Meter reading route determination method and device, processor and readable storage medium
By determining the geographical location of the electricity meter and the difficulty coefficient of meter reading, planning the meter reading route and marking the difficulty coefficient, the problem of low meter reading efficiency was solved, and the meter reading route was optimized and efficiency was improved.
Patent Information
- Application Number
- CN202411146385.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-26
AI Technical Summary
Current meter reading technology is inefficient, manual meter reading is time-consuming and labor-intensive, and meter readers have difficulty accurately predicting the location and time of the meter, resulting in insufficient accuracy and timeliness of meter reading.
By determining the geographical location of the electricity meter and the difficulty coefficient of meter reading, the meter reading route is planned and the difficulty coefficient is marked, and the meter reading route is optimized to improve efficiency.
This enables the rational planning of meter reading routes based on actual conditions, improving meter reading efficiency and accuracy, and ensuring the safe and stable operation of the power grid.
Smart Images

Figure CN119022916A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of route planning, and in particular to a method, device, processor and readable storage medium for determining a meter reading route. Background Art
[0002] At present, meter reading is one of the basic management and operation means of the power industry. Through meter reading, users' electricity consumption can be monitored in real time, users' electricity demand can be understood in a timely manner, and data support and decision-making basis can be provided for the power industry. The accuracy and timeliness of meter reading are crucial to the operation and management of the power industry. Only through accurate meter reading data can the reasonable planning and resource allocation of the power industry be realized, and the safe and stable operation of the power grid be ensured.
[0003] In the related technologies, manual meter reading is time-consuming and laborious, and its accuracy and timeliness cannot be guaranteed. In addition, because the meters are installed in different locations, the difficulty coefficient of meter reading is different, and it is difficult for the meter reader to predict the time it takes to read the meter. If the traditional method is used to divide the area into sections and read the meter according to the concentrator or transformer, it is difficult to achieve the goal of efficient meter reading. Therefore, there is a technical problem of low meter reading efficiency.
[0004] Currently, no effective solution has been proposed for the above-mentioned technical problem of low meter reading efficiency. Summary of the invention
[0005] The embodiments of the present invention provide a method, device, processor and readable storage medium for determining a meter reading route, so as to at least solve the technical problem of low meter reading efficiency.
[0006] According to one aspect of an embodiment of the present invention, a method for determining a meter reading route is provided. The method may include: determining a plurality of meters to be read; obtaining the geographical location of each meter to be read; determining a map positioning point and a meter reading difficulty coefficient of each meter to be read based on the geographical location of each meter to be read, wherein the map positioning point is used to indicate the location of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; determining a meter reading route for the meter to be read based on each map positioning point and the meter reading difficulty coefficient, and marking the meter reading difficulty coefficient in the meter reading route.
[0007] Optionally, obtaining the geographical location of each meter to be read includes: obtaining the asset number of each meter to be read; matching the asset number with the electricity usage address of the meter to be read to determine the electricity usage address of each meter to be read; determining the location of the operating meter in the electricity usage address; and determining the location of the operating meter as the geographical location of the meter to be read.
[0008] Optionally, based on the geographical location of each meter to be read, determining the map location point of each meter to be read includes: mapping the geographical location of each meter to be read on a map to obtain the map location point of each meter to be read.
[0009] Optionally, based on the geographical location of each meter to be read, determining the meter reading difficulty coefficient of each meter to be read, includes: obtaining a target distance of the meter to be read, wherein the target distance is used to indicate the distance between the meter to be read and the ground or the distance between the meters to be read; in response to the target distance being less than a distance threshold, determining the meter reading difficulty coefficient of the meter to be read as a first-level coefficient; in response to the target distance being greater than the distance threshold, determining the meter reading difficulty coefficient of the meter to be read as a second-level coefficient, wherein the meter reading difficulty corresponding to the second-level coefficient is greater than the meter reading difficulty corresponding to the first-level coefficient.
[0010] Optionally, based on each map positioning point and the meter reading difficulty coefficient, the meter reading route of the meter to be read is determined, including: based on each map positioning point, determining the running time of the object to be read from the power supply station to each meter to be read; based on the meter reading difficulty coefficient, determining the meter reading time for the object to be read to read the meter to be read; summing the running time and the meter reading time to obtain the total meter reading time corresponding to each meter to be read, wherein the total meter reading time is used to indicate the time consumed to complete reading the meter to be read; based on the total meter reading time, determining the meter reading route of the meter to be read.
