A tunnel expansion pre-reinforcement system and reinforcement method suitable for shallow buried tunnels
By using pre-reinforcement systems such as supporting frames and height adjustment devices in tunnel expansion construction, stress adjustment and support are achieved, solving the problem of high construction risks in the existing technology, reducing safety hazards and preventing excessive stress release from excessive stress .
Patent Information
- Application Number
- CN202011251379.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-11-09
- Publication Date
- 2024-11-26
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing technology lacks active reinforcement equipment in the construction of shallow buried tunnel expansion, resulting in the inability to prevent construction risks and bring safety hazards to construction personnel and machinery.
Provide a tunnel expansion pre-reinforcement system including a support frame, a height adjustment device, a web and a walking mechanism. Stress adjustment and support are achieved through articulation and hydraulic jacks, and the leading and rear continuous variable stress extension induction adjustment is adopted, and the front and rear continuous variable stress extension induction adjustment is adopted. Intervention and protection.
Active intervention and protection of surrounding rocks during the expansion process is achieved, blasting stress is balanced, stress release is prevented, structural stability is protected, construction risks are reduced, and collapse accidents are avoided.
Smart Images

Figure CN112253205B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of underground engineering and tunnel engineering, and in particular to a tunnel expansion pre-reinforcement system and a reinforcement method suitable for shallow buried tunnels. Background Art
[0002] The demand for expansion or reconstruction of existing tunnels can be roughly divided into those based on increased traffic volume, additional ventilation or escape space, and maintenance and reinforcement of old tunnels.
[0003] As the excavation construction progresses, the initial support of the excavation section is continuously implemented. The constraints provided by the surrounding rock and supporting structure inside the tunnel change accordingly, the surrounding rock stress is adjusted accordingly, and the direction and magnitude of the deformation of the initial support structure are also constantly changing. During the excavation construction process, it is necessary to ensure that the initial support structure after the excavation can bear the corresponding surrounding rock pressure. Therefore, ensuring the force safety of the initial support structure of the excavation section can ensure the construction safety of the entire tunnel.
[0004] For the expansion of existing tunnels, there is no active reinforcement equipment at home and abroad, only the traditional flexible support of geological pre-intervention. In the tunnel expansion stage, advanced anchor rods and advanced pipe sheds are used for pre-reinforcement, active intervention, and passive protection. There are construction risks that cannot be controlled in advance, and adjustments are made while working, and passive operations bring great safety risks to construction personnel and machinery. Summary of the invention
[0005] The purpose of the present invention is to overcome the problems in the prior art and to provide a pre-reinforcement system and a reinforcement method suitable for shallow buried tunnel expansion.
[0006] The present invention provides a tunnel expansion pre-reinforcement system suitable for shallow burial, comprising a support frame, comprising a first door-type support, a second door-type support and a third door-type support, wherein the second door-type support and the third door-type support are respectively arranged on both sides of the first door-type support and are parallel to the first door-type support, the second door-type support is hinged to the first door-type support through a hinge, and the third door-type support is fixedly connected to the first door-type support;
[0007] A height adjustment device is arranged on the top of the first door-type bracket, the second door-type bracket and the third door-type bracket, and a mounting frame is arranged on the height adjustment device, and a plurality of first hydraulic jacks are arranged on the mounting frame;
[0008] The web comprises two vertical parts and a dome part, the dome part is located on the top of the two vertical parts, the vertical parts are parallel to the columns of the first door-type bracket, the second door-type bracket and the third door-type bracket, and a plurality of horizontally arranged second hydraulic jacks are arranged between the side web and the columns, and the second hydraulic jacks are fixed on the columns; the first hydraulic jack is arranged between the dome part and the mounting frame;
[0009] The walking mechanism is arranged at the bottom of the first door-type bracket, the second door-type bracket and the third door-type bracket, and is used to move the supporting frame.
[0010] Preferably, the first door-type bracket, the second door-type bracket and the third door-type bracket are all provided with obliquely arranged reinforcing ribs at their corners.
[0011] Preferably, the height adjustment device is a hydraulic lifting mechanism.
[0012] Preferably, the first door-type bracket, the second door-type bracket and the third door-type bracket are all welded with 50 channel steel.
