A method for filling roadbed with recycled resources for road reconstruction and expansion

Through the resource-based filling method of construction waste, the problems of construction waste utilization and roadbed settlement in road widening have been solved, the effects of policy compliance, engineering cost and environmental protection have been achieved, and the scope of green protection application has been expanded.

CN114481735BActive Publication Date: 2024-11-26XIAN HIGHWAY INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210203485.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-03
Publication Date
2024-11-26
Estimated Expiration
2042-03-03

AI Technical Summary

Technical Problem

The existing road widening methods fail to effectively utilize the construction waste resources demolished during renovation and expansion, resulting in high environmental pollution and engineering costs, and uneven settlement of new and old roadbeds, resulting in frequent road diseases.

Method used

The roadbed regeneration and filling is carried out by resource utilization of construction waste, including surface cleaning, compaction, slope excavation, coarse-grained recycled filler backfilling, drainage pipe burial, slope masonry, lime-improved dirt roadbed backfilling, geogrid room grass planting, etc. Steps to form a stable roadbed structure.

Benefits of technology

It has achieved beneficial practices of policy compliance, engineering cost and engineering operability, solved the problem of roadbed filling, combined masonry and grass planting protection, reduced construction investment and protected the ecological environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114481735B_ABST
    Figure CN114481735B_ABST
Patent Text Reader

Abstract

The invention discloses a method for filling roadbed with recycled resources for road reconstruction and expansion. The method mainly treats the original roadbed slope and the widening section foundation, then steps the original roadbed slope, backfills and compacts it in layers with coarse-grained recycled filler, and simultaneously lays stone blocks on the edge, fills the roadbed, and finally uses geocells to cultivate soil and plant grass on the slope. The method disclosed by the invention has a simple construction process, is easy to operate, speeds up construction progress, reduces construction investment, meets quality requirements, and also plays a positive role in protecting the ecological environment, and has a wide application prospect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of road engineering, and in particular to a method for filling roadbed with recycled resources for road reconstruction and expansion. Background Art

[0002] In recent years, with the rapid development of my country's economy and the rapid growth of traffic volume, the main highways built in the early days have all reached varying degrees of saturation. Therefore, there will be more and more demand for the widening and reconstruction of highways. The road widening method is the most widely used road reconstruction and expansion method at this stage. The conventional widening method mainly focuses on the splicing of the new and old roadbeds, but does not explore the resource utilization of construction waste removed during reconstruction and expansion. Compared with conventional new highway construction projects, from a technical perspective, the most critical technical issue in road widening projects is to avoid the occurrence of longitudinal and transverse cracks on the road surface after the road is opened to traffic due to uneven settlement between the new and old roadbeds; from a policy-oriented perspective, how to use the concrete, mortar-laid slabs and other masonry materials such as protection, drainage, bridge and culvert structures removed during road reconstruction and expansion is an inevitable trend to achieve greening of the industry.

[0003] The demolition of protective and drainage facilities and bridge and culvert structures in the road reconstruction and expansion project generated a large amount of construction waste such as concrete blocks, mortar-laid slabs and waste bricks. Construction waste not only affects the living environment, but also occupies land resources, pollutes the natural environment, and seriously restricts the healthy development of engineering construction. The masonry materials demolished in the road reconstruction and expansion have a relatively pure source of materials. Construction waste such as waste concrete blocks and waste bricks has good strength and water stability. It is a solid waste with resource attributes. After recycling, classification and treatment, it can produce new building materials for recycling and reuse, thereby achieving effective resource conservation and protection of the ecological environment.

[0004] The present invention combines the above two aspects and adopts the resource utilization of construction waste to carry out roadbed widening and filling, which is of great significance both in terms of building a resource-intensive society and achieving sustainable development of the industry, and realizes the beneficial practice of the trinity of policy compliance, project cost and project operability. Summary of the invention

[0005] In view of the shortcomings of the above problems, the present invention provides a method for filling roadbed with renewable resources for road reconstruction and expansion, the method comprising:

[0006] Step 1: Clear and compact the original roadbed slope and the original foundation of the widened section;

[0007] Step 2: After clearing and compacting, the original roadbed slope is excavated from bottom to top in the form of steps;

[0008] Step 3: After the slope excavation is completed, backfill with coarse-grained recycled filler;

[0009] Step 4: bury the drainage pipe at the edge of the newly laid roadbed;

[0010] Step 5: Carry out slope paving on the edge of the newly laid roadbed;

[0011] Step 6: After the coarse-grained recycled filler and the edges are stacked to the bottom of the roadbed, the roadbed is backfilled;

[0012] Step 7: Set up geocells on the newly laid slope and plant grass in the geocells;

[0013] Step 8: Lay the pavement structure layer.

