Geothermal well heat exchange enhancing device and method
By setting up electric pumps and packers in geothermal wells, forcibly flowing formation water, the problems of low heat transfer efficiency and slow formation water flow in traditional geothermal well development are solved, and more efficient thermal reservoir heat replenishment and heat recovery efficiency are achieved.
Patent Information
- Application Number
- CN202310593799.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-05-24
- Publication Date
- 2024-11-26
AI Technical Summary
The existing geothermal well development method that "heat is taken without water" has low heat transfer efficiency, resulting in poor economic benefits, and slow water flow in the formation near the underground thermal reservoir, affecting the heat recovery efficiency.
An electric pump is provided in a geothermal well, and the outer pipe is divided into first and second pipe sections through a lower packer. The electric pump pumps the water in the first pipe section to the second pipe section, forcibly flow the formation water to improve heat exchange efficiency, and The stability of the fluid passage is ensured through the upper packer and the straightening mechanism.
By forcibly flowing formation water, rapid heat replenishment is improved, the thermal production efficiency of geothermal wells is reduced, and the economic benefits of geothermal development is improved.
Smart Images

Figure CN119022488A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of geothermal development, and in particular, relates to a geothermal well heat exchange enhancement device and a geothermal well heat exchange enhancement method. Background Art
[0002] At present, the "heat-extracting but not water" geothermal well development method is mainly to inject fluid (such as water) from the annulus through a concentric wellbore. After heat exchange is completed at the bottom of the well, it flows to the inner tube and is finally produced from the inner tube (or the inner tube is injected into the annulus for production). The fluid in the well does not enter the formation, and formation water does not enter the well. The main heat transfer method is heat conduction, which has low heat transfer efficiency and low economic benefits.
[0003] Chinese patent document CN216557734U discloses a geothermal pipe for geothermal development, including an outer tube body and an inner tube body, the outer tube body is sleeved on the outside of the inner tube body, and the outer tube body and the inner tube body are both located on the same axis, a spiral blade is fixed between the outer tube body and the inner tube body, the inner tube body is evenly coated with a thermal insulation coating, the top of the outer tube body is fixedly connected to a first end tube, and the inner wall of the first end tube is provided with a threaded groove, the bottom of the outer tube body is fixedly connected to a second end tube, and the outer wall of the second end tube is provided with a threaded column, the top of the inner tube body is fixedly connected to a connecting tube, and a slot is provided at the port of the connecting tube. The utility model increases the cold water flow path passing through the inner tube body by providing a spiral blade between the outer tube body and the inner tube body, and the effect of heat exchange with geothermal heat is better. The heat-conducting fins provided inside the outer tube body can better conduct the heat on the outer tube body to the cold water, further improving the efficiency and effect of cold water heat absorption.
[0004] Chinese patent document CN214371027U discloses a heat exchange casing device and a geothermal single well system for efficiently exploiting geothermal resources. The heat exchange casing device is arranged in the target heat reservoir section, including a steel casing and a high-efficiency heat exchange component. The steel casing is the main structure, and the steel casing is provided with an original hole position of the heat exchange component for installing the high-efficiency heat exchange component; the high-efficiency heat exchange component is made of a material with a higher thermal conductivity than steel, and is adapted to be installed with the original hole position of the heat exchange component, and is sealed; the geothermal single well system includes an outer casing and an inner oil pipe, the annulus formed between the casing and the oil pipe is used as an injection well, and the oil pipe is used as a production well, and the casing is a segmented structure, and the section located on the non-target heat reservoir adopts an ordinary casing made of steel, and the section located on the target heat reservoir adopts a heat exchange casing device. The utility model high-efficiency heat exchange casing device is located in the target heat reservoir section, and is applied to geothermal resource exploitation to increase heat exchange efficiency and improve the utilization rate of geothermal resources. Summary of the invention
[0005] In view of the technical problems described above, the present invention aims to provide a geothermal well heat exchange enhancement device, which can enhance the heat exchange efficiency of the geothermal well.
[0006] The present invention also proposes a method for enhancing heat exchange of a geothermal well. The method uses the geothermal well heat exchange enhancement device provided by the present invention to enhance the heat exchange efficiency of the geothermal well.