[0013] The present invention also provides the above reinforcement method applicable to the shallow buried tunnel expansion pre-reinforcement system, which comprises the following steps:
[0014] S101. Detailed determination of the cross-sectional dimensions of the existing tunnel profile, and pre-assemble and weld a tunnel expansion pre-reinforcement system in proportion to the cross-sectional dimensions of the existing tunnel based on the existing tunnel profile;
[0015] S102, before excavation, the tunnel expansion pre-reinforcement system is moved into the excavation line, and the second hydraulic jack is adjusted to make the outer wall of the vertical part of the web fully contact with the inner wall of the existing tunnel contour line, and the arch part is kept in full contact with the top rock surface;
[0016] S103, the tunnel expansion section is excavated in stages: first, the upper guide is excavated to H = 1.7-2.1m, and the upper guide is supported by anchor spraying; the middle guide is excavated to H = 3.0m, and the middle guide is supported by anchor spraying; the lower guide is excavated to H = 3.0m, and the lower guide is supported by anchor spraying, and then the secondary lining concrete is laid, and finally the invert backfill road surface construction;
[0017] S104. After the tunnel expansion section is completed, slag is discharged, and support is followed up in time, after the next ring of drilling, slag blowing, and explosive charging are completed, the pre-reinforcement system will be withdrawn outside the detonation line to avoid damage.
[0018] Preferably, the arch portion maintains full contact with the top rock surface during the excavation stage. If deformation or cracking of the top rock surface is found, advance support should be strengthened to ensure stable excavation.
[0019] Preferably, the length of the step in step S102 is 4.5m. During construction, the length and number of steps can be appropriately adjusted according to the stability of the surrounding rock. At the same time, according to the initial support construction conditions, a combination of long and short arches are adopted, and the construction is staggered. The length of the arch should not be greater than 2 arch frames.
[0020] Compared with the prior art, the present invention has the following beneficial effects:
[0021] By adopting the pre-reinforcement system of the present invention, a graded reaction force of the pre-compressed rock mass is applied to the existing section to balance the blasting stress to expand the damaged rock mass. The front consolidation section serves as a rigid support point, and the rear section adopts a hinged adjustment stress transfer point to adjust and change with the blasting stress and the reaction force of the surrounding rock, thus combining active intervention protection and passive unloading balance into a dynamic load-bearing device.
[0022] The tunnel expansion pre-reinforcement method of the present invention is applicable to various underground structures and the expansion construction of existing tunnels. When the cross section of the existing tunnel cannot meet the use requirements, the tunnel expansion is adopted at the old site. Both concentric radial tunnel expansion and unilateral tunnel expansion can adopt this system to actively reinforce the expansion section to prevent collapse accidents from occurring during the tunnel expansion process.
[0023] The present invention adopts the pre-reinforcement system with continuous variable leading and trailing, stress extension induction adjustment, and active intervention to prevent excessive stress release and damage to the structure itself. During the construction process, it actively protects the stability of the existing structure, and achieves the ability of controllable and dynamic adjustment of concentrated stress in the later excavation section. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a front view of the schematic diagram of the hole enlarging and reinforcing system of the present invention;
[0025] Figure 2 is a side view of the support frame of the present invention;
[0026] Figure 3 It is a side view of the schematic diagram of the construction process of the present invention;
[0027] Figure 4 It is a front view of a schematic diagram of the construction process of the present invention.
[0028] Description of reference numerals:
[0029] 1. Support frame, 11. First portal bracket, 12. Second portal bracket, 13. Third portal bracket, 2. Height adjustment device, 3. Mounting frame, 4. First hydraulic jack, 5. Web, 51. Vertical part, 52. Arch part, 6. Second hydraulic jack, 7. Traveling mechanism, 8. Articulated part, 9. Bearing concrete. DETAILED DESCRIPTION
[0030] The following is combined with Figure 1-4 , the specific implementation of the present invention is described in detail, but it should be understood that the protection scope of the present invention is not limited by the specific implementation. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0031] The present invention provides a tunnel expansion pre-reinforcement system suitable for shallow buried tunnels, comprising:
[0032] A support frame 1, comprising a first door-shaped support 11, a second door-shaped support 12 and a third door-shaped support 13, wherein the second door-shaped support 12 and the third door-shaped support 13 are respectively arranged on both sides of the first door-shaped support 11 and are parallel to the first door-shaped support 11, the second door-shaped support 12 is hinged to the first door-shaped support 11 through a hinge 8, and the third door-shaped support 13 is fixedly connected to the first door-shaped support 11; a height adjustment device 2, arranged on the top of the first door-shaped support 11, the second door-shaped support 12 and the third door-shaped support 13, the height adjustment device 2 is provided with a mounting frame 3, and the mounting frame 3 is provided with a plurality of first hydraulic jacks 4;
[0033] The web 5 includes two vertical parts 51 and a dome part 52. The dome part 52 is located on the top of the two vertical parts 51. The vertical parts 51 are parallel to the columns of the first door-type bracket 11, the second door-type bracket 12 and the third door-type bracket 13. A plurality of horizontally arranged second hydraulic jacks 6 are arranged between the side web and the columns. The second hydraulic jacks 6 are fixed on the columns. The first hydraulic jack 4 is arranged between the dome part 52 and the mounting frame 3.