[0011] Optionally, based on the total meter reading time, determining the meter reading route of the meter to be read includes: a comparison step, comparing the total meter reading times corresponding to multiple meters to be read respectively to obtain comparison results, and determining the nodes of the meter reading route based on the comparison results; a first determination step, in response to the comparison result being less than a preset threshold, determining the meter to be read corresponding to the total meter reading time as a node of the meter reading route, executing the comparison step until the total meter reading time is greater than the preset total time threshold; a second determination step, connecting each node in a target order to obtain the meter reading route of the meter to be read, executing the comparison step and the first determination step until the meters to be read are all determined as nodes, wherein the determination order is used to indicate the order in which the meters to be read are determined as nodes in the first determination step.
[0012] According to another aspect of an embodiment of the present invention, a device for determining a meter reading route is also provided. The device may include: a first determining unit, used to determine a plurality of meters to be read; an acquiring unit, used to acquire the geographical location of each meter to be read; a second determining unit, used to determine the map positioning point and meter reading difficulty coefficient of each meter to be read based on the geographical location of each meter to be read, wherein the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; a third determining unit, used to determine the meter reading route of the meter to be read based on each map positioning point and the meter reading difficulty coefficient, and mark the meter reading difficulty coefficient in the meter reading route.
[0013] According to another aspect of an embodiment of the present invention, a computer-readable storage medium is provided. The computer-readable storage medium includes a stored program. When the program is executed by a processor, the device where the storage medium is located is controlled to execute the method for determining a meter reading route in an embodiment of the present invention.
[0014] According to another aspect of an embodiment of the present invention, a processor is further provided. The processor is used to run a program, wherein when the program is run, the method for determining a meter reading route in an embodiment of the present invention is executed.
[0015] According to another aspect of the embodiment of the present invention, a computer program product is provided, which includes computer instructions, and when the computer instructions are executed by a processor, the method for determining a meter reading route in the embodiment of the present invention is implemented.
[0016] In an embodiment of the present invention, multiple meters to be read are determined; the geographical location of each meter to be read is obtained; according to the geographical location of each meter to be read, the map positioning point and the meter reading difficulty coefficient of each meter to be read are determined, wherein the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; based on each map positioning point and the meter reading difficulty coefficient, the meter reading route of the meter to be read is determined, and the meter reading difficulty coefficient is marked in the meter reading route. That is to say, the present invention determines the map positioning point and the meter reading difficulty coefficient of each meter to be read through the geographical location of each meter to be read, thereby determining the meter reading route of the meter to be read according to each map positioning point and the meter reading difficulty coefficient, and by using the actual geographical location of the meter to be read and the meter reading difficulty degree, the purpose of rationally planning the meter reading route according to the actual situation is achieved, thereby solving the technical problem of low meter reading efficiency and achieving the technical effect of improving meter reading efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0018] Figure 1 is a flow chart of a method for determining a meter reading route according to an embodiment of the present invention;
[0019] Figure 2 is a flow chart of a method for optimizing an electric meter line according to an embodiment of the present invention;
[0020] Figure 3 2 is a schematic diagram of a device for determining a meter reading route according to an embodiment of the present invention. DETAILED DESCRIPTION
[0021] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0022] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, functional component or device that includes a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, functional components or devices.
[0023] Example 1
[0024] According to an embodiment of the present invention, an embodiment of a method for determining a meter reading route is provided. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical sequence is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.
[0025] Figure 1 is a flow chart of a method for determining a meter reading route according to an embodiment of the present invention. Figure 1 As shown, the method may include the following steps:
[0026] Step S101, determining a plurality of electricity meters to be read.
[0027] In the technical solution provided in the above step S101 of the present invention, the electricity meter to be read may be referred to as an unread electricity meter.
[0028] In this embodiment, multiple meters to be read are determined. For example, the meters to be read are determined by querying the meter reader account. This is only an example and does not limit the specific method of determining the meters to be read.
[0029] For example, at the beginning of each month, after logging into the mobile application portal on the mobile terminal, the network-level mobile management of the corresponding meter reader account is opened, and the "Unread Meter Query" module in the management system is used to query the unread meters of the meter reader that month.
[0030] Step S102, obtaining the geographical location of each electricity meter to be read.