[0007] According to the present invention, a geothermal well heat exchange enhancement device is provided, comprising:
[0008] Inner tube;
[0009] An annular tube is coaxially and gap-typely sleeved outside the inner tube, the lower end of the annular tube is closed, and a first through hole communicating with the annular tube is provided at the lower end of the inner tube;
[0010] An outer pipe is coaxially and gap-typely sleeved outside the annular pipe, a first pipe section and a second pipe section are arranged inside the outer pipe, the inner pipe and the annular pipe are located inside the first pipe section, a water inlet is arranged on the first pipe section, and a water outlet is arranged on the second pipe section;
[0011] An electric pump is arranged between the first pipe section and the second pipe section, and the electric pump pumps water in the first pipe section to the second pipe section.
[0012] In a specific embodiment, the electric pump is disposed in the outer pipe through a lower packer, the lower packer divides the outer pipe into the first pipe section and the second pipe section, and the electric pump is located below the inner pipe and the annulus pipe.
[0013] In a specific embodiment, the water inlet is arranged on the pipe wall of the first pipe section, and the length range from the water inlet to the lower packer at least overlaps with a portion of the inner pipe and the annulus pipe.
[0014] In a specific embodiment, the lower end of the second pipe section is closed, and the water outlet is arranged on the pipe wall of the second pipe section.
[0015] In a specific embodiment, the lower end of the inner tube and / or the annulus tube is sealed and connected to the electric pump.
[0016] In a specific embodiment, a cable is arranged in the inner pipe or the annulus pipe, and the cable is electrically connected to the electric pump.
[0017] In a specific embodiment, an upper packer is provided between the annulus pipe and the outer pipe, and the upper packer is located above the water inlet.
[0018] In a specific embodiment, at least one straightening mechanism is provided between the inner tube and the annulus tube.
[0019] In a specific embodiment, the water inlet is connected to the thermal reservoir underground, and the annulus pipe is a corrugated pipe or a round pipe.
[0020] According to the present invention, a geothermal well heat exchange enhancement method is also provided. The geothermal well heat exchange enhancement device provided by the present invention accelerates the flow rate of formation water near the heat reservoir and improves the heat exchange efficiency.
[0021] Compared with the prior art, the advantages of the present application are as follows.
[0022] The existing geothermal wells that "extract heat but not water" have low heat extraction efficiency. The underground heat reservoir and the formation water nearby flow slowly. The geothermal water after heat exchange uses weak seepage and natural convection to replenish heat, which takes a long time and the temperature decays quickly, greatly affecting the heat extraction efficiency of geothermal development. The present invention sets an electric pump underground to force the formation water in the underground heat reservoir and the surrounding area to flow, so as to achieve the effect of rapid heat replenishment, thereby improving the heat extraction efficiency of geothermal wells.
[0023] Furthermore, the electric pump of the present invention can be powered by a cable connected to the ground. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The present invention will be described below with reference to the accompanying drawings.
[0025] Figure 1 A schematic diagram showing an embodiment of a geothermal well heat exchange enhancement device according to the present invention.
[0026] In the figure:
[0027] 1. inner tube; 101. first through hole;
[0028] 2. Annular pipe;
[0029] 3. Electric pump;
[0030] 4. Install the packer;
[0031] 5. Lower packer;
[0032] 6. Thermal reservoir;
[0033] 8. Cable;
[0034] 9. Righting mechanism;
[0035] 10. Low temperature water;
[0036] 11. High temperature water;
[0037] 12, outer pipe; 121, first pipe section; 122, second pipe section; 123, water inlet; 124, water outlet;
[0038] 100. Geothermal well heat exchange enhancement device.
[0039] In the present application, all drawings are schematic drawings, which are only used to illustrate the principles of the present invention and are not drawn according to the actual scale. DETAILED DESCRIPTION
[0040] The present invention will be described below with reference to the accompanying drawings.
[0041] It should be noted that, in the present application, the direction along the outer tube 12 approaching the wellhead after entering the well according to the present invention is described as "upward" or similar terms, and the direction away from the wellhead is described as "downward" or similar terms.
[0042] Figure 1 The structure of the geothermal well heat exchange enhancement device 100 according to the present invention is shown. Figure 1 As shown, the geothermal well heat exchange enhancement device 100 includes an inner pipe 1, an annulus pipe 2, an outer pipe 12 and an electric pump 3.
[0043] The inner pipe 1, the annular pipe 2 and the outer pipe 12 are coaxially spaced from the inside to the outside.
[0044] Specifically, the annular tube 2 is coaxially sleeved outside the inner tube 1 in a gap-type manner, and the lower end of the annular tube 2 is closed. In one embodiment, as Figure 1 As shown, the lower end of the inner tube 1 is closed, and a first through hole 101 is provided on the outer wall of the inner tube 1 near the lower end, and the first through hole 101 connects the annulus between the inner tube 1 and the annulus pipe 2 with the inner cavity of the inner tube 1. The lower ends of the inner tube 1 and the annulus pipe 2 are both within the range of the thermal reservoir 6.
