Intelligent informatization rapid installation system for bridge wet joint formwork and construction method
Through the intelligent information-based rapid installation system of bridge wet seam templates, the automation technology of mobile lifting devices and track components is used to solve the existing problems of low construction efficiency and large labor investment, and the efficient installation and accuracy of bridge wet seam templates are achieved. Position positioning, suitable for various types of prefabricated bridge construction.
Patent Information
- Application Number
- CN202411146030.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-15
AI Technical Summary
The existing bridge wet joint construction methods are inefficient and labor investment is large, especially under conditions such as crossing rivers and seas.
The intelligent information-based rapid installation system of bridge wet seam templates is adopted, including mobile lifting devices, track components and template components. The fixed length walking of mobile lifting devices, electric jack driving of track components and magnetic adsorption and fixing of template components are realized. Automatic installation and precise positioning.
It improves the installation efficiency of wet seam formwork, reduces labor investment, and is suitable for various types of prefabricated bridge construction, especially in complex terrain and environments, and realizes the possibility of large-scale production.
Smart Images

Figure CN118958150A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a bridge wet joint construction process, and in particular to an intelligent information-based rapid installation system and a construction method for a bridge wet joint template. Background Art
[0002] In highway bridge construction, precast beams, as an important component of highway beam bridges, are used in the upper structure of highway beam bridge assembly due to their many advantages such as short production cycle, mass production and good quality. Early prefabricated beam bridges generally adopted a simply supported beam structure. After later development, bridges with simple support followed by continuous structure have been widely used due to their good structural stability, fast beam and slab hoisting speed, and large-scale prefabrication in advance. This structural form can effectively shorten the construction period and ensure construction quality and safety. Precast beams are changed from simply supported to continuous beams, and the gaps between beams are generally connected and fixed by cast-in-place concrete, that is, wet joints. Wet joints are set between precast beams and slabs of bridges. The width of the wet joints is related to the size of the bridge, which is approximately between 30cm and 60cm, and the length is the same as the length of the bridge.
[0003] At present, there are two main methods for wet joint construction on highway bridges: full-span scaffolding construction and hanging formwork construction. Due to the limitations of bridge height, foundation below, and various unfavorable conditions below (crossing rivers, crossing seas, etc.), the full-span scaffolding method is less and less used; while hanging formwork construction, by hanging the wet joint bottom formwork on the bridge deck and fixing the bottom formwork, is currently mostly done manually or by some manual wet joint mobile lifting devices for semi-manual construction, which has the disadvantages of low construction efficiency and high labor input. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide an intelligent information-based rapid installation system and construction method for bridge wet joint templates, so as to improve construction efficiency, reduce construction costs and reduce labor input.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: A bridge wet joint formwork intelligent information-based rapid installation system, comprising a mobile lifting device, a track assembly, and a formwork assembly; The mobile lifting device comprises a main truss, a travel wheel is installed at the lower end of the main truss, and the travel wheel is driven by a driving device to intermittently travel a fixed distance; at least two groups of winches are installed on the main truss at intervals along the length direction, and the end of the hoisting rope of each group of winches is connected to an electromagnet; The track assembly comprises a track body, which is laid on the prefabricated beams on the left and right sides of the wet joint, the upper parts of the left and right track bodies are for running wheels, and the lower parts of the left and right track bodies are arranged with multiple groups of through holes at intervals along the length direction, and the two ends of the track beam pass through the through holes and are driven up and down by electric jacks; The template assembly includes a template body, and a plurality of template hanging points are arranged on the upper end surface of the template body, and the template hanging points are fixed or detached with corresponding electromagnets by magnetic adsorption; a plurality of groups of hanging rods are fixed on the front and back of the template body, and the hanging rods are covered with sheaths, and the tops of the hanging rods are detachably connected to hooks, and the hooks are correspondingly hung or detached with the track beams.
[0006] The fixed length of the movable lifting device is equal to the length of one template body.
[0007] A ceiling is fixed on the top of the main truss.
[0008] The track body is formed by laying a plurality of I-beams smoothly and straightly, the length of each I-beam matches the length of the template and through holes are opened at the front and rear ends, and the length of the through holes is greater than the diameter of the track beam.