[0031] In the technical solution provided in the above step S102 of the present invention, after a plurality of electricity meters to be read are determined in step S101, the geographical location of each of the electricity meters to be read is obtained.
[0032] In this embodiment, the asset number of each meter to be read is obtained; the asset number is matched with the electricity usage address of the meter to be read, and the electricity usage address of each meter to be read is determined.
[0033] Optionally, after the electricity usage addresses of the meters to be read are determined, the positions of the operating meters in the electricity usage addresses are determined; and the positions of the operating meters are determined as the geographical locations of the meters to be read.
[0034] Optionally, matching the corresponding electricity usage address with the asset number of the electricity meter can ensure accurate positioning of the specific electricity usage address, avoid information confusion or errors, and save time and effort in searching for information.
[0035] Step S103, based on the geographical location of each electricity meter to be read, determining the map positioning point and meter reading difficulty coefficient of each electricity meter to be read.
[0036] In the technical solution provided in the above step S103 of the present invention, the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read.
[0037] In this embodiment, after the geographical location of each meter to be read is obtained in step S102, the map positioning point and meter reading difficulty coefficient of each meter to be read are determined according to the geographical location of each meter to be read.
[0038] Optionally, in order to determine the map positioning point of each electricity meter to be read according to the geographical location of each electricity meter to be read, the geographical location of each electricity meter to be read may be mapped on a map to obtain the map positioning point of each electricity meter to be read.
[0039] Optionally, the meter reading difficulty coefficient of each meter to be read may be determined according to the geographical location of each meter to be read by acquiring a target distance of the meter to be read, wherein the target distance is used to indicate the distance between the meter to be read and the ground or the distance between the meters to be read.
[0040] Optionally, when the target distance is less than the distance threshold, it means that the meter to be read is not far from the ground, based on which, it can be determined that the meter reading difficulty coefficient of the meter to be read is the first level;
[0041] Optionally, when the target distance is greater than the distance threshold, it means that the meter to be read is far from the ground. Based on this, it can be determined that the meter reading difficulty coefficient of the meter to be read is the second level, wherein the meter reading difficulty coefficient corresponding to the second level is greater than the meter reading difficulty coefficient corresponding to the first level.
[0042] For example, assuming that the distance threshold is 1.5 meters (m), and the height of the meter to be read is 1.7m, since 1.7>1.5, that is, the target distance is greater than the distance threshold, based on this, it can be determined that the meter reading difficulty coefficient of the meter to be read is the second level coefficient.
[0043] Step S104: determining a meter reading route for the meter to be read based on each map positioning point and the meter reading difficulty coefficient, and marking the meter reading difficulty coefficient in the meter reading route.
[0044] In the technical solution provided in the above step S104 of the present invention, after the map positioning points and meter reading difficulty coefficients of each meter to be read are determined in step S103, the meter reading routes of the meters to be read are determined according to the map positioning points and the meter reading difficulty coefficients, and the meter reading difficulty coefficients are marked in the meter reading route.
[0045] In this embodiment, the running time of the object to be read from the power supply station to each meter to be read is determined according to each map positioning point; and the meter reading time of the object to be read to read the meter to be read is determined according to the meter reading difficulty coefficient.
[0046] Optionally, after determining the meter reading time, the total meter reading time corresponding to each meter to be read is determined according to the operating time and the meter reading time, wherein the total meter reading time is used to indicate the time consumed to complete reading the meters to be read.
[0047] For example, the running time and the meter reading time are summed to obtain the total meter reading time corresponding to each meter to be read.
[0048] Optionally, after the total meter reading time is determined, a meter reading route of the meter to be read is determined according to the total meter reading time.
[0049] For example, in the comparison step, the total meter reading times corresponding to multiple meters to be read are compared respectively to obtain comparison results, and the nodes of the meter reading route are determined based on the comparison results; in the first determination step, in response to the comparison result being less than a preset threshold, the meter to be read corresponding to the total meter reading time is determined as a node of the meter reading route, and the comparison step is executed until the total meter reading time is greater than the preset total time threshold; in the second determination step, each node is connected in a target order to obtain the meter reading route of the meter to be read, and the comparison step and the first determination step are executed until all the meters to be read are determined as nodes, wherein the determination order is used to indicate the order in which the meters to be read are determined as nodes in the first determination step.
[0050] It should be noted that the above embodiment can be executed by a device for determining a meter reading route.
