Construction method of steel-concrete structure foundation pit trestle based on BIM

Through the BIM-based steel-concrete structure foundation pit trench construction method, the problem of difficulty in coordination between foundation pit trench and earthwork excavation construction is solved, and construction costs are reduced, quality improvement and construction period are shortened, meeting the lean management needs of engineering projects .

CN114662189BActive Publication Date: 2024-12-06SHENZHEN HONGYEJI GEOTECHNICAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210243463.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-03-11
Publication Date
2024-12-06
Estimated Expiration
2042-03-11

AI Technical Summary

Technical Problem

In the construction of high-rise buildings, the construction coordination between the foundation pit trench and the earth and stone excavation is difficult, resulting in excessive material losses and extended construction period, which makes it difficult to meet the requirements of lean management of engineering projects.

Method used

Using the BIM-based steel-concrete structure foundation pit trench construction method, by obtaining project drawings and construction environment information, establishing a Revit model, combining site and support models, optimizing the earth and stone excavation plane, calculating the required main materials, and performing the overall complex parts Structural prefabrication and real-time adjustment, construction information is entered simultaneously, and cost and quality are monitored in real time.

Benefits of technology

It reduces the cost of foundation pit trest construction, improves construction quality and progress, solves the problem of difficult construction coordination, and meets the lean management requirements of engineering projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114662189B_ABST
    Figure CN114662189B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of foundation pit trestles, and discloses a BIM-based steel-concrete structure foundation pit trestles construction method, comprising the following construction steps: 1) obtaining foundation pit project drawings and construction environment information; 2) forming a foundation pit construction BIM model according to the construction environment information; 3) arranging earthwork excavation and transportation planes; 4) integrating a foundation pit trestles model in the foundation pit construction BIM model in equal proportions; 5) arranging earthwork excavation and transportation spaces; 6) calculating the main materials required for the construction of the foundation pit trestles, installing the complex parts of the foundation pit trestles, and performing construction previews of hoisting operations; prefabricating the overall structure of the difficult-to-construct parts; 7) synchronously entering the actual construction information of each component into the foundation pit construction BIM model, and comparing the spatial difference between the foundation pit trestles model and the physical foundation pit trestles; 8) counting the actual cost in the construction process of the foundation pit trestles, and monitoring the difference between the incurred costs and the expected costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The patent of this invention relates to the technical field of foundation pit trestles, and specifically, to a BIM-based steel-concrete structure foundation pit trestles construction method. Background Art

[0002] With the rapid development of the domestic economy, construction land in large cities is becoming increasingly scarce. In the process of building construction planning, in order to maximize land utilization, the edge of the basement of high-rise buildings often approaches the red line of the construction land, and the technical requirements for basement excavation are increased accordingly.

[0003] In this construction context, the design and construction of deep and large foundation pit projects often use steel-concrete structure foundation pit trestles to carry out the excavation and transportation of earth and stone on the site. The setting of the foundation pit trestles is convenient for the transportation of earth and stone, and is conducive to the deployment of facilities and equipment on the construction site. However, due to the adverse effects of tight project schedule and low level of project management, the overall coordination and deployment between the foundation pit trestles and earth and stone excavation and foundation pit support is unreasonable. During the actual construction of the project, the engineering personnel have great difficulty in coordinating the construction between the assembly of the foundation pit trestles and the excavation and transportation of earth and stone, resulting in excessive material loss and extended construction period during the actual construction of the foundation pit trestles, and the construction quality is more difficult to control stably. These problems will have a great impact on the subsequent foundation pit processing, and it is more difficult to meet the requirements of the era of lean management of engineering projects. Summary of the invention

[0004] The purpose of the present invention is to provide a BIM-based steel-concrete structure foundation pit trestle construction method, aiming to solve the problem of difficulty in construction coordination between the foundation pit trestle and earth and stone excavation and transportation in the prior art.