[0014] As a further improvement of the present invention, step one is specifically: clearing the original roadbed slope and the original foundation of the widened section, removing the surface humus, grass roots and domestic garbage, and fully compacting the original foundation with a compaction degree of not less than 90%.

[0015] As a further improvement of the present invention, step two is specifically as follows: after clearing and compacting, the original roadbed slope is excavated from bottom to top, and the steps have an inward slope to enhance the connection between the new and old roadbeds; the slope is not less than 2%; and the step excavation width is not less than 200 cm.

[0016] As a further improvement of the present invention, in step three: the coarse-grained recycled filler is the waste concrete blocks and mortar-laid stone blocks removed during the renovation and expansion, which are crushed into recycled aggregates with a maximum particle size of 50 mm; the content of particles below 0.075 mm in the recycled aggregates is not more than 10%, and the unevenness coefficient is not less than 5%.

[0017] As a further improvement of the present invention, step three also includes: compacting the coarse-grained regenerated filler.

[0018] As a further improvement of the present invention, the compaction process is layered compaction using large mechanical vibration.

[0019] As a further improvement of the present invention, the layer thickness is controlled at 25-35 cm; and the compaction degree of the coarse-grained recycled granular material after compaction is not less than 93%.

[0020] As a further improvement of the present invention, in step 4: the drainage pipes laid are PVC drainage pipes, and one drainage pipe is set every 200 cm along the route; the aperture of the PVC drainage pipe is not less than 10 cm.

[0021] As a further improvement of the present invention, step five is specifically as follows: stacking blocks of stone within a width range of 100cm to 200cm on the edge of the newly laid roadbed; the particle size of the blocks of stone is not less than 30cm; and the strength grade of the blocks of stone is not less than mu40.

[0022] As a further improvement of the present invention, in step six: lime-improved soil is used for roadbed backfill; the lime-improved soil has a no-load expansion rate of <1%, no obvious collapse after immersion in water for 72 hours, and a lime-soil content of 8% of the roadbed soil is used; the loose laying thickness of the lime-improved soil building material is 20 cm to 30 cm.

[0023] As a further improvement of the present invention, in step six: the total thickness of the roadbed is 80 cm to 120 cm; the maximum particle size of the roadbed filler is less than 100 mm, the minimum strength CBR of the filler is 8%, and the compaction degree is not less than 96%.

[0024] As a further improvement of the present invention, in step seven: the geocell is a honeycomb three-dimensional grid structure formed by high-strength high-density polyethylene through high-frequency ultrasonic welding or buckling; the geocell product height is 50-250mm, the welding distance is 330-800mm, and the peel strength of the cell weld reaches 1450N / 10cm.

[0025] As a further improvement of the present invention, the specific process of step seven is: manually trimming the slope; measuring and laying out; laying geocell nets; filling and burying; compacting; planting vegetation; covering with non-woven fabrics; and taking compulsory maintenance.

[0026] Compared with the prior art, the present invention has the following beneficial effects:

[0027] 1. The present invention uses construction waste resources to carry out roadbed widening and filling, achieving the beneficial practice of policy compliance, project cost, and project operability.

[0028] 2. The present invention solves the problem of widening roadbed filling without increasing the difficulty of the project, and specifically adopts the masonry materials removed during widening, which is innovative and practical.

[0029] 3. The slope protection of the present invention realizes the combination of masonry and grass planting protection, has excellent landscape effect, is suitable for areas with a lack of fill materials or a large amount of stone, and expands the application scope of green protection.

[0030] 4. The invention has a simple construction process, is easy to operate, speeds up construction progress, reduces construction investment, meets quality requirements, and also plays a positive role in protecting the ecological environment, and has a broad application prospect. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 It is a schematic diagram of the structure of widening a road according to an embodiment of the present invention.

