Benefit measuring and calculating method and device for passenger train, computer equipment and storage medium
By obtaining and analyzing the train plan and passenger flow information of passenger trains and calculating the energy consumption of each resource category, the lack of timeliness and accuracy of passenger trains' guarantee point analysis in the existing technology is solved, and the cost of more refined and timeliness is achieved Estimation, suitable for high-density operation evaluation under complex road network conditions.
Patent Information
- Application Number
- CN202411088849.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-15
AI Technical Summary
The existing technology lacks timeliness, accuracy and comprehensiveness in the analysis of the guaranteed points of passenger trains, making it difficult to meet the evaluation needs of high-density trains and frequent daily adjustments under complex road network conditions, mainly because cost calculations rely on railway energy consumption. The liquidation method does not consider passenger flow fluctuations and floating fare strategies, and lacks support from information system.
By obtaining the train plan information of the passenger train, multiple target resource categories are determined, and the energy consumption of each resource category is calculated based on the train plan and passenger flow result information. Combined with the differences in passenger flow factors, the total operating energy consumption and guarantee points of the passenger train are calculated. Provide computer equipment and programs to implement this method.
Improve the comprehensiveness, accuracy and timeliness of passenger train cost estimation, adapt to the evaluation needs of high-density train operation and frequent adjustments under complex road network conditions, consider various resource categories and passenger flow factors, and improve the refinement of calculations and Real-time.
Smart Images

Figure CN118966546A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of energy consumption planning of rail transit, and in particular, to a benefit calculation method for a passenger train, a benefit calculation device for a passenger train, a computer device, and a computer storage medium. Background Art
[0002] With the continuous construction of high-speed railway networks, the continuous opening of passenger-dedicated line trains and the growing passenger demand, in order to meet the differentiated travel needs of different passengers at different times, it is necessary to continuously optimize the train operation structure, continuously practice and explore diversified operation modes to adapt to market changes. The corresponding train operation diagram also presents a new normal of "one diagram per day" with the flexible and changeable market demand. And the flexibility and variability of the above-mentioned passenger trains also put forward higher requirements for the benefit calculation of passenger trains. In the process of benefit calculation of passenger trains, break-even point analysis is an important basis for passenger train operation adjustment decisions, and plays a very important and positive role in reducing costs and increasing efficiency of railway transportation enterprises. It is usually calculated by the ratio of the total cost of passenger trains to the income of all employees throughout the journey.
[0003] In the relevant technical scheme, the break-even point analysis of passenger trains is carried out by the following method: manual estimation based on manual experience, that is, the benefit estimation personnel make subjective judgments on each passenger train according to historical operating experience, and then simply divide the trains according to the number of trips based on the annual train total budget, and estimate the break-even point.
[0004] However, the above technical solutions are mainly restricted by the following factors: (1) The current cost estimation is mainly based on the railway energy consumption settlement method, which leads to the fact that the operating cost expenditure of the railway transportation enterprise itself is not taken into account. The break-even point determined is often too small, and the method of annual or monthly average division lacks consideration of the differences in the actual daily train operation; (2) In some cost estimation processes, it is necessary to estimate the train passenger flow, but the existing break-even point analysis often does not take into account the passenger flow fluctuations and uneven distribution, and does not consider the impact of the floating ticket price strategy on revenue. The integration of the three is not sufficient; (3) At present, there is no information system support for the break-even point analysis of passenger trains within the railway industry. The pressure of manual collection and processing is too great, which leads to the lack of timeliness, accuracy and comprehensiveness of the break-even point analysis of passenger trains. It is difficult to meet the evaluation needs of high-density train operation and frequent daily adjustments under the existing complex road network conditions. Summary of the invention
[0005] The embodiments of the present application provide a method for calculating the benefits of a passenger train, a device for the method, a computer device and a computer storage medium, thereby overcoming, at least to a certain extent, the technical problems that the timeliness, accuracy and comprehensiveness of the break-even point analysis of passenger trains are insufficient due to the limitations and defects of related technologies, and it is difficult to meet the evaluation requirements of high-density train operation and frequent daily adjustments under the existing complex road network conditions.
[0006] A first aspect of an embodiment of the present application provides a method for calculating the benefits of a passenger train, which is applied to calculating and planning the total operating energy consumption of a passenger train, the method comprising: obtaining train plan information corresponding to the passenger train; determining a plurality of target resource categories corresponding to the passenger train, and based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, determining the energy consumption value corresponding to each target resource category of the passenger train, so as to obtain the total operating energy consumption of the passenger train based on the energy consumption value of each target resource category; and calculating the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train.
[0007] The second aspect of the embodiment of the present application provides a benefit calculation device for a passenger train, which includes: an information acquisition module, used to obtain train plan information corresponding to the passenger train; a determination module, used to determine multiple target resource categories corresponding to the passenger train according to the transportation resource category, and determine the energy consumption value corresponding to each resource category of the passenger train based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, so as to obtain the total operating energy consumption of the passenger train based on the energy consumption value of each target resource category; a break-even point calculation module, used to calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train.
[0008] According to a third aspect of an embodiment of the present application, a computer device is provided, including a memory and a processor, wherein the memory stores a computer program, and when the processor executes the computer program, the steps of any of the above passenger train benefit calculation methods are implemented.
[0009] According to a fourth aspect of an embodiment of the present application, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, the steps of the method for calculating the benefit of a passenger train as described in any one of the above items are implemented.
[0010] A fifth aspect of an embodiment of the present application provides a computer program product, including a computer program, which is executed by a processor to implement the steps of any one of the above passenger train benefit calculation methods.
[0011] The technical solution of this application has the following beneficial effects:
[0012] Through the passenger train benefit calculation method, the train plan information corresponding to the passenger train is obtained; multiple resource categories corresponding to the passenger train are determined according to the transportation resource category, and based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, the energy consumption value corresponding to each resource category of the passenger train is determined to obtain the total operating energy consumption of the passenger train; the break-even point of the passenger train is calculated based on the total operating energy consumption and the total operating income of the passenger train. This method obtains the train plan information of the passenger train to determine the operation and stop information of the passenger train, and when determining the total operating energy consumption of the passenger train, the energy consumption of each resource category of the passenger train is considered, and combined with the differences in passenger flow factors, the break-even point calculation result of the passenger train is more refined and more in line with the actual evaluation needs of railway transportation enterprises. The cost of various resource categories of passenger trains is also taken into account. Compared with the related technical solutions that only use the current railway energy consumption collection and payment settlement method for manual calculation, the method proposed in this application can improve the comprehensiveness, accuracy and timeliness of the total cost estimation of passenger trains, and thus is more suitable for the evaluation needs of high-density train operation and frequent daily adjustments under the existing complex road network conditions. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0014] Figure 1 An architectural diagram of a passenger train benefit calculation system provided in accordance with an embodiment of the present application;
[0015] Figure 2 A flow chart of a method for calculating the benefits of a passenger train provided in one embodiment of the present application;
[0016] Figure 3 A flow chart schematically shows a method for calculating vehicle traction energy consumption in this exemplary embodiment;
[0017] Figure 4 A flow chart of a method for determining the passenger flow ratio coefficient of each intermediate stop provided in one embodiment of the present application;
[0018] Figure 5 A schematic diagram of the structure of a benefit calculation device for a passenger train provided in one embodiment of the present application;
[0019] Figure 6 A schematic diagram of the computer device structure provided for one embodiment of the present application. DETAILED DESCRIPTION
[0020] Example embodiments will now be described more fully with reference to the accompanying drawings. However, example embodiments can be implemented in a variety of forms and should not be construed as being limited to the examples set forth herein; on the contrary, these embodiments are provided so that the present disclosure will be more comprehensive and complete, and the concepts of the example embodiments are fully conveyed to those skilled in the art. The described features, structures, or characteristics may be combined in one or more embodiments in any suitable manner. In the following description, many specific details are provided to provide a full understanding of the embodiments of the present disclosure. However, those skilled in the art will appreciate that the technical solutions of the present disclosure may be practiced while omitting one or more of the specific details, or other methods, components, devices, steps, etc. may be adopted. In other cases, known technical solutions are not shown or described in detail to avoid obscuring various aspects of the present disclosure.
[0021] In addition, the accompanying drawings are only schematic illustrations of the present disclosure and are not necessarily drawn to scale. The same reference numerals in the figures represent the same or similar parts, and their repeated description will be omitted. Some of the block diagrams shown in the accompanying drawings are functional entities and do not necessarily correspond to physically or logically independent entities. These functional entities can be implemented in software form, or implemented in one or more hardware modules or integrated circuits, or implemented in different networks and / or processor devices and / or microcontroller devices.