[0005] The present invention is implemented in this way: a BIM-based steel-concrete structure foundation pit trestle construction method includes the following construction steps:

[0006] 1) Obtain foundation pit project drawings and construction environment information;

[0007] 2) Establish a site Revit model based on the construction environment information, and establish a foundation pit support Revit model based on the foundation pit design drawing data; In the Revit software, merge and coordinate the site Revit model and the foundation pit support Revit model to form a foundation pit construction BIM model;

[0008] 3) Arrange the excavation and transportation plane of earth and stone in the foundation pit construction BIM model;

[0009] 4) According to the foundation pit trestle drawings and data, establish the foundation pit trestle model, integrate the foundation pit trestle model in proportion into the foundation pit construction BIM model, and carry out engineering collaborative management of the foundation pit trestle construction;

[0010] 5) In the foundation pit construction BIM model, the travel paths of large vehicles are optimized and the excavation and transportation space of earth and stone is arranged;

[0011] 6) Based on the foundation pit construction BIM model, calculate the main materials required for the foundation pit trestle construction, issue detailed component drawings for the complex parts of the foundation pit trestle, and perform construction previews for the installation and lifting operations of the complex parts of the foundation pit trestle; prefabricate the overall structure of the difficult-to-construct parts of the foundation pit trestle;

[0012] 7) While the foundation pit trestle is being constructed on site, the actual construction information of each component is synchronously entered into the foundation pit construction BIM model, and the spatial difference between the foundation pit trestle model and the physical foundation pit trestle is compared. The foundation pit trestle model is adjusted in real time according to the original construction data, so that the data of the foundation pit trestle model and the physical trestle are consistent;

[0013] 8) According to the data of the components of the foundation pit trestle entered into the foundation pit construction BIM model, the actual cost of the foundation pit trestle construction process is counted, and the difference between the incurred cost and the expected cost is monitored in real time.

[0014] Furthermore, in the construction step 1), construction environment information is collected using an unmanned aerial vehicle (UAV) photogrammetry-assisted method.

[0015] Furthermore, in the construction step 3), the earthwork excavation and transportation plane includes a simulated layout of the plane positions of a car wash system, a drainage system, a vehicle identification system, electrical facilities and safety facilities during the earthwork excavation and transportation process.

[0016] Furthermore, in the construction step 5), a zoning and layered detailed site model of earthwork excavation of the foundation pit is further established in the foundation pit construction BIM model, and the improved foundation pit construction BIM model is imported into Navisworks in proportion. At the same time, the overall construction progress plan MPP format file is imported into the construction simulation system in Navisworks, and the various components of the detailed site model of each stage are linked in turn according to the overall construction progress plan, and a proportional model is used for construction simulation.

[0017] Furthermore, the difficult construction parts of the foundation pit trestle include the place where the foundation pit trestle has a variable cross-section, the length of the scissor-shaped channel steel at the intersection of the support beam and the foundation pit trestle structure, and the welding node parts.

[0018] Furthermore, when the site car washing system is arranged on the foundation pit trestle, the site car washing system is prefabricated as a whole and installed in modules.

[0019] Furthermore, the complex parts of the foundation pit trestle include the connection between the column pile and the steel cage, the connection between the column nodes, the connection between the column and the foundation pit trestle slab beam, and the connection between the channel steel and the column.

[0020] Furthermore, the actual construction information of the component includes construction date, plane position, elevation, specification quantity, finished product quality, cost, on-site handler, and material channel.

[0021] Compared with the prior art, the BIM-based steel-concrete structure foundation pit trestle construction method provided by the present invention utilizes BIM technology to simulate various working conditions that will be encountered in the construction of the foundation pit trestle, and iteratively optimizes the detailed structures of the foundation pit trestle based on reducing costs, improving quality, and accelerating progress, and guides the actual construction. The use effect meets expectations, and can solve the problem of poor control of construction details of foundation pit steel-concrete structure trestle in the past, successfully meet the requirements of lean management of engineering projects, and solve the problem of difficulty in construction coordination between foundation pit trestle assembly and earthwork excavation and transportation. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic flow chart of the BIM-based steel-concrete structure foundation pit trestle construction method provided by the present invention. DETAILED DESCRIPTION

[0023] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0024] The implementation of the present invention is described in detail below in conjunction with specific embodiments.

[0025] The same or similar numbers in the drawings of this embodiment correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.

