Manufacturing process technology change management closed loop method and system

By capturing, identifying and integrating technical change notification information, pushing execution and confirmation operations, and generating multi-dimensional reports, the technical change management closed-loop system solves the problems of missing registration, missing confirmation and poor traceability, and improves the integrity of technical change management. and efficiency.

CN118798808APending Publication Date: 2024-10-18CSR CHENGDU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410861520.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-28
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

There are missing registrations, missing confirmations, lack of traceability and data display tools in the existing technology change management process, resulting in incomplete execution, low accuracy, reduced decision-making efficiency and waste of resources.

Method used

A closed-loop method and system for technical change management in the manufacturing process is designed. By capturing, identifying, and registering technical change notification information, the integrated message fields are pushed to the execution and confirmation unit, the execution and confirmation information is filled in, and multi-dimensional reports are generated. Using The hardware server runs the server module to achieve automation and traceability.

Benefits of technology

It realizes the automatic capture and registration of technical change notifications, avoids missing registrations and confirmations, improves traceability and decision-making efficiency, and intuitively displays the implementation status through multi-dimensional reports to eliminate missing implementation of notifications.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118798808A_ABST
    Figure CN118798808A_ABST
Patent Text Reader

Abstract

The invention discloses a manufacturing process technology change management closed-loop method and a manufacturing process technology change management closed-loop system. Comprising the following steps: S1, capturing technology change notification information; s2, identifying the technology change notification information, and registering the technology change notification information; s3, integrating the registration technology change notification information, generating a message field, pushing the message field to an execution unit and a quality confirmation unit, and performing execution operation and confirmation operation respectively; s4, after the execution unit completes the execution operation, execution information is filled and reported, and a prompt is pushed to a quality confirmation unit; s5, after the quality confirmation unit completes confirmation operation, a confirmation condition is filled and reported; and S6, generating a corresponding chart for the user accessing the report. According to the invention, all modules of the server side are operated through the hardware server, automatic capturing and account establishment of technology change notification information and execution information are realized, and manual missing login is avoided; the execution information is automatically pushed to a related unit, and a prompt is sent to avoid errors; operation information is recorded, and traceability is improved; and a report is automatically generated, so that notification execution omission is avoided.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of technology change management, and in particular to a closed-loop method and system for technology change management in a manufacturing process. Background Art

[0002] In the current technology management process, the implementation of technology changes mainly depends on the issuance of technology change notifications. Once there is a new technology change requirement, the relevant unit will issue the corresponding technology change notification. However, there are a series of problems in the implementation of this process:

[0003] First, after receiving the technical change notification, the execution unit and the quality confirmation unit need to query and register the receiving ledger. However, due to manual errors, the technical change notification may be missed, affecting the subsequent process execution.

[0004] Secondly, after the execution unit executes the technical change notification, it needs to feedback the execution status to the quality confirmation unit. However, due to the lack of an effective supervision mechanism, the execution unit may miss this step, resulting in missed confirmation of the technical change, affecting the completeness and accuracy of the technical change.

[0005] In addition, since the current process lacks a unified platform or system to record and manage the process of receiving, executing and confirming technical changes, it is difficult to trace these processes. Once a problem occurs, it is difficult to quickly locate the root cause of the problem, which affects the efficiency of problem solving.

[0006] Finally, due to the lack of data display and analysis tools, it is difficult for relevant personnel to intuitively understand the overall implementation of technical changes. This not only affects decision-making, but may also lead to waste of resources and reduced efficiency. Summary of the invention

[0007] In view of this, the present invention discloses a method and system for closed-loop management of technical changes in a manufacturing process, which solves the above-mentioned problems.

[0008] The technical solution of the present invention is a method for closed-loop management of technical changes in a manufacturing process, comprising:

[0009] S1: Capture technical change notification information;

[0010] S2: Identify the technical change notification information and register it;

[0011] S3: Integrate the registered technical change notification information, generate a message field, and push the message field to the execution unit and the quality confirmation unit to perform execution operations and confirmation operations respectively;

[0012] S4: After the execution unit completes the execution operation, it fills in the execution information and pushes a reminder to the quality confirmation unit;

[0013] S5: After the quality confirmation unit completes the confirmation operation, it reports the confirmation status;

[0014] S6: Generate corresponding charts for users who access the report.