[0009] The template body is made of steel template, and the template hanging points are made of strong suction magnets.
[0010] When the hook is connected to the track beam, a gap of 3cm-5cm is maintained between the upper end surface of the template body and the lower end surface of the horizontal part of the prefabricated beam.
[0011] The electric jack is installed in the lower wing plate groove of the track body through a connecting plate, and a pressure sensor is arranged at the contact position between the upper end of the electric jack and the track cross beam.
[0012] A method for quickly installing a bridge wet joint formwork using an intelligent information-based rapid installation system comprises the following steps: Step 1) Laying the track assembly: Lay the track assembly along both sides of the wet joint of the prefabricated beam. The width of the track assembly is consistent with the spacing between the left and right running wheels of the mobile lifting device. Step 2) Place the mobile lifting device: Place the mobile lifting device in the inner groove of the wing plate on the track, and debug the mobile lifting device's travel distance by controlling the power-on time of the drive device each time to ensure that the mobile lifting device's travel distance is equal to the template length; Step 3) Place the formwork components: If the conditions are met on site and there are no bad conditions for crossing under the bridge, lay the formwork components one by one along the direction of the wet joints under the bridge; if the conditions for laying are not met on site, the formwork components can be concentrated at several points to ensure that the shaking of the formwork components during the lifting process does not hit the bridge piers and operators; if there are rivers or seas under the bridge, the formwork components can be placed on a ship, and the ship follows the mobile lifting device on the bridge to ensure the lifting of the formwork components; Step 4) Lift the formwork assembly: After the formwork assembly is placed, put the plastic tube on the hanging rod, and the hanging rod and the hook are connected to form a whole; then the winch is started and the hanging rope falls; the electromagnet at the end of the hanging rope is manually aligned with the formwork hanging point of the formwork body; after alignment, the electromagnet is energized to attract the formwork hanging points on both sides of the formwork body, and the formwork assembly is evenly lifted by the winch; Step 5) Hang the template assembly on the beam: lift the template assembly until the four hooks are hung on the two track beams and then close the winch; the electromagnet is powered off and detached from the template hanging point; start the winch again and make the lifting rope completely reel in the winch; Step 6) Tighten the template: After the template assembly is hung on the track beam, start the four sets of electric jacks to push the track beam upward; when the pressure sensors of the four sets of electric jacks reach the set pressure, the template and the wing plate of the precast beam fit tightly, and the electric jacks stop pushing; at the same time, the mobile lifting device starts to start; Step 7), the mobile lifting device moves, and the next mold is constructed: the mobile lifting device moves forward, and the walking distance is equal to the length of a template, and reaches the installation position of the next template component, and repeats steps 4) to 6) to continue the lifting and installation construction of the next template component; Step 8) Concrete pouring: After all the formwork components are installed, fill the joint gaps between the formwork bodies with foam glue sealant to avoid leakage during pouring. After the gaps are filled, pour concrete; Step 9) Remove the formwork: After the concrete reaches the designed removal strength, remove the formwork assembly; before removal, retract the electric jack and move the track beam downward, so that the formwork body moves downward and loosens the wing plate of the precast beam; lift the hook a short distance and twist the hook to separate the hook from the hanging rod, and remove the formwork body and hanging rod; in the process of removing the formwork body, in order to prevent the formwork body from falling freely and damaging the formwork body, each formwork body is tied with a rope when removing the last hanging rod, and slowly removed through the hole.
[0013] The present invention provides a bridge wet joint formwork intelligent information rapid installation system and construction method, which has the following technical effects: 1) By setting up a mobile lifting device, the formwork assembly can be lifted and the formwork assembly can be assisted to be hung on the track assembly; the mobile lifting device can be moved at a fixed length and can face each set of formwork assemblies directly without repeated adjustments.
[0014] 2) By setting up the track assembly, a movable track beam is set on the track assembly, and the track beam is driven to lift by an electric jack; since the length of each section of the track assembly matches the length of the formwork assembly, and the position of the track beam on each section of the track assembly is accurate and corresponds to the position of the hook, multiple sets of formwork assemblies can be automatically spliced and installed in place after being lifted by the electric jack, so that the track assembly not only has the function of providing a track for the mobile lifting device to travel, but also realizes the function of secondary lifting of the formwork body and tightening it on the prefabricated beam for installation. Conventional treatment between the formworks can be performed later to realize pouring.
