By configuring a safe and controllable monitoring system for domestic chips in a 1000kV ultra-high voltage substation, using the station control layer network to interact with the equipment for information, and operating in parallel to the data comparison with conventional systems, the application verification of domestic chips in ultra-high voltage substations is solved. The problem has achieved system performance verification and independent operation security guarantee of conventional systems, and improved the national strategic security level.

CN119010345APending Publication Date: 2024-11-22CHINA POWER ENG CONSULTING GRP CORP EAST CHINA ELECTRIC POWER DESIGN INST
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411107138.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-13
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

The existing technology lacks effective verification methods to apply the performance and compatibility of domestic chips' safe and controllable monitoring systems in 1000kV ultra-high voltage substations, resulting in equipment safety hazards and affecting the risk resistance of the power grid and industrial systems.

Method used

A verification method is proposed, by configuring a safe and controllable monitoring system in a 1000kV ultra-high voltage substation, using domestic chips, and using the station control layer I and II networks, respectively, relay protection devices, measurement and control devices, electrical energy harvesting terminals and other equipment. Conduct information interaction and run in parallel with conventional monitoring systems to perform data comparison to verify the reliability and compatibility of the system.

Benefits of technology

It has realized the functional verification of the safe and controllable monitoring system in a 1000kV ultra-high voltage substation, ensured the independent operation safety and reliability of the original monitoring system, and verified the performance of domestic chips through cost-effective configuration, improving the national strategic security level. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119010345A_ABST
    Figure CN119010345A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of transformer substation monitoring systems, in particular to a verification method for applying a safety controllable monitoring system to an extra-high voltage transformer substation. Equipment related to the safe controllable monitoring system adopts domestic chips and comprises a station control layer I area network C and a station control layer II area network C which are connected through a firewall C. The station control layer I area network C collects data of a relay protection device C and a measurement and control device C; the station control layer I area network C performs information interaction with a time synchronization host C, a monitoring host C, a five-prevention host C, various work stations C and an I area gateway machine C at the upper end; the lower end of the station control layer II area network C performs information interaction with the electric energy acquisition terminal C, the primary equipment online monitoring system C and the fault recorder C, and the upper end of the station control layer II area network C performs information interaction with the II area gateway machine C and the network safety monitoring device C. According to the method, the interface scheme of the safe and controllable monitoring system is defined, the operation performance of the system is verified, and meanwhile, independent and reliable operation of a conventional system is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of ultra-high voltage substation monitoring systems, and in particular to a verification method for applying a safe and controllable monitoring system in an ultra-high voltage substation. Background Art

[0002] The "bottleneck" problem of substation monitoring system is concentrated on the core chips of equipment manufacturing, such as CPU / DSP, FPGA, ADC, etc., and these chips are almost all from European and American countries. In view of the current international situation, the risk of "bottleneck" in the power secondary system is becoming more and more serious. It is urgent to develop a safe and controllable UHV substation monitoring system, verify its performance and reliability, and increase its application efforts to promote the rapid maturity of the domestic chip industry, truly increase the risk resistance of power grid security and even the entire industrial system, and enhance the national strategic security level. The UHV substation monitoring system using domestic chips has great strategic value in the promotion and application of new substations and the operation and maintenance of existing substations, and the market prospects are optimistic. From the perspective of national strategic security development, it is imperative to make the substation monitoring system safe and controllable and to de-monopolize foreign countries. The existing verification methods mainly verify the application of safe and controllable monitoring systems in 500kV and below substations, but there is still a lack of effective verification methods for the application of safe and controllable monitoring systems in 1000kV UHV substations.

[0003] The conventional configuration of the monitoring system of 1000kV UHV substation adopts dual hosts at the station control layer, single measurement and control device at the bay layer and dual star network configuration of network equipment. Conventional monitoring system equipment is generally based on imported chips. 1000kV UHV substation is the backbone of China's unified strong smart grid. The monitoring system using imported chips in UHV substations has many hidden dangers. The chips cannot be self-sufficient and the equipment safety cannot be fully guaranteed.

