AI Technical Summary
It is difficult to accurately measure P wave velocity in coal mines in prior art, resulting in insufficient accuracy of impact ground pressure monitoring and early warning, affecting coal mine production safety.
Provide a P wave speed calculation and correction method based on microseismic monitoring system. By analyzing the ore earthquake waveform or blasting waveform collected by the sensor, the spatial coordinates and time data of multiple monitoring channels can be used to calculate and correct the P wave speed to improve the wave speed. The accuracy of the measurement.
It significantly improves the accuracy of the microseismic monitoring system, enhances the accuracy of impact ground pressure prediction, ensures safe production of coal mines, and reduces ground pressure hazards.
Smart Images

Figure CN118884528A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of coal mine rock burst monitoring, and in particular relates to a P-wave velocity calculation and correction method based on a microseismic monitoring system. Background Art
[0002] Mine tremors are a natural phenomenon in which underground rock strata release energy due to stress redistribution during mining, causing rock strata to break or slip. The energy released by mine tremors is propagated in the form of shock waves, which include longitudinal waves (P waves) and transverse waves (S waves), which propagate at different speeds in different media. Longitudinal waves propagate quickly and are usually the first waves to reach the monitoring equipment; transverse waves propagate slowly but have greater destructive power on the rock mass. Studying the propagation characteristics of mine tremors and shock waves is extremely important for predicting and preventing mining disasters.
[0003] Mine earthquakes and the shock waves they cause pose a major threat to mine safety and often lead to rock burst disasters. During the mining process, due to stress concentration, the coal rock mass may suddenly become unstable and release a large amount of energy, resulting in strong vibrations and destruction, which will not only damage the structure of the mine, but also threaten the lives of miners. Rock bursts are sudden and unpredictable. Therefore, how to effectively monitor and warn of mine earthquakes and the rock bursts they cause has become a key technical issue in mine safety production. Accurately understanding the propagation speed and characteristics of shock waves can help improve the accuracy of rock burst predictions, thereby significantly reducing the harm they cause.
[0004] Microseismic monitoring technology is widely used in many domestic coal mines as an important means of monitoring and predicting rock burst. The microseismic monitoring system monitors and records the tiny vibrations of underground coal and rock in real time by arranging a series of highly sensitive seismic sensors in key monitoring areas. Due to the different physical and mechanical properties and stress distribution of coal and rock masses, the propagation speed of shock waves in them is also different. However, for the large scale of the earth, the P-wave velocity of a small-scale monitoring area underground can be regarded as unchanged. Combined with the spatial coordinates of the sensor and the time when the sensor receives the shock wave signal, the actual location of the earthquake source can be calculated and determined.
[0005] Therefore, the key to the normal operation of the microseismic monitoring system lies in the accurate measurement of the P-wave velocity. Traditional wave velocity measurement mainly relies on geological exploration and laboratory testing. The core is obtained by drilling and then directly measured in the laboratory. This method is limited by the site conditions and equipment layout, and it is difficult to fully reflect the average wave velocity of the rock mass. In actual application, it is usually determined in advance by blasting, and then the source is solved by different wave velocities, and the average wave velocity is further inferred. This method is relatively blind and limited by the actual conditions of the mine. There may be situations where blasting may not be possible. Therefore, it is urgent to provide a more convenient and reasonable method to determine the accurate P-wave velocity, so as to more effectively ensure the safe production of coal mines. Summary of the invention
[0006] In view of the problems existing in the above-mentioned prior art, the present invention provides a method for calculating and correcting the P-wave velocity based on a microseismic monitoring system. The method can accurately and efficiently calculate the P-wave velocity and calibrate the original wave velocity by analyzing the mine seismic waveform or blasting waveform collected by the sensor, which can significantly improve the accuracy of the microseismic monitoring system and is conducive to ensuring the safe production of coal mines.