[0022] The flowcharts shown in the accompanying drawings are only exemplary and do not necessarily include all the steps. For example, some steps may be decomposed, while some steps may be combined or partially combined, so the actual execution order may change according to the actual situation.
[0023] With the continuous construction of high-speed railway network, the continuous opening of passenger dedicated lines and the growing passenger demand, on the one hand, in order to meet the differentiated travel needs of different passengers at different times, it is necessary to continuously optimize the train operation organization, continuously practice and explore diversified operation modes to adapt to market changes. The train operation diagram has changed from the past "one adjustment every few years" to "multiple adjustments a year". For example, under the organization of the National Railway Group, four basic diagram adjustments and two temporary passenger diagram adjustments for the Spring Festival and Summer Travel are carried out every year. In addition, each railway bureau group company will also organize the adjustment of the train operation diagram within the scope of the bureau. The train operation diagram is based on the operation plan of the basic diagram passenger train. In the early stage of the diagram adjustment, the National Railway Group organized the passenger transportation departments of each railway bureau group company to prepare the adjustment plan and held several consultations and discussions. After the plan is basically confirmed, the drawing of the train operation diagram can be started. Among them, the preparation content of the operation plan of the above-mentioned basic diagram passenger train includes optimization adjustment types (such as additional operation, suspension, change of route, change of section, change of operation rules, reorganization of group rules, etc.) and various elements of the operation plan. On the other hand, with the transformation of the railway operating system in recent years, railway operation management has changed from "extensive and experience-based" to "fine and scientific", and the "one-day-one-chart" train operation has become the new normal. The scientific and reasonable design and management of passenger train operation plans based on flexible and changeable market demands play a key role in maximizing railway transportation revenue. This requires that during the implementation period of the basic chart, according to the actual passenger flow fluctuations, the train break-even point should be accurately evaluated, and the passenger train operation plan should be dynamically adjusted to achieve the optimal match between transportation capacity and passenger flow demand. In addition, in daily actual operations, when encountering abnormal and emergency situations, it is also necessary to quickly adjust the passenger train operation plan to control the loss of benefits and quickly restore transportation order.
[0024] The break-even point analysis in the process of benefit measurement is an important basis for the decision-making of railway passenger train operation adjustment, and plays a positive role in reducing costs and increasing efficiency for railway transportation enterprises. It is generally calculated by the ratio of total energy consumption of the train to the total income of all employees throughout the journey. In addition, in the stages of preparing railway passenger train operation plans, operation diagrams, ticket quota plans, and fare plans, dynamically evaluating the break-even points under different passenger train plans and guiding the adjustment and optimization of plans are important means for railway transportation enterprises to improve their own operating capabilities under the background of market-oriented reforms.
[0025] For a long time, the benefit calculation of passenger trains has been mainly based on the following two methods: manual calculation based on manual experience. That is, based on the transfer and payment energy consumption settlement data of the railway company's capital settlement center and the 123 tables maintained manually on a daily basis and the relevant cost quota data during the train operation, and with the help of office software such as Excel, calculations can be performed. However, this process inevitably has a series of technical problems such as large workload, easy errors in manual reduction, poor data timeliness, insufficient accuracy, and long time consumption, which makes it difficult to ensure the accuracy and real-time nature of the calculation results; and a complete and systematic evaluation index system for the benefit of running trains has not yet been established, which seriously affects the efficiency and quality of the preparation of train plans. Secondly, under the influence of the operating and management system of two lines of revenue and expenditure, passenger ticket revenue and passenger flow data are controlled by the passenger transport department, and cost data are controlled by the financial department. The revenue and expenditure data are scattered and the data use efficiency is low. In addition, the current manual method, relying on work experience, and using Excel, word and other tools to evaluate and optimize the plan is difficult to meet the actual work needs. It is urgent to use information and intelligent means to assist decision-making departments in multi-dimensional and intelligent benefit measurement, benefit evaluation and analysis and decision-making. In summary, the above-mentioned technical solutions are insufficient in timeliness, accuracy and comprehensiveness, and are difficult to meet the evaluation needs of high-density train operation and frequent daily adjustments under the existing complex railway network conditions.
[0026] This is mainly due to the following reasons: (1) The current cost calculation is mainly based on the railway's energy consumption settlement method, which results in the railway transportation company's own operating cost expenditure not being taken into account, the break-even point is often too small, and the annual or monthly average method lacks consideration of the differences in the actual daily train operations, and lacks a comprehensive cost and revenue calculation method; (2) In some cost calculation processes, it is necessary to estimate train passenger flow, and the existing break-even point analysis often does not take into account passenger flow fluctuations and uneven distribution, and does not consider the impact of floating ticket price strategies on revenue. The integration of the three is not sufficient; (3) At present, there is no information system support for the break-even point analysis of passenger trains within the railway industry, and the pressure of manual collection and processing is too great.
[0027] Therefore, there is an urgent need for a passenger train benefit calculation method with strong real-time, high accuracy and comprehensiveness, specifically a passenger train break-even point calculation method, to meet the evaluation needs of high-density train operation and frequent daily adjustments under the existing complex road network conditions.
[0028] Taking the above problems into consideration, the exemplary embodiment of the present disclosure proposes a method for calculating the benefits of a passenger train, which can obtain the train plan information corresponding to the passenger train; determine multiple resource categories corresponding to the passenger train according to the transportation resource category, and determine the cost of each resource category corresponding to the passenger train based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train to obtain the total operating energy consumption of the passenger train; and calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train. The method obtains the train plan information of the passenger train to determine the operation and stop information of the passenger train, and when determining the total operating energy consumption of the passenger train, it takes into account the cost of each resource category of the passenger train, and combines the differences in passenger flow factors, so that the break-even point calculation result of the passenger train is more refined and more in line with the actual evaluation needs of railway transportation enterprises. The cost of various resource categories of passenger trains is also taken into account. Compared with the related technical solutions that only use the current railway energy consumption settlement method for manual calculation, the method proposed in this application can improve the comprehensiveness, accuracy and timeliness of the total cost estimation of passenger trains, and thus is more suitable for the evaluation needs of high-density train operation and frequent daily adjustments under the existing complex road network conditions.
[0029] In order to solve the above problems, the present invention proposes a method and device for calculating the benefits of passenger trains, which can be applied to Figure 1 In the system architecture of the exemplary application environment shown.
[0030] like Figure 1 As shown, the system architecture 100 may include one or more of passenger trains 101, 102, 103, 104, a network 105, and a server 106. The network 105 is used to provide a medium for communication links between the passenger trains 101, 102, 103, 104 and the server 106. The network 105 may include various connection types, such as wired or wireless communication links or optical fiber cables, etc. The passenger trains 101, 102, 103, 104 may be, for example, high-speed trains, EMUs, intercity suburban trains, ordinary trains, or any other passenger trains with networking functions, but are not limited thereto.
[0031] It should be understood that Figure 1The number of passenger trains, networks and servers in the example is only illustrative. Any number of passenger trains, networks and servers may be provided as required. For example, server 106 may be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server providing basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, content delivery networks (CDNs), and big data and artificial intelligence platforms.
[0032] For example, in an exemplary embodiment, the passenger train may include one or more of the plurality of passenger trains 101, 102, 103 or 104. The server 106 may obtain train plan information corresponding to the passenger train; determine a plurality of target resource categories corresponding to the passenger train, and determine the energy consumption value corresponding to each target resource category of the passenger train based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, so as to obtain the total operating energy consumption of the passenger train based on the energy consumption value of each target resource category; and calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train.
[0033] However, it is easy for those skilled in the art to understand that the above application scenarios are only used as examples and are not limited to this in the present exemplary embodiment.
[0034] The following uses the server 106 as the execution subject, and applies the benefit calculation method of the passenger train to the server 106 as an example for illustration. The benefit calculation for the passenger train in the embodiment of the present application refers to the calculation of the operating energy consumption of the passenger train, which includes but is not limited to: vehicle energy consumption, labor energy consumption, road network energy consumption, management energy consumption, service energy consumption, etc., so as to comprehensively calculate the operating energy consumption of the passenger train. Figure 2 A flowchart schematically showing a method for calculating the benefits of a passenger train in this exemplary embodiment is shown in FIG. Figure 2 The benefit calculation method of a passenger train provided in the embodiment of the present disclosure includes the following steps 201 to 203:
[0035] Step 201: Obtain train plan information corresponding to the passenger train.