[0015] 3) By setting a hanging rod with a sheath (plastic tube), the hanging rod and the hook can be detachably connected. When the hook and the hanging rod are installed in the early stage of the formwork, they can not only play a connecting role, but the cooperation between the hook and the track beam can also play a role in positioning the installation position of the formwork, ensuring the accurate position of the formwork and avoiding deviation; at the same time, it can be directly disassembled when the formwork is removed after pouring concrete in the later stage, and the hanging rod, hook and formwork body can be reused.
[0016] 4) The patent "A wet joint construction equipment and wet joint construction method" with application number "202010196861.7" and this application are both applied to wet joints, but there are differences between the two: the main tool of comparative document 1 is a robotic arm, which is used to support and operate the wet joint formwork. Considering the later pouring and curing, according to its relevant description, only the length of one formwork can be poured at a time, which is not conducive to large-scale production. Moreover, the content does not explain how the formwork is placed at the bottom by the robotic arm. According to a reasonable plan to lift it up from below, this process is only suitable for the construction of prefabricated beam and slab short bridges and small bridges. The present invention is mainly integrated in an intelligent and automated lifting device, which can be applied to the construction of all types of prefabricated beam and slab bridges, realizes the automatic installation of the formwork, is closer to reality, and is conducive to large-scale construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 It is the installation schematic diagram of the present invention (front view).
[0018] Figure 2 It is the installation schematic diagram of the present invention (left view).
[0019] Figure 3 for Figure 1 Schematic diagram without precast beams.
[0020] Figure 4 It is a schematic diagram of the main part of the mobile lifting device in the present invention.
[0021] Figure 5 It is the front view of the track body in the present invention.
[0022] Figure 6 It is a schematic diagram of the structure of the template assembly in the present invention.
[0023] Figure 7 It is a schematic diagram of the structure in which the template assembly is hung on the track assembly in the present invention.
[0024] Figure 8 It is a flow chart of the present invention.
[0025] Fig. 9 This is the electrical control block diagram of the present invention.
[0026] In the figure: mobile lifting device 1, track assembly 2, formwork assembly 3, prefabricated beam 4, ceiling 1.1, main truss 1.2, drive device 1.3, winch 1.4, lifting rope 1.5, walking wheel 1.6, electromagnet 1.7, track body 2.1, track beam 2.2, electric jack 2.3, through hole 2.4, formwork body 3.1, formwork hanging point 3.2, hanging rod 3.3, hook 3.4. DETAILED DESCRIPTION
[0027] like Figure 1-2 As shown, a smart information-based rapid installation system for bridge wet joint formwork includes a mobile lifting device 1, a track assembly 2, and a formwork assembly 3.
[0028] like Figure 3-4 As shown, the mobile lifting device 1 includes a main truss 1.2, which constitutes the main structure. A ceiling 1.1 is fixed to the top of the main truss 1.2. The ceiling 1.1 prevents the mobile lifting device 1 from being affected in construction due to bad weather such as rain, snow, and exposure to the sun. A walking wheel 1.6 is installed at the bottom end of the main truss 1.2, and the walking wheel 1.6 is driven by a driving device 1.3. The main part of the driving device 1.3 is installed on the main truss 1.2 and powered by a built-in battery (providing power support for the entire device). The driving device 1.3 includes a belt transmission mechanism + a motor. The motor drives the belt transmission mechanism to rotate, and the belt transmission mechanism drives the walking wheel 1.6 to rotate, thereby providing power for the movement of the mobile lifting device 1.
[0029] A winch 1.4 is arranged on each side of the main truss 1.2, and the two winches 1.4 rotate synchronously in the same direction. The end of the suspension rope 1.5 on the winch 1.4 is welded and fixed with an electromagnet 1.7, the size of which is about 10 cm in diameter, depending on the wet joint width and the weight of the template, to ensure sufficient magnetic force to adsorb and cooperate with the winch 1.4 to lift the template. The wire of the electromagnet 1.7 (wrapped with an insulator) is wound on the wire rope and is guaranteed to be free of force.