[0007] In order to achieve the above object, the present invention provides a P-wave velocity calculation and correction method based on a microseismic monitoring system, comprising the following steps:
[0008] Step 1: For coal mines that have not installed the microseismic monitoring system, install the microseismic monitoring system underground in the coal mine and ensure that it can operate normally; for coal mines that have installed the microseismic monitoring system, directly execute step 2;
[0009] Step 2: In the selected monitoring area underground, use the monitoring terminal to filter out the clear and easy-to-identify mining earthquake waveforms or blasting waveforms collected by the earthquake pickup sensor when the P wave arrives;
[0010] When the waveform is a blasting waveform, and the blasting source position and blasting time are known, directly execute S31 in step 3;
[0011] When the waveform is a blasting waveform and the blasting source position is known, directly execute S32 in step 3;
[0012] When the waveform is a mine earthquake waveform, directly execute S33 in step 3;
[0013] Step 3: Calculate the P-wave velocity v;
[0014] S31: record the spatial coordinates (x0, y0, z0) of the blasting source, record the blasting time t0, select a monitoring channel for the screened waveform, record the spatial coordinates (x1, y1, z1) of the seismic sensor corresponding to the monitoring channel, mark the monitoring channel, and read the first arrival time of the P wave as t1; then use formula (1) to list the equations for the selected monitoring channel, calculate the P wave velocity v, and then directly execute step 4;
[0015] (x1-x0) 2 +(y1-y0) 2 +(z1-z0) 2 =(v*(t1-t0)) 2 (1);
[0016] S32: record the spatial coordinates (x0, y0, z0) of the blasting source, select at least two monitoring channels for the screened waveform, record them as monitoring channel 1 and monitoring channel 2 respectively, and record the spatial coordinates (x1, y1, z1) and (x2, y2, z2) of the seismic sensors corresponding to the two monitoring channels respectively, mark the waveforms monitored by the two monitoring channels, read the first arrival time of the P wave, record them as t1 and t2 respectively; then use formula (2) to list the equations for the selected two monitoring channels respectively to establish an equation group, calculate the P wave velocity v, and then directly execute step 4;
[0017]
[0018] S33: After preliminarily determining the area where the earthquake source occurs according to the order of the first arrival of the P wave, the five monitoring channels corresponding to the five seismic sensors that receive the first arrival of the P wave are preferentially selected; for the five monitoring channels, the spatial coordinates of the five seismic sensors corresponding to them are determined respectively, and recorded as (x1, y1, z1), (x2, y2, z2), ..., (x5, y5, z5), and then the five monitoring channels are marked to read the first arrival time of the P wave, which are recorded as t1, t2, ..., t5 respectively;
[0019] Define five unknown quantities (x, y, z, v, t), where (x, y, z) is the spatial coordinate of the earthquake source, v is the P-wave velocity, and t is the time when the vibration occurs. Use formula (3) to list the equations to be solved for the five selected monitoring channels respectively, and then combine the five equations to establish the equation group (4) to calculate the P-wave velocity v, and then directly execute step 4;
[0020] (x i -x) 2 +(y i -y) 2 +(z i -z) 2 =(v*(ti -t)) 2 (3);
[0021] Where: i represents the channel number, i = 1, 2, 3, 4 and 5;
[0022]
[0023] Step 4: The calculated P-wave velocity v has multiple solutions, including real solutions and complex solutions. When the calculated vibration occurrence time is a real solution, it is recorded as t. When it is a complex solution, the real part is recorded as t'. According to the calculated t and t', the P-wave velocity v is determined according to the following judgment principles:
[0024] ① There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , but the complex solution's earthquake occurrence time t' is greater than the time t i , or there are only real solutions, take the real solution as the result;
[0025] ② The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , but there exists a complex solution where the earthquake occurrence time t' is less than the arrival time t of the receiving wave of each monitoring channel i , or if there are only complex solutions, take the modulus of the complex solution as the result;
[0026] ③ There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , and the occurrence time t' of the complex solution is also less than the time t i , take the average value of the modulus of the complex solution and the real solution that meet the conditions as the result;