[0004] In view of the above problems, it is urgent to develop a safe and controllable monitoring system with domestic chips and apply it in UHV substations to ensure the safety and reliability of equipment and power grid operation. Before the safe and controllable monitoring system is widely used in UHV substations, its performance needs to be verified. However, there is no systematic verification of all equipment and their mutual coordination in the safe and controllable monitoring system with domestic chips in 1000kV UHV substations. Summary of the invention

[0005] The problem to be solved by the present invention is to verify the equipment performance, system performance and compatibility and coordination capability of the entire safe and controllable monitoring system with other safe and controllable systems, while ensuring the reliable operation of the original 1000kV UHV substation monitoring system. The present invention proposes a verification method for verifying a safe and controllable monitoring system in a 1000kV UHV substation. The method can verify the function of the safe and controllable monitoring system of the UHV substation, while ensuring that the operation of the original conventional monitoring system in the UHV substation is not affected to the greatest extent.

[0006] In view of the shortcomings of the prior art, the technical solution adopted by the present invention to solve the technical problems is: a verification method for applying a safe and controllable monitoring system in an ultra-high voltage substation, the method adopts a safe and controllable 1000kV monitoring system, the equipment involved in the safe and controllable 1000kV monitoring system all adopts domestic chips, the safe and controllable 1000kV monitoring system includes a station control layer I zone network C and a station control layer II zone network C connected through a firewall C, the station control layer I zone network C collects data from a relay protection device C and a measurement and control device C, the station control layer I zone network C is connected to the upper end of the time synchronization host C, the monitoring host C, and the five-protection The host C, various workstations C and zone I gateway C exchange information; the lower end of the station control layer zone II network C exchanges information with the electric energy collection terminal C, the primary equipment online monitoring system C and the fault recorder C, and the upper end of the station control layer zone II network C exchanges information with the zone II gateway C and the network security monitoring device C. The conventional 1000kV monitoring system runs in parallel with the safe and controllable 1000kV monitoring system. The data of the safe and controllable 1000kV monitoring system is compared with the data of the conventional 1000kV monitoring system. The chips involved in the conventional 1000kV monitoring system are non-domestic chips.

[0007] Preferably, the relay protection device C includes a 1000kV relay protection device C, a 500kV relay protection device C and a 110kV relay protection device C.

[0008] Preferably, the gateway machine C in zone I transmits information upward through vertical encryption 1C; the gateway machine C in zone II transmits information upward through vertical encryption 2C.

[0009] Preferably, the station control layer zone I network C obtains data from the phasor measurement acquisition device C through the phasor measurement host C.

[0010] Preferably, the electric energy collection terminal C collects data from the electric energy meter C.

[0011] The beneficial effects of the present invention are as follows:

[0012] 1. Configure a monitoring system and a safe and controllable monitoring system at the same time in the 1000kV UHV substation, and the two systems will run simultaneously without affecting each other. Based on the same source data acquisition and processing, the data of the safe and controllable 1000kV monitoring system and the conventional 1000kV monitoring system can be compared on the same basis, fully verifying the reliability of the safe and controllable 1000kV monitoring system. At the same time, this configuration is different from the redundant configuration. The configuration method of selecting the typical interval configuration measurement and control device is adopted, so that the safe and controllable monitoring system can be economically and efficiently verified in the 1000kV UHV substation.

[0013] 2. Clarify the interface scheme between the safe and controllable monitoring system and other safe and controllable system equipment in the 1000kV UHV substation, systematically verify the performance of the safe and controllable monitoring system and ensure the safe, reliable and independent operation of the conventional monitoring system.

