Roadway type mud-water separation and pervious concrete plugging structure and construction method thereof
By combining the filter separation layer and the sealing layer in the tunnel-type mud-water separation and permeable concrete sealing structure, the problem of mud-water separation and sealing in the mine tunnel is solved, and the prevention of underground mud-slides and low-cost rapid sealing is achieved. For a variety of engineering needs.
Patent Information
- Application Number
- CN202411176685.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-26
- Publication Date
- 2024-11-26
AI Technical Summary
After mining in the mine, it is difficult to effectively separate and seal the mud and water in the tunnel, resulting in a high risk of underground mudslide accidents. It is difficult for the existing technology to have the separation and filtration capacity and sealing function of mud and water.
Design a tunnel-type mud-water separation and permeable concrete sealing structure. By setting up a filter separation layer and a sealing layer, combining two-stage filter layer and cross-welded sealing steel bars, using permeable concrete sealing, and using fixing bolts and external Expand the fixed ring connection and assembly to achieve rapid construction.
This structure effectively prevents the occurrence of underground mudslide accidents and has the characteristics of low-cost and rapid construction. It is suitable for the sealing and sealing needs of mines, highways, tunnels and other projects.
Smart Images

Figure CN119021750A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of tunnel type mud water separation and plugging, and in particular relates to a tunnel type mud water separation and permeable concrete plugging structure and a construction method thereof. Background Art
[0002] In the mining of metal and non-metal mines, especially mines using the caving method, when the ore resources collapsed on the upper part of the bottom structure are discharged, atmospheric rainfall and surface runoff rainwater enter the mine and mix with the loose materials in the mine to form a mud body, which is easy to cause underground mudslide accidents. Therefore, it is necessary to block the mine exit tunnel where the ore is discharged. At the same time, it is also necessary to consider filtering the mud water in the tunnel and discharging it out of the mine exit.
[0003] Therefore, the blocking structure of the mine exit tunnel where ore discharge is completed needs to have both the separation and filtration capabilities of mud water and the blocking function, so as to effectively prevent the occurrence of underground mudslides in the mine exit tunnel where ore discharge is completed. Summary of the invention
[0004] In order to solve the above technical problems, the present invention designs a tunnel-type mud-water separation and permeable concrete sealing structure and a construction method thereof. The tunnel-type sealing structure has both the mud-water separation and filtration capabilities and the sealing function, which can effectively prevent the occurrence of mudslide accidents in the tunnel where mining is completed, and can be quickly constructed and used at low cost through the construction method provided by the present invention.
[0005] In order to achieve the above technical objectives, the present invention is implemented through the following technical solutions: a tunnel-type mud-water separation and permeable concrete sealing structure, the sealing structure is connected to the connecting steel bars arranged on the tunnel entrance wall, and the sealing structure includes a filtering separation layer and a sealing layer arranged in sequence from the inside to the outside and fixed by an outward-expanding fixing ring.
[0006] Preferably, the filtration separation layer includes a coarse filter layer and a fine filter layer arranged from the inside to the outside; the coarse filter layer can be a metal mesh with a plurality of through holes, and the fine filter layer can be a filter geotextile.
[0007] Preferably, vertically and horizontally cross-welded blocking steel bars are arranged in the blocking layer, and the blocking steel bars are welded to the connecting steel bars; an embedded plate is arranged at the bottom of the blocking layer and inserted and connected with the bottom of the tunnel entrance, and permeable concrete is poured on the blocking steel bars to form the blocking layer.
[0008] Preferably, the coarse filter layer, fine filter layer and plugging layer are each provided with an outwardly expanding fixing ring on the outer contour, and the screw holes opened around the outwardly expanding fixing ring are connected by fixing bolts, thereby connecting the coarse filter layer, fine filter layer and plugging layer.
[0009] Another object of the present invention is to provide a method for constructing the above-mentioned tunnel type mud-water separation and permeable concrete plugging structure, the steps of which are as follows:
[0010] S1: Use fixing bolts to connect the outer expansion fixing rings of the coarse filter layer, the fine filter layer, and the plugging layer, and assemble and connect the filter separation layer and the plugging layer into a plugging structure;
[0011] S2: dig an insertion opening for the embedded plate at the bottom of the tunnel and fix the assembled blocking structure at the tunnel opening;
[0012] S3: After welding the corresponding ends of the sealing steel bars inside the sealing layer to the connecting steel bars at the edge of the tunnel entrance, the mold is supported and permeable concrete is poured.