[0027] ④ The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , and the complex solution's earthquake occurrence time t' is also greater than the time t when each monitoring channel receives the waveform i , then delete this group of solutions;
[0028] Step 5: Select the mining vibration waveform or blasting waveform that meets the requirements of step 2 in the selected monitoring area underground, and solve the P-wave velocity v according to steps 3 and 4 respectively; if the number of P-wave velocities v obtained does not exceed 10, remove the maximum and minimum values and use the average method to calculate the P-wave velocity v0; conversely, if the number of P-wave velocities v obtained is greater than 10, use the average method or median method to calculate the P-wave velocity v0 when the degree of dispersion is small, and use the majority method to calculate the P-wave velocity v0 when the degree of dispersion is large;
[0029] Step 6: According to the P-wave velocity v0 of the selected monitoring area in the well solved in step 5, the vibration of the known source position in the monitoring area is used to locate and solve the theoretical value of the known source position through the microseismic monitoring system written with the P-wave velocity v0, and the theoretical value of the known source position is compared with the actual value of the known source position. If the plane error is not greater than ±20m and the vertical error is not greater than ±50m, it is determined that the P-wave velocity v0 of the monitoring area solved is consistent with the actual situation on site; otherwise, it is determined that the P-wave velocity v0 of the monitoring area solved is not consistent with the actual situation on site, and it is deleted, and the final P-wave velocity v is optimized and adjusted again according to steps 1 to 5 until the P-wave velocity v0 of the monitoring area solved is consistent with the actual situation on site, thereby determining the P-wave velocity v P .
[0030] Furthermore, in order to screen clearer and more reasonable waveforms, the selected monitoring area in step 2 is an area without geological structures, not affected by mining disturbances, and without electrical equipment interfering with the vibration wave signal, and at least 5 seismic sensors are installed around the monitoring area.
[0031] Furthermore, in order to ensure the accuracy of calculation, in step 3 S31, a millisecond meter is used to record the blasting time t0 during the actual blasting, and the clock of the millisecond meter used is synchronized with the clock inside the microseismic monitoring system.
[0032] Furthermore, in order to improve the efficiency and accuracy of the solution, the Vpasolve algorithm of Matlab software is used for auxiliary calculation in the solution process in step three.
[0033] Furthermore, in order to improve the accuracy of the solution, in step five, for the selected monitoring area, a mine earthquake waveform or a blasting waveform that is within one month of the waveform in step two is selected.
[0034] Furthermore, in order to fully understand the propagation speed and characteristics of the shock wave, in step 6, the S-wave velocity v is further solved according to formula (5): S ;
[0035]
[0036] In the present invention, different numbers of monitoring channels are used for calibration of blasting waveforms and mine shock waveforms, and different numbers of equations are used to solve the P wave velocity, which can not only quickly and efficiently calculate and correct the accurate P wave velocity in the most reasonable way, so that the calculated P wave velocity conforms to the actual situation on site, which is of great significance to improving the accuracy and reliability of microseismic monitoring, but also helps to avoid the waste of computing power. The method can calculate the P wave velocity and correct the original wave velocity through the monitored mine shock waveform or blasting waveform, optimize and adjust the P wave velocity in the monitoring area, significantly improve the accuracy of the microseismic monitoring system in locating mine shocks, and is conducive to high-precision positioning of the source. At the same time, the propagation speed and characteristics of the shock wave can be more accurately understood through this method, which is helpful to improve the accuracy of rock burst prediction, and lay a reliable technical foundation for monitoring and warning of rock burst danger, thereby significantly reducing the harm caused by it and effectively ensuring the safe production of coal mines. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] Figure 1 is a flow chart of the present invention;
[0038] Figure 2 It is a schematic diagram of the arrangement of the mine earthquake monitoring network and the distribution of earthquake sources in the present invention;
[0039] Figure 3 It is a schematic diagram of the on-site arrangement of seismic sensors in the working faces 116 and 126 of a certain mine and their surroundings in the present invention.