[0036] Step 202: determine multiple target resource categories corresponding to the passenger train, and determine the energy consumption value corresponding to each target resource category of the passenger train based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, so as to obtain the total operating energy consumption of the passenger train based on the energy consumption value of each target resource category.
[0037] Step 203: Calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train.
[0038] In the technical solutions provided in some embodiments of the present disclosure, train plan information corresponding to a passenger train is obtained; multiple target resource categories corresponding to the passenger train are determined, and based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, the energy consumption value corresponding to each target resource category of the passenger train is determined to obtain the total operating energy consumption of the passenger train; the break-even point of the passenger train is calculated based on the total operating energy consumption and the total operating income of the passenger train. This method obtains the train plan information of the passenger train to determine the operation and stop information of the passenger train, and when determining the total operating energy consumption of the passenger train, the cost of each target resource category of the passenger train is considered, and combined with the differences in passenger flow factors, the break-even point calculation result of the passenger train is more refined and more in line with the actual evaluation needs of railway transportation enterprises. In addition, this application also takes into account the energy consumption values of each target resource category of passenger trains. Compared with the related technical solutions that only use the current railway energy consumption settlement method for manual calculation, the method proposed in this application can improve the comprehensiveness, accuracy and timeliness of the total cost estimation of passenger trains, thereby being more suitable for the evaluation needs of high-density train operation and frequent daily adjustments under the existing complex road network conditions.
[0039] The following will be combined with specific embodiments to Figure 2 The specific implementation methods of each step in the embodiment shown are described in detail:
[0040] In step 201, train plan information corresponding to a passenger train is obtained.
[0041] Among them, the passenger train (also referred to as a passenger train) can be a single passenger train or a train route composed of multiple passenger trains, such as a virtual train route composed of multiple passenger trains.
[0042] For example, when the passenger train is a single passenger train, the breakeven point of the single passenger train can be calculated, so as to obtain the breakeven point of a virtual train consisting of multiple passenger trains by superimposing the breakeven points of each passenger train; or the virtual train consisting of multiple passenger trains can be directly used as a whole to calculate the breakeven point of the whole, and the present disclosure does not impose any restrictions on this. The breakeven point refers to the ratio of the minimum ticket revenue that can cover the train operation cost to the passenger ticket revenue of the full capacity of the train.
[0043] In some embodiments of the present disclosure, the train plan information includes one or more of a train operation plan, a train operation diagram, a train formation plan, and a fare plan.
[0044] Among them, the train operation plan is a plan to determine the passenger train operation section, train type, route, number of pairs of trains and the car bottom responsible bureau. The train operation diagram is a technical document used to show the operation of trains in railway sections and the arrival, departure or passing time at stations; it stipulates the procedures for each train to occupy the section, the arrival and departure (or passing) time of the train at each station, the operation time of the train in the section, the stop time of the train at the station, as well as the train route, train weight and length, etc. It is a graphic illustration of the train operation timetable, which stipulates that each train runs in the section and arrives, departs and passes at the station at a certain time. The train operation diagram is a graphic illustration of the time and space relationship of train operation. It shows the two-dimensional line diagram of the train operation in each section and the parking or passing status at each station.
[0045] The train marshaling plan refers to the passenger train marshaling and routing plan, which combines multiple passenger trains in an orderly manner according to the order of arrival and departure from the perspective of the undercarriage routing, and determines the train grade, connection method, marshaling form, marshaling sequence, vehicle parameters, vehicle and crew responsibilities, etc. of the undercarriage routing, which is an important reference for the use of the undercarriage. The fare plan is the ticket price set based on the running mileage and estimated passenger flow level.
[0046] In step 202, multiple target resource categories corresponding to the passenger train are determined, and based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, the energy consumption value corresponding to each target resource category of the passenger train is determined, so as to obtain the total operating energy consumption of the passenger train based on the energy consumption value of each target resource category.
[0047] Among them, according to the transportation resource category, it can be determined that the multiple target resource categories corresponding to the passenger train may include one or more of the road network resource category, the power resource category, the vehicle resource category, the service resource category and the management resource category.
[0048] For example, after obtaining multiple resource categories according to the transport resource categories corresponding to the passenger train, the server can determine the cost of each resource category corresponding to the passenger train based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, so as to obtain the total operating energy consumption of the passenger train according to the cost of each resource category. The train operation section that the passenger train passes through during operation can be determined through the train plan information, so as to subsequently determine the energy consumption value of each target resource category.
[0049] For ease of explanation, the calculation process of determining the corresponding costs of the above-mentioned multiple target resource categories is exemplarily described below in conjunction with a specific embodiment.
[0050] 1) Total energy consumption of road network:
[0051] When multiple target resource categories include at least a road network resource category, the total energy consumption of the road network resources corresponding to the road network resource category can be determined, referred to as the total energy consumption of the road network. The total energy consumption of the road network usually includes the depreciation and maintenance costs of infrastructure such as lines and overhead lines.
[0052] In an optional embodiment of the present disclosure, when determining the total energy consumption of the road network, the line energy consumption and the contact network energy consumption corresponding to each train running section of the passenger train are obtained; based on the sum of the line energy consumption and the contact network energy consumption corresponding to each train running section, the total energy consumption of the road network corresponding to the road network resource category of the passenger train is determined.
[0053] Among them, the line energy consumption of passenger trains is the cost energy consumption compensation for the wear and tear of railway tracks, bridges, tunnels, and communication signal infrastructure by passenger trains. Line energy consumption can include basic line energy consumption, busy line energy consumption, and night line energy consumption.
[0054] Exemplarily, the line energy consumption of a passenger train may be the sum of the basic line energy consumption, the busy line energy consumption, and the night line energy consumption.
[0055] Among them, the overhead contact network is a special form of power transmission line erected in a zigzag shape above the rails in an electrified railway to supply power to electric locomotives. The overhead contact network is the main framework of the railway electrification project. It is a special form of power transmission line erected above the railway line to supply power to electric locomotives. It consists of contact suspension, support device, positioning device, pillars and foundation. The energy consumption of the overhead contact network can include the energy consumption of the basic overhead contact network and the energy consumption of the overhead contact network at night.
[0056] Exemplarily, the overhead contact network energy consumption can be determined by the sum of the basic overhead contact network energy consumption and the nighttime overhead contact network energy consumption.
[0057] In summary, the calculation process of the road network cost determined based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train is as shown in the following formula (1):
[0058]
[0059] In formula (1), c l represents the total energy consumption of the road network, unit: yuan; s represents the train operation section corresponding to the passenger train, and its value range is s=1,2,...,S; c lbase Indicates the energy consumption of basic lines, unit: yuan; c lbusy Indicates the energy consumption of busy lines, unit: yuan; c lnight Indicates the energy consumption of the line at night, unit: yuan, which is usually a negative value; c catenary Indicates the energy consumption of basic overhead line, unit: yuan; ccnight It represents the energy consumption of overhead contact network at night, unit: Yuan, which is usually a negative value.
[0060] The line energy consumption of passenger trains shown in the above formula (1) includes the basic line energy consumption c lbase 、Energy consumption of busy lines c lbusy , Night line energy consumption c lnight It can be determined based on the following formula (2):
[0061]
[0062] In formula (2), L s Indicates the running mileage of the train in the sth train running section, unit: kilometers; P ls Indicates the cost unit price of line energy consumption in the sth train running section, unit: yuan / km; L' s It indicates the running mileage of the train in the busy section of the sth train running section, in kilometers; P ls ' represents the surcharge for the busy section in the sth train operation section, unit: yuan / km; θ represents the proportion of passenger trains running at night in the sth train operation section (the night time period can be set to 22:00 to 6:00 the next day). It should be noted that if the train is a high-speed train or a sleeper train, and the section is a special 1 or special 2 line, θ can be calculated by the ratio of the total night operation time to the total section operation time, otherwise it is 0.
[0063] The overhead contact network energy consumption of passenger trains shown in the above formula (1) includes the basic overhead contact network energy consumption c catenary And the nighttime overhead line energy consumption c cnight The calculation method of is shown in the following formula (3):
[0064]
[0065] In formula (3), W s It indicates the total weight of the train passing through the sth train operation section, usually in units of 10,000 tons; P cs It represents the unit price of the overhead line energy consumption cost in the s-th train operation section, unit: yuan / 10,000 ton-kilometers; θ represents the proportion of passenger trains running at night in the s-th train operation section (the night time period can be set to 22:00 to 6:00 the next day). It should be noted that if the train is a high-speed train or a sleeper train, and the section is a special 1 or special 2 line, θ can be calculated by the ratio of the total night operation time to the total section operation time, otherwise it is 0.