[0026] Reference Figure 1 The figure shows a preferred embodiment of the present invention.

[0027] The BIM-based steel-concrete structure foundation pit trestle construction method includes the following construction steps:

[0028] 1) Obtain foundation pit project drawings and construction environment information;

[0029] 2) Establish a site Revit model based on the construction environment information, and establish a foundation pit support Revit model based on the foundation pit design drawing data; In the Revit software, merge and coordinate the site Revit model and the foundation pit support Revit model to form a foundation pit construction BIM model;

[0030] 3) Arrange the excavation and transportation plane of earth and stone in the foundation pit construction BIM model;

[0031] 4) According to the foundation pit trestle drawings and data, establish the foundation pit trestle model, integrate the foundation pit trestle model in proportion into the foundation pit construction BIM model, and carry out engineering collaborative management of the foundation pit trestle construction;

[0032] 5) In the foundation pit construction BIM model, the travel paths of large vehicles are optimized and the excavation and transportation space of earth and stone is arranged;

[0033] 6) Based on the foundation pit construction BIM model, calculate the main materials required for the foundation pit trestle construction, issue detailed component drawings for the complex parts of the foundation pit trestle, and perform construction previews for the installation and lifting operations of the complex parts of the foundation pit trestle; prefabricate the overall structure of the difficult-to-construct parts of the foundation pit trestle;

[0034] 7) While the foundation pit trestle is being constructed on site, the actual construction information of each component is synchronously entered into the foundation pit construction BIM model, and the spatial difference between the foundation pit trestle model and the physical foundation pit trestle is compared. The foundation pit trestle model is adjusted in real time according to the original construction data, so that the data of the foundation pit trestle model and the physical trestle are consistent;

[0035] 8) According to the data of the components of the foundation pit trestle entered into the foundation pit construction BIM model, the actual cost of the foundation pit trestle construction process is counted, and the difference between the incurred cost and the expected cost is monitored in real time.

[0036] The above-mentioned BIM-based steel-concrete structure foundation pit trestle construction method uses BIM technology to simulate various working conditions that will be encountered in the construction of the foundation pit trestle. Based on reducing costs, improving quality and accelerating progress, it iteratively optimizes the detailed structures of the foundation pit trestle and guides the actual construction. The use effect is in line with expectations, which can solve the problem of poor control of construction details of the foundation pit steel-concrete structure trestle in the past, successfully meet the lean management requirements of the engineering project, and solve the problem of difficult construction coordination between the foundation pit trestle assembly and the excavation and transportation of earth and stone.

[0037] In construction step 1), construction environment information is collected by drone photogrammetry. In environments shaded by buildings or trees, manual measurements are used to supplement the information, and the environmental data obtained is checked and optimized with the survey and design data obtained, so that the initial construction information on site is more realistic and conducive to the development of construction operations.

[0038] In construction step 3), the earthwork excavation plane includes the simulated layout of the plane positions of the car wash system, drainage system, vehicle identification system, electrical facilities and safety facilities during the earthwork excavation process. In this way, each system is easy to install, the operating efficiency is maximized, and the pre-set index requirements on site are met. At this stage, the foundation pit trestle has not yet been built, and the vehicle driving route and the ancillary facilities during the earthwork excavation process are all temporary settings. They should be changed according to the actual situation on site, and the connection with subsequent processes should be considered.

[0039] In construction step 5), a zoning and layered detailed site model of earthwork excavation of the foundation pit is further established in the foundation pit construction BIM model, and the improved foundation pit construction BIM model is imported into Navisworks in proportion. At the same time, the overall construction progress plan MPP format file is imported into the construction simulation system in Navisworks. According to the overall construction progress plan, the various components of the detailed site model of each stage are linked in turn, and the proportional model is used for construction simulation.

[0040] Based on the principle of vertical zoning and layered excavation of foundation pit earth and stone, the phased construction of the foundation pit trestle is closely combined with the phased excavation and transportation of earth and stone. Under different foundation pit excavation conditions, corresponding earth ramps are set up to connect with the completed foundation pit trestle part, so as to ensure high efficiency of earth and stone excavation and transportation while ensuring the stability of the foundation pit trestle.

