Mass concrete pouring construction method
By using control lines in large-volume concrete pouring, the area is divided into two parts A and B, and using oblique layered pouring and moisturizing and curing technology, the problems of interlayer gaps and premature condensation are solved, and the large-volume concrete is realized. Continuous pouring and strength increase.
Patent Information
- Application Number
- CN202411325940.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-23
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-09-23
AI Technical Summary
In the pouring method of large-volume concrete, problems of interlayer gaps and construction cold joints are prone to occur, resulting in leakage risks and strength impacts, and insufficient supply strength or traffic control leads to premature condensation of concrete, resulting in discontinuity of construction.
The rectangular pouring area is divided into two parts A and B using the control line. The two sets of pouring equipment start from the starting point of the control line and gradually advance in oblique layered pouring. Part of the areas are given priority to reduce the paving area, ensure continuous pouring, and Moisturizing and curing before the concrete is initially set.
The smallest paving area and rapid pouring to the design elevation can be achieved as much as possible, avoiding cold joints and premature condensation of construction, ensuring the continuous pouring and strength of large-volume concrete, and effectively controlling the generation of cold joints of construction.
Smart Images

Figure CN119021469A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to concrete pouring construction, in particular to a large volume concrete pouring construction method. Background Art
[0002] Mass concrete refers to large-volume concrete with a minimum geometric dimension of not less than 1m, or concrete that is expected to cause harmful cracks due to temperature changes and shrinkage caused by hydration of cementitious materials in the concrete. At present, there are two methods for pouring mass concrete: integral layered pouring and push-type continuous pouring, among which: The overall layered pouring is to divide the entire mass concrete component into several layers of small thickness, pour a full layer at a time, and then go back to pour the upper layer, and repeat the construction until the pouring is completed to the designed elevation of the concrete structure. This pouring method makes the overall mass concrete structure become a layered structure, and there are gaps between layers, which is easy to cause leakage risks and affect the strength of the mass concrete structure; The push-type continuous pouring is also divided into several layers, but each layer is not completely poured. After a part of the next layer is poured, the previous layer is poured. The pouring point keeps moving forward, and the concrete in front of the pouring point naturally flows into an inclined surface to gradually form a stepped pouring layer. The concrete behind the pouring point is poured to the designed elevation. This pouring method has a large paving area, and the uncast surface area is too large. It is easy for the upper concrete to fail to be poured in time before the lower concrete begins to set due to insufficient concrete supply strength or external factors such as traffic control, which will cause construction cold joints and cause leakage problems. Summary of the invention
[0003] In view of the problem that the current large-volume concrete pouring method is prone to gaps between layers or construction cold joints, the purpose of the present invention is to provide a large-volume concrete pouring construction method, which pours concrete step by step with as small a paving area as possible and pours to the designed elevation as quickly as possible, thereby solving the problems of insufficient supply strength of large-volume concrete and premature coagulation due to prolonged exposure, realizing continuous pouring of large-volume concrete, and achieving the effect of effectively controlling the generation of construction cold joints.
[0004] The technical solution adopted by the present invention is: A large volume concrete pouring construction method for a rectangular pouring area: Before pouring, set a control line above it: The control line is a continuous broken line. The starting point and the ending point of its whole are respectively located at a pair of diagonal corners of the pouring area. The two ends of each broken line segment are respectively located at a pair of long sides of the pouring area. Its adjacent broken line segments are symmetric about the width direction of the pouring area. The control line successively divides the pouring area into A1, B1, A2, B2 ··· An, Bn in the length direction, where one corner of A1 and B1 intersects at the starting point of the control line and A1 < B1, and one corner of An and Bn intersects at the ending point of the control line and An > Bn; During pouring, use two sets of pouring equipment to start simultaneously and carry out continuous pouring at the same pouring speed: One set of pouring equipment starts from the starting point of the control line and successively completes the pouring of A1, A2 ··· An, and each small area is poured in an inclined layered manner and advances forward along the traveling path of the current broken line segment. The other set of pouring equipment starts from the starting point of the control line and successively completes the pouring of B1, B2 ··· Bn, and each small area is poured in an inclined layered manner and advances forward along the traveling path of the current broken line segment.
[0005] Furthermore, for an irregular pouring area, most of its area is divided into several rectangular pouring areas for the above-mentioned pouring, and the remaining small part of the area is poured conventionally.