[0032] In the figure:

[0033] 1 Pavement structure layer; 2 Roadbed; 3 Geocell; 4 Block stones; 5 Original roadbed slope; 6 Slope one; 7 Slope two; 8 Drainage pipe; 9 Coarse-grained recycled filler. DETAILED DESCRIPTION

[0034] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] In the description of the present invention, it should be noted that the orientation or positional relationship indicated by the term "on" or the like is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0036] The present invention is further described in detail below in conjunction with the accompanying drawings:

[0037] See also Figure 1 The present invention provides a method for filling roadbed with renewable resources for road reconstruction and expansion, the method comprising:

[0038] Step 1: Clear and compact the original roadbed slope 5 and the original foundation of the widened section. When widening the road for reconstruction and expansion, first clear the original roadbed slope 5 and the original foundation of the widened section, clean up the surface humus, grass roots and domestic garbage, and fully compact the original foundation with a compaction degree of not less than 90%.

[0039] Step 2: After clearing and compacting, the original roadbed slope 5 is excavated from bottom to top, and the slope is excavated in the form of steps. The steps have a certain inward slope to enhance the connection between the new and old roadbeds. The slope is generally not less than 2%, and can generally be controlled at 4%. The excavation width of each step is not less than 200cm, and the height is determined according to the slope.

[0040] Step 3: After the excavation of the slope is completed, the coarse-grained recycled filler 9 is backfilled. The coarse-grained recycled filler 9 is a recycled aggregate with a maximum particle size of 50 mm, which is made by crushing the waste concrete blocks, mortar-laid slabs and stones removed during the renovation and expansion. It has the characteristics of large particle size and low fine particle content. Compared with traditional fine-grained soil roadbed filling materials, it has special compaction characteristics. In addition, the reason for using coarse-grained recycled filler 9 is that, on the one hand, coarse-grained fillers can more easily form a skeleton structure, which is beneficial to the stability of the roadbed and excellent mechanical properties; on the other hand, it reduces the difficulty of processing, thereby reducing the cost of resource utilization of construction waste.

[0041] The directly generated construction waste raw materials have a large size and are not suitable for direct use in roadbed filling. Crushing and screening equipment can be used to process construction waste into granular materials that meet the standard particle size requirements. The maximum particle size of coarse-grained recycled filler 9 is controlled at 50mm, the content of particles below 0.075mm should not be greater than 10%, and the unevenness coefficient should not be less than 5%. Ensure that the coarse-grained recycled materials have good gradation, can meet the requirements of roadbed filling and can block the capillary action of groundwater.

[0042] The compaction process of the coarse-grained regenerated filler 9 is a process of recombining the three-phase system of solid particles, water in the soil and gas in the soil. Under the action of pressure, the solid particles overcome the frictional resistance between the particles, rearrange, embed the particles, and reduce the void volume to form an overall dense structure, thereby improving the overall strength and stability of the roadbed and reducing the plastic deformation under the vehicle load. The compaction process of the present invention is to use large mechanical vibration layered compaction, which includes vibration compaction and layered compaction. Vibration compaction has the characteristics of low amplitude and high frequency. It generates periodic pressure during operation, so that the particles are rearranged from an unstable state to a stable state, so that the construction waste granules have a good compaction effect. At the same time, the coarse-grained regenerated filler 9 of the present invention also adopts layered compaction. The layered filling thickness affects the compaction quality and construction efficiency of the construction waste granules. The smaller the filling thickness, the more effectively the compaction energy can be diffused, so that the overall density is higher and the compaction quality is better. However, reducing the filling thickness will increase the filling layering, affect the construction progress, and increase the construction cost. Generally, the filling thickness increases with the increase of the maximum particle size of construction waste. Under the condition that the compaction function remains unchanged, the layered filling thickness is controlled by the maximum particle size. When the maximum particle size of the crushed granular material does not exceed 50mm, the layered filling thickness is generally controlled at 25-35cm. The compaction degree of coarse-grained recycled granular material after compaction is not less than 93%.

