A method for preventing and controlling groundwater pollution in tailings ponds in karst development areas
Through hydrogeological survey and diversion hole system, surface water drainage channels and underground drainage tunnels are set up in tailings ponds in karst development areas, which solves the applicability problem of groundwater pollution prevention and control technology in tailings ponds in karst development areas and realizes the elimination of pollutants. Effectively reduce and improve sewage treatment efficiency.
Patent Information
- Application Number
- CN202411026718.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-07-30
AI Technical Summary
Existing methods of groundwater pollution prevention and control technology in tailings ponds in karst development areas are not applicable, making it difficult to cut off pollutants. Existing interception wall technology cannot effectively cut off the huge karst space in karst development areas, making it difficult to effectively treat pollutants.
Determine the pollution prevention and control area through preliminary and detailed hydrogeological surveys, set up surface water drainage channels and underground drainage tunnels, use longitudinal diversion holes to conduct pumping tests, determine the location and elevation of underground drainage tunnels, ensure clean groundwater is exported, and reduce the influx of pollutants. According to the amount of water flowing out, a regulating wall and an electronically controlled valve are set up to adjust the amount of water flowing out.
It effectively reduces the outflow of pollutants upstream of the tailings pond, improves sewage treatment efficiency, reduces the burden on sewage treatment stations, and improves environmental, social and economic benefits.
Smart Images

Figure CN118563896B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of groundwater pollution prevention and control in tailings ponds, and in particular to a method for groundwater pollution prevention and control in tailings ponds in karst development areas. Background Art
[0002] Tailings ponds are environmental protection facilities equipped by mining companies. The tailings produced by the ore mined from the mining site after sorting in the beneficiation plant are stored in the tailings pond. Its narrow definition is: a place composed of dams to block the valley mouth or enclosures, used to store tailings discharged after ore sorting in metal and non-metal mines. The broad definition is: a place used to store tailings.
[0003] Most heavy metal-containing tailings ponds do not have standardized anti-seepage measures, especially the ownerless tailings ponds left over from history. The leachate produced by the stored tailings under the action of rainfall leaching contains heavy metal pollutants. The leachate leaks into the groundwater and causes heavy metal pollution to the groundwater quality downstream of the tailings pond, thereby affecting the surrounding water and soil environment, and posing a threat to human health.
[0004] Some early tailings ponds or historical tailings ponds have caused leachate from tailings ponds to infiltrate and pollute groundwater due to site selection issues (located in fault zones or karst areas, etc.), lack of anti-seepage measures, and failure of anti-seepage measures. At present, the main technology for groundwater pollution prevention and control in tailings ponds is to build a seepage cutoff wall downstream or around the tailings dam to block the contaminated groundwater from flowing downstream, and to build an extraction well inside the seepage cutoff wall to extract the blocked contaminated groundwater to the sewage treatment plant for treatment. This treatment method is mainly aimed at tailings ponds in porous water or fissure water areas, and the pumped contaminated groundwater needs to be sent to the sewage treatment plant for treatment, which has high energy consumption and large investment. This seepage cutoff wall technology is not applicable to tailings ponds in karst development areas, because karst development areas often develop huge karst spaces such as caves and underground rivers, and it is difficult for the seepage cutoff wall to intercept the huge karst space, resulting in failure of pollution interception. At present, there are few reports on technical methods for groundwater pollution prevention and control in tailings ponds in karst development areas. Summary of the invention
[0005] The purpose of this application is to provide a method for preventing and controlling groundwater pollution in tailings ponds in karst development areas to solve the above-mentioned problems.
[0006] To achieve the above purpose, the present application provides a method for preventing and controlling groundwater pollution in a tailings pond in a karst development area, wherein the tailings pond leaks and pollutes karst water (including karst water in an underground river), the source of the karst water comes from upstream surface water and groundwater, and the karst water has a surface outlet;
[0007] The prevention and control methods include:
[0008] Conduct a preliminary (first) hydrogeological survey based on the location of the tailings pond to determine the source of contaminated groundwater recharge, and then determine the pollution prevention and control area, and divide the pollution prevention and control area into a surface water treatment area and a groundwater treatment area;
[0009] A surface water drainage channel is provided in the surface water treatment area to transport the surface water to the downstream of the surface water outlet;
[0010] Conduct a detailed (second) hydrogeological survey of the groundwater treatment area to determine the concentrated groundwater runoff area and the corresponding groundwater level upstream of the tailings pond;
[0011] A plurality of longitudinal diversion holes are arranged in and near the concentrated groundwater runoff area, and the position and elevation of the underground drainage tunnel in the concentrated groundwater runoff area are determined by a pumping test and the groundwater level;
[0012] The outlet of the underground drainage tunnel is selected downstream of the surface water outlet, and the underground drainage tunnel is excavated according to the outlet, the position and the elevation. The underground drainage tunnel is connected to all or part of the longitudinal diversion holes to transport the groundwater in the concentrated groundwater runoff area upstream of the tailings pond to the downstream of the surface water outlet.
[0013] Optionally, the distance between the longitudinal guide holes is 10m-20m.
[0014] Optionally, the diameter of the longitudinal guide hole is 185mm-305mm.
[0015] Optionally, the number of the longitudinal diversion holes matches the length of the designed underground drainage tunnel in the concentrated runoff zone.
[0016] Optionally, the depth of the longitudinal guide hole is 100m-250m.
[0017] Optionally, the pumping test includes:
[0018] A water pump is respectively arranged at the same preset position in the plurality of longitudinal diversion holes to pump water within a preset time, and obtain the total amount of water pumped, whether the pumped water contains the marked pollutants, and the amount of water reduction at the surface water outlet;
[0019] When the water extracted by the pumping test does not contain the marked pollutants and the water reduction at the surface outlet meets the preset target, it is determined that the preset position falls within the theoretical interval of the elevation;
[0020] If the preset position does not fall within the theoretical range of the elevation, the height of the preset position is changed, and the above test is repeated until the preset position falls within the theoretical range of the elevation.