[0030] like Figure 4-5As shown, the track assembly 2 includes a track body 2.1, which is made of I-beams and laid in sections (the length of each section is approximately equal to the length of the template, 2 to 3 meters is recommended) smoothly and straightly along the prefabricated beams 4 on both sides of the wet joint. The width between the two track bodies 2.1 on the left and right sides matches the width of the wet joint and the mobile lifting device 1. The walking wheels 1.6 are placed in the upper wing plate groove of the track body 2.1. Through holes 2.4 are opened in the front and back of the lower wing plate of each section of the track body 2.1, and the front and back through holes 2.4 on the left and right track bodies 2.1 are opposite to each other. The two ends of the track beam 2.2 are respectively inserted into the opposite through holes 2.4 of the left and right track bodies 2.1 and partially extend out, and the ends are limited by the clamping plate to prevent the track beam 2.2 from falling off.
[0031] The through hole 2.4 has a certain length in the vertical direction. After the track beam 2.2 extends into the through hole 2.4, the track beam 2.2 can move up and down a short distance along the through hole 2.4. An electric jack 2.3 is arranged under the corresponding beam, and the track beam 2.2 moves up and down under the action of the electric jack 2.3.
[0032] The electric jack 2.3 uses a lithium battery remote-controlled hydraulic electric jack (chargeable), which is placed in the lower wing plate groove of the track body 2.1. The electric jack 2.3 is welded to the connecting plate (steel plate), and the connecting plate (steel plate) is welded to the wing plates on both sides, so that the electric jack 2.3 and the lower wing plate form a whole.
[0033] like Figure 6 As shown, the formwork assembly 3 includes a formwork body 3.1, and the formwork body 3.1 is made of steel formwork, and the magnet has a small suction force on it. Formwork hanging points 3.2 are set on both sides of the formwork body 3.1. There are two sets of formwork hanging points 3.2 and they correspond to the electromagnet 1.7 at the end of the hoisting wire rope. The formwork hanging points 3.2 and the formwork body 3.1 are welded into a whole, ensuring that the template hanging points 3.2 and the panels of the formwork body 3.1 are polished and integrated together, without gaps, protrusions, misalignment, etc., to ensure that the concrete pouring will not leave hanging point marks. The template hanging points 3.2 use strong suction magnets.
[0034] Hanging rods 3.3 are arranged around the formwork body 3.1, and there are four groups of hanging rods 3.3, two groups at the front and back. The hanging rods 3.3 are made of plain round steel bars, and the lower ends of the hanging rods 3.3 are smoothly welded to the formwork body 3.1. The spacing between the front and rear hanging rods 3.3 is consistent with the spacing of the track beam 2.2. The upper end of the hanging rod 3.3 is provided with a threaded section, and the corresponding hook 3.4 is provided with a threaded barrel below, and the threaded barrel is threadedly connected with the threaded section of the hanging rod 3.3 to form a whole. The hook 3.4 is made of plain round steel bars, and the upper end is set to be hook-shaped, which is convenient for hanging on the track beam 2.2.
[0035] In addition, the device is provided with an information system, which includes: a first switch signal receiver arranged on the electric jack, A pressure sensor is arranged on the electric jack, and the pressure sensor and the first switch signal transmitter are arranged between the electric jack and the track beam, and can be arranged to send a signal to the first switch signal receiver and the travel signal receiver of the mobile lifting device when a certain pressure is reached.
[0036] The second switch signal receiver is arranged on the hoist, and the signal received by the receiver can control the on / off of the hoist.
[0037] The third switch signal receiver is arranged on the electromagnet, and the signal received by the third switch signal receiver can control the on / off of the electromagnet.
[0038] The walking signal receiver installed on the mobile lifting device can control the on / off of the walking motor of the mobile lifting device through the walking signal receiver. Each time the walking switch signal of the mobile lifting device is turned on, a certain power-on time is set, which can make the mobile lifting device walk a fixed distance, and the walking distance is equal to the length of the template assembly.