[0043] The new slope formed after backfilling has a certain inward slope, and the slope is generally not less than 3%. Multiple steps can also be set on the new slope as needed.

[0044] Step 4: Drain pipes 8 are buried at the edge of the newly laid roadbed. Since the coarse-grained recycled filler 9 has certain gaps, in order to effectively remove the moisture inside the roadbed, a drainage pipe 8 is buried at the edge of the roadbed. The diameter of the drainage pipe 8 is determined according to the hydrological conditions of the project. Generally, the diameter of the drainage pipe 8 is not less than 10 cm. In addition, a drainage pipe 8 is set every 200 cm along the route. The drainage pipe 8 is preferably a PVC drainage pipe.

[0045] Step 5: Slope masonry is performed on the edge of the newly laid roadbed. Masonry blocks 4 are masonry within a width of 100cm to 200cm on the edge of the newly laid roadbed. The particle size of the blocks 4 is not less than 30cm. The blocks 4 should be regular, and the masonry blocks 4 should be as close and dense as possible, without obvious voids or looseness. Masonry should be carried out from bottom to top, layer by layer. Larger blocks 4 should be masonry below, and the surface of the blocks 4 used for facing should be flat. The strength grade of the blocks 4 should not be less than mu40.

[0046] Step six, after the coarse-grained recycled filler 9 and the edges are stacked to the bottom of the roadbed 2, the roadbed 2 is backfilled. The roadbed 2 is the foundation of the road surface, and bears the load transmitted from the road surface and the gravity of the soil. Therefore, the roadbed 2 material should have good bearing capacity and water stability. In order to ensure the excellent performance of the roadbed 2, cement or lime is generally used to improve the soil within the roadbed range. Since there is an interface between the new and old roadbeds in the reconstruction and expansion project, in order to prevent the surface runoff from infiltrating into the interface through the roadbed gaps and causing roadbed diseases, lime-improved soil is preferably used for backfilling the roadbed 2 in the present invention. Because the lime-improved soil not only has good strength after compaction, but also has water-sealing properties, it can effectively prevent rainwater from seeping in.

[0047] The lime content in lime-improved soil is determined according to the water content of the roadbed soil. The control standards for the lime-mixing ratio are: the strength of the improved soil meets the quality requirements of the roadbed filling; the no-load expansion rate is <1%; there is no obvious collapse after immersion in water for 72 hours. The lime should be fully dissolved and used as soon as possible. The dissolved lime should maintain a certain humidity to avoid flying due to excessive dryness, but it should not be too wet to form a mass. Generally, 8% of the lime-soil content of the roadbed soil can be used. The loose laying thickness of the lime-improved soil filling material is generally 20cm to 30cm. It is leveled on a large area by a bulldozer and leveled locally by manual work. The method of mesh cloth is used for filling. The thickness of the roadbed 2 is generally 80cm to 120cm according to the designed traffic flow. The maximum particle size of the filler of the highway roadbed 2 should be less than 100mm, the minimum strength CBR (California Bearing Ratio) of the filler is 8%, and the compaction degree is not less than 96%.

[0048] Step 7, set up geocell 3 on the newly laid slope surface, and plant grass in geocell 3. Geocell 3 grass slope protection is to fill the inside of geocell 3 with planting soil, and then fix it on the slope surface, so as to allow plants to grow normally and create a good growth environment in places that are not conducive to plant growth. Geocell 3 has the characteristics of high survival rate of spraying greening, smooth and beautiful slope edge, good stability of slope protection, which can make the slope fully greened. Geocell 3 with holes can also increase the drainage performance of the slope, which is suitable for greening protection of different soils and slopes. Geocell 3 and upper and lower soils are combined into an integral multi-layer protection structure through the vegetation root system, thereby solving the problem of slope surface soil stability and slope protection. The geocell 3 slope stability and protection system can isolate, strengthen and restrain the soil and filler above the slope, so as to control the downward movement and sliding of the slope caused by hydraulic and gravity. In addition, the flexible structure of geocell 3 adapts to foundation settlement and deformation, and solves the problem of steep slope soil stability.