[0040] In the figure: 1. Return air chute of working face 126, 2. Inlet air chute of working face 126, 3. Return air chute of working face 116, 4. Inlet air chute of working face 116, 5. Working face 126, 6. Working face 116, 7. Vibration pickup sensor. DETAILED DESCRIPTION
[0041] The present invention will be further described below.
[0042] like Figures 1 to 3 As shown, the present invention provides a P-wave velocity calculation and correction method based on a microseismic monitoring system, comprising the following steps:
[0043] Step 1: For coal mines that have not installed the microseismic monitoring system, install the microseismic monitoring system underground in the coal mine and ensure that it can operate normally; for coal mines that have installed the microseismic monitoring system, directly execute step 2;
[0044] Step 2: In the selected monitoring area underground, the monitoring terminal is used to select the clear and easy-to-identify mining earthquake waveforms or blasting waveforms collected by the earthquake pickup sensor 7 when the P wave arrives;
[0045] When the waveform is a blasting waveform, and the blasting source position and blasting time are known, directly execute S31 in step 3;
[0046] When the waveform is a blasting waveform and the blasting source position is known, directly execute S32 in step 3;
[0047] When the waveform is a mine earthquake waveform, directly execute S33 in step 3;
[0048] Step 3: Calculate the P-wave velocity v;
[0049] S31: record the spatial coordinates (x0, y0, z0) of the blasting source, record the blasting time t0, select a monitoring channel for the screened waveform, record the spatial coordinates (x1, y1, z1) of the vibration sensor 7 corresponding to the monitoring channel, mark the monitoring channel, and read the first arrival time of the P wave as t1; then use formula (1) to list the equations for the selected monitoring channel, calculate the P wave velocity v, and then directly execute step 4;
[0050] (x1-x0) 2 +(y1-y0) 2 +(z1-z0) 2 =(v*(t1-t0)) 2 (1);
[0051] S32: record the spatial coordinates (x0, y0, z0) of the blasting source, select at least two monitoring channels for the screened waveform, record them as monitoring channel 1 and monitoring channel 2 respectively, and record the spatial coordinates (x1, y1, z1) and (x2, y2, z2) of the vibration pickup sensor 7 corresponding to the two monitoring channels respectively, mark the waveforms monitored by the two monitoring channels, read the first arrival time of the P wave, record them as t1 and t2 respectively; then use formula (2) to list the equations for the selected two monitoring channels respectively to establish an equation group, calculate the P wave velocity v, and then directly execute step 4;
[0052]
[0053] S33: After preliminarily determining the area where the earthquake source occurs according to the order of the first arrival of the P wave, the five monitoring channels corresponding to the five seismic sensors 7 that receive the first arrival of the P wave are preferentially selected; for the five monitoring channels, the spatial coordinates of the five seismic sensors 7 corresponding to them are determined respectively, and are recorded as (x1, y1, z1), (x2, y2, z2), ..., (x5, y5, z5), and then the five monitoring channels are marked to read the first arrival time of the P wave, which are recorded as t1, t2, ..., t5 respectively;
[0054] Define five unknown quantities (x, y, z, v, t), where (x, y, z) is the spatial coordinate of the earthquake source, v is the P-wave velocity (Note: for the large scale of the earth, the P-wave velocity of a small-scale monitoring area in the well is assumed to be constant), and t is the time when the vibration occurs. Use formula (3) to list the equations to be solved for the selected five monitoring channels respectively, and combine the five equations to establish the equation group (4) to calculate the P-wave velocity v, and then directly execute step 4;
[0055] (x i -x) 2 +(y i -y) 2 +(z i -z) 2 =(v*(t i -t)) 2 (3);
[0056] Where: i represents the channel number, i = 1, 2, 3, 4 and 5;
[0057]
[0058] Step 4: The calculated P-wave velocity v has multiple solutions, including real solutions and complex solutions. When the calculated vibration occurrence time is a real solution, it is recorded as t. When it is a complex solution, the real part is recorded as t'. According to the calculated t and t', the P-wave velocity v is determined according to the following judgment principles:
[0059] ① There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , but the complex solution's earthquake occurrence time t' is greater than the time t i , or there are only real solutions, take the real solution as the result;