[0066] In the above implementation process, it is also necessary to combine the passenger flow result information corresponding to each passenger train stop to determine the total energy consumption of the road network. It should be understood that the greater the passenger flow, the greater the number of people riding a passenger train on a single trip, which in turn increases the energy consumption cost.
[0067] In this embodiment, the current energy consumption settlement method is broken down into smaller details, and the network costs for various aspects of the operation process are reorganized to be more in line with the cost connotation of this resource category, further enhancing the comprehensiveness and pertinence of cost calculation, and achieving the technical effect of improving the accuracy of energy consumption planning for passenger trains.
[0068] 2) Energy consumption cost:
[0069] When multiple resource categories include at least an energy consumption resource category, the cost corresponding to the energy consumption resource category can be determined, referred to as the energy consumption cost. The energy consumption cost for passenger trains includes: energy consumption, additional energy consumption, passenger air conditioning oil, and electricity consumption.
[0070] In an optional embodiment of the present disclosure, the electric power consumption, additional electric power consumption, and passenger refrigeration system energy consumption corresponding to each train operating section of a passenger train are obtained; and the energy consumption cost of the corresponding energy consumption resource category of the passenger train is determined based on the electric power consumption, additional electric power consumption, and passenger refrigeration system energy consumption corresponding to each train operating section.
[0071] Among them, the energy consumption cost of passenger trains usually includes electricity consumption and energy consumption cost, which can be specifically electricity consumption, additional electricity consumption, and passenger refrigeration system energy consumption. The passenger refrigeration system cost can include the consumption of energy such as oil and electricity, for example, it can be the oil and electricity consumption of passenger air conditioners.
[0072] Exemplarily, the energy consumption cost calculation process of a passenger train is shown in the following formula (4):
[0073]
[0074] In formula (4), C e represents the energy consumption cost, unit: yuan; s represents the train operation section corresponding to the passenger train, and its value range is s=1,2,...,S; L s Indicates the running mileage of the train in the sth train running section, unit: kilometers; W s It indicates the total weight of the train passing through the sth train operation section, usually in units of 10,000 tons; P es P represents the unit price of electricity consumption cost in the sth train operation section, unit: yuan / 10,000 tons / km; fd P is the unit price of additional power consumption, in RMB / 1,000 vehicle kilometers; W is the total vehicle kilometers. ydIt is the unit cost price of energy consumption of passenger refrigeration system, such as the unit price of oil and electricity consumption of passenger air conditioner, the unit is: Yuan / 1000 vehicle-kilometers.
[0075] The calculation method of the total vehicle mileage W is shown in the following formula (5):
[0076] W=R×L×10 -3 Formula (5)
[0077] In formula (5), W is the total vehicle kilometers; R is the number of trains; and L is the train mileage.
[0078] It can be seen from the above formula (5) that the power consumption corresponding to each train operation section is related to the power consumption unit price corresponding to each train operation section, the operating mileage and the total weight of the vehicle, while the additional power consumption cost is related to the total vehicle kilometers and the additional power consumption unit price, and the passenger refrigeration system cost is related to the passenger air conditioning oil, power consumption unit price and the total vehicle kilometers.
[0079] In the above implementation process, it is also necessary to combine the passenger flow result information corresponding to each stop of the passenger train to determine the total energy consumption. It should be understood that the greater the passenger flow, the greater the number of people riding a passenger train on a single trip, which in turn increases the energy consumption cost.
[0080] In this embodiment, the current energy consumption settlement method is combined with the railway transportation enterprise's own operating cost expenditure to integrate the energy consumption costs of various aspects of the enterprise's operation process, further enhancing the comprehensiveness of cost calculation, and avoiding the technical problem that the break-even point is often too small due to the related technical solutions mainly relying on the railway energy consumption settlement method to calculate the cost, thereby affecting the accuracy of the break-even point calculation of passenger trains, thereby achieving the technical effect of improving the accuracy of passenger train benefit calculation.
[0081] 3) Vehicle cost:
[0082] When multiple resource categories include at least a vehicle resource category, the cost corresponding to the vehicle resource category can be determined, which usually refers to the vehicle maintenance / repair cost, referred to as vehicle cost. Among them, vehicle cost usually includes the depreciation, maintenance (operation maintenance), overhaul (advanced maintenance), and section maintenance costs of locomotives, passenger cars, EMUs, etc.
[0083] In an optional embodiment of the present disclosure, the vehicle traction energy consumption, vehicle maintenance energy consumption, vehicle depreciation energy consumption, and vehicle maintenance labor energy consumption corresponding to each train operating section of the passenger train are obtained; and the vehicle cost of the corresponding vehicle resource category of the passenger train is determined based on the vehicle traction energy consumption, vehicle maintenance energy consumption, vehicle depreciation energy consumption, and vehicle maintenance labor energy consumption corresponding to each train operating section.
[0084] Among them, vehicle maintenance energy consumption includes at least one or more of vehicle operation and maintenance energy consumption, vehicle advanced maintenance energy consumption, vehicle daily maintenance energy consumption, vehicle overhaul energy consumption and vehicle depot maintenance energy consumption; vehicle maintenance labor energy consumption includes at least one or more of maintenance labor energy consumption and EMU mechanic labor energy consumption.
[0085] For ease of understanding, it should be explained that the first and second level maintenance of EMUs are operational maintenance, and the third, fourth and fifth level maintenance are advanced maintenance. Operational maintenance is mainly based on condition maintenance, and advanced maintenance is mainly based on disassembly maintenance. Each maintenance process is closely linked to ensure the long-term high-speed, safe and comfortable operation of passenger trains. Major overhaul refers to the comprehensive and thorough maintenance and technical upgrading and transformation of ordinary speed vehicles to restore the vehicle performance to the factory state. Generally, the vehicle will be returned to the factory for maintenance. Daily maintenance refers to the daily technical inspection, cleaning and maintenance of ordinary speed vehicles to ensure that the vehicle can be used normally every day and improve driving safety. Section maintenance refers to the process of comprehensive inspection and key analysis of the vehicle, usually including the disassembly inspection of components such as the vehicle's running gear, coupler buffer device and brake device, with the aim of maintaining the basic performance of the vehicle, extending the service life of the vehicle and ensuring the safe operation of the vehicle. To sum up, the vehicle maintenance energy consumption of EMU trains includes the energy consumption of vehicle operation and maintenance and the energy consumption of vehicle advanced maintenance; the vehicle maintenance energy consumption of conventional passenger cars includes the energy consumption of vehicle daily maintenance, vehicle overhaul and vehicle depot maintenance.
[0086] Exemplarily, the vehicle cost calculation process of a passenger train is shown in the following formula (6):
[0087]
[0088] In formula (6), C c Indicates vehicle cost, unit: Yuan; L s Indicates the running mileage of the train in the sth train running section, unit: kilometers; H s It indicates the total traction weight of the passenger train in the sth train operation section, in ten thousand tons; P ts It represents the unit price of locomotive traction energy consumption cost in the sth train operation section, unit: yuan / 10,000 tons / kilometers. wx is the unit price of vehicle maintenance energy consumption, in yuan / thousand vehicle kilometers; P dx P is the unit price of energy consumption for vehicle overhaul, in yuan / thousand vehicle kilometers; dux P is the unit price of energy consumption for vehicle depot repair, in yuan / thousand vehicle kilometers; zj P is the unit price of vehicle depreciation energy consumption, in yuan / thousand kilometers; jx P is the unit price of maintenance labor energy consumption, in yuan / thousand vehicle kilometers; dj is the unit price of labor energy consumption of EMU mechanics, unit: Yuan / thousand vehicle-kilometers; W is the total vehicle-kilometers.
[0089] W in formula (6) can still be determined by formula (5), while H s The calculation method is shown in the following formula (7):
[0090]
[0091] In formula (7), r represents a passenger train vehicle or EMU, and its value range is r=1,2,...,R; Z wr The weight of the rth passenger train vehicle or EMU, in tons; Z lr It represents the vehicle load of the rth passenger train vehicle or EMU, in tons.