[0045] Low-temperature water 10 is injected into the annulus of the inner tube 1 and the annulus tube 2 from a wellhead (not shown in the figure, the wellhead is located above the inner tube 1 and the annulus tube 2). The low-temperature water 10 flows to the range where the heat reservoir 6 is located, and after sufficient heat exchange, it forms high-temperature water 11. The high-temperature water 11 enters the inner cavity of the inner tube 1 through the first through hole 101 and flows upward.
[0046] It is easy to understand that low-temperature water 10 can also be injected into the inner cavity of the inner pipe 1 from the wellhead, and then high-temperature water 11 flows upward from the annular space between the inner pipe 1 and the annular pipe 2 .
[0047] In another embodiment, the lower end of the inner tube 1 can be directly set to be an opening to serve as the first through hole 101 .
[0048] According to the present invention, a first pipe section 121 and a second pipe section 122 are provided in the outer pipe 12 , the inner pipe 1 and the annular pipe 2 are located in the first pipe section 121 , a water inlet 123 is provided on the first pipe section 121 , and a water outlet 124 is provided on the second pipe section 122 .
[0049] The electric pump 3 is disposed between the first pipe section 121 and the second pipe section 122 , and the electric pump 3 can pump water in the first pipe section 121 to the second pipe section 122 .
[0050] Under this setting, after the low-temperature water 10 completes heat exchange with the formation water within the range of the heat reservoir 6 to form the high-temperature water 11, the formation water here (the formation water in the first pipe section 121) will reduce the heat accordingly, and the electric pump 3 forcibly pumps the formation water in the first pipe section 121 into the second pipe section 122, and flows into the heat reservoir 6 through the water outlet 124, so that the formation water in the heat reservoir 6 is replenished into the first pipe section 121 through the water inlet 123. In this way, the water in the first pipe section 121 is always maintained at a higher temperature level, thereby improving the heat exchange efficiency.
[0051] In a specific embodiment, the electric pump 3 is arranged in the outer pipe 12 through the lower packer 5. The lower packer 5 fixes the electric pump 3 at the central axis of the outer pipe 12. At the same time, the lower packer 5 divides the outer pipe 12 into a first pipe section 121 and a second pipe section 122. The fluid in the first pipe section 121 can only enter the second pipe section 122 under the pumping of the electric pump 3. The electric pump 3 is located below the inner pipe 1 and the annulus pipe 2.
[0052] In a specific embodiment, at least one water inlet 123 is arranged on the pipe wall of the first pipe segment 121, and the outer wall of the first pipe segment 121 is in direct contact with the heat reservoir 6. The water inlet 123 is located within the range of the heat reservoir 6, and the formation water in the heat reservoir 6 can be quickly replenished into the first pipe segment 121 through the water inlet 123.
[0053] The length range from the water inlet 123 to the lower packer 5 at least overlaps with a portion of the inner pipe 1 and the annulus pipe 2. That is, the lower ends of the inner pipe 1 and the annulus pipe 2 are located between the water inlet 123 and the lower packer 5, and the formation water in the heat reservoir 6 can exchange heat with the fluid in the inner pipe 1 and the annulus pipe 2 as quickly as possible after entering the first pipe section 121 through the water inlet 123.
[0054] Furthermore, the first through hole 101 on the inner tube 1 is located between the water inlet 123 and the lower packer 5 .
[0055] In a specific embodiment, the lower end of the second pipe section 122 is closed, and at least one water outlet 124 is disposed on the pipe wall of the second pipe section 122 .
[0056] According to the present invention, in one embodiment, the lower end of the inner tube 1 extends out of the annulus pipe 2 in the direction of the central axis by a sealed connection, and is sealed and fixedly connected to the electric pump 3. The cable 8 is arranged inside the inner tube 1, one end of the cable 8 is electrically connected to the electric pump 3, and the other end extends upward along the inner tube 1 to the wellhead.
[0057] In another embodiment, the inner tube 1 is located inside the annulus tube 2, that is, the inner tube 1 is shorter than the annulus tube 2, and the electric pump 3 is fixedly and sealedly connected to the lower end of the annulus tube 2. The cable 8 is arranged in the annulus tube 2, one end of the cable 8 is electrically connected to the electric pump 3, and the other end extends upward along the annulus tube 2 to the wellhead.