[0039] Main switch control platform, including: A first switch signal transmitter matched with a first switch signal receiver disposed on the electric jack; A second switch signal transmitter matched with a second switch signal receiver provided on the hoist; a third switch signal transmitter cooperating with a third switch signal receiver disposed on the electromagnet; The travel switch signal transmitter cooperates with the travel signal receiver on the mobile lifting device arranged on the mobile lifting device, and these signal transmitters are assembled on a unified flat panel for remote control.
[0040] The signal receiver and the signal transmitter are used for receiving a switch signal and transmitting a signal respectively.
[0041] A method for quickly installing a bridge wet joint formwork comprises the following steps: Step 1), laying the track assembly 2: laying the track assembly 2 along both sides of the wet joint of the prefabricated beam 4, the width of the track assembly 2 is consistent with the distance 1.6 between the left and right running wheels of the mobile lifting device 1; Step 2), place the mobile lifting device 1: place the mobile lifting device 1 in the inner groove of the wing plate on the track, transmit the mobile lifting device walking switch signal through the main switch control platform, debug the mobile lifting device's walking distance by controlling the power-on time of each switch, and ensure that the mobile lifting device's walking distance is equal to the template length; Step 3), placing the formwork assembly 3: if the conditions are met on site and there is no adverse crossing condition under the bridge (soft soil foundation, river, sea, etc.), the formwork assembly 3 is laid one by one along the direction of the wet joint under the bridge; if the conditions for laying are not met on site, the formwork assembly 3 can be concentrated at several points to ensure that the shaking of the formwork assembly 3 during the lifting process does not hit the bridge piers and operators; if there is a river or sea under the bridge, the formwork assembly 3 can be placed on a ship, and the ship follows the mobile lifting device on the bridge to ensure the lifting of the formwork assembly 3; Step 4), lift the template assembly 3: After the template assembly 3 is placed, put a slightly larger diameter plastic PVC pipe on the hanging rod 3.3 (to facilitate the later removal of the template), and the hanging rod 3.3 is connected with the hook 3.4 to form a whole. Through the main switch control platform, the hoisting machine transmits the signal switch, so that the hoisting machine 1.4 rotates to send the lifting rope 1.5 down, and manually aligns the electromagnet 1.7 at the end of the lifting rope 1.5 with the template hanging point 3.2 of the template body 3.1 (if the template body 3.1 is a flat template, the lifting rope 1.5 can be directly lowered, and the electromagnet 1.7 and the template hanging point 3.2 of the flat template are automatically aligned without manual participation). After alignment, turn on the electromagnet switch in the main switch control platform, so that the electromagnet 1.7 is energized to absorb the template hanging points 3.2 on both sides of the template body 3.1, and turn on the hoisting machine switch in the main switch control platform again to lift the template assembly 3 evenly; Step 5), the template assembly 3 is hung on the beam: the total length of the hanging rod 3.3 and the hook 3.4 is set to be slightly larger than the distance h1 between the lower end surface of the precast beam 4 and the upper edge of the track beam 2.2, and h1 is 3cm-5cm; that is, after the hook 3.4 is hung on the track beam 2.2, the gap between the upper end surface of the template body 3.1 and the lower end surface of the horizontal part of the precast beam 4 is 3cm-5cm. This setting makes it easy for the template hook to hang on the track beam and is also convenient for later disassembly.