[0060] ② The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , but there exists a complex solution where the earthquake occurrence time t' is less than the arrival time t of the receiving wave of each monitoring channel i , or if there are only complex solutions, take the modulus of the complex solution as the result;
[0061] ③ There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , and the occurrence time t' of the complex solution is also less than the time t i , take the average value of the modulus of the complex solution and the real solution that meet the conditions as the result;
[0062] ④ The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i, and the complex solution's earthquake occurrence time t' is also greater than the time t when each monitoring channel receives the waveform i , then delete this group of solutions;
[0063] Step 5: Select the mining vibration waveform or blasting waveform that meets the requirements of step 2 in the selected monitoring area underground, and solve the P-wave velocity v according to steps 3 and 4 respectively; if the number of P-wave velocities v obtained does not exceed 10 (including 10), remove the maximum and minimum values and use the average method to calculate the P-wave velocity v0; conversely, if the number of P-wave velocities v obtained is greater than 10, use the average method or median method to calculate the P-wave velocity v0 when the degree of dispersion is small, and use the majority method to calculate the P-wave velocity v0 when the degree of dispersion is large;
[0064] Step 6: According to the P-wave velocity v0 of the selected monitoring area in the well solved in step 5, the vibration of the known source position (i.e., the artificially excited source) in the monitoring area is used to locate and solve the theoretical value of the known source position through the microseismic monitoring system written with the P-wave velocity v0, and the theoretical value of the known source position is compared with the actual value of the known source position. If the plane error is not greater than ±20m and the vertical error is not greater than ±50m, it is determined that the solved P-wave velocity v0 of the monitoring area meets the actual situation on site; otherwise, it is determined that the solved P-wave velocity v0 of the monitoring area does not meet the actual situation on site, and it is deleted, and the final P-wave velocity v is optimized and adjusted again according to steps 1 to 5 until the solved P-wave velocity v0 of the monitoring area meets the actual situation on site, thereby determining the P-wave velocity v0. P .
[0065] In order to select a clearer and more reasonable waveform, the selected monitoring area in step 2 is an area without geological structure, not affected by mining disturbance, and without electrical equipment interfering with the vibration wave signal, and at least 5 vibration sensors 7 are installed around the monitoring area.
[0066] In order to ensure the accuracy of calculation, in step 3 S31, a millisecond meter is used to record the blasting time t0 during the actual blasting, and the clock of the millisecond meter used is synchronized with the clock inside the microseismic monitoring system.
[0067] In order to improve the efficiency and accuracy of the solution, the Vpasolve algorithm of Matlab software is used for auxiliary calculation in the solution process in step three.
[0068] In order to improve the accuracy of the solution, in step five, for the selected monitoring area, a mine earthquake waveform or a blasting waveform that is within one month of the waveform in step two is selected.
[0069] In order to fully understand the propagation speed and characteristics of the shock wave, in step 6, according to the determined P wave velocity vP and the S wave velocity v S The relationship between formula (5) is used to solve the S wave velocity v S ;
[0070]
[0071] The present invention will be further described below in conjunction with embodiments:
[0072] Embodiment 1:
[0073] A mine is equipped with a microseismic monitoring system, in which a number of underground seismic sensors 7 (the number is greater than 5) are arranged. There are 6 monitoring channels 1# to 6# in total, which can be connected to 6 seismic sensors 7. The partial schematic diagram is shown in FIG. Figure 3 As shown, in Figure 3 There are 126 working face return air chute 1, 126 working face inlet air chute 2, 116 working face return air chute 3, 116 working face inlet air chute 4, 126 working face 5, 116 working face 6, and seismic sensor 7. In the monitoring area surrounded by seismic sensor 7, the monitoring terminal is used to screen out the clear and easy-to-identify mine seismic waveforms collected by seismic sensor 7 when the P wave arrives, and the five monitoring channels that receive the first arrival of the P wave are preferentially selected as monitoring channel 1, monitoring channel 2, monitoring channel 3, monitoring channel 4, and monitoring channel 5.