[0006] Furthermore, before setting the control line, first complete the steel bar installation in the pouring area.
[0007] Furthermore, the method of setting the control line is: First, fix positioning steel bars at equal intervals on the upper layer steel bar surface of the pouring area. The steel bars are higher than the design elevation of the pouring area. Then, select several positioning steel bars on a pair of long sides of the pouring area as attachment points, and install the cloth or wire along the selected positioning steel bars to form the control line.
[0008] Furthermore, during pouring, prepare standby pouring equipment. When the working pouring equipment stops working due to reasons, the standby pouring equipment is promptly put into operation to complete the remaining work.
[0009] Furthermore, during pouring, the slump of the mass concrete mixture is not greater than 180 mm, and the thickness of each layer for inclined layered pouring is 500 mm.
[0010] Furthermore, during pouring, adopt a cloth feeding process of synchronous vibration, simultaneous retreat, layered stacking, and gradually reaching the top. The vibration of each layer of concrete is carried out on the naturally formed slope surface.
[0011] Furthermore, during pouring, the vibration moving distance is not greater than 1.5 times the vibration radius. The vibration equipment inserts into the lower layer of concrete by 50 - 100 mm, and vibrates in two to three times to avoid missing vibration and affecting the construction quality of the concrete.
[0012] Furthermore, carry out heat preservation maintenance after pouring and forming.
[0013] Further, before the initial setting of the concrete, spray curing work shall be carried out immediately; within 6 - 12 hours after the concrete is poured and formed, moisture - retaining curing shall be carried out: cover the top surface of the concrete and sprinkle water for moisture - retaining curing to keep the concrete surface always wet and avoid the appearance of surface shrinkage cracks. If the surface temperature of the concrete rises too fast, the water - storage method shall be adopted for curing. If the cooling rate is too fast after the peak temperature rise, heat - preservation covering shall be adopted, and at the same time, the on - site temperature shall be monitored; the duration of moisture - retaining curing shall not be less than 14 days. After curing, when the maximum temperature difference between the surface temperature of the concrete and the environment is less than 20 °C, the heat - preservation covering layer shall be removed.
[0014] The beneficial effects of the present invention are as follows: The control line divides the rectangular pouring area into two parts, A and B, and the areas of the two pouring areas are basically the same. When the pouring speeds are the same and the pouring paths are the same as the traveling paths of the current broken - line segments, the two sets of pouring equipment will start pouring from the starting point of the control line and end pouring at the end point of the control line. During the pouring process, since A1 < B1, after A1 is poured first, it will then come around to pour A2, thus forming a closed area for B1 and reducing the concrete spreading area within the B1 area. Similarly, after B1 is poured first, it will then come around to pour B2, thus forming a closed area for A2 and reducing the concrete spreading area within the A2 area. Pouring the remaining parts in this way successively, the concrete in areas A and B advances synergistically and complements each other, gradually pouring to the design elevation with as small a spreading area as possible and as fast as possible, solving the problems of insufficient supply strength of mass concrete and premature setting due to long - time exposure, realizing the continuous pouring of mass concrete, and achieving the effect of effectively controlling the generation of construction cold joints. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of setting a control line for a rectangular pouring area in an embodiment of the present invention.
[0016] Figure 2 It is a schematic diagram of the control line successively dividing the pouring area into several small areas in the length direction in an embodiment of the present invention.
[0017] Figure 3 It is a pouring route map of area A in an embodiment of the present invention.
[0018] Figure 4 It is a pouring route map of area B in an embodiment of the present invention.
[0019] Figure 5 It is a relationship diagram between the pouring area and the pouring time in an embodiment of the present invention.
[0020] Figure 6It is the pouring sectional view in the embodiment of the present invention.
[0021] In the figure: 1 - positioning steel bars; 2 - control line. Specific implementation manners
[0022] The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
[0023] A construction method for mass concrete pouring, aiming at a rectangular pouring area, adopts the following steps: S1. Complete the steel bar installation in the pouring area S2. Before pouring, set the control line 2 above it As Figure 1 and Figure 2 shown, the control line 2 is a continuous broken line, the starting point and the ending point of the whole are respectively located at a pair of diagonal corners of the pouring area, the two ends of each broken line segment are respectively located at a pair of long sides of the pouring area, and the adjacent broken line segments are symmetric about the width direction of the pouring area. The control line 2 divides the pouring area into A1, B1, A2, B2 ··· An, Bn in sequence in the length direction, where one corner of A1 and B1 intersects at the starting point of the control line 2 and A1 < B1, and one corner of An and Bn intersects at the ending point of the control line 2 and An > Bn.