[0014] 3. The present invention is applicable to 1000kV UHV substations and has a certain degree of originality. It is a technological innovation for exploring new power systems and can be further extended to application scenarios when distributed power sources are connected to the main grid. It is an important practice for exploring new technologies. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 This is the network structure diagram of a conventional 1000kV monitoring system;

[0016] Figure 2 This is the network structure diagram of the safe and controllable 1000kV monitoring system. DETAILED DESCRIPTION

[0017] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The embodiments of the present invention are provided for the purpose of illustration and description, and are not intended to be exhaustive or to limit the present invention to the disclosed forms. Many modifications and variations will be apparent to those of ordinary skill in the art. The embodiments are selected and described in order to better illustrate the principles and practical applications of the present invention, and to enable those of ordinary skill in the art to understand the present invention and thereby design various embodiments with various modifications suitable for specific uses.

[0018] As shown in the figure, the present invention is applicable to a 1000kV ultra-high voltage substation. The monitoring system is configured with a conventional 1000kV monitoring system and a safe and controllable 1000kV monitoring system. The secondary equipment used in the conventional 1000kV monitoring system adopts non-domestic chips, and the secondary equipment used in the safe and controllable 1000kV monitoring system is a domestic chip. The two monitoring systems run simultaneously, the two systems are not connected to each other on the network, and the electrical connection between the two systems is reduced as much as possible.

[0019] (1) The conventional 1000kV monitoring system adopts the following design principles:

[0020] The 1000kV UHV substation is equipped with a set of conventional integrated computer monitoring system to monitor and control the equipment in the station. The monitoring system includes telecontrol function. In terms of the functional realization of the monitoring system, considering the future development of technology and the requirements of smart grid construction, the monitoring system should have the basic functions that a substation with few or no people on duty should have in the future. It should be able to realize sequential control and automatically generate combined operation tickets according to different operation modes; it should be able to layer and classify the information on the station control layer network, optimize and integrate it, and have the functions of intelligent alarm and analysis and decision-making. The interlocking function of the whole station to prevent misoperation is realized through computer measurement and control devices and electrical interlocking circuits, and no independent five-protection workstation is set. The monitoring system should have the logic identification function of the four states of operation, hot standby, cold standby and maintenance, and automatically realize the interlocking to prevent electrical misoperation. The interlocking circuit of the distribution device sets a complete logical interlocking and a complete electrical interlocking as mandatory interlocking measures. The two types of interlocking are in series.

[0021] The whole station uniformly builds a dual-star station control layer network according to the DL / T 860 standard, adopts the MMS service of DL / T 860, and the protection equipment, I / O measurement and control devices of the station control layer and the monitoring system of the station control layer are directly connected to the station control layer network through dual network ports, realizing the common network transmission of the secondary equipment information of the whole station, making the information in the substation shared and unique, and avoiding repeated information collection. The monitoring system can remotely modify the set value, switch the set value group, and put and withdraw the soft pressure plate on the protection at the station control layer. The monitoring system can remotely modify the set value, switch the set value group, and put and withdraw the soft pressure plate on the protection at the station control layer.

[0022] Conventional 1000kV monitoring system network Figure 1As shown: the chips involved in the conventional 1000kV monitoring system network are non-domestic chips, including the redundantly set station control layer I zone network A and station control layer I zone network B. Taking the station control layer I zone network A as an example, the upper end of the station control layer I zone network A is equipped with a time synchronization host A, a monitoring host A, a five-protection host, various workstations and I zone gateway zone A. The terminal devices of the station control layer I zone network A include 1000kV relay protection devices, 500kV relay protection devices, 110kV relay protection devices and measurement and control devices. The 1000kV relay protection devices, 500kV relay protection devices, 110kV relay protection devices and measurement and control devices transmit data to the upper host through the station control layer I zone network A. The I zone gateway zone A transmits data to the dispatching data network I zone switch A (real-time). The dispatching data network I zone switch A (real-time) communicates with the national dispatching data network through vertical encryption 1A and router 1A. The station control layer area I network A sends the data of the phasor measurement collection device to the dispatching data network area I switch A (real time) through the phasor measurement host A. The station control layer area II network A is connected to the station control layer area I network A through the firewall A, and the station control layer area II network B is connected to the station control layer area I network B through the firewall B. The station control layer area II network A and the station control layer area II network B are still redundant. Taking the station control layer area II network A as an example, the area II gateway machine A, network security monitoring device, integrated application server and various workstations upload the data of the station control layer area II network A to the dispatching data network area II switch A (non-real time). The station control layer area II network A receives the downstream equipment, including the electric energy collection terminal, the primary equipment online monitoring system, the protocol conversion and the auxiliary control system; the dispatching data network area II switch A (non-real time) communicates with the national dispatching data network through the vertical encryption 2A and the router 2A, and the dispatching data network area II switch A (non-real time) will also collect fault recording information. The station control layer II zone network A and the station control layer II zone network B are connected to the zone IV network through forward / reverse isolation. The zone IV network will provide the collected information to the zone IV gateway machine, online monitoring status access CAC and intelligent patrol host. The zone IV gateway machine and online monitoring status access CAC will exchange information with the integrated data network.