[0074] For the above five monitoring channels, the spatial coordinates (x1, y1, z1), ..., (x5, y5, z5) of each corresponding vibration pickup sensor 7 are determined to be (34581192.75, 4026923.04, 1148.18), (34581572.19, 4027107.51, 1195.24), (34581371.63, 4026705.27 3, 1103.24), (34581083.66, 4026705.573, 1101.56), (34581548.96, 4026928.452, 1165.414), these 5 monitoring channels are calibrated, and the first arrival time of the P wave is read, which are t1=3.555, t2=3.614, t3=3.611, t4=3.6, t5=3.61 respectively. Define the spatial coordinates of the earthquake source as (x, y, z), the velocity of the P wave as v, and the time of the vibration as t, with a total of 5 unknown quantities (x, y, z, v, t). Substitute the above parameters to establish a quadratic equation of five variables as follows.
[0075]
[0076] The Vpasolve method of Matlab software is used to solve the above equation group (6). The calculated P-wave velocity v has some real solutions and some complex solutions. The P-wave velocity v is determined according to the following judgment principle:
[0077] ① There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , but the earthquake occurrence time t' (real part) of the complex solution is greater than the time t when each monitoring channel receives the waveform i , or there are only real solutions, take the real solution as the result;
[0078] ② The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , but there exists a complex solution where the earthquake occurrence time t' (real part) is less than the arrival time t of the receiving wave of each monitoring channel i , or if there are only complex solutions, take the modulus of the complex solution as the result;
[0079] ③ There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , and the occurrence time t' (real part) of the complex solution is also less than the time t when each monitoring channel receives the waveform i , take the average value of the modulus of the complex solution and the real solution that meet the conditions as the result;
[0080] ④ The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , and the complex solution's earthquake occurrence time t' (real part) is also greater than the time t when each monitoring channel receives the waveform i , then delete this group of solutions.
[0081] The final result of P-wave velocity v was determined to be 4320.87 m / s.
[0082] In order to reduce the calculation error of the P-wave velocity v, the remaining 9 mine earthquake waveforms that meet the requirements are selected in the monitoring area surrounded by the seismic sensor 7 around the 116 and 126 working faces, and the P-wave velocity v is obtained according to the above steps. The results are: 4146.09, 4188.41, 4320.87, 4213.49, 4148.1, 4348.14, 4305.6, 4632.73, 4554.67, 4481.44, in units of m / s.
[0083] Since the number of solved P-wave velocities v does not exceed 10, the maximum and minimum values are removed and the average method is used to calculate the P-wave velocity v0 as 4320.09 m / s.
[0084] The P wave velocity v0 of the monitoring area obtained according to the above steps is 4320.09 m / s. Using the waveform of a blast in the monitoring area, the microseismic monitoring system (writes the obtained P wave velocity v0) is used to locate and obtain the location of the earthquake source as (34581325.46, 4026691.8, 1224.28). Compared with the actual location of the blasting in the well (34581315.26, 4026692.95, 1201.18), the maximum plane error is 10.2m, which is no more than ±20m, and the maximum vertical error is 23.1m, which is no more than ±50m. Therefore, the P wave velocity v0 of the monitoring area is in line with the actual situation on site and is determined as the P wave velocity v P .