[0049] The geocell 3 is a honeycomb three-dimensional grid structure formed by high-strength high-density polyethylene (HDPE) through high-frequency ultrasonic welding or buckling. Since the geocell 3 has many specifications, the specifications of the geocell 3 product used in the present invention are: height 50-250mm, welding distance 330-800mm, and the peel strength of the cell welding point reaches 1450N / 10cm.

[0050] Step 8: Lay the pavement structure layer 1 on the paved roadbed 2. The pavement structure layer 1 should be parallel to the original road surface at the same height.

[0051] The present invention also provides a construction method for geocell grass-planting slope protection, comprising:

[0052] Step 7-1: Manually trim the slope

[0053] The slope and the groove should be trimmed from top to bottom, and the slope should be cleaned and smoothed as much as possible so that the geocell 3 can be closely combined with the slope, which is conducive to the laying of materials and achieves a smooth and beautiful effect.

[0054] Step 7-2: Measure and lay out

[0055] For the construction slope, the "layout" is carried out according to the specified size, and wedge piles are pulled along the horizontal and vertical directions of the slope to ensure that the construction slope is straight and has a beautiful appearance.

[0056] Step 7-3: Laying geocell 3 net

[0057] The fixed geocell 3 is connected to the shoulder structure to facilitate the drainage of road surface water without eroding the slope protection. Pull out the geocell 3 net and lay it flat on the slope. When laying the geocell 3 net, it should start from the shoulder and unfold along the slope to the bottom of the slope. After the top and bottom are fixed with steel bars, first fix the edges on the left and right sides of the tensioned geocell 3 net, and then temporarily fix the bottom of the lowest end with an anchor bar. Then, install and position the grid in the middle of the slope. According to the above method, lay the geocell 3 net in groups one by one. Adjacent groups of geocell 3 nets must be aligned, overlapped on both sides, and connected together with special buckles to connect the ends of adjacent groups of geocell 3 nets into a whole.

[0058] Step 7-4: Filling and burying

[0059] Fill the soil from top to bottom. After the height of the geocell 3 is buried, the thickness of the geocell 3 height needs to be increased upwards.

[0060] Step 7-5: Compact

[0061] After manual raking, the compaction work is completed by machine to prevent displacement. In order to prevent the damage of the completed slope surface by the impact of heavy objects, the potential energy height of the rolling equipment is required to be no more than 1m.

[0062] Step 7-6: Planting vegetation

[0063] According to the requirements, the treated seeds and soil conditioners, pulp fibers, compound fertilizers, and moisturizers are mixed with a certain proportion of clean water, dissolved in a sprayer, and fully stirred mechanically to form a uniform mixture. Then, using the principle of water flow and the action of a high-pressure pump, the mixture is sprayed evenly and at high speed onto the treated slope surface to form a uniform grass seed layer under the protection of the covering. Excess water seeps into the soil, and the fibers and colloids form a translucent moisturizing surface layer.

[0064] Step 7-7: Cover with non-woven fabric

[0065] Cover the grass seeds with non-woven fabric immediately after sowing. The overlap of the non-woven fabric (not less than 15cm) and the head and tail of each piece of non-woven fabric are fixed with iron wire or bamboo sticks, and a small amount of fine sand or fine soil is sprinkled on the edges. The main function of the non-woven fabric is to reduce the evaporation of water on the slope, improve the germination and growth environment of the seeds, prevent birds from pecking at the seeds, and at the same time reduce the erosion of seeds by heavy precipitation (heavy rain). When the grass seedlings grow to 3cm-5cm, the non-woven fabric should be removed in time on cloudy days or after 3 pm. The seedlings should be lifted after a night of dew so that the seedlings can adapt to the natural climate as soon as possible. The non-woven fabric should not be opened too early, because the young grass seedlings cannot withstand the sun exposure and bad weather. Opening it too late will cause the grass seedlings to grow deformed.

[0066] Step 7-8: Take mandatory maintenance

[0067] Mandatory maintenance refers to the daily watering of plants within the first two months after the spraying is completed. Specifically, it is within two days after the spraying is completed. During the mandatory maintenance period, attention should also be paid to the germination uniformity and germination rate of plant seeds, and replanting should be carried out on slopes with uneven germination or no germination.

[0068] in conclusion:

[0069] 1. The present invention uses construction waste resources to carry out roadbed widening and filling, achieving the beneficial practice of policy compliance, project cost, and project operability.