[0015] Furthermore, the S1 is specifically:

[0016] S11: Logging in to the technical change notification release platform based on the pre-stored account information;

[0017] S12: Get API authentication key;

[0018] S13: Read the ID1 of the technical change notification information captured last time and its issuance time t1, then use the API authentication key to obtain the IDs of all technical change notification information from t1 to t1+n days, and remove the technical change notification information of ID1; where n is the difference in days between the current time and t1.

[0019] Furthermore, the S2 is specifically:

[0020] S21: Using the API authentication key to obtain the technical change notification information corresponding to each ID;

[0021] S22: Register the technical change notification information.

[0022] Furthermore, the S3 is specifically:

[0023] S31: Integrate notification information based on each technical change notification ID into a message field, wherein the technical change notification information includes the responsible unit, notification content, issuer, and issue time;

[0024] S32: Push the message field to the execution unit and the quality confirmation unit via websocks.

[0025] Preferably, the step S4 also includes: after filling in the execution information, uploading relevant attachments.

[0026] Preferably, the step S5 further comprises: after filling in the confirmation status, uploading relevant attachments.

[0027] Preferably, step S6 comprises:

[0028] S61: The user accesses the report through a browser;

[0029] S62: Generate a corresponding chart for the user through query, judgment, combination and statistics.

[0030] Accordingly, the present invention also provides a closed-loop system for managing technical changes in a manufacturing process, including a server:

[0031] A technical change notification capture module is used to capture and identify technical change notification information;

[0032] A technical change notification data processing module is used to store the technical change notification information, integrate the technical change notification information into a message field, and push it to the technical change notification push module;

[0033] A technical change notification push module, used to receive the technical change notification information from the technical change notification data processing module and send it to a set execution unit and quality confirmation unit;

[0034] A closed-loop module for handling technical change notifications: after the execution unit completes the execution of the technical change notification, the execution information is filled in the closed-loop module for handling technical change notifications; after the quality confirmation unit completes the confirmation of the execution, the confirmation status is filled in the closed-loop module for handling technical change notifications;

[0035] The technical change notification report generation module includes a combined query box, which searches the technical change notification data processing module according to the search conditions and outputs it in a table form.

[0036] Preferably, the technology change notification data processing module includes a database, and the database is used to store the technology change notification information.

[0037] Preferably, the closed-loop system for managing technical changes in the manufacturing process also includes a hardware server for running the server.

[0038] The beneficial effects of the present invention are:

[0039] The present invention runs each service-side module through a hardware server, realizes automatic capture of technical change notifications and execution information from a technical change notification publishing platform, automatically forms an account, and eliminates missed registrations; automatically pushes execution information to the execution unit and quality confirmation unit for processing, and sends message reminders and overdue reminders to avoid manual batching errors and omissions of technical change notifications; can record the operation time and operator of receiving, pushing, transferring, confirming, closing, etc., supports uploading attachments, and improves traceability; and automatically generates reports in multiple dimensions to eliminate missed execution of notifications. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] Figure 1 It is a simplified flow chart of the closed-loop method for technology change management of the manufacturing process of the present invention;

[0041] Figure 2 is a simplified flow chart of step S1 of the present invention;

[0042] Figure 3 is a simplified flow chart of step S2 of the present invention;

[0043] Figure 4 is a simplified flow chart of step S3 of the present invention;

[0044] Figure 5 is a simplified flow chart of step S6 of the present invention;

[0045] Figure 6 It is a schematic diagram of the service end composition of the system for closed-loop management of technical changes in the manufacturing process of the present invention. DETAILED DESCRIPTION

[0046] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0047] like Figure 1 As shown, the present invention discloses a closed-loop method for technology change management of a manufacturing process, comprising:

[0048] S1: Capture technical change notification information;

[0049] S2: Identify the technical change notification information and register it;

[0050] S3: Integrate the registered technical change notification information, generate a message field, and push the message field to the execution unit and the quality confirmation unit to perform execution operations and confirmation operations respectively;

[0051] S4: After the execution unit completes the execution operation, it fills in the execution information and pushes a reminder to the quality confirmation unit;

[0052] S5: After the quality confirmation unit completes the confirmation operation, it reports the confirmation status;

[0053] S6: Generate corresponding charts for users who access the report.