[0085] In the present invention, different numbers of monitoring channels are used for calibration of blasting waveforms and mine shock waveforms, and different numbers of equations are used to solve the P wave velocity, which can not only quickly and efficiently calculate and correct the accurate P wave velocity in the most reasonable way, so that the calculated P wave velocity conforms to the actual situation on site, which is of great significance to improving the accuracy and reliability of microseismic monitoring, but also helps to avoid the waste of computing power. The method can calculate the P wave velocity and correct the original wave velocity through the monitored mine shock waveform or blasting waveform, optimize and adjust the P wave velocity in the monitoring area, significantly improve the accuracy of the microseismic monitoring system in locating mine shocks, and is conducive to high-precision positioning of the source. At the same time, the propagation speed and characteristics of the shock wave can be more accurately understood through this method, which is helpful to improve the accuracy of rock burst prediction, and lay a reliable technical foundation for monitoring and warning of rock burst danger, thereby significantly reducing the harm caused by it and effectively ensuring the safe production of coal mines.
Claims
1. A P-wave velocity calculation and correction method based on microseismic monitoring system, It is characterized in that The steps include: Step 1: For coal mines that have not installed the microseismic monitoring system, install the microseismic monitoring system underground in the coal mine and ensure that it can operate normally; for coal mines that have installed the microseismic monitoring system, directly execute step 2; Step 2: In a selected monitoring area underground, the monitoring terminal is used to select the clear and easily identifiable mining earthquake waveform or blasting waveform collected by the earthquake pickup sensor (7) when the P wave arrives; When the waveform is a blasting waveform, and the blasting source position and blasting time are known, directly execute S31 in step 3; When the waveform is a blasting waveform and the blasting source position is known, directly execute S32 in step 3; When the waveform is a mine earthquake waveform, directly execute S33 in step 3; Step 3: Calculate the P-wave velocity v; S31: record the spatial coordinates of the blast source (x 0 ,,y 0 , z 0 ), record the firing time t 0 , select a monitoring channel for the filtered waveform, and record the spatial coordinates (x 1 ,y 1 , z 1 ), the monitoring channel is calibrated and the first arrival time of the P wave is read as t 1 ; Then use formula (1) to list the equations for the selected monitoring channel, calculate the P wave velocity v, and then directly execute step 4; (x 1 -x 0 ) 2 +(y 1 -y 0 ) 2 +(z 1 -z 0 ) 2 =(v*(t 1 -t 0 )) 2 (1); S32: record the spatial coordinates of the blasting source (x 0 ,,y 0 , z 0 ), select at least two monitoring channels for the filtered waveform, record them as monitoring channel 1 and monitoring channel 2 respectively, and record the spatial coordinates (x 1 ,y 1 , z 1 )、(x 2 ,y 2 , z 2 ), the waveforms monitored by the two monitoring channels are calibrated, and the first arrival time of the P wave is read, which is recorded as t 1 ,t 2 ; Then use formula (2) to list equations for the two selected monitoring channels to establish an equation group, calculate the P wave velocity v, and then directly execute step 4; S33: After preliminarily determining the area where the earthquake source occurs according to the order of the P wave first arrival, the five monitoring channels corresponding to the five seismic sensors (7) that receive the P wave first arrival are preferentially selected; for the five monitoring channels, the spatial coordinates of the five seismic sensors (7) corresponding to them are respectively determined and recorded as (x 1 ,y 1 , z 1 )、(x 2 ,y 2 , z 2 ),……、(x 5 ,y 5 , z 5 ), and then the above five monitoring channels are calibrated to read the first arrival time of the P wave, which are recorded as t 1 ,t 2 ,……,t 5 ; Define five unknown quantities (x, y, z, v, t), where (x, y, z) is the spatial coordinate of the earthquake source, v is the P-wave velocity, and t is the time when the vibration occurs. Use formula (3) to list the equations to be solved for the five selected monitoring channels respectively, and then combine the five equations to establish the equation group (4) to calculate the P-wave velocity v, and then directly execute step 4; (x i -x) 2 +(y i -y) 2 +(z i -z) 2 =(v*(t i -t)) 2 (3); Where: i represents the channel number, i = 1, 2, 3, 4 and 5; Step 4: The calculated P-wave velocity v has multiple solutions, including real solutions and complex solutions. When