[0024] As Figure 1 shown, the method of setting the control line 2 is: first, fix the positioning steel bars 1 equidistantly on the upper steel bar surface of the pouring area, and the steel bars are higher than the design elevation of the pouring area. Then, select several positioning steel bars 1 on a pair of long sides of the pouring area as attachment points, and install the cloth or wire along the selected positioning steel bars 1 to form the control line 2.
[0025] S3. During pouring, use two sets of pouring equipment to start simultaneously and carry out continuous pouring at the same pouring speed As Figure 3 、 Figure 5 and Figure 6 shown, one set of pouring equipment starts from the starting point of the control line 2 and sequentially completes the pouring of A1, A2 ··· An, and each small area adopts the method of diagonal layer pouring and advances forward along the traveling path of the current broken line segment. As Figure 4 、 Figure 5 and Figure 6 shown, the other set of pouring equipment starts from the starting point of the control line 2 and sequentially completes the pouring of B1, B2 ··· Bn, and each small area adopts the method of diagonal layer pouring and advances forward along the traveling path of the current broken line segment.
[0026] During pouring, prepare standby pouring equipment, and when the working pouring equipment stops working due to reasons, the standby pouring equipment is put into use in time to complete the remaining work.
[0027] During pouring, the slump of the mass concrete mixture shall not be greater than 180 mm, and the thickness of each layer for inclined layered pouring shall be 500 mm.
[0028] During pouring, a feeding process of synchronous vibration compaction, simultaneous backward movement, layered stacking, and gradually reaching the top shall be adopted. As Figure 6 shown, the vibration compaction of each layer of concrete is carried out on the naturally formed slope surface.
[0029] During pouring, the moving distance of vibration compaction shall not be greater than 1.5 times the vibration radius. The vibration compaction equipment shall be inserted into the lower layer of concrete by 50 - 100 mm and vibrated and compacted in two to three times to avoid missing vibration and affecting the construction quality of concrete.
[0030] S4. Conduct heat preservation and maintenance after pouring and forming Immediately carry out spray maintenance work before the initial setting of the concrete; within 6 - 12 hours after the concrete is poured and formed, conduct moisture preservation maintenance: cover the top surface of the concrete and sprinkle water for moisture preservation maintenance to keep the concrete surface always moist and avoid the appearance of surface shrinkage cracks. If the surface temperature of the concrete rises too fast, adopt the water storage method for maintenance. If the cooling rate is too fast after the peak temperature rise, adopt heat preservation covering, and at the same time monitor the on-site temperature; the duration of moisture preservation maintenance shall not be less than 14 d. After maintenance, when the maximum temperature difference between the surface temperature of the concrete and the environment is less than 20 °C, remove the heat preservation covering layer.
[0031] According to the above scheme, it can be known that: The control line 2 divides the rectangular pouring area into two parts A and B, and the areas of the two pouring areas are basically the same. In the case of the same pouring speed and the same pouring path as the current broken line's traveling path, the two sets of pouring equipment will start pouring from the starting point of the control line 2 and end pouring at the end point of the control line 2. During the pouring process, since A1 < B1, after A1 is preferentially poured and completed, it will then come around to pour A2. In this way, a closed area can be formed for B1, reducing the concrete paving area within the B1 area. Similarly, after B1 is preferentially poured and completed, it will then come around to pour B2. In this way, a closed area can be formed for A2, reducing the concrete paving area within the A2 area. Pouring the rest in turn according to this situation, the concrete in areas A and B is advanced synergistically and complementarily, and the pouring is carried out step by step with as small a paving area as possible and as quickly as possible to the design elevation, solving the problems of insufficient supply intensity of mass concrete and premature setting due to excessive exposure for too long, realizing the continuous pouring of mass concrete, and achieving the effect of effectively controlling the generation of construction cold joints.
[0032] For irregular casting areas, most of the area can be divided into several rectangular casting areas for the above casting, and conventional casting is used for the redundant small area. The embodiments described above are part of the embodiments of the present application, not all of the embodiments. The detailed description of the embodiments of the present application is not intended to limit the scope of the present application for protection, but merely represents the selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.