[0021] Optionally, the method for preventing and controlling groundwater pollution in tailings ponds in karst development areas satisfies at least one of the following conditions:
[0022] A. When the extracted water contains the marked pollutants, raising the position of the water pump;
[0023] B. When the reduction in water outflow from the surface outlet does not meet the preset target, lower the position of the water pump.
[0024] Optionally, the elevation of a section of the concentrated groundwater runoff zone exposed by the underground drainage tunnel is between the highest position of the pump that meets the preset target and the lowest position of the pump at which the pumped water does not contain marker pollutants.
[0025] Optionally, the underground drainage tunnel is further provided with a regulating wall, and the regulating wall is provided with an electrically controlled valve, and the water output of the underground drainage tunnel is controlled by automatically adjusting the opening of the electrically controlled valve.
[0026] Optionally, in the method for preventing and controlling groundwater pollution in a tailings pond in a karst development area, the surface water drainage channel and the underground drainage tunnel have a slope, satisfying at least one of the following conditions:
[0027] A. The slope of the surface water drainage channel is 1%-5%;
[0028] B. The slope of the underground drainage tunnel is 0.5%-10%.
[0029] Compared with the prior art, the beneficial effects of this application include:
[0030] The present application provides a method for preventing and controlling groundwater pollution in a tailings pond in a karst development area. The present application conducts a preliminary (first) hydrogeological survey based on the location of the tailings pond to determine the source of recharge of the contaminated groundwater, and then determines the pollution prevention and control area, and divides the pollution prevention and control area into a surface water treatment area and a groundwater treatment area; builds canals and diverts water in the surface water treatment area to reduce the amount of surface water replenishing groundwater through sinkholes, and at the same time avoids waterlogging in this area during heavy rains that affects the normal growth of crops; at the same time, conducts a detailed (second) hydrogeological survey in the groundwater treatment area to determine the location of the concentrated groundwater runoff zone, set up multiple longitudinal diversion holes, and conduct pumping tests through the longitudinal diversion holes to verify the relationship between the water volume in the concentrated groundwater runoff zone and the water volume at the surface outlet, and to ensure The water drained in the underground drainage tunnel is all clean water. The longitudinal diversion holes run through the underground drainage tunnel from top to bottom, ensuring that the underground drainage tunnel can effectively divert clean groundwater from the upstream groundwater concentrated runoff zone, so as to achieve the goal of reducing the clean groundwater recharge upstream of the tailings pond, and realize the source reduction of the sewage volume at the surface outlet of the groundwater concentrated runoff zone. Ultimately, the amount of contaminated water gushing out of the tailings pond contaminated area through the surface outlet (karst spring) of the groundwater concentrated runoff zone will be greatly reduced, avoiding the situation where sewage floods the sewage treatment station during heavy rains, resulting in the direct discharge of sewage into the environment. Since the amount of pollution sources remains unchanged and the water volume is reduced, the concentration of pollutants in the sewage is increased, which is conducive to improving the efficiency of sewage treatment. The entire tailings pond groundwater pollution prevention and control method has good environmental, social and economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope of the present application.
[0032] Figure 1 It is a plan view of the water level influence range of the pump;
[0033] Figure 2 A schematic diagram for determining the elevation of clean and dirty water diversion after the water pump is pumped out;
[0034] Figure 3 Schematic diagram of regulating wall and electric control valve;
[0035] Figure 4 It is the karst spring hydrogeological unit in Example 1;
[0036] Figure 5 This is the general layout diagram of Example 1. DETAILED DESCRIPTION
[0037] As used herein:
[0038] "Prepared from" is synonymous with "comprising." As used herein, the terms "comprising," "including," "having," "containing," or any other variation thereof, are intended to cover a non-exclusive inclusion. For example, a composition, process, method, article, or apparatus that comprises the listed elements is not necessarily limited to only those elements but may include other elements not expressly listed or inherent to such composition, process, method, article, or apparatus.
[0039] The conjunction "consisting of excludes any unspecified element, step, or component. If used in a claim, this phrase renders the claim closed-ended so that it does not include materials other than those described, except for conventional impurities associated therewith. When the phrase "consisting of" appears in a clause of the body of a claim rather than immediately following the subject matter, it limits only the elements described in that clause; other elements are not excluded from the claim as a whole.
[0040] When an amount, concentration, or other value or parameter is expressed as a range, a preferred range, or a range defined by a series of upper preferred values and lower preferred values, this should be understood as specifically disclosing all ranges formed by any pairing of any range upper limit or preferred value with any range lower limit or preferred value, regardless of whether the range is disclosed separately. For example, when a range of "1 to 5" is disclosed, the described range should be interpreted as including ranges "1 to 4", "1 to 3", "1 to 2", "1 to 2 and 4 to 5", "1 to 3 and 5", etc. When a numerical range is described in this article, unless otherwise stated, the range is intended to include its end values and all integers and fractions within the range.
[0041] In these examples, parts and percentages are by mass unless otherwise indicated.
[0042] "Mass parts" refers to the basic unit of measurement for expressing the mass ratio of multiple components. 1 part can represent any unit mass, such as 1g or 2.689g. If we say that the mass parts of component A are a parts and the mass parts of component B are b parts, it means the ratio of the mass of component A to the mass of component B is a:b. Alternatively, it means that the mass of component A is aK and the mass of component B is bK (K is an arbitrary number, indicating a multiple factor). It should not be misunderstood that, unlike the mass parts, the sum of the mass parts of all components is not limited to 100 parts.
[0043] "And / or" is used to indicate that one or both of the stated situations may occur, for example, A and / or B includes (A and B) and (A or B).
[0044] The present application provides a method for preventing and controlling groundwater pollution in a tailings pond in a karst development area, wherein the tailings pond leaks and pollutes an underground river, the water source of the underground river comes from surface water and groundwater, and the underground river has a surface outlet;
[0045] In some embodiments, the surface water outlet is a large karst spring.