[0041] Based on the scale model of the project engineering, the construction sequence of the original staggered system of the foundation pit trestle and support beams was optimized to reduce the construction difficulty of the staggered area. After the construction of the foundation pit trestle was completed, the length and slope of the last section of the earth ramp at the bottom of the foundation pit and the vehicle turning radius at the connection with the revolving platform of the foundation pit trestle were optimized based on the scale model of the project engineering to ensure smooth driving of earth-moving vehicles and reduce the probability of objective factors affecting safety accidents.

[0042] The difficult parts of the foundation pit trestle include the cross-section change of the foundation pit trestle, the length of the scissor-shaped channel steel at the intersection of the support beam and the foundation pit trestle structure, and the welding node parts. According to the length, elevation and other data of each channel steel component in the foundation pit construction BIM model, the overall structure of such nodes is prefabricated to reduce construction errors.

[0043] When the site car washing system is arranged on the foundation pit trestle, the site car washing system is prefabricated as a whole and installed in modules to speed up the construction progress and installation quality.

[0044] In this embodiment, the complex parts of the foundation pit trestle include the connection between the column pile and the steel cage, the connection between the column node, the connection between the column and the foundation pit trestle slab beam, and the connection between the channel steel and the column.

[0045] Technical briefing work is carried out based on the detailed component drawings issued by the foundation pit construction BIM model, which makes it easier for operators to quickly grasp the construction sequence and technical points of the foundation pit trestle. While improving the installation quality and construction progress of the on-site foundation pit trestle, it also eliminates potential safety hazards that are prone to occur during the operation.

[0046] In construction step 6), the installation of complex parts of the foundation pit trestle and the construction rehearsal of the lifting operation are carried out; the mechanical equipment model, operation route, installation sequence and related safety protection measures for the lifting and installation of components are clarified; the purchased and prepared components are lifted to the construction site, and the on-site execution is strictly carried out according to the model rehearsal data to improve the reliability of the actual installation and positioning of the components.

[0047] The actual construction information of the components includes construction date, plane position, elevation, specification quantity, finished product quality, cost, on-site handlers, and material channels. The original data is recorded in detail to facilitate later extraction and comparison.

[0048] In construction step 7), the foundation pit trestle model is adjusted in real time according to the original construction data, so that the data of the foundation pit trestle model is consistent with that of the physical foundation pit bridge, which is conducive to the synchronous adjustment and quality control of the subsequent lifting and installation construction of components in complex parts, and reduces the deviation of subsequent processes.

[0049] In construction step 8), the difference between the incurred costs and the expected costs is monitored in real time, and reasonable intervention measures are taken to ensure that the project cost targets are achieved.

[0050] Based on the construction date, plane position, elevation, specification quantity, finished product quality, on-site handlers and material channel source information of each detailed component (column piles, pier bridge deck, steel, etc.) in the foundation pit construction BIM model, the construction quality of each detailed component in the foundation pit pier construction process is controlled and traced in a targeted manner, which is conducive to tracking the specific responsible parties, eliminating quality risks and ensuring the realization of project quality goals.

[0051] The BIM-based steel-concrete structure foundation pit trestle construction method provided in this embodiment has the following advantages:

[0052] 1) Based on the proportional foundation pit construction BIM model, analyze the mutual influence between the support system and the on-site environment to provide a visual basis for construction deployment;

[0053] 2) Establish a BIM model for foundation pit construction based on BIM technology, conduct construction previews for complex parts of the foundation pit trestle, improve the reliability of actual installation positioning, and prevent repeated construction;

[0054] 3) Calculate the required main material quantity based on the foundation pit construction BIM model, produce detailed component drawings for complex parts and carry out prefabrication to reduce material waste and construction costs;

[0055] 4) Based on the BIM model of foundation pit construction, provide technical briefing materials for each detailed structure to reduce communication barriers among on-site workers and improve the control index of construction details;

[0056] 5) While the foundation pit trestle is being constructed, the actual construction information of each detail will be synchronously entered into the components of the corresponding foundation pit construction BIM model to facilitate the actual cost statistics and quality traceability of the later components.