[0092] From the above formula (6), we can know that the vehicle traction energy consumption is determined by the running mileage L of the train in the sth train running section: s , the total traction weight H of the passenger train in the sth section s and the unit price P of locomotive traction energy consumption cost in the sth train operation section ts Determine; vehicle maintenance energy consumption includes vehicle operation and maintenance energy consumption, vehicle advanced maintenance energy consumption, vehicle daily maintenance energy consumption, vehicle overhaul energy consumption and vehicle section maintenance energy consumption, among which the vehicle daily maintenance energy consumption and vehicle operation and maintenance energy consumption are determined by the unit price P of vehicle daily maintenance or operation and maintenance energy consumption. wx The total vehicle mileage W is determined by the energy consumption of vehicle overhaul and vehicle advanced repair. The energy consumption of vehicle overhaul or advanced repair is determined by the energy consumption unit price P dx and the total vehicle mileage W; the energy consumption of vehicle depot repair is determined by the unit price of vehicle depot repair energy consumption P dux Determined by the total vehicle mileage W. Correspondingly, the vehicle depreciation energy consumption is determined by the vehicle depreciation energy consumption unit price P zj Determined with the total vehicle kilometres W.
[0093] The labor energy consumption of vehicle maintenance includes the labor energy consumption of maintenance and the labor energy consumption of EMU mechanics. The labor energy consumption of maintenance is calculated by the maintenance labor energy consumption unit price P jx and the total vehicle kilometers W, and the labor energy consumption of the EMU mechanic is determined by the labor energy consumption unit price P of the EMU mechanic dj Determined with the total vehicle kilometres W.
[0094] It should be understood that when there is no energy consumption cost, the mathematical symbol corresponding to formula (6) is 0. For example, when there is no manual energy consumption of the EMU mechanic, the corresponding P in formula (6) is dj ×W=0.
[0095] In this embodiment, the difference in maintenance schedule between EMUs and conventional car-based trains is taken into account in the calculation of vehicle maintenance energy consumption, thereby improving the level of refinement of the calculation, and combining the current energy consumption settlement method with the operating cost expenditure of the railway transportation enterprise itself to integrate the vehicle costs of various aspects of the enterprise's operation process, further enhancing the comprehensiveness of cost calculation, and avoiding the technical problem in related technical solutions that the break-even point is often too small due to the main use of the railway energy consumption settlement method to calculate costs, thereby affecting the accuracy of the break-even point calculation of passenger trains, thereby achieving the technical effect of improving the accuracy of passenger train benefit calculation.
[0096] In the above vehicle cost calculation process, the locomotive traction energy consumption unit price for determining vehicle traction energy consumption can be determined according to different types of passenger trains. Figure 3 The above steps of obtaining the vehicle traction energy consumption corresponding to each train running section of the passenger train are exemplarily described. Figure 3 A flowchart schematically shows a method for calculating vehicle traction energy consumption in this exemplary embodiment, see Figure 3 The method for calculating vehicle traction energy consumption provided by the embodiment of the present disclosure includes the following steps 301 to 307:
[0097] Step 301: Determine the type of passenger train.
[0098] Among them, the passenger train types may include "one-stop direct" train types and "long-distance" train types, among which the "long-distance" train type refers to the passenger train whose running route exceeds the preset kilometres (for example, 800 kilometers) for the first time, and the passenger train is not changed in the middle; the "one-stop direct" train type refers to the passenger train running point-to-point, with the locomotive pulling the passenger car to run continuously from the starting station to the terminal station without stopping in the middle.
[0099] Step 302: Determine whether the passenger train is of the first type.
[0100] Among them, the first train type can be a "one-stop direct" train type.
[0101] If the passenger train type is the first type, execute step 303 to determine the vehicle traction unit price based on the sum of the first vehicle traction unit price corresponding to the first type and the locomotive direct power supply additional unit price, and finally execute step 304 to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train.
[0102] On the contrary, if the passenger train type is not the first type, step 305 is executed to determine whether it is the second type. The second type is the "long route" type.
[0103] If the passenger train type is not the first type, but the passenger train type is the second type, then step 306 is executed to determine the vehicle traction unit price based on the sum of the second vehicle traction unit price corresponding to the second type and the locomotive direct power supply additional unit price. Finally, step 304 is executed to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train.
[0104] On the contrary, if the passenger train type is not the first type and the passenger train is not the second type, step 307 is executed to determine the vehicle traction unit price based on the sum of the preset third vehicle traction unit price and the locomotive direct power supply additional unit price. Finally, step 304 is executed to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train.
[0105] Based on the above embodiment, the vehicle traction unit price P of the s-th train operation section in the above formula (6) is ts It can be determined based on the following formula (8), where the direct train in formula (8) is the first type of train, and the long route is the second type of train:
[0106]
[0107] In formula (8), P t1 P is the first vehicle traction unit price corresponding to a one-stop direct trip; t2 is the second vehicle traction unit price corresponding to the long route; and P t3 P is the corresponding third vehicle traction unit price set in advance; t4 Add a unit price for locomotive direct power supply. Among them, the above-mentioned preset corresponding third vehicle traction unit price can be preset by the enterprise. In the field of railway transportation technology, the enterprise is usually a railway bureau and a joint venture and a local enterprise.
[0108] In the above implementation process, it is also necessary to combine the passenger flow result information corresponding to each stop of the passenger train to determine the total energy consumption of the vehicle. It should be understood that the greater the passenger flow, the greater the number of people riding a passenger train on a single trip, which in turn increases the energy consumption cost.
[0109] In this embodiment, different vehicle traction unit prices are determined taking into account different types of passenger trains, which can further enhance the comprehensiveness of cost calculation and improve the accuracy of break-even point calculation for passenger trains.
[0110] 4) Service cost:
[0111] When multiple resource categories include at least a service resource category, the cost corresponding to the service resource category can be determined, referred to as the service cost. The service resource category is the cost of various services provided to passengers during the operation of the train, such as water supply service, personnel service, sewage treatment service, ticket inspection service, etc.
[0112] In an optional embodiment of the present disclosure, the manual service energy consumption corresponding to the passenger train is determined based on the passenger flow result information corresponding to each stop of the passenger train; the manual service energy consumption of the resources provided by the passenger train is determined based on the train plan information; and the service cost of the service resource category corresponding to the passenger train is determined based on the manual service energy consumption and the resource service energy consumption.
[0113] Exemplarily, the service resource categories provided by passenger trains include manual services and resource services provided. Among them, manual services include at least one or more of station passenger service energy consumption, sewage suction manual service energy consumption, crew manual service energy consumption, and ticket inspection manual service energy consumption; resource manual services provided by passenger trains include at least one or more of water supply services (i.e. water supply services) and power-supported resource manual service energy consumption (such as air conditioning, charging equipment, etc.).
[0114] In this regard, the calculation process of service cost is shown in the following formula (9):
[0115]
[0116] In formula (9), C s Indicates service cost, unit: yuan; I other represents the revenue of out-of-station tickets, unit: yuan; ρ represents the energy consumption rate of ticketing service, usually 0.01; n represents the number of train stops, and its value range is n=1,2,...,k,...,N; U n represents the number of passengers sent from the kth station (transfer station), unit: person; P sn represents the unit price of passenger service energy consumption cost at the kth station, unit: yuan / person (for example, in the estimation of the new passenger train plan, the above P sn For ordinary trains, the estimated cost is 3 yuan per passenger (transfer) and for EMU trains, the estimated cost is 5 yuan per passenger (transfer), which can be adjusted according to actual conditions); Q represents the number of water supply times, unit: train times; P w It represents the unit price of energy consumption cost of water supply service at the station, unit: yuan / train; P cf P is the unit price of energy consumption for train services, in RMB / 1,000 vehicle-km; xw P is the unit price of train pollution absorption energy consumption, in yuan / thousand vehicle kilometers; cw P is the unit price of crew energy consumption, in yuan / thousand vehicle kilometers; lj P is the unit price of energy consumption for ordinary passenger train inspection, in yuan / thousand vehicle kilometers;kt P is the unit price of energy consumption for passenger air conditioner, in yuan / 1,000 vehicle kilometers; ds is the unit price of labor energy consumption of EMU driver, unit: Yuan / thousand vehicle-kilometers; W is the total vehicle-kilometers.
[0117] The logic of the water supply times Q in the above formula (9) is shown in formula (10):
[0118]
[0119] In formula (10), T is the total running time of passenger trains, unit: hour; Used to indicate a round-up operation.
[0120] In this embodiment, the current energy consumption settlement method is combined with the railway transportation enterprise's own operating cost expenditure to integrate the service costs of various aspects of the enterprise's operation process, further enhancing the comprehensiveness of cost calculation, and avoiding the technical problem that the break-even point is often too small due to the related technical solutions mainly using the railway energy consumption settlement method to calculate costs, thereby affecting the accuracy of the break-even point calculation of passenger trains, thereby achieving the technical effect of improving the accuracy of passenger train benefit calculation.