[0046] The prevention and control methods include:
[0047] Conduct a preliminary (first) hydrogeological survey based on the location of the tailings pond to determine the source of groundwater, and then determine the pollution prevention and control area, and divide the pollution prevention and control area into a surface water treatment area and a groundwater treatment area;
[0048] It should be noted that, through the preliminary (first) hydrogeological survey, the smallest hydrogeological unit containing the impact range of the tailings pond is divided according to the distribution of ridge lines and regional faults in the area where the tailings pond is located, and the pollution prevention and control area is determined according to the hydrogeological conditions such as surface water runoff, karst depression distribution, sinkhole distribution, spring distribution, etc. in the hydrogeological unit, and the pollution prevention and control area is divided into surface water treatment area and groundwater treatment area;
[0049] In some embodiments, the surface water treatment area and the groundwater treatment area may be two different areas, or they may be interchangeably in the same area;
[0050] A surface water drainage channel is set in the surface water treatment area to transport the surface water to the downstream of the surface water outlet to prevent it from flowing into the connecting channel between the surface and the underground, that is, the sinkhole, and being converted into groundwater.
[0051] It should be noted that surface water drainage channels include, but are not limited to, surface drainage ditches and underground box culverts;
[0052] It is understandable that the outlet position of the surface water drainage channel can be determined according to actual conditions.
[0053] In some embodiments, the outlet of the surface water drainage channel is set to the nearest point of a nearby river. It should be noted that if there is no river nearby, the surface water can be drained to a nearby valley and then flow into a downstream river.
[0054] In some embodiments, when the collected surface water cannot be discharged to a nearby river through an open channel due to mountain obstruction, a water diversion culvert is constructed to drain the surface water, or a drainage tunnel is constructed from the surface to the underground to allow the surface water to flow through the drainage tunnel to the downstream of the surface outlet. For example, the elevation of the outlet of the drainage tunnel needs to be lower than the elevation of the location where the underground drainage tunnel upstream of the tailings pond intercepts and discharges groundwater, so as to ensure that the intercepted groundwater and surface water can be discharged by gravity.
[0055] Conduct a detailed (second) hydrogeological survey of the groundwater treatment area to determine the concentrated groundwater runoff area and the corresponding groundwater level upstream of the tailings pond;
[0056] It should be noted that the concentrated groundwater runoff area is also called the underground river distribution area;
[0057] It should be noted that the detailed (second) hydrogeological survey includes:
[0058] (1) Geophysical profiles perpendicular to the groundwater flow direction are laid out through geophysical exploration techniques (in karst areas, high-density electrical method and transient electromagnetic method can be used) to infer the shape, depth and distribution range of the concentrated groundwater runoff area; the shape, depth, distribution range and water volume of the concentrated groundwater runoff area are verified and finally determined through drilling technology (in karst areas, air down-the-hole hammer technology can be used to drill large-diameter and deep boreholes) and connectivity tests;
[0059] (2) Deploy water level monitoring wells in and around the concentrated groundwater runoff area to determine the groundwater level elevation in the concentrated groundwater runoff area and the surrounding area;
[0060] A plurality of longitudinal diversion holes are arranged in the concentrated groundwater runoff area, and the position and elevation of the underground drainage tunnel in the concentrated groundwater runoff area are determined by a pumping test and the groundwater level;
[0061] It should be noted that a plurality of longitudinal diversion holes are set in the concentrated groundwater runoff area, and the position and elevation of the underground drainage tunnel in the concentrated groundwater runoff area are determined by conducting a pumping test in the key diversion holes and the groundwater level;
[0062] In some embodiments, the longitudinal diversion holes are generally distributed in a straight line along the direction of the underground drainage tunnel. The number of longitudinal diversion holes matches the length of the designed underground drainage tunnel in the concentrated runoff zone, and can pass through the concentrated runoff zone of groundwater and extend a certain distance, which is determined by the local hydrogeological conditions. It should be noted that the extension of a certain distance is to allow the scattered water outside the concentrated runoff zone (i.e., the water in the non-concentrated runoff zone) to be drained as much as possible;
[0063] It should be noted that the underground drainage tunnel and the longitudinal diversion hole form a unified body that diverts clean groundwater from the upstream, which is called the groundwater diversion system. Due to the complex terrain of the karst development area, when the elevation of the underground drainage tunnel is relatively low, the amount of water diverted is relatively large. However, when the elevation of the underground drainage tunnel is too low, it will seize the sewage around the downstream tailings pond, causing the drainage water of the underground drainage tunnel to be polluted. Therefore, the elevation of the underground drainage tunnel needs to be determined according to the pumping test.
[0064] The outlet of the underground drainage tunnel is selected downstream of the surface water outlet, and the underground drainage tunnel is excavated according to the outlet, the position and the elevation. The underground drainage tunnel is connected to all or part of the longitudinal diversion holes to transport the groundwater in the concentrated groundwater runoff area upstream of the tailings pond to the downstream of the surface water outlet.
[0065] It should be noted that the more longitudinal diversion holes the underground drainage tunnel is connected to, the greater the amount of water discharged from the underground drainage tunnel; when the preset target can be achieved by connecting some of the longitudinal diversion holes in the underground drainage tunnel, it is not necessary to connect all the longitudinal diversion holes.
[0066] It should be noted that the downstream of the surface outlet may be a nearby river, a nearby valley, or other location that can ensure that the groundwater flowing out of the surface outlet can be discharged by gravity.
[0067] In some embodiments, the outlet of the underground drainage tunnel is generally located downstream of the surface outlet of the karst spring;
[0068] In some embodiments, the underground drainage tunnel is connected to the surface water drainage channel, and the underground drainage tunnel and the surface water drainage channel have the same outlet.
[0069] In some embodiments, the outlet of the surface water drainage channel is connected to a water diversion culvert, the water diversion culvert is connected to a surface drainage ditch, and the surface water can be discharged into a nearby river through the surface drainage ditch.