[0054] Preferably, the technical change notification information is stored in a technical change notification publishing platform, such as a product management system, a product design system, a production scheduling system, and other related systems.

[0055] Preferably, after capturing the technical change notification information, information recognition is first performed. Through a preset recognition algorithm or rule, the key content in the notification information can be automatically parsed and stored in a database for registration.

[0056] Preferably, the execution unit and the quality confirmation unit are the entities that execute and confirm the technical change notification information.

[0057] Among them, after the execution unit completes the execution operation, it is necessary to fill in the execution information, including the operation time, operator, operation results, etc., and push reminders to the quality confirmation unit so that the quality confirmation unit can perform subsequent operations.

[0058] Among them, after receiving the reminder from the execution unit, the quality confirmation unit performs confirmation operations, including checking the execution results, evaluating the change effects, etc., and fills in the confirmation status for subsequent analysis and summary.

[0059] In practical applications, this method can be implemented through a computer program and integrated into a manufacturing process management system. Technical change notification information can be captured from relevant systems or departments regularly or in real time, and identification, registration and push operations can be performed. The execution unit and the quality confirmation unit can operate and fill in information through relevant interfaces or interfaces. This method can generate corresponding reports and charts according to user needs and permissions, so that users can view and analyze the implementation and effects of technical changes.

[0060] According to a preferred embodiment, Figure 2 As shown, step S1 includes:

[0061] S11: Logging in to the technical change notification release platform based on the pre-stored account information;

[0062] S12: Get API authentication key;

[0063] S13: Read the ID1 of the technical change notification information captured last time and its issuance time t1, then use the API authentication key to obtain the IDs of all technical change notification information from t1 to t1+n days, and remove the technical change notification information of ID1; where n is the difference in days between the current time and t1.

[0064] Preferably, when S11 is implemented, the pre-stored account information (including user name and password) is first called to log in to the technical change notification publishing platform. The account information can be fixed or dynamically acquired to ensure successful access and acquisition of technical change notification information.

[0065] Preferably, when S12 is implemented, after successfully logging into the technical change notification publishing platform, an API authentication key will be requested and obtained. This key is used to access and obtain technical change notification information through the API interface in the future. Different technical change notification publishing platforms may have different API authentication methods and key formats, but it is necessary to ensure that the key can be correctly obtained and stored.

[0066] Preferably, when implementing S13:

[0067] The unique identifier (ID1) and the time (t1) of the last successfully captured technical change notification information will be read and obtained first. This information is usually stored in the database by the system for subsequent query and use.

[0068] Then, based on the time difference between the current time and t1 (n days), use the API authentication key to obtain the IDs of all technical change notification information from t1 to t1+n days from the technical change notification release platform through the API interface. These IDs are the unique identifiers of technical change notifications and are used for subsequent management and processing of technical change notifications.

[0069] Finally, the system will remove the already captured technical change notification information (i.e. the technical change notification information corresponding to ID1) to ensure that only new and unprocessed technical change notifications are processed. In this way, the system can achieve incremental capture of technical change notification information and improve capture efficiency and accuracy.

[0070] Through the above specific implementation methods, step S1 can ensure that new and unprocessed technology change notification information can be accurately obtained from the technology change notification publishing platform, providing basic data support for subsequent technology change management.

[0071] According to a preferred embodiment, Figure 3 As shown, step S2 includes:

[0072] S21: Using the API authentication key to obtain the technical change notification information corresponding to each ID;

[0073] S22: Register the technical change notification information.

[0074] The registration process usually includes the following steps:

[0075] Information analysis: Analyze the acquired technical change notification information and extract key information, such as change type, change content, change reason, impact scope, etc.

[0076] Data storage: The parsed technical change notification information will be stored in the database. The system will assign a unique identifier (such as ID) to each technical change notification information and store it together with the key information. This will facilitate the subsequent query, management and analysis of the technical change notification information.

[0077] Log Recording: The system will record the registration process of the technical change notification information, including registration time, registrant, registration status, etc. This information can be used to track and audit the processing of the technical change notification information.