[0034] The walking mechanism 7 is disposed at the bottom of the first door-shaped bracket 11 , the second door-shaped bracket 12 and the third door-shaped bracket 13 , and is used to move the support frame 1 .
[0035] Since the second door-type bracket 12 is hinged to the first door-type bracket 11 through the hinge 8, and the third door-type bracket 13 is fixedly connected to the first door-type bracket 11, the second door-type bracket 12 can produce displacement changes and can be adjusted according to the stress change, while the third door-type bracket 13 is a rigid support. The height adjustment device (2) can adjust the first hydraulic jack 4 to a predetermined position, and the first hydraulic jack 4 can firmly support the dome part of the web. The vertical part 51 of the web 5 abuts against the cave wall, and is supported and reinforced by multiple second hydraulic jacks 6.
[0036] Preferably, the first door-shaped bracket 11, the second door-shaped bracket 12 and the third door-shaped bracket 13 are all provided with obliquely arranged reinforcing ribs at their corners, in order to increase the stability of each door-shaped bracket.
[0037] Preferably, the height adjustment device 2 is a hydraulic lifting mechanism.
[0038] Preferably, the first door-type bracket 11, the second door-type bracket 12 and the third door-type bracket 13 are all welded with 50 channel steel.
[0039] It should be noted that the hinge 8 can be realized by opening a hole at the connection between the steel plates and then arranging a movable steel rod in the hole.
[0040] The above reinforcement method applicable to the shallow buried tunnel expansion pre-reinforcement system comprises the following steps:
[0041] S101. Detailed determination of the cross-sectional dimensions of the existing tunnel profile, and pre-assemble and weld a tunnel expansion pre-reinforcement system in proportion to the cross-sectional dimensions of the existing tunnel based on the existing tunnel profile;
[0042] S102, before excavation, the tunnel expansion pre-reinforcement system is moved into the excavation line, and the second hydraulic jack 6 is adjusted so that the outer wall of the vertical part 51 of the web is in full contact with the inner wall of the existing tunnel contour line, and the arch part 52 is in full contact with the top rock surface;
[0043] S103, the tunnel expansion section is excavated in stages: first, the upper guide is excavated to H = 1.7-2.1m, and the upper guide is supported by anchor spraying; the middle guide is excavated to H = 3.0m, and the middle guide is supported by anchor spraying; the lower guide is excavated to H = 3.0m, and the lower guide is supported by anchor spraying, and then the secondary lining concrete is laid, and finally the invert backfill road surface construction;
[0044] S104. After the tunnel expansion section is completed, slag is discharged, and support is followed up in time, after the next ring of drilling, slag blowing, and explosive charging are completed, the pre-reinforcement system will be withdrawn outside the detonation line to avoid damage.
[0045] Preferably, the arch portion 52 maintains full contact with the top rock surface during the excavation stage. If deformation or cracking of the top rock surface is found, advance support should be strengthened to ensure stable excavation.
[0046] Preferably, the length of the stepped steps is 4.5m. During construction, the length and number of steps can be appropriately adjusted according to the stability of the surrounding rock. At the same time, according to the initial support construction conditions, a combination of long and short arches are adopted, and the construction is staggered. The length of the arch should not be greater than 2 arch frames.
[0047] Example background: During the reconstruction of the Taihang Mountain Tourist Highway, the Transportation Bureau of Yu County, Yangquan City, expanded the existing shallow buried section. During the expansion process, the pre-reinforcement system of the present invention was used to reinforce and support the existing cave body to achieve secondary stress redistribution. It can make adjustments and changes according to the blasting stress and the reaction force of the surrounding rock, actively intervene in protection, and reduce the safety risks of construction.