[0070] In some embodiments, the outlet of the surface water drainage channel is connected to a surface water drainage tunnel, and the surface water drainage tunnel is connected to an underground drainage tunnel.
[0071] In some embodiments, according to the setting of the target water outflow reduction amount of the surface water outlet, the underground drainage tunnel can be connected to all the longitudinal diversion holes.
[0072] In some embodiments, according to the setting of the target water outflow reduction amount of the surface water outlet, the underground drainage tunnel can be connected to part of the longitudinal diversion holes.
[0073] In some embodiments, the distance between the longitudinal guide holes is 10m-20m.
[0074] Optionally, the distance between the longitudinal guide holes may be 10 m, 11 m, 12 m, 13 m, 14 m, 15 m, 16 m, 17 m, 18 m, 19 m, 20 m or any value between 10 m and 20 m.
[0075] It should be noted that, according to the hydrogeological conditions of the karst area, its groundwater-bearing water medium is extremely uneven. Even if the distribution of the groundwater concentrated runoff zone is basically clarified through detailed (second) hydrogeological survey, the groundwater concentrated runoff zone is not necessarily a regular continuous space of a large underground river, but may be some unevenly distributed but interconnected tortuous fissure channels, so it is difficult to be accurately exposed by underground drainage tunnels and longitudinal diversion holes. Therefore, the density of the longitudinal diversion holes needs to be increased to increase the probability that the longitudinal diversion holes can expose the water-conducting fissures in the groundwater concentrated runoff area. Too much density (that is, the distance between the two diversion holes is too close) will also affect the stability of the longitudinal diversion holes. According to the hydrogeological conditions of the karst area, the distance between the longitudinal diversion holes is determined to be 10m-20m.
[0076] It should be noted that some sections can be directly crossed due to obstacles such as construction conditions, and no longitudinal diversion holes are set in these sections.
[0077] In some embodiments, the diameter of the longitudinal guide hole is 185 mm-305 mm.
[0078] Optionally, the aperture of the longitudinal guide hole can be 185mm, 190mm, 200mm, 210mm, 220mm, 230mm, 240mm, 250mm, 260mm, 270mm, 280mm, 290mm, 300mm, 305mm or any value between 185mm and 305mm.
[0079] It should be noted that when the aperture of the longitudinal diversion hole is 185mm-305mm, the hole inclination can be better controlled in karst development areas, especially in limestone areas, to ensure that it can be more accurately connected to the underground drainage tunnel in the future; and at this aperture, a larger pump can be used to carry out pumping tests on the diversion holes, which is suitable for pumping tests with large drawdown and large flow rates, and plays an important role in the success of this method.
[0080] In some embodiments, the number of the longitudinal diversion holes matches the length of the designed underground drainage tunnel in the concentrated runoff zone.
[0081] In some embodiments, the diversion hole passes through the concentrated groundwater runoff zone in the horizontal direction and extends a certain distance, and the extension distance is determined by the local hydrogeological conditions.
[0082] It should be noted that the number of longitudinal diversion holes should be moderate, which can not only play a role in exposing more water-conducting fissures in the concentrated runoff zone of groundwater, but also save investment and reduce land occupation.
[0083] In some embodiments, the depth of the longitudinal guide hole is 100m-250m.
[0084] Optionally, the depth of the longitudinal guide hole may be 100 m, 150 m, 200 m, 250 m or any value between 100 m and 250 m.
[0085] It should be noted that the depth of the longitudinal diversion hole must be greater than the depth of the underground drainage tunnel. Since the longitudinal diversion hole is located in the karst development area, the underground karst development is very complex, and the development of karst space or underground river is not straight or regular. In order to enable the constructed underground drainage tunnel to effectively collect groundwater, the depth of the longitudinal diversion hole should be deep enough to collect groundwater in the large karst fissures or fractures connected to the groundwater concentrated runoff zone, so as to avoid the underground drainage tunnel being dry due to the underground drainage tunnel crossing the concentrated runoff zone without exposing the groundwater.
[0086] In some embodiments, the pumping test includes: respectively setting pumps at the same preset positions in the plurality of longitudinal diversion holes, pumping water within a preset time, obtaining the total amount of pumped water, whether the pumped water contains marker pollutants, and the amount of water reduction at the surface outlet;
[0087] Optionally, water pumps are respectively arranged at the same preset positions in a plurality of key longitudinal diversion holes to pump water within a preset time, and obtain the total amount of water pumped, whether the pumped water contains marker pollutants, and the amount of water reduction at the surface water outlet;
[0088] It should be noted that the preset time can be set as needed. In some embodiments, the preset time can be one week, one month, two months, or other time that meets the pumping requirements;
[0089] When the water extracted by the pumping test does not contain the marked pollutants and the water reduction at the surface outlet meets the preset target, it is determined that the preset position falls within the theoretical interval of the elevation;
[0090] It should be noted that whether the longitudinal diversion hole is in the concentrated groundwater runoff area can be verified by a pumping test. The verification method is: conduct a pumping test within a preset time to see whether the amount of water pumped out meets the theoretical amount of water in the concentrated groundwater runoff area;
[0091] It should also be noted that the water extracted from the pumping test can be tested for marker pollutants to ensure that the extracted water is all clean water. In some embodiments, the pump extracts from a high position to a low position. When the pump extracts clean water at a high position, the position can be further lowered until the extracted water contains marker pollutants. After repeated tests, the position of the clean and dirty diversion elevation is determined, that is, the lowest elevation of the underground drainage tunnel. When it is lower than this position, the drainage water of the underground drainage tunnel is not clean water.
[0092] It can be understood that, Figure 1 As shown, the yellow frame is the water level influence range formed when the pump is at a high position, and the pumped water is clean water at this time; the red frame is the water level influence range formed when the pump is at a low position, and the pumped water is sewage at this time.
[0093] It should be noted that the results of the pumping test may deviate from the actual situation. If, according to the results of the pumping test, the location of the drainage tunnel happens to fall on the clean and sewage diversion elevation, the tunnel diversion can be carried out directly.