[0042] Lift the template assembly 3 so that the four hooks 3.4 are hung on the two track beams 2.2. Send a signal to close the electromagnet switch, turn on the winch switch again, and fully reel the lifting rope 1.5 into the winch; Step 6), tighten the template: after the track beam 2.2 is hung on the template assembly 3, the main switch control platform sends a signal to start the four sets of electric jacks 2.3 at the same time, so that the four sets of electric jacks 2.3 push the track beam 2.2 upward; when the pressure sensors of the four sets of electric jacks 2.3 reach the set pressure (this pressure can make the template and the wing plate of the prefabricated beam 4 fit tightly), it is sent to the electric jack switch signal receiver to cut off the power and stop the jacking, and at the same time send a signal to the mobile lifting device walking signal receiver; Step 7), the mobile lifting device 1 moves, and the next mold is constructed: after the mobile lifting device 1 receives the signal sent by the electric jack pressure sensor, it turns on the power and automatically moves forward. The walking distance is equal to the length of a template, and the lifting and installation construction of the template assembly 3 is continued to cycle; Step 8), concrete pouring: After all the formwork components 3 are installed, the joint gaps between the formwork bodies 3.1 are filled with foam glue sealant to prevent leakage during pouring. After the gaps are filled, concrete pouring is performed; Step 9), remove the formwork: After the concrete reaches the standard design removal strength, remove the formwork assembly 3; before removal, the main switch control platform sends a signal to retract the electric jack 2.3, so that the formwork body 3.1 and the wing plate of the prefabricated beam body 4 are loosened; twist the hook 3.4 to separate the hook 3.4 from the hanging rod 3.3, and remove the formwork body 3.1. In the process of removing the formwork body 3.1, prevent the formwork body 3.1 from falling freely and damaging the formwork body 3.1. When removing the last hanging rod 3.3 of each formwork body 3.1, tie the hanging rod 3.3 with a rope and slowly remove it through the hole.
Claims
1. A bridge wet joint formwork intelligent information rapid installation system, characterized by: It comprises a mobile lifting device (1), a track assembly (2), and a template assembly (3); The mobile lifting device (1) comprises a main truss (1.2), a travel wheel (1.6) being installed at the lower end of the main truss (1.2), and the travel wheel (1.6) being driven by a driving device (1.3) to intermittently travel a fixed distance; at least two groups of winches (1.4) are installed at intervals along the length direction on the main truss (1.2), and the end of the hoisting rope (1.5) of each group of winches (1.4) is connected to an electromagnet (1.7); The track assembly (2) comprises a track body (2.1), the track body (2.1) being laid on prefabricated beams (4) on the left and right sides of the wet joint, the upper parts of the left and right track bodies (2.1) being provided with running wheels (1.6), the lower parts of the left and right track bodies (2.1) being provided with a plurality of groups of through holes (2.4) arranged at intervals along the length direction, and the two ends of the track cross beam (2.2) passing through the through holes (2.4) and being driven up and down by an electric jack (2.3); The template assembly (3) comprises a template body (3.1), the upper end surface of the template body (3.1) is provided with a plurality of template hanging points (3.2), the template hanging points (3.2) are fixed or detached from corresponding electromagnets (1.7) by magnetic adsorption; a plurality of groups of hanging rods (3.3) are fixed to the front and rear of the template body (3.1), the hanging rods (3.3) are covered with sheaths, the tops of the hanging rods (3.3) are detachably connected to hooks (3.4), and the hooks (3.4) are correspondingly connected or detached from the track beams (2.2).
2. According to claim 1, a bridge wet joint formwork intelligent information rapid installation system is characterized by: The fixed length of the movable lifting device (1) is the length of one template body (3.1).
3. According to claim 1, a bridge wet joint formwork intelligent information rapid installation system is characterized by: A ceiling (1.1) is fixed to the top of the main truss (1.2).
4. According to claim 1, a bridge wet joint formwork intelligent information rapid installation system is characterized by: The track body (2.1) is formed by laying a plurality of I-beams smoothly and straightly, the length of each I-beam matches the length of the template and both the front and rear ends are provided with through holes (2.4), the length of the through holes (2.4) being greater than the diameter of the track crossbeam (2.2).
5. According to claim 1, a bridge wet joint formwork intelligent information rapid installation system is characterized by: The template body (3.1) is made of steel template, and the template hanging point (3.2) is made of strong suction magnet.
6. According to claim 1, a bridge wet joint formwork intelligent information rapid installation system is characterized by: When the hook (3.4) is correspondingly hooked to the track crossbeam (2.2), a gap is maintained between the upper end surface of the template body (3.1) and the lower end surface of the horizontal part of the prefabricated beam (4), and the gap is 3 cm to 5 cm.
7. According to claim 1, a bridge wet joint formwork intelligent information rapid installation system is characterized by: The electric jack (2.3) is installed in the lower wing plate groove of the track body (2.1) via a connecting plate, and a pressure sensor is provided at the contact position between the upper end of the electric jack (2.3) and the track crossbeam (2.2).