[0121] When determining the number of passengers, since there is no actual passenger flow information in the application scenario of this application, it is considered that the overall passenger flow level of different passenger trains should be consistent, but there are differentiated passenger flow distribution patterns at different stops, so as to minimize the impact of external passenger flow fluctuations on the break-even point calculation, and at the same time meet the needs of differentiated passenger flow analysis at different stops, so as to more clearly reflect the break-even point differences in the passenger train product design process, which is helpful for product adjustment decisions. The embodiment of this application provides a passenger flow estimation method as follows:
[0122] In an optional embodiment of the present disclosure, if the stopping station of a passenger train is the departure station, the first passenger flow result information corresponding to the departure station is determined according to the train capacity of the passenger train and the passenger occupancy rate of the departure station; if the stopping station of the passenger train is the terminal station, the second passenger flow result information corresponding to the terminal station is a first preset value; if the stopping station of the passenger train is any intermediate stopping station between the departure station and the terminal station, the third passenger flow result information corresponding to the intermediate stopping station is determined according to the train capacity of the passenger train, the ratio of the number of people sent, the passenger flow ratio coefficient of each stopping station and the first passenger flow result information.
[0123] Among them, the first preset value is 0, and the train capacity refers to the number of seats and vacancies configured by the passenger train in accordance with regulations and standards. This number is fixed and will not change due to changes in the number of passengers on board. Normally, the train capacity is determined by the railway department based on factors such as the type, length, speed and operational needs of the train. The passenger seat rate is the ratio of the number of passengers carried by the passenger train and the cumulative turnover of the transportation mileage to the total number of seats (train capacity) kilometers provided by the train. The number of passengers sent (referred to as passenger sending volume) refers to the total number of passengers boarding the passenger train at each stop, and the passenger flow ratio coefficient is the ratio of the number of passengers sent corresponding to each intermediate stop to the total number of passengers sent.
[0124] Normally, the passenger load factor α and the dispatch capacity ratio β are usually preset, and the passenger load factor α is generally 0.6; and the capacity ratio β is generally 1.7.
[0125] In order to ensure that the passenger load factor of each train operation section of the passenger train is maintained at the α level, the number of passengers boarding at the departure station and the number of passengers getting off at the final station can be calculated based on α, and the number of passengers getting on and off at each stop (i.e., the passenger flow result information of each stop) can be calculated based on the sending number ratio β. That is, the number of passengers U sent (transfer station) at the kth station shown in the above formula (9) is determined based on the following formula (11): n :
[0126]
[0127] In formula (11), α is the passenger load factor; β is the dispatch capacity ratio; F is the train capacity; μ n is the passenger flow ratio coefficient of each stop where the nth train stops, and the value range of n is n=1,2,...,k,...,N.
[0128] For the passenger flow ratio coefficient μ of each stop of the nth train stop n , can be determined according to different passenger flow allocation methods, and the specific implementation examples are as follows:
[0129] In an optional embodiment of the present disclosure, the passenger flow ratio coefficient of each intermediate stop can be determined based on the following method: Figure 4 For example, Figure 4 A flow chart of a method for determining the passenger flow ratio coefficient of each intermediate stop is schematically shown; the method for determining the passenger flow ratio coefficient of each intermediate stop includes the following steps 401 to 407:
[0130] Step 401: Determine the passenger flow distribution method for each intermediate stop between the departure station and the terminal station.
[0131] Step 402: Determine whether it is the first allocation method.
[0132] If the passenger flow distribution method of each intermediate stop is the first distribution method, step 403 is executed and the passenger flow ratio coefficient of each intermediate stop is set to the second preset value.
[0133] Otherwise, step 404 determines whether it is the second allocation method.
[0134] If the passenger flow distribution method of each intermediate stop is the second distribution method, step 405 is executed to determine the passenger flow ratio coefficient of each intermediate stop based on the historical passenger flow of each intermediate stop.
[0135] Otherwise, step 406 determines whether it is the third allocation method.
[0136] If the passenger flow distribution method of each intermediate stop is the third distribution method, step 407 is executed to determine the passenger flow ratio coefficient of each intermediate stop based on the historical passenger flow of the area level.
[0137] Among them, the first allocation method is to equally distribute passenger flow to each intermediate stop, and the corresponding second preset value is 1; the second allocation method is to allocate passenger flow to each intermediate stop according to the historical passenger flow level; the third allocation method is to allocate passenger flow to each intermediate stop according to the historical passenger flow level of the regional level.
[0138] The details are as follows:
[0139] (1) The first allocation method:
[0140] Each intermediate stop evenly distributes the passenger flow. At this time, the passenger flow ratio coefficient μ of each intermediate stop in formula (11) is n =1.
[0141] (2) Second distribution method:
[0142] Each intermediate stop distributes passenger flow according to the historical passenger flow level. At this time, the passenger flow ratio coefficient of each intermediate stop in formula (11) is Among them, H m The number of passengers sent by the current intermediate stop, which can generally be the total passenger flow in the previous quarter.
[0143] (3) The third distribution method:
[0144] Each intermediate stop allocates passenger flow according to the historical passenger flow level of the regional level. At this time, the passenger flow ratio coefficient of each intermediate stop in formula (11) is
[0145] In this formula, h1, h2, and h3 are the historical passenger flow ratios of provincial, prefectural, and county-level cities, respectively, and h1, h2, and h3 satisfy h1+h2+h3=1. The historical passenger flow is generally taken as the total passenger flow of the previous quarter; h nis the city level ratio of the intermediate stop n, and N is the last stop (i.e., the terminal station).
[0146] Through this embodiment, the passenger flow ratio coefficient of each intermediate stop is determined corresponding to different passenger flow distribution methods, which can more comprehensively and accurately determine the passenger flow ratio coefficient of each intermediate stop, further enhancing the accuracy and comprehensiveness of break-even point calculation.
[0147] 5) Management costs:
[0148] When the multiple resource categories include at least a management resource category, a cost corresponding to the management resource category may be determined, referred to as management cost.
[0149] In an optional embodiment of the present disclosure, the vehicle supervision energy consumption corresponding to the passenger train, other artificial energy consumption in the passenger section and other artificial energy consumption in the non-passenger section are determined; and the management cost of the management resource category corresponding to the passenger train is determined based on the vehicle supervision energy consumption corresponding to the passenger train, other artificial energy consumption in the passenger section and other artificial energy consumption in the non-passenger section.
[0150] Among them, other labor energy consumption in the passenger section is the labor energy consumption corresponding to the service cost, and other labor energy consumption in the non-passenger section is the labor energy consumption corresponding to the vehicle cost.
[0151] In this regard, the calculation process of management cost is shown in the following formula (12):
[0152] C m =P jg ×W+P kyd ×W+P cld ×W Formula (12)
[0153] In formula (12), C m Indicates management cost, unit: yuan; P jg P is the unit price of vehicle energy consumption supervision, in yuan / thousand vehicle kilometers; kyd P is the unit price of other labor energy consumption in the passenger transport section, in yuan / thousand vehicle kilometers; cld The unit price of other labor energy consumption in the vehicle depot, in yuan / thousand vehicle-kilometers.
[0154] Based on the above embodiment, the total operating energy consumption of a passenger train is the sum of the costs corresponding to the above resource categories. That is, the total operating energy consumption C of a passenger train is the network cost C l , Energy consumption cost C e 、Vehicle cost C c , service cost C s and management costs C m The sum of .
[0155] In step 203, the break-even point of the passenger train is calculated based on the total operating energy consumption and the total operating income of the passenger train.
[0156] For example, after the total operating energy consumption of the passenger train is determined in step 202, the breakeven point of the passenger train can be calculated based on the total operating energy consumption and the total operating income of the passenger train, wherein the total operating income is the sum of the operating income corresponding to all passenger trains and all operating mileage.
[0157] However, in actual application scenarios, total operating revenue is affected differently by ticket price fluctuations.
[0158] In an optional embodiment of the present disclosure, the train capacity of a passenger train and the target ticket price corresponding to each train capacity are obtained; the total operating income is determined based on the product of the train capacity and the target ticket price corresponding to each train capacity; and the break-even point of the passenger train is calculated based on the total operating energy consumption and the total operating income of the passenger train.
[0159] Among them, the target fare can be the published fare or the discounted fare; the published fare is the unified fare set by the railway bureau based on the operating mileage, vehicle type, etc.; the discounted fare is the fare after a discount is generated on the basis of the published fare.
[0160] Exemplarily, the calculation method of the break-even point of a passenger train is as follows:
[0161]
[0162] In formula (13), z is the seat of the passenger train (also called seat class), and its value range is z = 1, 2, ..., Z; F z U is the seat capacity of class z; z is the full fare for seat class z (target fare).