[0094] It should also be noted that the pumping test can also verify whether the reduction in water output from the surface outlet is in line with expectations. By conducting a pumping test on multiple longitudinal diversion holes that expose the concentrated groundwater runoff zone, theoretically the amount of water pumped out in the pumping test is the amount of groundwater reduced in the concentrated groundwater runoff zone, that is, the amount of contaminated groundwater reduced at the surface outlet, thereby verifying whether the reduced water volume meets the preset target.
[0095] In some embodiments, if the preset position of the water pump does not fall within the theoretical range of the elevation, the height of the preset position of the water pump is changed, and the pumping test is repeated until the preset position of the water pump falls within the theoretical range of the elevation.
[0096] In some embodiments, the method for preventing and controlling groundwater pollution in tailings ponds in karst development areas meets the following conditions: no marker pollutants are allowed to be contained in groundwater discharged from underground drainage tunnels; it should be noted that in order to intercept as much clean water as possible, the position of the water pump will be lowered as much as possible until the extracted water contains marker pollutants; it should also be noted that the results of the pumping test in the detailed (second) hydrogeological survey stage can directly guide the construction of the next underground drainage tunnel; that is, the amount of water pumped out in the pumping test is theoretically the amount of water discharged from the underground drainage tunnel; that is, the final reasonable position of the water pump in the pumping test is the elevation of the underground drainage tunnel.
[0097] Specifically, when the underground drainage tunnel is drained, its drainage effect will form a groundwater drop funnel, that is, the water level influence range, such as Figure 2 As shown, the range of the groundwater drop funnel determines whether sewage will be captured; if the funnel range extends to the sewage area, sewage will be captured; if it does not extend to the sewage area, sewage will not be captured, which depends on the drainage volume of the underground drainage tunnel; the lower the position of the pump, the greater the drainage volume, and the larger the range of the drop funnel, the easier it is to capture sewage; similarly, the higher the position of the pump, the smaller the drainage volume, and the smaller the range of the drop funnel, the less likely it is to capture sewage.
[0098] In some embodiments, the underground drainage tunnel exposes a section of the concentrated groundwater runoff zone at an elevation between the highest position of the pump that meets the preset target and the lowest position of the pump at which the extracted water does not contain marker pollutants.
[0099] It should be noted that the highest position of the pump that meets the preset target must satisfy that its pumping capacity can reach the preset sewage reduction amount at the surface outlet. If the pump is higher than this position, the pumping capacity will not reach the preset sewage reduction amount at the surface outlet. In some embodiments, the preset target is to reduce the sewage volume at the surface outlet by at least 70%. The highest position of the pump that meets this preset target must satisfy that its pumping capacity can reach the preset sewage reduction amount at the surface outlet by at least 70%. If the pump is higher than this position, the sewage reduction amount at the surface outlet will be less than 70%.
[0100] In some embodiments, the underground drainage tunnel is further provided with an adjusting wall, and the adjusting wall is provided with an electrically controlled valve, and the water output of the underground drainage tunnel is controlled by automatically adjusting the opening of the electrically controlled valve.
[0101] Optionally, a regulating wall can be constructed outside the water outlet point where the underground drainage tunnel exposes the underground river (i.e., outside the tunnel face), and the regulating wall is provided with an electric-controlled valve to control the water outlet of the underground drainage tunnel by automatically adjusting the opening of the electric-controlled valve.
[0102] In some embodiments, the structural diagram of the adjustment wall is as follows: Figure 3 As shown, it can be understood specifically as follows: when the underground drainage tunnel reveals the concentrated runoff zone of groundwater, water gushing occurs, and the groundwater discharged from the water outlet is the groundwater in the concentrated runoff zone. A regulating wall is built outside the water outlet to block the water, and a water storage space is formed between the wall and the face. The water in this water storage space is connected to the groundwater in the concentrated runoff zone of groundwater; pipelines, electric-controlled valves, flow meters and pressure gauges are provided on the regulating wall, and the discharge volume of the pipeline can be adjusted by the electric-controlled valves. The discharge volume of the pipeline is equivalent to the pumping volume of the pumping test in the detailed (second) hydrogeological survey.
[0103] It should be noted that the results of the pumping test have verified that when a certain groundwater level is at the most reasonable elevation, the water pressure reading of the water pressure gauge corresponding to the elevation is set to the preset water pressure, that is, the parameters are set for the electric control valve so that the pressure of the electric control valve is always maintained at this preset water pressure. Once the groundwater level fluctuates, the electric control valve will adjust the valve opening to adjust the water output so that the groundwater level returns to the corresponding groundwater level of the preset water pressure; in some embodiments, when the rainy season comes, the upstream groundwater increases and the groundwater level rises, the opening of the electric control valve increases, so that the amount of water discharged increases to ensure that the water pressure gauge reading is at the preset water pressure. At this preset water pressure, the groundwater discharged from the underground drainage tunnel does not contain the marked pollutants. In other embodiments, when the upstream groundwater decreases due to drought, the groundwater level decreases, and the opening of the electric control valve decreases, so that the amount of water discharged decreases to ensure that the water pressure gauge reading is at the preset water pressure. At this preset water pressure, the groundwater discharged from the underground drainage tunnel does not contain the marked pollutants.
[0104] It should be noted that the greater the drainage volume of the regulating wall pipe, the lower the regional groundwater level caused by tunnel drainage, and the smaller the pressure reading of the pressure gauge; the smaller the drainage volume of the regulating wall pipe, the higher the regional groundwater level, and the greater the pressure reading of the pressure gauge; therefore, the reading of the pressure gauge is directly proportional to the height of the groundwater level. For example, after actual construction, if the elevation of the underground drainage tunnel falls above the clean and sewage diversion elevation, clean water will be discharged, but the water volume will be less than that at the clean and sewage diversion elevation; for example, if the elevation of the underground drainage tunnel falls below the clean and sewage diversion elevation, sewage will be discharged. In this case, the drainage volume of the underground drainage tunnel can be regulated, a water volume regulating wall is built outside the water outlet, and an electric control valve is installed on the regulating wall. The groundwater level at the water outlet is controlled by controlling the drainage flow rate, so that the groundwater level is restored to the clean and sewage diversion elevation or the most reasonable elevation verified by the pumping test, ensuring that the underground drainage tunnel discharges clean water; it can be understood that when the elevation of the underground drainage tunnel is too low, resulting in the discharged water containing marked pollutants, the drainage volume can be adjusted by adjusting the wall, and the drainage volume can be reduced to restore the groundwater level to the clean and sewage diversion elevation or the most reasonable elevation verified by the pumping test, ensuring that the water discharged from the underground drainage tunnel is clean water.