[0013] Preferably, the connecting steel bars are installed by drilling holes in the side wall of the tunnel, and anchoring agent or grouting is added after installation, and a certain length of the connecting steel bars is exposed outside the side wall of the tunnel and welded to the blocking steel bars.
[0014] Preferably, when the mold is poured with permeable concrete, it is poured until the sealing layer completely closes the tunnel entrance.
[0015] The beneficial effects of the present invention are:
[0016] This tunnel-type plugging structure combines two-stage separation technology with permeable reinforced concrete plugging function, and has the ability to separate and filter mud water and plug mud in the tunnel. It can effectively prevent the occurrence of mudslide accidents in the tunnel at the end of mining. It can not only be used for the sealing and plugging of underground mine tunnel-type projects, such as the sealing of tunnels in the mining area before filling in the filling method, and the plugging of the mine exit tunnel in the caving method. It can also be used in other projects that require plugging, such as roads, tunnels, foundation excavation, etc. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for describing the embodiments are briefly introduced below.
[0018] Figure 1 It is a schematic diagram of the separation and blocking structure of the present invention blocking the tunnel entrance;
[0019] Figure 2 It is a schematic diagram of the separation and plugging structure decomposition of the present invention;
[0020] Figure 3 is a front view structural schematic diagram of the fixing screw of the present invention;
[0021] In the accompanying drawings, the structural names represented by the reference numerals are:
[0022] 1-tunnel entrance wall, 2-sealing layer, 21-sealing steel bar, 22-embedded plate, 3-connecting steel bar, 4-filtration separation layer, 41-coarse filter layer, 42-fine filter layer, 5-outward expansion fixing ring, 51-screw hole, 6-fixing bolt. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0024] Example 1
[0025] In order to solve the problem that in the mining of metal and non-metal mines, especially mines using caving method, after the ore resources of the upper part of the bottom structure are emptied, atmospheric rainfall and surface runoff rainwater enter the mine and mix with the loose materials in the mine to form mud, which is easy to cause underground debris flow accidents, a tunnel type mud-water separation and permeable concrete plugging structure is proposed. Figure 1 The plugging structure is connected to the connecting steel bar 3 provided on the tunnel entrance wall 1. The plugging structure includes a filtering separation layer 4 and a plugging layer 2 which are fixed from the inside to the outside by an outwardly expanding fixing ring 5. The filtering separation layer 4 filters and separates the mud, and only allows the filtered and separated water to flow out of the tunnel entrance. The plugging layer 2 blocks the mud and sand in the tunnel entrance, and allows the separated mud and water to flow out, thereby avoiding the occurrence of mudslide accidents in the tunnel.
[0026] Example 2
[0027] Based on Example 1, in this embodiment, refer to Figures 2 to 3 As shown, the coarse filter layer 41, the fine filter layer 42, and the plugging layer 2 are each provided with an outwardly expanding fixing ring 5 on the outer contour, and the screw holes 51 opened around the outwardly expanding fixing ring 5 are connected by fixing bolts 6, so as to connect the coarse filter layer 41, the fine filter layer 42, and the plugging layer 2, so that they are fixed as a whole, which is convenient for subsequent installation at the tunnel entrance.
[0028] The filtration and separation layer 4 includes a coarse filter layer 41 and a fine filter layer 42 which are arranged from the inside to the outside; the coarse filter layer 41 can be a metal mesh with a plurality of through holes to filter and block large particles flowing outward from the tunnel, and the fine filter layer 42 can be a filtering geotextile to filter and separate the fine particles passing through the coarse filter layer 41, and perform two stages of filtration and separation in sequence, so that only the thin muddy water containing fine suspended matter flows out, thereby avoiding disasters such as mudslides underground.
[0029] The sealing layer 2 is provided with vertically and horizontally cross-welded sealing steel bars 21, so that the sealing layer has good supporting strength. The sealing steel bars 21 are welded to the connecting steel bars 3 to completely fix the sealing layer 2. An embedded plate 22 is provided at the bottom of the sealing layer 2 and inserted and connected with the bottom of the tunnel entrance so that the bottom of the sealing layer 2 is installed inside the bottom of the tunnel, which is more stable. Permeable concrete is poured on the sealing steel bars 21 to form the sealing layer 2, which further supports the internal filtration separation layer 4.