[0023] (2) The chips used in the equipment of the safe and controllable 1000kV monitoring system are all domestically produced chips. The safe and controllable 1000kV monitoring system includes the station control layer I zone network C. The station control layer I zone network C collects data from 1000kV relay protection devices C, 500kV relay protection devices C, 110kV relay protection devices C and measurement and control devices C. The station control layer I zone network C exchanges information with the upper-end timing host C, monitoring host C, five-defense host C, various workstations C and I zone gateway C. The I zone gateway C transmits information upward through vertical encryption 1C, and the phase measurement and control device C is connected to the station control layer. The quantity acquisition device C sends the data to the phasor measurement host C, which exchanges information with the station control layer area I network C. The station control layer area I network C is connected to the station control layer area II network C through the firewall C. The station control layer area II network C exchanges information with the electric energy acquisition terminal C, the primary equipment online monitoring system C and the fault recording C. The electric energy acquisition terminal C collects data from N electric energy meters C. The station control layer area II network C exchanges information with the area II gateway C and the network security monitoring device C at the upper end. The area II gateway C transmits information upward through the vertical encryption 2C. The safe and controllable 1000kV monitoring system builds a single star station control layer network according to the DL / T 860 standard and adopts the MMS service of DL / T 860. The protection equipment, I / O measurement and control devices of the station control layer and the monitoring system of the station control layer are directly connected to the station control layer network through a single network port to realize the common network transmission of safe and controllable secondary equipment information. The safe and controllable monitoring system has all the functions of a conventional monitoring system. The configuration of the safe and controllable 1000kV monitoring system is not redundant. Only typical and representative intervals are selected for configuration. This can save investment and meet functional requirements while meeting the requirements of functional verification.

[0024] External interface and connection principle of safe and controllable 1000kV monitoring system:

[0025] 1) The measuring current of the measurement and control device C of the safe and controllable 1000kV monitoring system is connected in series with the measurement and control device of the conventional 1000kV monitoring system.

[0026] 2) The measurement and control device C of the safe and controllable 1000kV monitoring system measures the voltage and adopts a voltage circuit breaker independent of the conventional measurement and control device, and uses the third winding of the voltage transformer to share the same voltage circuit breaker with the safe and controllable phasor measurement and acquisition device C and the safe and controllable protection device.

[0027] 3) The safe and controllable measurement and control device C, the gateway machine C in zone I and the gateway machine C in zone II are synchronized by the synchronization system of the timing host C using the electronic B code.

[0028] 4) The host of the safe and controllable 1000kV monitoring system is synchronized with the NTP network by the synchronization host C synchronization system.

[0029] 5) 1000kV relay protection device C, 500kV relay protection device C, and 110kV relay protection device C only send device fault alarm signals to the conventional 1000kV monitoring system and are connected to the conventional line measurement and control device of this interval.