[0078] Through the above specific implementation, step S2 can ensure that the system can accurately obtain and register the technical change notification information, and provide accurate data support for subsequent technical change management. At the same time, by recording the registration process, the processing process of the technical change notification information can be easily tracked and audited.

[0079] According to a preferred embodiment, Figure 4 As shown, step S3 includes:

[0080] S31: Integrate notification information based on each technical change notification ID into a message field, wherein the technical change notification information includes the responsible unit, notification content, issuer, and issue time;

[0081] S32: Push the message field to the execution unit and the quality confirmation unit via websocks.

[0082] Preferably, when integrating message fields, the system can use a specific format or template to ensure the clarity and consistency of information. For example, the message field can include a title such as "Technical Change Notice", responsible unit, notification content, issuer, issue time, etc., and can use appropriate separators or markers to distinguish different parts of the information.

[0083] After integrating the good message fields, the message fields are pushed to the execution unit and the quality confirmation unit through the WebSocket protocol. WebSocket is a network communication protocol that allows full-duplex communication on a single TCP connection and is suitable for scenarios such as real-time data transmission and message push.

[0084] Specifically, it is necessary to first establish a WebSocket connection with the execution unit and the quality confirmation unit. This can be done by sending a WebSocket handshake request and waiting for the other party's response. Once the connection is successfully established, the system can encapsulate the message fields into a WebSocket message and send it to the execution unit and the quality confirmation unit through the connection.

[0085] After receiving the WebSocket message, the execution unit and quality confirmation unit can parse the technical change notification information and perform corresponding execution or confirmation operations. At the same time, they can also send feedback information to the system through the WebSocket connection, such as execution results, confirmation results, etc.

[0086] Through the above specific implementation methods, step S3 can ensure that the system can accurately integrate the technical change notification information, and push the message fields to the execution unit and the quality confirmation unit through the WebSocket protocol, so as to realize the real-time delivery and rapid response of the technical change notification.

[0087] According to a preferred embodiment, step S4 further includes: uploading relevant attachments after filling in the execution information. Similarly, step S5 further includes: uploading relevant attachments after filling in the confirmation information.

[0088] Among them, attachments include relevant documents, materials, etc. The uploaded attachments will be associated with the execution information and confirmation status and stored in the database. In this way, when the execution information and confirmation status are queried, the relevant attachments can also be displayed together, providing more comprehensive and detailed information for the relevant personnel of technical change management.

[0089] Preferably, Figure 5 As shown, step S6 includes:

[0090] S61: The user accesses the report through a browser;

[0091] S62: Generate a corresponding chart for the user through query, judgment, combination and statistics.

[0092] After the user selects the report to be viewed, the system will query the relevant data in the database according to the user's request. The query conditions can be customized by the user, such as filtering according to the type of technical change, time range, execution unit, etc.

[0093] After the data is queried, the system will judge and process the data. The judgment process may include data integrity check, outlier processing, data conversion, etc. The processed data will be used to generate charts.

[0094] The chart generation process involves the combination and statistics of data. The system will select the appropriate chart type based on the user's needs and the characteristics of the data, and combine and count the data according to certain rules. The final generated chart will intuitively display the implementation of technical changes, trend analysis and other information.

[0095] A closed-loop system for technology change management in manufacturing processes, including the following modules on the service side:

[0096] A technical change notification capture module is used to capture and identify technical change notification information;

[0097] A technical change notification data processing module is used to store the technical change notification information, integrate the technical change notification information into a message field, and push it to the technical change notification push module;

[0098] A technical change notification push module is used to receive the technical change notification information from the technical change notification data processing module and send it to the set execution unit and quality confirmation unit;

[0099] A closed-loop module for handling technical change notifications: after the execution unit has executed the technical change notification, it shall fill in the execution information in the closed-loop module for handling technical change notifications; after the quality confirmation unit has confirmed the execution status, it shall fill in the confirmation status in the closed-loop module for handling technical change notifications;

[0100] The technical change notification report generation module is used to search the technical change notification data processing module according to the search conditions and output it in a table form.

[0101] Wherein, the technical change notification data processing module includes a database, and the database is used to store the technical change notification information.

[0102] Preferably, the closed-loop system for managing technical changes in the manufacturing process also includes a hardware server for running the server.