[0163] Considering that floating fare measures will be implemented in current practical applications, in order to fully support the adjustment of fare plans, the break-even point changes under different fare discount levels are analyzed. The embodiment of the present application provides the following two fare conditions: z :
[0164] (1) Non-discounted floating fare, i.e. U z To announce the ticket price,
[0165] (2) Discounted floating fares, that is, floating fares according to the unified fare discount rate ω, ω is generally set to 0.88, and of course other values may be used according to actual conditions, and the embodiments of the present disclosure do not impose any special restrictions on this.
[0166] Through this embodiment, the differences in passenger flow and ticket price factors are taken into account in the break-even point evaluation process, and the evaluation results are more refined and more in line with the actual evaluation needs of railway transportation enterprises.
[0167] It should be understood that, although the various steps in the flow chart are displayed in sequence according to the indication of the arrows, these steps are not necessarily executed in sequence according to the order indicated by the arrows. Unless there is a clear description in this article, the execution of these steps is not strictly limited in order, and these steps can be executed in other orders. Moreover, at least a portion of the steps in the figure may include multiple sub-steps or multiple stages, and these sub-steps or stages are not necessarily executed at the same time, but can be executed at different times, and the execution order of these sub-steps or stages is not necessarily to be carried out in sequence, but can be executed in turn or alternately with other steps or at least a portion of the sub-steps or stages of other steps.
[0168] Furthermore, an embodiment of the present application also provides a method for planning the operating energy consumption of a passenger train. The method for planning the operating energy consumption of a passenger train can execute the benefit calculation method of the passenger train shown in any of the above embodiments, and the embodiments of the present application are not described in detail here.
[0169] In order to implement the above passenger train benefit calculation method, please refer to Figure 5 An embodiment of the present application provides a benefit calculation device for a passenger train. The benefit calculation device 500 for a passenger train may include an information acquisition module 501, a determination module 502, and a break-even point calculation module 503:
[0170] The information acquisition module 501 is used to obtain the train plan information corresponding to the passenger train;
[0171] The determination module 502 is used to determine multiple resource categories corresponding to the passenger train according to the transportation resource category, and determine the cost of each resource category corresponding to the passenger train based on the train plan information and the passenger flow result information corresponding to each stop of the passenger train, so as to obtain the total operating energy consumption of the passenger train;
[0172] The break-even point calculation module 503 is used to calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train.
[0173] In an optional embodiment of the present disclosure, multiple resource categories include at least a road network resource category, and a determination module 502 is used to obtain the line energy consumption and the contact network energy consumption corresponding to each train running section of the passenger train; based on the sum of the line energy consumption and the contact network energy consumption corresponding to each train running section, determine the road network cost of the passenger train corresponding to the road network resource category.
[0174] In an optional embodiment of the present disclosure, multiple resource categories include at least an energy consumption resource category, and a determination module 502 is used to obtain the electric energy consumption cost, additional electric energy consumption cost, and passenger refrigeration system energy consumption cost corresponding to each train operating section of the passenger train; based on the electric energy consumption cost, additional electric energy consumption cost, and passenger refrigeration system energy consumption cost corresponding to each train operating section, the energy consumption cost of the energy consumption resource category corresponding to the passenger train is determined.
[0175] In an optional embodiment of the present disclosure, multiple resource categories include at least a vehicle resource category, and a determination module 502 is used to obtain vehicle traction energy consumption, vehicle maintenance energy consumption, vehicle depreciation energy consumption, and vehicle maintenance labor energy consumption corresponding to each train operating section of a passenger train; wherein the vehicle maintenance energy consumption includes at least one or more of vehicle operation and maintenance energy consumption, vehicle advanced maintenance energy consumption, vehicle daily maintenance energy consumption, vehicle overhaul energy consumption, and vehicle section repair energy consumption; based on the vehicle traction energy consumption, vehicle maintenance energy consumption, vehicle depreciation energy consumption, and vehicle maintenance labor energy consumption corresponding to each train operating section, the vehicle cost of the passenger train corresponding to the vehicle resource category is determined.
[0176] In an optional embodiment of the present disclosure, a determination module 502 is used to determine the type of a passenger train; if the type of the passenger train is the first type of train, the vehicle traction unit price is determined based on the sum of the first vehicle traction unit price corresponding to the first type of train and the additional unit price of locomotive direct power supply, so as to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train; or, if the type of the passenger train is not the first type of train, and the type of the passenger train is the second type of train, the vehicle traction unit price is determined based on the sum of the second vehicle traction unit price corresponding to the second type of train and the additional unit price of locomotive direct power supply, so as to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train; or, if the type of the passenger train is not the first type of train, and is not the second type of train, the vehicle traction unit price is determined based on the sum of a preset third vehicle traction unit price and the additional unit price of locomotive direct power supply, so as to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train.
[0177] In an optional embodiment of the present disclosure, multiple resource categories include at least a service resource category, and a determination module 502 is used to determine the manual service energy consumption corresponding to the passenger train based on the passenger flow result information corresponding to each stop of the passenger train; determine the resource service energy consumption corresponding to the passenger train based on the train plan information; and determine the service cost of the service resource category corresponding to the passenger train based on the manual service energy consumption and the resource service energy consumption.
[0178] In an optional embodiment of the present disclosure, a determination module 502 is used to determine, if the stopping station of the passenger train is the departure station, first passenger flow result information corresponding to the departure station according to the train capacity of the passenger train and the passenger occupancy rate of the departure station; if the stopping station of the passenger train is the terminal station, second passenger flow result information corresponding to the terminal station is a first preset value; if the stopping station of the passenger train is any intermediate stop between the departure station and the terminal station, third passenger flow result information corresponding to the intermediate stop station is determined according to the train capacity of the passenger train, the ratio of the number of passengers sent, the passenger flow ratio coefficient of the intermediate stop station and the first passenger flow result information.
[0179] In an optional embodiment of the present disclosure, a determination module 502 is used to determine the passenger flow ratio coefficient of each intermediate stop based on the following method: determine the passenger flow distribution method of each intermediate stop between the departure station and the terminal station; if the passenger flow distribution method of each intermediate stop is the first distribution method, set the passenger flow ratio coefficient of each intermediate stop to a second preset value; if the passenger flow distribution method of each intermediate stop is the second distribution method, determine the passenger flow ratio coefficient of each intermediate stop based on the historical passenger flow of each intermediate stop; if the passenger flow distribution method of each intermediate stop is the third distribution method, determine the passenger flow ratio coefficient of each intermediate stop based on the historical passenger flow of the area level.
[0180] In an optional embodiment of the present disclosure, the multiple resource categories include at least a management resource category, and a determination module 502 is used to determine the vehicle supervision energy consumption corresponding to the passenger train, other artificial energy consumption of the passenger section, and other artificial energy consumption of the non-passenger section, the other artificial energy consumption of the passenger section is the artificial energy consumption corresponding to the service cost, and the other artificial energy consumption of the non-passenger section is the artificial energy consumption corresponding to the vehicle cost; based on the vehicle supervision energy consumption corresponding to the passenger train, other artificial energy consumption of the passenger section, and other artificial energy consumption of the non-passenger section, the management cost of the management resource category corresponding to the passenger train is determined.
[0181] In an optional embodiment of the present disclosure, the break-even point calculation module 503 is used to obtain the train capacity of the passenger train and the target fare corresponding to each train capacity, where the target fare is the published fare or a discounted fare of the published fare; determine the total operating revenue based on the product of the train capacity and the target fare corresponding to each train capacity; and calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating revenue of the passenger train.
[0182] In an optional embodiment of the present disclosure, the train plan information includes one or more of a train operation plan, a train operation diagram, a train formation plan, and a fare plan.
[0183] For the specific definition of the above-mentioned benefit calculation device for passenger trains, please refer to the definition of the benefit calculation method for passenger trains in the above text, which will not be repeated here. Each module in the above-mentioned benefit calculation device for passenger trains can be implemented in whole or in part by software, hardware and a combination thereof. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0184] In one embodiment, a computer device is provided, the internal structure diagram of which can be as follows: Figure 6 As shown. The computer device includes a processor, a memory, a network interface and a database connected via a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store data. The network interface of the computer device is used to communicate with an external terminal via a network connection. When the computer program is executed by the processor, a method for calculating the benefits of a passenger train as described above is implemented. It includes: a memory and a processor, the memory stores a computer program, and when the processor executes the computer program, any step in the method for calculating the benefits of a passenger train as described above is implemented.