[0105] In some embodiments, in the method for preventing and controlling groundwater pollution in tailings ponds in karst development areas, the surface water drainage channel and the underground drainage tunnel have a slope, satisfying at least one of the following conditions:
[0106] It should be understood that by setting the slope, water in the surface water drainage channel and the underground drainage tunnel can flow to the downstream of the surface outlet by itself without the need for power.
[0107] A. The slope of the surface water drainage channel is 1%-5%;
[0108] Optionally, the slope of the surface water drainage channel may be 1%, 2%, 3%, 4%, 5%, or any value between 1% and 5%;
[0109] B. The slope of the underground drainage tunnel is 0.5%-10%.
[0110] Optionally, the slope of the underground drainage tunnel can be 0.5%, 1%, 2%, 3%, 4%, 5%, 6%, 7%, 8%, 9%, 10% or any value between 0.5% and 10%.
[0111] The patent of this application will be described in detail below in conjunction with specific embodiments, but it will be appreciated by those skilled in the art that the following examples are only used to illustrate this application and should not be considered as limiting the scope of this application. If specific conditions are not specified in the examples, they are carried out according to normal conditions or conditions recommended by the manufacturer. If the manufacturer is not specified for the reagents or instruments used, they are all conventional products that can be purchased commercially.
[0112] Example 1
[0113] This embodiment provides a method for preventing and controlling groundwater pollution in a tailings pond in a karst development area, comprising:
[0114] In the karst development area in southwest my country, there is a karst spring hydrogeological unit with an area of 3.22 square kilometers. Figure 4 As shown, the main pollution sources in the area are tailings pond 1 (430,000 cubic meters of tailings storage), tailings pond 2 (1.05 million cubic meters of tailings storage) and karst springs (surface outlets of concentrated groundwater runoff zones, whose groundwater is polluted by leachate from tailings ponds). The sewage flowing out of the karst springs flows to the sewage treatment station on the southwest side. Under normal circumstances, the amount of sewage from the karst springs is 2,500-3,000 cubic meters per day, and the concentration of certain characteristic pollutants is between 10 mg / L and 30 mg / L most of the time, which is a large-flow, low-concentration sewage. The sewage treatment station is not efficient in treating such sewage, and costs more than 4 million yuan each year, which is a heavy economic burden. When it rains, the amount of water in the karst springs increases, causing sewage to overflow from the collection pool of the sewage treatment station and flood the sewage treatment station.
[0115] To solve the above problems, this embodiment first conducts a preliminary (first) hydrogeological survey based on the location of the tailings pond, and finds that the groundwater flow direction in the area is: from northeast to southwest. The surface water upstream also flows from the northeast to the sinkholes on the southwest side. A large amount of surface water enters the underground river from the K4 sinkhole and the K5 sinkhole. The underground river flows from the northeast to the southwest, passing through tailings pond 1 and tailings pond 2. The groundwater near these two tailings ponds is polluted by the leachate of the tailings ponds and merges into the underground river. Finally, the polluted groundwater flows out from the karst spring;
[0116] Based on the above survey and the surrounding hydrogeological conditions such as ridgelines and faults, the overall governance area is determined, namely Figure 4 The yellow border in the figure is used to identify the source of groundwater, and then the pollution prevention and control area is determined, and the pollution prevention and control area is divided into surface water treatment area A and groundwater treatment area B;
[0117] In the surface water treatment area A, open channels (surface drainage ditches), water diversion culverts and AB drainage tunnels are set up to transport surface water to nearby rivers. Among them, the repaired drainage ditch A1 is 410m long × 0.8m wide × 1.2m high. A new drainage ditch A2 is built at the outlet of the repaired drainage ditch A1, which is 1066m long × 1.2m wide × 1.2m high. The outlet of drainage ditch A2 is connected to the A3 water diversion culvert with a length of 47m × 2m wide × 1.8m high. In addition, the A4 water diversion culvert is 12m long × 2m wide × 1.8m high to drain the dispersed and gathered surface water. The outlets of A3 and A4 water diversion culverts are the inlets of AB drainage tunnels. AB drainage tunnels are connected to B1 underground drainage tunnels. Clean surface water from upstream is drained to nearby rivers through AB drainage tunnels and B1 underground drainage tunnels. In the past, surface water was dispersed and gathered in K4 and K5 sinkholes, and then transformed into groundwater and flowed to the karst spring. After the completion of this project, surface water will flow through the surface drainage ditch, water diversion box culvert and AB drainage tunnel, and no longer enter the sinkholes. Therefore, cofferdams are set up for the sinkholes to prevent surface water from entering and transforming into groundwater. The cofferdam of K4 sinkhole is 33m long, 0.6m wide and 3m high, and the cofferdam of K5 sinkhole is 24m long, 0.6m wide and 3m high.
[0118] Conduct a detailed (second) hydrogeological survey of the groundwater treatment area B to determine the concentrated groundwater runoff area and the corresponding groundwater level upstream of the tailings pond;
[0119] 24 longitudinal diversion holes (aperture 185-305mm, depth 200m) are set in the concentrated groundwater runoff area. The distance between the longitudinal diversion holes is 10m-20m (in some sections, due to obstacles such as roads, the distance may be greater than 20m, which is a special case). They penetrate underground drainage tunnels and regional fissures, fractures and other water-filled structures to collect groundwater.