[0030] 6) 1000kV relay protection device C, 500kV relay protection device C, and 110kV relay protection device C use hard contact signals to access the safe and controllable measurement and control device C.

[0031] 7) The safe and controllable relay protection equipment uses a single optical port to access the safe and controllable station control layer zone I network C.

[0032] 8) The safe and controllable integrated power supply system is connected to the safe and controllable station control layer zone I network C.

[0033] 9) The safe and controllable phasor measurement host C is connected to the safe and controllable station control layer zone I network C.

[0034] 10) The safe and controllable electric energy collection terminal C (electric energy metering system) is connected to the safe and controllable station control layer zone II network C.

[0035] 11) The safe and controllable 1000kV monitoring system network is not connected to the conventional 1000kV monitoring system network.

[0036] 12) The safe and controllable primary equipment online monitoring system C is connected to the safe and controllable station control layer zone I network C.

[0037] The key of the present invention is that according to the characteristics of 1000kV UHV substation, a verification method for application in 1000kV UHV substation is proposed, and the interface scheme of safe and controllable 1000kV monitoring system is clarified, the operating performance of safe and controllable monitoring system in 1000kV UHV substation is systematically verified, and the independent and reliable operation of conventional monitoring system is guaranteed at the same time. Based on the data acquisition and processing of the same source, the data of safe and controllable 1000kV monitoring system and conventional 1000kV monitoring system can be compared on the same basis, and the reliability of safe and controllable 1000kV monitoring system is fully verified. When a set of safe and controllable 1000kV monitoring system is configured in 1000kV UHV substation, another set of conventional 1000kV monitoring system is configured, and the two systems run simultaneously without affecting each other. At the same time, this configuration is different from redundant configuration, and the typical interval configuration is selected to make the safe and controllable monitoring system obtain economical and efficient functional verification in 1000kV UHV substation. The emergence of this configuration scheme verifies the system performance of the safe and controllable monitoring system equipment to the maximum extent while ensuring the safe, reliable and independent operation of the conventional monitoring system.

Claims

1. A verification method for applying a safe and controllable monitoring system in a UHV substation, characterized by: The method adopts a safe and controllable 1000kV monitoring system. The equipment involved in the safe and controllable 1000kV monitoring system all adopts domestic chips. The safe and controllable 1000kV monitoring system includes a station control layer I zone network C and a station control layer II zone network C connected through a firewall C. The station control layer I zone network C collects data from relay protection devices C and measurement and control devices C. The station control layer I zone network C exchanges information with the upper-end time synchronization host C, monitoring host C, five-defense host C, various workstations C and I zone gateway host C; the station control layer I zone network C The lower end of the zone I network C exchanges information with the electric energy collection terminal C, the primary equipment online monitoring system C and the fault recorder C. The upper end of the zone II network C of the station control layer exchanges information with the zone II gateway C and the network security monitoring device C. A conventional 1000kV monitoring system runs in parallel with the safe and controllable 1000kV monitoring system. The data of the safe and controllable 1000kV monitoring system is compared with the data of the conventional 1000kV monitoring system. The chips involved in the conventional 1000kV monitoring system are non-domestic chips.

2. A verification method for applying a safe and controllable monitoring system in a UHV substation according to claim 1, characterized in that: The relay protection device C includes a 1000kV relay protection device C, a 500kV relay protection device C and a 110kV relay protection device C.

3. A verification method for applying a safe and controllable monitoring system in a UHV substation according to claim 1, characterized in that: The gateway machine C in zone I transmits information upward through vertical encryption 1C; the gateway machine C in zone II transmits information upward through vertical encryption 2C.

4. A verification method for applying a safe and controllable monitoring system in a UHV substation as claimed in claim 3, characterized in that: The station control layer zone I network C obtains data from the phasor measurement acquisition device C through the phasor measurement host C.

5. A verification method for applying a safe and controllable monitoring system in a UHV substation as claimed in claim 4, characterized in that: The electric energy collection terminal C collects data from the electric energy meter C.