Claims
1. A method for pouring large-volume concrete, characterized in that: For the rectangular pouring area: Before pouring, set a control line above it: The control line is a continuous broken line. The starting point and the ending point of its whole are respectively located at a pair of diagonal corners of the pouring area. The two ends of each broken line segment are respectively located at a pair of long sides of the pouring area. Its adjacent broken line segments are symmetric about the width direction of the pouring area. The control line divides the pouring area into A1, B1, A2, B2 ··· An, Bn in sequence in the length direction, where one corner of A1 and B1 intersects at the starting point of the control line and A1 < B1, and one corner of An and Bn intersects at the ending point of the control line and An > Bn; During pouring, use two sets of pouring equipment to start continuous pouring simultaneously at the same pouring speed: One set of pouring equipment starts from the starting point of the control line and sequentially completes the pouring of A1, A2 ··· An, and each small area uses the inclined layer pouring method to advance forward along the traveling path of the current broken line segment. The other set of pouring equipment starts from the starting point of the control line and sequentially completes the pouring of B1, B2 ··· Bn, and each small area uses the inclined layer pouring method to advance forward along the traveling path of the current broken line segment.
2. The mass concrete pouring construction method according to claim 1, characterized in that: Before setting the control line, first complete the steel bar installation in the pouring area.
3. The mass concrete pouring construction method according to claim 2, characterized in that: The method of setting the control line is: First, fix positioning steel bars equidistantly on the upper layer steel bar surface of the pouring area. The steel bars are higher than the design elevation of the pouring area. Then, select several positioning steel bars on a pair of long sides of the pouring area as attachment points, and install the cloth or wire along the selected positioning steel bars to form the control line.
4. The mass concrete pouring construction method according to claim 1, characterized in that: During pouring, prepare standby pouring equipment. When the working pouring equipment stops due to reasons, the standby pouring equipment is promptly put into operation to complete the remaining work.
5. The mass concrete pouring construction method according to claim 1, characterized in that: During pouring, the slump of the mass concrete mixture is not greater than 180 mm, and the thickness of each inclined layer for pouring is 500 mm.
6. The mass concrete pouring construction method according to claim 1, characterized in that: During pouring, adopt the cloth feeding process of synchronous vibration compaction, simultaneous backward movement, layered stacking, and gradually reaching the top. The vibration compaction of each layer of concrete is carried out on the naturally formed slope surface.
7. The mass concrete pouring construction method according to claim 1, characterized in that: During pouring, the vibration moving distance is not greater than 1.5 times the vibration radius. The vibration compaction equipment inserts into the lower layer of concrete by 50 - 100 mm, and vibrates and compacts in two to three times to avoid missing vibration and affecting the construction quality of the concrete.
8. The mass concrete pouring construction method according to claim 1, characterized in that: After pouring and forming, carry out heat preservation and curing.
9. The mass concrete pouring construction method according to claim 8, characterized in that: Before the initial setting of the concrete, immediately carry out spray curing work; within 6 - 12 hours after the concrete is poured and formed, carry out moisture preservation curing: cover the top surface of the concrete and sprinkle water for moisture preservation curing to keep the concrete surface always moist and avoid the appearance of surface shrinkage cracks. If the surface temperature of the concrete rises too fast, adopt the water storage method for curing. If the cooling rate is too fast after the peak temperature rise, adopt heat preservation covering, and at the same time monitor the on-site temperature; the duration of moisture preservation curing is not less than 14 d. After curing, when the maximum temperature difference between the surface temperature of the concrete and the environment is less than 20 °C, remove the heat preservation covering layer.
10. A method for pouring large-volume concrete, characterized in that: For the irregular pouring area, most of its area is divided into several rectangular pouring areas for pouring construction by using the mass concrete pouring construction method described in any one of claims 1 to 9, and the conventional pouring method is adopted for the remaining small part of the area.
Citation Information
Patent Citations
Construction method for jump bin of super long basement with core tube mixed structure
CN111424707A
Prefabricated model of rock-fill concrete and preparation method thereof
CN114509316A
Mass concrete construction method
CN117306872A
Floor slab concrete placing method
JP1996053938A
Placing method for mass concrete
JP1996100528A