the calculated vibration occurrence time is a real solution, it is recorded as t. When it is a complex solution, the real part is recorded as t'. According to the calculated t and t', the P-wave velocity v is determined according to the following judgment principles: ① There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , but the earthquake occurrence time t' of the complex solution is greater than the time t i , or there are only real solutions, take the real solution as the result; ② The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , but there exists a complex solution where the earthquake occurrence time t' is less than the arrival time t of the receiving wave at each monitoring channel i , or if there are only complex solutions, take the modulus of the complex solution as the result; ③ There exists a real number solution where the earthquake occurrence time t is less than the time t when each monitoring channel receives the waveform i , and the occurrence time t' of the complex solution is also less than the time t i , take the average value of the modulus of the complex solution and the real solution that meet the conditions as the result; ④ The real number solution’s earthquake occurrence time t is greater than the time t when each monitoring channel receives the waveform i , and the complex solution's earthquake occurrence time t' is also greater than the time t when each monitoring channel receives the waveform i , then delete this group of solutions; Step 5: Select the mining waveform or blasting waveform that meets the requirements of step 2 in the selected monitoring area underground, and solve the P-wave velocity v according to steps 3 and 4 respectively; if the number of P-wave velocities v obtained does not exceed 10, remove the maximum and minimum values and use the average method to calculate the P-wave velocity v 0 On the contrary, if the number of P wave velocities v obtained is greater than 10, the mean method or median method is used to calculate the P wave velocity v when the degree of dispersion is small. 0 When the degree of dispersion is large, the P wave velocity v is calculated by the majority method. 0 ; Step 6: Calculate the P-wave velocity v of the selected monitoring area in the well according to the solution in step 5 0 , using the vibration of the known source location in the monitoring area, by writing the P wave velocity v 0 The microseismic monitoring system locates and solves the theoretical value of the known source position, and compares the theoretical value of the known source position with the actual value of the known source position. If the plane error is not greater than ±20m and the vertical error is not greater than ±50m, the P wave velocity v of the monitored area is determined. 0 If it is consistent with the actual situation on site, then the P wave velocity v of the monitored area is determined. 0 If it does not conform to the actual situation on site, it will be deleted, and the final P-wave velocity v will be optimized and adjusted again according to steps 1 to 5 until the P-wave velocity v of the monitored area is solved. 0 In line with the actual situation on site, the P wave velocity v is determined P .
2. According to claim 1, a P-wave velocity calculation and correction method based on a microseismic monitoring system, It is characterized in that The selected monitoring area in step 2 is an area without geological structures, not affected by mining disturbances, and without electrical equipment interfering with the vibration wave signal, and at least five vibration sensors (7) are installed around the monitoring area.
3. According to the method for calculating and correcting P-wave velocity based on a microseismic monitoring system according to claim 1, It is characterized in that In step 3, S31, during the actual blasting, a millisecond meter is used to record the blasting time t 0 , and the clock of the millisecond meter used is synchronized with the clock inside the microseismic monitoring system.
4. According to claim 3, a P-wave velocity calculation and correction method based on a microseismic monitoring system, It is characterized in that In the process of solving the problem in step three, the Vpasolve algorithm of Matlab software is used for auxiliary calculation.
5. According to claim 4, a method for calculating and correcting P-wave velocity based on a microseismic monitoring system, It is characterized in that In step five, for the selected monitoring area, a mine earthquake waveform or a blasting waveform that is within one month of the waveform in step two is selected.
6. A P-wave velocity calculation and correction method based on a microseismic monitoring system according to claim 5, It is characterized in that In step 6, the S-wave velocity v is further solved according to formula (5): S ;