[0058] In this embodiment, if Figure 1 As shown, the inner pipe 1 is still located inside the annular pipe 2, the length of the inner pipe 1 is smaller than the annular pipe 2, the electric pump 3 extends to the inside of the annular pipe 2 and the inner pipe 1, and the lower ends of the inner pipe 1 and the annular pipe 2 are fixedly sealed and connected to the electric pump 3. The cable 8 is arranged inside the inner pipe 1, one end of the cable 8 is electrically connected to the electric pump 3, and the other end extends upward along the inner pipe 1 to the wellhead.
[0059] The electric pump 3 can be powered on the ground through the cable 8, and the motion state of the electric pump 3 can be controlled, such as controlling the start and stop of the electric pump 3, or controlling the speed of the electric pump 3. It is easy to understand that the method of controlling the motion state of the electric pump 3 through the circuit is a prior art, which is not the technical point of the present invention and will not be described in detail here.
[0060] After the electric pump 3 is started, Figure 1 As shown, the formation water in the heat reservoir 6 enters the first pipe section 121 from the water inlet 123, and after sufficient heat exchange with the water in the inner pipe 1 and the annular pipe 2, enters the electric pump 3 from the side port of the electric pump 3 under the action of the electric pump 3, and then flows from the right end outlet of the electric pump 3 to the right side of the lower packer 5, that is, the second pipe section 122, and finally flows back to the heat reservoir 6 from the water outlet 124, and returns to the heat reservoir 6 again to exchange heat with the heat reservoir 6. Through this arrangement, it can be ensured that the formation water in the first pipe section 121 always maintains a high temperature, so that the water in the inner pipe 1 and the annular pipe 2 can have a higher heating efficiency.
[0061] According to the present invention, in a specific embodiment, an upper packer 4 is provided between the annulus pipe 2 and the outer pipe 12, so that the annulus pipe 2 can be coaxially fixedly arranged in the outer pipe 12. The upper packer 4 is located above the water inlet 123, that is, the upper packer 4 and the lower packer 5 are the upper and lower end surfaces of the first pipe section 121 respectively, and the upper packer 4, the lower packer 5 and the outer pipe 12 together constitute the first pipe section 121, and the main process of low-temperature water 10 becoming high-temperature water 11 through heat exchange with formation water occurs in the first pipe section 121 between the upper packer 4 and the lower packer 5.
[0062] According to the present invention, in a specific embodiment, at least one straightening mechanism 9 is disposed between the inner tube 1 and the annular tube 2 , and the straightening mechanism 9 coaxially fixes the inner tube 1 in the annular tube 2 .
[0063] It is easy to understand that a hole for fluid to pass through is provided in the axial direction on the centralizing mechanism 9. The centralizing mechanism 9 can be any centralizer in the prior art, as long as the inner tube 1 can be coaxially fixed inside the annular tube 2 and the fluid can flow normally. The specific structure of the centralizer is not the technical point of the present invention and will not be described in detail here.
[0064] According to the present invention, the annular pipe 2 is a corrugated pipe or a round pipe.
[0065] In a preferred embodiment, the annulus pipe 2 is configured as a bellows, which can increase the contact area between the annulus pipe and the formation water, thereby further enhancing the heat exchange efficiency.
[0066] In one embodiment of the present invention, a geothermal well heat exchange enhancement method is provided, and a geothermal well heat exchange enhancement device provided according to the present invention is used to accelerate the flow rate of formation water near the heat reservoir 6, so that the formation water after heat exchange with the inner tube 1 and the annulus tube 2 can flow away quickly, thereby replenishing high-temperature formation water, thereby improving the heat exchange efficiency.
[0067] Combination Figure 1 As shown, the wellhead injects low-temperature water 10 downward into the annular space between the annular pipe 2 and the inner pipe 1. The low-temperature water 10 flows through the upper packer 4 and enters the range where the first pipe section 121 is located. In this range, the low-temperature water 10 exchanges heat with the formation water in the first pipe section 121. The temperature of the thermal reservoir 6 is high, and the formation water in the thermal reservoir 6 can heat the low-temperature water 10, thereby turning the low-temperature water 10 into high-temperature water 11. The high-temperature water 11 then enters the inner cavity of the inner pipe 1 through the first through hole 101 and flows upward.