[0057] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. The BIM-based steel-concrete structure foundation pit trestle construction method is characterized by: The construction steps include: 1) Obtain foundation pit project drawings and construction environment information; 2) Establish a site Revit model based on the construction environment information, and establish a foundation pit support Revit model based on the foundation pit design drawing data; In the Revit software, merge and coordinate the site Revit model and the foundation pit support Revit model to form a foundation pit construction BIM model; 3) Arrange the excavation and transportation plane of earth and stone in the foundation pit construction BIM model; 4) According to the foundation pit trestle drawings and data, establish the foundation pit trestle model, integrate the foundation pit trestle model in proportion into the foundation pit construction BIM model, and carry out engineering collaborative management of the foundation pit trestle construction; 5) In the foundation pit construction BIM model, the travel paths of large vehicles are optimized and the excavation and transportation space of earth and stone is arranged; 6) Based on the foundation pit construction BIM model, calculate the main materials required for the foundation pit trestle construction, issue detailed component drawings for the complex parts of the foundation pit trestle, install the complex parts of the foundation pit trestle and conduct construction previews for the lifting operations; for the difficult construction parts of the foundation pit trestle, prefabricate the overall structure of the difficult construction parts; 7) While the foundation pit trestle is being constructed on site, the actual construction information of each component is synchronously entered into the foundation pit construction BIM model, and the spatial difference between the foundation pit trestle model and the physical foundation pit trestle is compared. The foundation pit trestle model is adjusted in real time according to the original construction data, so that the data of the foundation pit trestle model and the physical trestle are consistent; 8) According to the data of the components of the foundation pit trestle entered in the foundation pit construction BIM model, the actual cost of the foundation pit trestle construction process is counted, and the difference between the incurred cost and the expected cost is monitored in real time; In the construction step 3), the earthwork excavation and transportation plane includes a simulated layout of the plane positions of the car wash system, drainage system, vehicle identification system, electrical facilities and safety facilities during the earthwork excavation and transportation process; In the construction step 5), a detailed site model of earthwork excavation of the foundation pit is further established in the foundation pit construction BIM model, and the improved foundation pit construction BIM model is imported into Navisworks in proportion. At the same time, the MPP format file of the general construction progress plan is imported into the construction simulation system in Navisworks, and each component of the detailed site model of each stage is linked in turn according to the general construction progress plan, and construction simulation is performed according to the proportional model; Based on the principle of vertical zoning and layered excavation of foundation pit earth and stone, the phased construction of foundation pit trestle is closely combined with the phased excavation and transportation of earth and stone. Under different foundation pit excavation conditions, corresponding earth ramps are set up to connect with the completed foundation pit trestle part. After the construction of the foundation pit trestle is completed, the length and slope of the last section of the earth ramp at the bottom of the foundation pit and the vehicle turning radius at the connection with the revolving platform of the foundation pit trestle will be optimized based on the scale model of the project.

2. The BIM-based steel-concrete structure foundation pit trestle construction method according to claim 1, characterized in that: In the construction step 1), construction environment information is collected using drone photogrammetry assistance.

3. The BIM-based steel-concrete structure foundation pit trestle construction method according to any one of claims 1 to 2, characterized in that: The difficult construction parts of the foundation pit trestle include the place where the foundation pit trestle has a variable cross-section, the length of the scissor-shaped channel steel at the intersection of the supporting beam and the foundation pit trestle structure, and the welding node parts.

4. The BIM-based steel-concrete structure foundation pit trestle construction method according to any one of claims 1 to 2, characterized in that: When the site car washing system is arranged on the foundation pit trestle, the site car washing system is prefabricated as a whole and installed in modules.

5. The BIM-based steel-concrete structure foundation pit trestle construction method according to any one of claims 1 to 2, characterized in that: The complex parts of the foundation pit trestle include the connection between the column pile and the steel cage, the column node connection, the column and the foundation pit trestle slab beam connection, and the channel steel and the column connection.

6. The BIM-based steel-concrete structure foundation pit trestle construction method according to any one of claims 1 to 2, characterized in that: The actual construction information of the components includes construction date, plane position, elevation, specification quantity, finished product quality, cost, on-site handlers, and material channels.