8. A method for rapid installation of a bridge wet joint formwork according to any one of claims 1 to 7, comprising the following steps: Step 1), laying the track assembly (2): laying the track assembly (2) along both sides of the wet joint of the prefabricated beam (4), wherein the width of the track assembly (2) is consistent with the spacing between the left and right running wheels (1.6) of the mobile lifting device (1); Step 2), placing the mobile lifting device (1): placing the mobile lifting device (1) in the inner groove of the wing plate on the track, and adjusting the travel distance of the mobile lifting device (1) by controlling the power-on time of the driving device (1.3) each time, to ensure that the travel distance of the mobile lifting device (1) is equal to the template length; Step 3), placing the formwork components (3): if the conditions are met on site and there are no unfavorable conditions for crossing under the bridge, the formwork components (3) are laid flat one by one along the direction of the wet joints under the bridge; if the conditions for laying flat are not met on site, the formwork components (3) can be placed at several points to ensure that the formwork components (3) do not shake during the lifting process and do not hit the bridge piers and operators; if there is a river or sea under the bridge, the formwork components (3) can be placed on a ship, and the ship follows the mobile lifting device (1) on the bridge to ensure the lifting of the formwork components (3); Step 4) lifting the template assembly (3): after the template assembly (3) is placed, the plastic tube is put on the hanging rod (3.3), and the hanging rod (3.3) is connected with the hook (3.4) to form a whole; then the winch (1.4) is started, and the hanging rope (1.5) falls; the electromagnet (1.7) at the end of the hanging rope (1.5) is manually aligned with the template hanging point (3.2) of the template body (3.1); After alignment, the electromagnet (1.7) is energized to attract the template hanging points (3.2) on both sides of the template body (3.1), and the template assembly (3) is evenly lifted by the winch (1.4); Step 5), the template assembly (3) is hung on the crossbeam: the template assembly (3) is lifted up until the four hooks (3.4) are hung on the two track crossbeams (2.2), and then the winch (1.4) is closed; the electromagnet (1.7) is powered off and separated from the template hanging point (3.2); the winch (1.4) is started again, so that the hanging rope (1.5) is completely rolled into the winch (1.4); Step 6), tighten the template: after the track beam (2.2) is hung on the template assembly (3), start the four sets of electric jacks (2.3) so that the four sets of electric jacks (2.3) push the track beam (2.2) upward; when the pressure sensors of the four sets of electric jacks (2.3) reach the set pressure, the template and the wing plate of the prefabricated beam (4) are tightly fitted, and the electric jacks (2.3) stop pushing; at the same time, the mobile lifting device (1) starts to start; Step 7), the mobile lifting device (1) moves, and the next mold is constructed: the mobile lifting device (1) moves forward, and the walking distance is equal to the length of a template, and reaches the installation position of the next template component (3), and repeats steps 4) to 6) to continue the lifting and installation construction of the next template component (3); Step 8), concrete pouring: After all the formwork components (3) are installed, the joint gaps between the formwork bodies (3.1) are filled with foam glue sealant to prevent leakage during pouring. After the gaps are filled, concrete pouring is performed; Step 9), removing the formwork: after the concrete reaches the design removal strength, the formwork assembly (3) is removed; before removal, the electric jack (2.3) is retracted, the track beam (2.2) is moved downward, and the formwork body (3.1) is moved downward and loosened from the wing plate of the prefabricated beam (4); the hook (3.4) is lifted up a short distance and the hook (3.4) is twisted to separate the hook (3.4) from the hanging rod (3.3), and the formwork body (3.1) and the hanging rod (3.3) are removed; in the process of removing the formwork body (3.1), in order to prevent the formwork body (3.1) from falling freely and damaging the formwork body (3.1), each formwork body (3.1) is tied with a rope when the last hanging rod (3.3) is removed, and the hanging rod (3.3) is slowly removed through the hole.
Citation Information
Patent Citations
Wet joint construction equipment and wet joint construction method
CN111379224A
Cited By
Beam piece formwork-free seamless construction method based on prefabricated bridge
CN119913832A
Rail sliding type bridge reverse hanging bracket system and construction method
CN120739001A
Formwork-free seamless beam piece structure for post-pouring of top plate
CN223837887U