[0068] The formation water in the first pipe section 121 that has been deprived of heat is pumped by the electric pump 3 through the lower packer 5, enters the second pipe section 122 below, and enters the thermal reservoir 6 through the water outlet 124. Under the action of pressure, the formation water in the thermal reservoir 6 will enter the first pipe section 121 through the water inlet 123 to replenish the formation water in the first pipe section 121, so that the formation water forms a cycle from the thermal reservoir 6 to the first pipe section 121, and then returns to the thermal reservoir 6 through the second pipe section 122. The forced flow of formation water can maintain the formation water in the first pipe section 121 at a higher temperature level, thereby greatly strengthening the heat exchange between the formation water and the low-temperature water 10 and improving the heat extraction. After the formation water is pressed back to the thermal reservoir 6 through the second pipe section 122, it can flow in the formation again, achieving the effect of rapid heat replenishment, thereby improving the heat extraction efficiency of the geothermal well.
[0069] It should be noted that the present invention can be used in various well conditions such as horizontal wells, inclined wells, vertical wells, etc., and is not limited to the well inclination in this embodiment.
[0070] In a preferred embodiment, a filter screen (not shown in the figure) is provided between the water inlet 123 and the inlet end of the electric pump 3, and the filter screen can block the entry of mud and sand.
[0071] In a preferred embodiment, a filter screen (not shown in the figure) is also provided between the water outlet 124 and the outlet section of the electric pump 3, and the filter screen can block the entry of mud and sand.
[0072] In the description of the present invention, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0073] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0074] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "examples", "specific examples", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0075] Finally, it should be noted that the above is only a preferred embodiment of the present invention and does not constitute any limitation to the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for a person skilled in the art to modify the technical solutions described in the aforementioned embodiments or to replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A geothermal well heat exchange enhancement device, include: Inner tube (1); an annular tube (2) coaxially and gap-type sleeved outside the inner tube (1), the lower end of the annular tube (2) being closed, and a first through hole (101) communicating with the annular tube (2) being provided at the lower end of the inner tube (1); An outer pipe (12) is coaxially spaced outside the annular pipe (2), a first pipe section (121) and a second pipe section (122) are arranged inside the outer pipe (12), the inner pipe (1) and the annular pipe (2) are located inside the first pipe section (121), a water inlet (123) is arranged on the first pipe section (121), and a water outlet (124) is arranged on the second pipe section (122); An electric pump (3) is arranged between the first pipe section (121) and the second pipe section (122), and the electric pump (3) pumps water in the first pipe section (121) to the second pipe section (122).
2. The geothermal well heat exchange enhancement device according to claim 1, It is characterized in that The electric pump (3) is arranged in the outer pipe (12) through a lower packer (5), and the lower packer (5) divides the outer pipe (12) into the first pipe section (121) and the second pipe section (122). The electric pump (3) is located below the inner pipe (1) and the annulus pipe (2).
3. The geothermal well heat exchange enhancement device according to claim 2, It is characterized in that The water inlet (123) is arranged on the pipe wall of the first pipe section (121), and the length range from the water inlet (123) to the lower packer (5) at least overlaps with a portion of the inner pipe (1) and the annulus pipe (2).
4. The geothermal well heat exchange enhancement device according to any one of claims 1 to 3, It is characterized in that The lower end of the second pipe section (122) is closed, and the water outlet (124) is arranged on the pipe wall of the second pipe section (122).
5. The geothermal well heat exchange enhancement device according to any one of claims 1 to 3, It is characterized in that The lower ends of the inner tube (1) and / or the annular tube (2) are sealedly connected to the electric pump (3).
6. The geothermal well heat exchange enhancement device according to claim 5, It is characterized in that A cable (8) is arranged in the inner pipe (1) or the annular pipe (2), and the cable (8) is electrically connected to the electric pump (3).
7. The geothermal well heat exchange enhancement device according to any one of claims 1 to 3, It is characterized in that An upper packer (4) is arranged between the annulus pipe (2) and the outer pipe (12), and the upper packer (4) is located above the water inlet (123).
8. The geothermal well heat exchange enhancement device according to any one of claims 1 to 3, It is characterized in that At least one straightening mechanism (9) is provided between the inner tube (1) and the annular tube (2).
9. The geothermal well heat exchange enhancement device according to any one of claims 1 to 3, It is characterized in that The water inlet (123) is connected to the thermal reservoir (6) downhole, and the annular pipe (2) is a corrugated pipe or a round pipe.
10. A method for enhancing heat exchange of a geothermal well, It is characterized in that The geothermal well heat exchange enhancement device according to any one of claims 1 to 9 is used to accelerate the flow rate of formation water near the heat reservoir (6) and improve the heat exchange efficiency.
Citation Information
Patent Citations
Heat exchange sleeve device for efficiently exploiting geothermal resources and geothermal single well system
CN214371027U
Geothermal pipe for geothermal development
CN216557734U