[0070] 2. The present invention solves the problem of widening roadbed filling without increasing the difficulty of the project, and specifically adopts the masonry materials removed during widening, which is innovative and practical.

[0071] 3. The slope protection of the present invention realizes the combination of masonry and grass planting protection, has excellent landscape effect, is suitable for areas with a lack of fill materials or a large amount of stone, and expands the application scope of green protection.

[0072] 4. The invention has a simple construction process, is easy to operate, speeds up construction progress, reduces construction investment, meets quality requirements, and also plays a positive role in protecting the ecological environment, and has a broad application prospect.

[0073] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for filling roadbed with renewable resources for road reconstruction and expansion, characterized in that: The method comprises: Step 1: Clear and compact the original roadbed slope and the original foundation of the widened section; Step 2: After clearing and compacting, the original roadbed slope is excavated from bottom to top in the form of steps; Step 3: After the slope excavation is completed, backfill with coarse-grained recycled filler; Step 4: bury the drainage pipe at the edge of the newly laid roadbed; Step 5: Carry out slope paving on the edge of the newly laid roadbed; Step 6: After the coarse-grained recycled filler and the edges are stacked to the bottom of the roadbed, the roadbed is backfilled; Step 7: Set up geocells on the newly laid slope and plant grass in the geocells; Step 8: Laying the pavement structure layer; The second step is as follows: after clearing and compacting, the original roadbed slope is excavated from bottom to top, and the steps have an inward slope to enhance the connection between the new and old roadbeds; the slope is not less than 2%; the step excavation width is not less than 200 cm; In the step 3, the coarse-grained recycled filler is the waste concrete blocks and mortar-laid stone blocks removed during the renovation and expansion, which are crushed and processed into recycled aggregates with a maximum particle size of 50 mm; the content of particles below 0.075 mm in the recycled aggregates is not more than 10%, and the non-uniformity coefficient is not less than 5%; The step three also includes: compacting the coarse-grained regenerated filler; The compaction process is to use large mechanical vibration to compact in layers; The layer thickness is controlled to be 25 to 35 cm; the compaction degree of the coarse-grained recycled granular material after compaction is not less than 93%; In the step 7: the geocell is a three-dimensional honeycomb grid structure formed by high-strength high-density polyethylene through high-frequency ultrasonic welding or buckling; The geocell product has a height of 50 to 250 mm, a welding distance of 330 to 800 mm, and a peeling strength of the cell welding point of 1450 N / 10 cm.

2. The filling method according to claim 1, characterized in that: The step one is specifically as follows: clearing the original roadbed slope and the original foundation of the widened section, removing the surface humus, grass roots and domestic garbage, and fully compacting the original foundation with a compaction degree of not less than 90%.

3. The filling method according to claim 1, characterized in that: In the step 4: the drainage pipes laid are PVC drainage pipes, and one drainage pipe is set every 200 cm along the route; the aperture of the PVC drainage pipe is not less than 10 cm.

4. The filling method according to claim 1, characterized in that: The step five is specifically as follows: stacking the stone blocks within a width of 100cm to 200cm at the edge of the newly laid roadbed; the particle size of the stone blocks is not less than 30cm; and the strength grade of the stone blocks is not less than mu40.

5. The filling method according to claim 1, characterized in that: In the step 6: lime-improved soil is used for roadbed backfill; The lime-improved soil has a no-load expansion rate of less than 1%, has no obvious collapse after being immersed in water for 72 hours, and adopts a lime-soil content of 8% of the roadbed soil; The loose laying thickness of the lime-improved soil building material is 20cm to 30cm; The total thickness of the roadbed is between 80cm and 120cm; the maximum particle size of the roadbed filler is less than 100mm, the minimum strength CBR of the filler is 8%, and the compaction degree is not less than 96%.

6. The filling method according to claim 1, characterized in that: The step seven specifically includes: Step 7-1, manually trimming the slope; Step 7-2, measuring and laying out; Step 7-3, laying geocell net; Step 7-4, filling and burying; Step 7-5, compaction; Step 7-6: Planting vegetation; Step 7-7, covering with non-woven fabric; Steps 7-8: Mandatory maintenance.