[0103] According to a preferred embodiment, the hardware server runs the service-side modules to implement the above-mentioned closed-loop method for managing technical changes in the manufacturing process.

[0104] The above is a detailed introduction to a method and system for closed-loop management of technical changes in a manufacturing process provided by an embodiment of the present invention. The various embodiments in the specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same and similar parts between the embodiments can be referenced to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part description. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the present invention, several improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0105] Professionals may further appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, computer software, or a combination of the two. In order to clearly illustrate the interchangeability of hardware and software, the composition and steps of each example have been generally described in the above description according to function. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professionals and technicians may use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0106] The steps of the method or algorithm described in conjunction with the embodiments disclosed herein may be implemented directly using hardware, a software module executed by a processor, or a combination of the two. The software module may be placed in a random access memory (RAM), a memory, a read-only memory (ROM), an electrically programmable ROM, an electrically erasable programmable ROM, a register, a hard disk, a removable disk, a CD-ROM, or any other form of storage medium known in the art.

Claims

1. A closed-loop method for technology change management in a manufacturing process, characterized in that: include: S1: Capture technical change notification information; S2: Identify the technical change notification information and register it; S3: Integrate the registered technical change notification information, generate a message field, and push the message field to the execution unit and the quality confirmation unit to perform execution operations and confirmation operations respectively; S4: After the execution unit completes the execution operation, it fills in the execution information and pushes a reminder to the quality confirmation unit; S5: After the quality confirmation unit completes the confirmation operation, it reports the confirmation status; S6: Generate corresponding charts for users who access the report.

2. The closed-loop method for managing technical changes in the manufacturing process according to claim 1 is characterized in that: The step S1 comprises: S11: Logging in to the technical change notification release platform based on the pre-stored account information; S12: Get API authentication key; S13: Read the ID1 of the technical change notification information captured last time and its issuance time t1, then use the API authentication key to obtain the IDs of all technical change notification information from t1 to t1+n days, and remove the technical change notification information of ID1; where n is the difference in days between the current time and t1.

3. The closed-loop method for managing technical changes in the manufacturing process according to claim 1, characterized in that: The step S2 comprises: S21: Using the API authentication key to obtain the technical change notification information corresponding to each ID; S22: Register the technical change notification information.

4. The closed-loop method for managing technical changes in a manufacturing process according to claim 1, characterized in that: The step S3 comprises: S31: Integrate notification information based on each technical change notification ID into a message field, wherein the technical change notification information includes a responsible unit, notification content, issuer, and issue time; S32: Push the message field to the execution unit and the quality confirmation unit via websocks.

5. The closed-loop method for managing technical changes in a manufacturing process according to claim 1, characterized in that: The step S4 also includes: after filling in the execution information, uploading relevant attachments.

6. The closed-loop method for managing technical changes in a manufacturing process according to claim 1, characterized in that: The step S5 also includes: after filling in the confirmation information, uploading relevant attachments.

7. The closed-loop method for managing technical changes in a manufacturing process according to claim 1, characterized in that: The step S6 comprises: S61: The user accesses the report through a browser; S62: Generate a corresponding chart for the user through query, judgment, combination and statistics.

8. A closed-loop system for managing technical changes in a manufacturing process, characterized in that: The server comprises: A technical change notification capture module is used to capture and identify technical change notification information; A technical change notification data processing module is used to store the technical change notification information, integrate the technical change notification information into a message field, and push it to the technical change notification push module; A technical change notification push module, used to receive the technical change notification information from the technical change notification data processing module and send it to a set execution unit and quality confirmation unit; A closed-loop module for handling technical change notifications: after the execution unit completes the execution of the technical change notification, the execution information is filled in the closed-loop module for handling technical change notifications; after the quality confirmation unit completes the confirmation of the execution, the confirmation status is filled in the closed-loop module for handling technical change notifications; The technical change notification report generation module is used to search the technical change notification data processing module according to the search conditions and output it in a table form.

9. The closed-loop system for managing technical changes in the manufacturing process according to claim 8, characterized in that: The technical change notification data processing module includes a database, and the database is used to store the technical change notification information.

10. The closed-loop system for managing technical changes in the manufacturing process according to claim 8, characterized in that: It also includes a hardware server for running the server.