[0120] According to the survey results, the groundwater level in the area is 385m above sea level, and the elevation of the concentrated groundwater runoff zone is 378m (about 85m underground). It starts from the two sinkholes in the northeastern depression and extends to the direction of the karst spring on the southwest side of the downstream. Its downstream passes near two tailings ponds, so the groundwater is polluted after passing through the tailings pond area. Among the 24 diversion holes, 4 diversion holes located in the concentrated groundwater runoff zone were selected for pumping tests. Four pumps were placed at an elevation of 380m in the four diversion holes, and a total of 1,200 cubic meters of water was pumped every day. At the same time, it was observed that the water volume of the downstream karst spring decreased by about 1,000 cubic meters, indicating that the amount of water pumped was well correlated with the water volume of the karst spring. After sampling and testing, the pumped water was clear water without marked pollutants; then 4 pumps were placed at an elevation of 371m in the four diversion holes, and a total of 2,400 cubic meters of water was pumped every day. At the same time, it was observed that the water volume of the downstream karst spring decreased by about 1,000 cubic meters. This shows that the amount of water pumped is well correlated with the amount of water in the karst spring. After sampling and testing, the pumped water was clear water without marked pollutants; then 4 pumps were placed at an elevation of 371m in the four diversion holes, and a total of 2,400 cubic meters of water was pumped every day. At the same time, it was observed that the water volume of the downstream karst spring decreased by about 1,000 cubic meters. The amount of water pumped decreased by about 2,200 cubic meters, indicating that the amount of water pumped was well correlated with the amount of water in the karst spring. After sampling and testing, the pumped water was sewage, which showed that the pump needed to be raised. After repeated tests, it was found that 4 pumps were placed at the 375m elevation of the 4 diversion holes, and a total of 2,000 cubic meters of water were pumped every day. At the same time, it was observed that the amount of water in the downstream karst spring decreased by about 1,900 cubic meters. After sampling and testing, the pumped water was clean water, and the 375m elevation was the clean and sewage diversion elevation. Therefore, the excavation elevation of the underground drainage tunnel should be 375m, that is, 88m underground. The underground drainage tunnel at the 375m elevation can exchange hydraulic power with the groundwater concentrated runoff zone at the 378m elevation above it through the karst fissures.
[0121] The collection and storage of water samples shall refer to the "Technical Guidelines for Water Sampling" (GB12998-91), "Technical Regulations for the Preservation and Management of Water Quality Sampling Samples" (GB12999-91), "Technical Specifications for Groundwater Environmental Monitoring" (HJ / T 164-2020) and other relevant standards, specifications or regulations;
[0122] According to the above test, the position and elevation of the B2 underground drainage tunnel (471m long × 4m wide × 4.5m high) in the concentrated groundwater runoff area are determined. The outlet of the B2 underground drainage tunnel, the outlet of the AB drainage tunnel and the inlet of the B1 underground drainage tunnel (761m long × 4m wide × 4.5m high) are connected. The outlet of the B1 underground drainage tunnel is selected in the river near the downstream of the surface outlet. The underground drainage tunnel is excavated according to the outlet, position and elevation. The B2 underground drainage tunnel is connected to all longitudinal diversion holes to transport most of the clean groundwater in the concentrated groundwater runoff area upstream of the tailings pond to the nearby river.
[0123] Among them, the slope of drainage ditch A2 is 1.47%;
[0124] The slope of underground drainage tunnel B1 is 0.7%;
[0125] The slope of underground drainage tunnel B2 is 0.5%;
[0126] Through the above method, the final sewage volume of the karst spring is 400-600 cubic meters per day, and the concentration of a certain characteristic pollutant is between 80mg / L and 100mg / L most of the time.
[0127] The specific arrangement of groundwater pollution prevention and control methods for tailings ponds in this karst development area is as follows: Figure 5 shown.
[0128] In some embodiments, if it is necessary to further improve the ultimate goal and increase the reduction in water output from the surface outlet, and if conditions (including financial conditions, terrain conditions, social conditions, etc.) permit, surface and groundwater treatment areas can be set up on the side or other directions of the tailings pond using the same technical methods, depending on actual conditions.
[0129] It should be noted that this method must first be used to govern key areas that can achieve the preset goals, while other areas that are not highly operational and do not play a major role in achieving the goals do not need to be governed.
[0130] In some embodiments, the reduction in water discharge from the surface outlet has far exceeded the requirements. By connecting only some of the longitudinal diversion holes (6), the final sewage volume of the karst spring can be 400 cubic meters / day to 600 cubic meters / day, and the concentration of a certain characteristic pollutant is between 80 mg / L and 100 mg / L most of the time.
[0131] In some embodiments, under the condition that an underground drainage tunnel has been built, when the water at the tunnel outlet is not clean water, a regulating wall is also set 5m outside the tunnel outlet. The regulating wall is provided with an electric-controlled valve. The opening of the electric-controlled valve is automatically adjusted to control the water output of the underground drainage tunnel, thereby controlling the groundwater level at the outlet point behind the regulating wall, and keeping the groundwater level at or above the clean and sewage diversion elevation, so as to discharge as much clean water as possible on the basis of achieving the preset target.
[0132] According to the above embodiment, the results are as follows:
[0133] (1) Surface water treatment area (Area A): The construction of surface water drainage ditches, water diversion culverts, and AB drainage tunnels was completed, meeting the goal of guiding and draining surface water, preventing surface water from entering the ground through sinkholes and transforming into groundwater, which then flows out from karst springs, thus diverting the amount of surface water from upstream. At the same time, it also prevented surface water from flooding farmland in depressions during rainstorms and causing waterlogging, and prevented surface water from entering the ground through sinkholes and transforming into groundwater, which then flows out from karst springs and then flows into the collection pool of the sewage treatment plant, and overflowing from the collection pool to flood the sewage treatment plant.