[0030] Example 3
[0031] In this embodiment, the construction of the tunnel type mud-water separation and permeable concrete plugging structure is carried out, and the steps are as follows:
[0032] S1: Use fixing bolts 6 to connect the coarse filter layer 41, the fine filter layer 42, and the outer expansion fixing ring 5 of the plugging layer 2, and assemble and connect the filtration separation layer 4 and the plugging layer 2 into a plugging structure;
[0033] S2: digging an insertion opening for the embedded plate 22 at the bottom of the tunnel, and fixing the assembled blocking structure at the tunnel opening;
[0034] S3: After welding the corresponding ends of the sealing steel bars 21 inside the sealing layer 2 to the connecting steel bars 3 at the edge of the tunnel entrance, a mold is supported to cast permeable concrete. The connecting steel bars 3 are installed by drilling holes in the tunnel side wall, and anchoring agent or grouting is added after installation. The connecting steel bars 3 are exposed outside the tunnel side wall for a certain length and welded to the sealing steel bars 21. When casting the permeable concrete in the mold, pour it until the sealing layer 2 completely closes the tunnel entrance.
[0035] Through the above steps, the tunnel type mud and water separation and permeable concrete blocking structure are quickly constructed to block the tunnel entrance.
Claims
1. A tunnel type mud-water separation and permeable concrete plugging structure, It is characterized in that The blocking structure is connected to a connecting steel bar (3) provided on a tunnel entrance wall (1), and the blocking structure comprises a filtering separation layer (4) and a blocking layer (2) which are arranged in sequence from the inside to the outside and fixed by an outwardly expanding fixing ring (5).
2. According to the tunnel type mud-water separation and permeable concrete plugging structure of claim 1, It is characterized in that The filtering and separation layer (4) comprises a coarse filtering layer (41) and a fine filtering layer (42) arranged from the inside to the outside; the coarse filtering layer (41) is a metal mesh with a plurality of through holes, and the fine filtering layer (42) is a filtering geotextile.
3. According to the tunnel type mud-water separation and permeable concrete plugging structure of claim 1, It is characterized in that The sealing layer (2) is provided with sealing steel bars (21) welded in a vertical and horizontal manner, and the sealing steel bars (21) are welded to the connecting steel bars (3); an embedded plate (22) is provided at the bottom of the sealing layer (2) and is inserted and connected to the bottom of the tunnel entrance, and permeable concrete is poured on the sealing steel bars (21) to form the sealing layer (2).
4. According to claim 2, the tunnel type mud-water separation and permeable concrete plugging structure, It is characterized in that The coarse filter layer (41), the fine filter layer (42), and the plugging layer (2) are each provided with an outwardly expanding fixing ring (5) on the outer contour, and fixing bolts (6) are used to connect screw holes (51) provided around the outwardly expanding fixing ring (5), thereby connecting the coarse filter layer (41), the fine filter layer (42), and the plugging layer (2).
5. A method for constructing the tunnel type mud-water separation and permeable concrete plugging structure as claimed in claim 1, wherein the steps are as follows: S1: Using fixing bolts (6) to connect the coarse filter layer (41), the fine filter layer (42), and the outer expansion fixing ring (5) of the plugging layer (2), the filtration separation layer (4) and the plugging layer (2) are assembled and connected to form a plugging structure; S2: digging an insertion opening for the embedded plate (22) at the bottom of the tunnel, and fixing the assembled blocking structure at the tunnel opening; S3: After welding the corresponding ends of the blocking steel bars (21) inside the blocking layer (2) to the connecting steel bars (3) at the edge of the tunnel opening, a mold is supported and permeable concrete is poured.
6. The method for constructing the tunnel type mud-water separation and permeable concrete plugging structure according to claim 5, It is characterized in that The connecting steel bars (3) in S3 are installed by drilling holes in the side wall of the tunnel, and anchoring agents or grouting are added after installation. The connecting steel bars (3) are exposed outside the side wall of the tunnel for a certain length and are welded to the blocking steel bars (21).
7. The method for constructing the tunnel type mud-water separation and permeable concrete plugging structure according to claim 5, It is characterized in that When the mold in S3 is poured with permeable concrete, it is poured until the blocking layer (2) completely closes the tunnel entrance.