[0185] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, any step in the above-mentioned method for calculating the benefits of a passenger train can be implemented.
[0186] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0187] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0188] These computer program instructions may also be stored in a computer readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0189] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0190] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.
[0191] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.
Claims
1. A method for calculating the benefits of a passenger train, characterized in that: Applied to calculating and planning the total operating energy consumption of passenger trains, the method comprises: Obtaining train plan information corresponding to the passenger train; Determine a plurality of target resource categories corresponding to the passenger train, and determine an energy consumption value corresponding to each target resource category of the passenger train based on the train plan information and passenger flow result information corresponding to each stop station of the passenger train, so as to obtain a total operating energy consumption of the passenger train based on the energy consumption value of each target resource category; The break-even point of the passenger train is calculated based on the total operating energy consumption and the total operating income of the passenger train.
2. The method for calculating the benefits of a passenger train according to claim 1, characterized in that: The multiple target resource categories include at least a road network resource category, and determining the energy consumption value of the passenger train corresponding to each target resource category based on the train plan information and the passenger flow result information corresponding to each stop station of the passenger train includes: Obtaining the line energy consumption and overhead line energy consumption corresponding to each train running section of the passenger train; Based on the sum of the line energy consumption and the contact network energy consumption corresponding to each train running section, the total network resource energy consumption of the passenger train corresponding to the network resource category is determined.
3. The method for calculating the benefits of a passenger train according to claim 1, characterized in that: The multiple target resource categories at least include an energy consumption resource category, and determining the energy consumption value of each target resource category corresponding to the passenger train based on the train plan information and the passenger flow result information corresponding to each stop station of the passenger train includes: Obtaining the power energy consumption, additional power energy consumption, and passenger refrigeration system energy consumption corresponding to each train operation section of the passenger train; The total energy consumption of energy resources corresponding to the energy consumption resource category of the passenger train is determined based on the electric power consumption, additional electric power consumption, and passenger refrigeration system energy consumption corresponding to each train operation section.
4. The method for calculating the benefits of a passenger train according to claim 1, characterized in that: The multiple target resource categories include at least a vehicle resource category, and determining the energy consumption value of the passenger train corresponding to each target resource category based on the train plan information and the passenger flow result information corresponding to each stop station of the passenger train includes: Obtaining vehicle traction energy consumption, vehicle maintenance energy consumption, vehicle depreciation energy consumption, and vehicle maintenance labor energy consumption corresponding to each train operation section of the passenger train; wherein the vehicle maintenance energy consumption at least includes one or more of vehicle operation and maintenance energy consumption, vehicle advanced maintenance energy consumption, vehicle daily maintenance energy consumption, vehicle overhaul energy consumption, and vehicle depot maintenance energy consumption; Based on the vehicle traction energy consumption, vehicle maintenance energy consumption, vehicle depreciation energy consumption, and vehicle maintenance labor energy consumption corresponding to each train operation section, the total vehicle resource energy consumption of the vehicle resource category corresponding to the passenger train is determined.
5. The passenger train benefit calculation method according to claim 4, characterized in that: The vehicle traction energy consumption is determined based on the product of the vehicle traction unit price and the running mileage of the passenger train. The obtaining of the vehicle traction energy consumption corresponding to each train running section of the passenger train includes: Determining the type of the passenger train; If the passenger train type is the first type, the vehicle traction unit price is determined based on the sum of the first vehicle traction unit price corresponding to the first type and the locomotive direct power supply additional unit price, so as to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train; Alternatively, if the train type of the passenger train is not the first train type, and the train type of the passenger train is the second train type, the vehicle traction unit price is determined based on the sum of the second vehicle traction unit price corresponding to the second train type and the locomotive direct power supply additional unit price, so as to determine the vehicle traction energy consumption based on the product of the vehicle traction unit price and the running mileage of the passenger train; Alternatively, if the passenger train type is neither the first type nor the second type, the vehicle traction unit price is determined based on the sum of a preset third vehicle traction unit price and a locomotive direct power supply additional unit price, and the vehicle traction energy consumption is determined based on the product of the vehicle traction unit price and the operating mileage of the passenger train.
6. The method for calculating the benefits of a passenger train according to claim 1, characterized in that: The multiple target resource categories include at least a service resource category, and determining the energy consumption value of the passenger train corresponding to each target resource category based on the train plan information and the passenger flow result information corresponding to each stop station of the passenger train includes: Determine the manual service energy consumption corresponding to the passenger train according to the passenger flow result information corresponding to each stop of the passenger train; Determine the resource service energy consumption provided by the passenger train based on the train plan information; The total service energy consumption of the passenger train corresponding to the service resource category is determined according to the manual service energy consumption and the resource service energy consumption.
7. The passenger train benefit calculation method according to claim 1 or 6, characterized in that: The method further comprises: If the stop station of the passenger train is the departure station, determining the first passenger flow result information corresponding to the departure station according to the train capacity of the passenger train and the passenger occupancy rate of the departure station; If the stop of the passenger train is a terminal station, the second passenger flow result information corresponding to the terminal station is a first preset value; If the stop of the passenger train is any intermediate stop between the departure station and the terminal station, the third passenger flow result information corresponding to the intermediate stop is determined according to the train capacity, capacity ratio, passenger flow ratio coefficient of the intermediate stop and the first passenger flow result information of the passenger train.
8. The passenger train benefit calculation method according to claim 7, characterized in that: The method further includes determining the passenger flow ratio coefficient of each intermediate stop based on the following method: Determine the passenger flow distribution method of each intermediate stop between the departure station and the terminal station; If the passenger flow distribution method of each intermediate stop is the first distribution method, the passenger flow ratio coefficient of each intermediate stop is set to a second preset value; If the passenger flow allocation method of each intermediate stop is the second allocation method, then determining the passenger flow ratio coefficient of each intermediate stop based on the historical passenger flow of each intermediate stop; If the passenger flow allocation method of each intermediate stop is the third allocation method, the passenger flow ratio coefficient of each intermediate stop is determined based on the historical passenger flow of the area level.
9. The passenger train benefit calculation method according to claim 1, characterized in that: The multiple target resource categories include at least a management resource category, and determining the energy consumption value of each target resource category corresponding to the passenger train based on the train plan information and the passenger flow result information corresponding to each stop station of the passenger train includes: Determine the vehicle supervision energy consumption, other artificial energy consumption of the passenger section and other artificial energy consumption of the non-passenger section corresponding to the passenger train, wherein the other artificial energy consumption of the passenger section is the artificial energy consumption corresponding to the service cost, and the other artificial energy consumption of the non-passenger section is the artificial energy consumption corresponding to the vehicle cost; The total management energy consumption of the management resource category corresponding to the passenger train is determined based on the vehicle supervision energy consumption corresponding to the passenger train, other artificial energy consumption of the passenger section, and other artificial energy consumption of the non-passenger section.
10. The passenger train benefit calculation method according to claim 1, characterized in that: The calculating the breakeven point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train comprises: Obtaining the train capacity of the passenger train and the target fare corresponding to each train capacity, wherein the target fare is a published fare or a discounted fare; Determining the total operating income based on the product of the train capacity and the target ticket price corresponding to the capacity of each train; The break-even point of the passenger train is calculated based on the total operating energy consumption and the total operating income of the passenger train.
11. The passenger train benefit calculation method according to claim 1, characterized in that: The train plan information includes one or more of a train operation plan, a train operation diagram, a train formation plan and a fare plan.
12. A benefit calculation device for a passenger train, characterized in that: Applicable to calculating and planning the total operating energy consumption of passenger trains, the device comprises: An information acquisition module is used to obtain train plan information corresponding to passenger trains; A determination module, used to determine a plurality of target resource categories corresponding to the passenger train, and determine the energy consumption value corresponding to each target resource category of the passenger train based on the train plan information and the passenger flow result information corresponding to each stop station of the passenger train, so as to obtain the total operating energy consumption of the passenger train based on the energy consumption value of each target resource category; A break-even point calculation module is used to calculate the break-even point of the passenger train based on the total operating energy consumption and the total operating income of the passenger train.
13. A computer device comprising: It comprises a memory and a processor, wherein the memory stores a computer program, and is characterized in that when the processor executes the computer program, the steps of the method for calculating the benefit of a passenger train described in any one of claims 1 to 11 are implemented.
14. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method for calculating the benefit of a passenger train according to any one of claims 1 to 11 are implemented.
Citation Information
Cited By
Rail transit energy consumption calculation method, device, equipment, medium and product
CN122390230A