed crane C use the balance beam to hook the left end A lifting point (9) of the box girder, and the cutting top crane A changes the hook and hooks the right end B lifting point (10) of the box girder (1). After the lifting point conversion is completed, the gun carriage (38) is evacuated; later, the roadbed cranes B, C and the cutting top crane A work together to translate the box girder into place; Step 2, execute the lifting plan of the middle span box girder; first, use the gun carriage to push and deliver the box girder along the existing road at the bridge head and the erected side span box girder; then, when the left end of the hoisted box girder (1) approaches the left end of the right span box girder in step 1, the roadbed work station crane B hooks the left end of the box girder A lifting point (9), and the gun carriage tail withdraws; secondly, the roadbed work station crane B cooperates with the gun carriage to continue to translate and deliver the box girder; again, when the gun carriage approaches the left end of the right span box girder in step 1, the roadbed work station crane C hooks the left end of the box girder lifting point A lifting point (9), and the roadbed work station crane B changes the hook and hooks the right end of the box girder B lifting point (10), and after the lifting point conversion is completed, the gun carriage withdraws; Later, the roadbed cranes B and C worked together to move the box girder into place; Before step one include: Step A, determine the position of the hanging point, based on the distance between the hanging point and the two ends of the object and the box beam's own moment balance as the calculation standard, that is, to ensure that the positive and negative bending moments at the hanging points are equal, the two hanging points are respectively set at 0.2L from the beam end, and the hanging points are wire rope tied pocket hanging type; Step B, crane selection; First, determine the calculated load G of the object to be hoisted j G j =K1K2T nZ (1)? Where, T nz It is the sum of the weight of the object being hoisted, the lifting lugs and the weight of the rigging; K1 is the dynamic load coefficient, which is taken as 1.1; K2 is the unbalanced coefficient of the double crane hoisting, which is taken as 1.2; Step B1, selecting roadbed crane B and roadbed crane C; First, the lifting capacity requirements of roadbed crane B and roadbed crane C are the same, both G jBC =K1K2G0 (3.1); In the formula, G0 is the sum of the weight of the load, the lifting lugs and the rigging weight shared by the crane; K1 is the dynamic load coefficient, which is taken as 1.1; K2 is the unbalanced coefficient of the double crane lifting, which is taken as 1.2; Then, determine the operating range R of the roadbed crane B B , lifting height H B ; The operating range R of the roadbed crane C C , lifting height H C Same as H B ; According to G jBC , R B , H B , R C , H C , considering that cranes B and C are of the same model, refer to the crane performance parameters to determine the roadbed crane B and roadbed crane C; Step B2, selection of crane A for the cutting top station; First, according to the performance parameters of roadbed crane B and roadbed crane C; according to the performance parameters of truck crane, determine the operating conditions to select the lifting weight G, arm length L, lifting height H, and corresponding maximum working range R; Then, it can be calculated that to realize the lifting point conversion of cranes B and C and crane A in working condition CB2, the minimum working range R of crane A is required A ; The lifting capacity requirement of crane A is calculated in the same way as in formula (3.1), and Gj is obtained A , refer to the crane performance parameters and select the truck crane; Step C, wire rope selection; First of all, the use standard of thick diameter wire rope is Where D min is the minimum diameter of the hoisting wire rope; Q is the weight of the crane; β is the load distribution coefficient, which is 66%; the unbalanced coefficient K for double crane lifting is 1.2, and the unbalanced coefficient K for multi-crane lifting is 1.