[0048] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A reinforcement method for a shallow tunnel expansion pre-reinforcement system, It is characterized in that include: The pre-reinforcement system for shallow tunnel expansion adopted by this method is as follows: A support frame (1), comprising a first door-shaped support (11), a second door-shaped support (12) and a third door-shaped support (13), wherein the second door-shaped support (12) and the third door-shaped support (13) are respectively arranged on both sides of the first door-shaped support (11) and are parallel to the first door-shaped support (11), the second door-shaped support (12) is hingedly connected to the first door-shaped support (11) via a hinge (8), and the third door-shaped support (13) is fixedly connected to the first door-shaped support (11); A height adjustment device (2) is arranged on the top of the first door-shaped bracket (11), the second door-shaped bracket (12) and the third door-shaped bracket (13); a mounting frame (3) is arranged on the height adjustment device (2); and a plurality of first hydraulic jacks (4) are arranged on the mounting frame (3); The web (5) comprises two vertical parts (51) and a dome part (52), wherein the dome part (52) is located on the top of the two vertical parts (51), the vertical parts (51) are parallel to the columns of the first door-type bracket (11), the second door-type bracket (12) and the third door-type bracket (13), and a plurality of horizontally arranged second hydraulic jacks (6) are arranged between the vertical parts (51) and the columns, and the second hydraulic jacks (6) are fixed on the columns; the first hydraulic jack (4) is arranged between the dome part (52) and the mounting frame (3); A walking mechanism (7) is arranged at the bottom of the first door-shaped bracket (11), the second door-shaped bracket (12) and the third door-shaped bracket (13), and is used to move the support frame (1); The reinforcement method of the above-mentioned tunnel expansion pre-reinforcement system applicable to shallow buried tunnels comprises the following steps: S101. Detailed determination of the cross-sectional dimensions of the existing tunnel profile, and pre-assemble and weld a tunnel expansion pre-reinforcement system in proportion to the cross-sectional dimensions of the existing tunnel based on the existing tunnel profile; S102, before excavation, the tunnel expansion pre-reinforcement system is moved into the excavation line, and the second hydraulic jack (6) is adjusted so that the outer wall of the vertical part (51) of the web is in full contact with the inner wall of the existing tunnel contour line, and the arch part (52) is in full contact with the top rock surface; S103, the tunnel expansion section is excavated in stages: first, the upper guide is excavated to H=1.7-2.1m, and the upper guide is supported by anchor spraying; the middle guide is excavated to H=3.0m, and the middle guide is supported by anchor spraying; the lower guide is excavated to H=3.0m, and the lower guide is supported by anchor spraying, and then the secondary lining concrete is laid, and finally the invert backfill road surface construction; S104. After the tunnel expansion section is completed, slag is discharged, and support is followed up in time, after the next ring of drilling, slag blowing, and explosive charging are completed, the pre-reinforcement system will be withdrawn outside the detonation line to avoid damage.
2. The reinforcement method for a shallow tunnel expansion pre-reinforcement system according to claim 1, It is characterized in that The first door-shaped bracket (11), the second door-shaped bracket (12) and the third door-shaped bracket (13) are all provided with obliquely arranged reinforcing ribs at their corners.
3. The reinforcement method for a shallow tunnel expansion pre-reinforcement system according to claim 1, It is characterized in that The height adjustment device (2) is a hydraulic lifting mechanism.
4. The reinforcement method for a shallow tunnel expansion pre-reinforcement system according to claim 1, It is characterized in that The first door-shaped bracket (11), the second door-shaped bracket (12) and the third door-shaped bracket (13) are all welded using 50 channel steel.
5. The reinforcement method for a shallow tunnel expansion pre-reinforcement system according to claim 1, It is characterized in that During the excavation stage, the arch portion (52) maintains full contact with the top rock surface. If deformation or cracking of the top rock surface is found, advance support should be strengthened to ensure stable excavation.
6. The reinforcement method for a shallow buried tunnel expansion pre-reinforcement system according to claim 1, It is characterized in that In step S102, the length of the step is 4.5m. During construction, the length and number of steps can be adjusted according to the stability of the surrounding rock. At the same time, according to the initial support construction conditions, a combination of long and short arches are adopted, and the construction is staggered. The length of the arch should not be greater than 2 arch frames.