[0134] (2) Groundwater treatment area (Area B): The construction of underground drainage tunnels and longitudinal diversion holes was completed, and the groundwater in the concentrated groundwater runoff zone was successfully connected and drained out. During the excavation of the underground drainage tunnel, the diversion hole pumping test was repeated to determine the elevation of the underground drainage tunnel and the possible water output. Although after the actual construction, the underground drainage tunnel discharged sewage at the design elevation, which was a deviation from the results of the pumping test, the deviation was not large. The pumping test still played a key role, that is, calculating the excavation elevation and water output of the underground drainage tunnel. In order to solve the problem that the water discharged from the underground drainage tunnel is sewage, a regulating wall is set 5m outside the tunnel outlet. The regulating wall is equipped with an electric control valve. The opening of the electric control valve is automatically adjusted to control the water output of the underground drainage tunnel, thereby controlling the groundwater level elevation at the outlet point behind the regulating wall, and keeping the groundwater level at or above the clean and sewage diversion elevation. On the basis of achieving the preset target, as much clean water as possible is discharged. Finally, the water discharged from the underground drainage tunnel is clean water, which not only achieves the goal of reducing the water output from the surface outlet, but also increases the pollutant concentration of the remaining sewage gushing out from the karst spring, improves the treatment efficiency of the sewage treatment plant, and saves the operating cost of the sewage treatment plant.
[0135] (3) In this embodiment, the construction of engineering measures in the surface water treatment area and the groundwater treatment area was completed, which not only achieved the preset goals, but also achieved good environmental, economic and social benefits.
[0136] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.
[0137] In addition, those skilled in the art will appreciate that, although some embodiments herein include certain features included in other embodiments but not other features, the combination of features of different embodiments is meant to be within the scope of the present application and form different embodiments. For example, in the above claims, any one of the claimed embodiments may be used in any combination. The information disclosed in this background technology section is intended only to deepen the understanding of the overall background technology of the present application and should not be regarded as an admission or in any form of implication that the information constitutes prior art known to those skilled in the art.
Claims
1. A method for preventing and controlling groundwater pollution in tailings ponds in karst development areas, characterized in that: The tailings reservoir is leaking and polluting an underground river, the water source of the underground river comes from surface water and groundwater, and the underground river has a surface outlet; The prevention and control methods include: Conduct preliminary hydrogeological surveys based on the location of the tailings pond to determine the source of groundwater, and then determine the pollution prevention and control area, and divide the pollution prevention and control area into surface water treatment areas and groundwater treatment areas; A surface water drainage channel is provided in the surface water treatment area to transport the surface water to the downstream of the surface water outlet; Conduct a detailed hydrogeological survey of the groundwater treatment area to determine the concentrated groundwater runoff area and the corresponding groundwater level upstream of the tailings pond; A plurality of longitudinal diversion holes are arranged in the concentrated groundwater runoff area, and the position and elevation of the underground drainage tunnel in the concentrated groundwater runoff area are determined by a pumping test and the groundwater level; Selecting the outlet of the underground drainage tunnel downstream of the surface water outlet, excavating the underground drainage tunnel according to the outlet, the position and the elevation, and the underground drainage tunnel is connected with all or part of the longitudinal diversion holes to transport the groundwater in the concentrated groundwater runoff area upstream of the tailings pond to the downstream of the surface water outlet; The pumping test includes: A water pump is respectively arranged at the same preset position in the plurality of longitudinal diversion holes to pump water within a preset time, and obtain the total amount of water pumped, whether the pumped water contains the marked pollutants, and the amount of water reduction at the surface water outlet; When the water extracted by the pumping test does not contain the marked pollutants and the water reduction at the surface outlet meets the preset target, it is determined that the preset position falls within the theoretical interval of the elevation; If the preset position does not fall within the theoretical range of the elevation, the height of the preset position is changed, and the above test is repeated until the preset position falls within the theoretical range of the elevation; When the extracted water contains the marked pollutant, raising the position of the water pump; When the water output reduction amount of the surface water outlet does not meet the preset target, lowering the position of the water pump; The elevation of the concentrated runoff area exposed by the underground drainage tunnel is between the highest position of the water pump that meets the preset target and the lowest position of the water pump at which the pumped water does not contain the marked pollutants.
2. The method for preventing and controlling groundwater pollution in tailings ponds in karst development areas according to claim 1, characterized in that: The distance between the longitudinal guide holes is 10m-20m.
3. The method for preventing and controlling groundwater pollution in tailings ponds in karst development areas according to claim 1, characterized in that: The diameter of the longitudinal guide hole is 185mm-305mm.
4. The method for preventing and controlling groundwater pollution in tailings ponds in karst development areas according to claim 1, characterized in that: The number of the longitudinal diversion holes matches the length of the designed underground drainage tunnel in the concentrated runoff area.
5. The method for preventing and controlling groundwater pollution in tailings ponds in karst development areas according to claim 1, characterized in that: The depth of the longitudinal guide hole is 100m-250m.
6. The method for preventing and controlling groundwater pollution in tailings ponds in karst development areas according to claim 1, characterized in that: The underground drainage tunnel is also provided with a regulating wall, and the regulating wall is provided with an electric-controlled valve, and the water output of the underground drainage tunnel is controlled by automatically adjusting the opening of the electric-controlled valve.
7. The method for preventing and controlling groundwater pollution in tailings ponds in karst development areas according to any one of claims 1 to 6, characterized in that: The surface water drainage channel and the underground drainage tunnel have a slope, satisfying at least one of the following conditions: A. The slope of the surface water drainage channel is 1%-5%; B. The slope of the underground drainage tunnel is 0.5%-10%.
Citation Information
Patent Citations
Pyrite mountain groundwater pollution remediation and treatment method based on groundwater flow field
CN113233525A
Bottom underground collecting and discharging and water sealing treatment method for leaked sewage of slag storage
CN115305965A
Physical simulation test device and method for karst underground water system
CN115825386A
Karst area sponge urban rainwater collects and dredges device
CN207130867U
Bedrock ground water intake installation
JP2006118298A