2. Q = 80.6 × 1.2 = 96.7 t; Then, according to formula (2), D min ; Secondly, the force F of the single-strand wire rope on one side N Calculate according to the following formula In the formula, 1.05 is the angle coefficient; Q is the weight borne by the crane sling; Total pulling force WITH n =K×F N (4); In the formula, K is the safety factor of the hoisting wire rope, which is 10; Secondly, the steel wire rope is a fiber core, so its breaking tension is converted. The conversion formula is: In the formula, α is the conversion coefficient, which is 1.226, and the breaking force is calculated as Where Z is the breaking force; F C is the tensile strength of the wire rope, take 1670kg / mm 2 ; Step D, calculate the bearing capacity of the outrigger foundation, First, from the lifting plan, we know that the load-bearing capacity of cranes C and B is equal; the total load-bearing capacity N of the foundation of a single crane is calculated as follows: In the formula, γ G , γ Q is the static and dynamic load combination coefficient, which are 1.2 and 1.4 respectively; G0 is the sum of the weight of the crane, the overload counterweight, the sling and the rigging weight. For cranes B and C of the same model, G L is the weight of the box girder; Then, assuming that the four outriggers of the crane are evenly stressed, the average compressive stress exerted on the foundation by each outrigger is Where A is the area of ​​the crane leg steel pad (m 2 ); Secondly, considering the construction of beam erection over the railway, taking 1.2 times the safety factor, the bearing capacity requirement of the work site is f a ≥1.2p, if the bearing capacity of the on-site foundation does not meet the above requirements, compaction or replacement can be used; Step E: hoisting safety analysis; First, the crane's anti-overturning stability standard is ∑M=K G ·M G +K Q ·M Q +K W ·M W ≥0 (9); Where, ∑M is the anti-overturning moment, K G is the weighted coefficient of self-weight, which is 1; K Q K is the weighted coefficient of lifting load, which is 1.15; W is the wind load weighting coefficient, which is 1; M G 、M Q 、M W The moments of the crane's deadweight, lifting load and wind load on the overturning edge respectively.

2. A multi-machine coordinated lifting system for box girders of highway bridges that cross the railway cutting under construction, characterized in that: It includes a gun carriage for transporting the box beam to the lifting area, a roadbed crane C, a roadbed crane B and a lifting auxiliary device installed on the box beam, which are arranged between the beam yard and the bridge site; There are A lifting point and B lifting point at both ends of the lifting auxiliary device; Lifting auxiliary devices include: A supporting device, used for being sleeved on the box beam; Balance monitoring device, used to monitor whether the box girder is level during the lifting process; Process base, used to support the box beam for easy installation; Mobile lifting lug device, used to change the position of the hoisted suspension; The support device comprises two side support frames and an intermediate support frame between the two side support frames; the two side support frames and the intermediate support frame are connected as a whole through a side connecting rod; a side center notch corresponding to the box beam is provided on the side support frame and the intermediate support frame; a side stopper for placing the box beam to slide out longitudinally is installed on the side center notch of the side support frame through bolts, and a side fixing hanging ring is provided on both the side support frames and the intermediate support frame; The balance monitoring device comprises a monitoring lifting guide frame vertically mounted on a supporting device; a monitoring hinge shaft is lifted and lowered in the monitoring lifting guide frame, a monitoring lower pressure head is provided at the lower end of the monitoring hinge shaft for pressing on the upper surface of the box beam, a monitoring side vertical frame is vertically provided on one side of the monitoring lower pressure head, a monitoring horizontal vertical cross bar is vertically provided on the monitoring side vertical frame, and a monitoring swing bar is swingably provided at the lower end of the monitoring horizontal vertical cross bar; a vertical marking line is provided on the monitoring side vertical frame, and whether the box beam is horizontal can be judged by observing the swing of the monitoring swing bar relative to the vertical marking line; The movable lifting lug device comprises a lifting lug longitudinal movable frame longitudinally arranged on the supporting device; the A lifting point and the B lifting point are arranged at two ends of the lifting lug longitudinal movable frame; a movable lifting lug seat is longitudinally moved by a push rod on the lifting lug longitudinal movable frame; A lifting eye B end limit block is provided at the B lifting point, and a lifting eye B end transverse stop bar for blocking the movement of the movable lifting eye seat is provided at the output end of the lifting eye B end limit block; The structure of the A lifting point is the same as that of the B lifting point; a transverse stop bar at the A end of the lifting eye is provided at the output end of the A lifting point to block the movement of the movable lifting eye seat; The auxiliary positioning device comprises an auxiliary bracket arranged on the supporting device, an auxiliary rotating shaft driven by a motor is arranged on the auxiliary bracket, an auxiliary swing arm driven by the auxiliary rotating shaft to swing, and a traction rope is swingingly connected under the auxiliary swing arm; A roller is arranged at the bottom of the supporting device; A winch is provided on the gun carriage, and a traction rope is connected to the winch; The winch pulls the box girder axially to position it close to the adjacent connecting body through the traction rope; Used to support the process described in claim 1.

Citation Information

Patent Citations

  • Hoisting method and hoisting device for concrete prefabricated box beam

    CN103437298A

  • High-speed rail operating line spanning beam body hoisting and separating method

    CN106276602A

  • Self-leveling nuclear power station construction matched hoisting structure