[0051] In the above steps S101 to S104 of the present invention, a plurality of meters to be read are determined; the geographical location of each meter to be read is obtained; according to the geographical location of each meter to be read, the map positioning point and the meter reading difficulty coefficient of each meter to be read are determined, wherein the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; based on each map positioning point and the meter reading difficulty coefficient, the meter reading route of the meter to be read is determined, and the meter reading difficulty coefficient is marked in the meter reading route. In other words, the present invention determines the map positioning point and the meter reading difficulty coefficient of each meter to be read through the geographical location of each meter to be read, thereby determining the meter reading route of the meter to be read according to each map positioning point and the meter reading difficulty coefficient, and by using the actual geographical location of the meter to be read and the meter reading difficulty degree, the purpose of rationally planning the meter reading route according to the actual situation is achieved, thereby solving the technical problem of low meter reading efficiency and achieving the technical effect of improving meter reading efficiency.
[0052] The above method of this embodiment is further introduced below.
[0053] As an optional implementation method, obtaining the geographical location of each meter to be read includes: obtaining the asset number of each meter to be read; matching the asset number with the electricity usage address of the meter to be read to determine the electricity usage address of each meter to be read; determining the location of the operating meter in the electricity usage address; and determining the location of the operating meter as the geographical location of the meter to be read.
[0054] In this embodiment, the asset number of each meter to be read is obtained; the asset number is matched with the electricity usage address of the meter to be read, and the electricity usage address of each meter to be read is determined.
[0055] Optionally, after the electricity usage addresses of the meters to be read are determined, the positions of the operating meters in the electricity usage addresses are determined; and the positions of the operating meters are determined as the geographical locations of the meters to be read.
[0056] Optionally, matching the corresponding electricity usage address with the asset number of the electricity meter can ensure accurate positioning of the specific electricity usage address, avoid information confusion or errors, and save time and effort in searching for information.
[0057] As an optional implementation manner, based on the geographical location of each meter to be read, determining the map location point of each meter to be read includes: mapping the geographical location of each meter to be read on a map to obtain the map location point of each meter to be read.
[0058] In this embodiment, the geographical location of each electricity meter to be read is mapped on a map to obtain a map positioning point of each electricity meter to be read.
[0059] As an optional implementation method, based on the geographical location of each meter to be read, determining the meter reading difficulty coefficient of each meter to be read includes: obtaining a target distance of the meter to be read, wherein the target distance is used to indicate the distance between the meter to be read and the ground or the distance between the meters to be read; in response to the target distance being less than a distance threshold, determining the meter reading difficulty coefficient of the meter to be read as a first level; in response to the target distance being greater than the distance threshold, determining the meter reading difficulty coefficient of the meter to be read as a second level, wherein the meter reading difficulty coefficient corresponding to the second level is greater than the meter reading difficulty coefficient corresponding to the first level.
[0060] In this embodiment, a target distance of the electric meter to be read is obtained, wherein the target distance is used to indicate the distance between the electric meter to be read and the ground or the distance between the electric meters to be read.
[0061] Optionally, when the target distance is less than the distance threshold, it means that the meter to be read is not far from the ground, based on which, it can be determined that the meter reading difficulty coefficient of the meter to be read is the first level;
[0062] Optionally, when the target distance is greater than the distance threshold, it means that the meter to be read is far from the ground. Based on this, it can be determined that the meter reading difficulty coefficient of the meter to be read is the second level, wherein the meter reading difficulty coefficient corresponding to the second level is greater than the meter reading difficulty coefficient corresponding to the first level.
[0063] For example, assuming that the distance threshold is 1.5m, and the height of the meter to be read is 1.7m, since 1.7>1.5, that is, the target distance is greater than the distance threshold, based on this, it can be determined that the meter reading difficulty coefficient of the meter to be read is the second-level coefficient.
[0064] Optionally, since the electricity consumption categories of the electricity meters to be read are different, different distance thresholds may be set to distinguish the electricity consumption categories of the electricity meters to be read.
[0065] For example, according to the electricity consumption category of the management system, it is divided into non-industrial, wholesale, residential, non-residential, agricultural production, agricultural irrigation and drainage, other electricity, large industrial electricity, general industry, and commerce. Among them, the electricity meters to be read in the residents' lives can be divided into two types: villages and residential areas. After the electricity consumption category is identified, the distance is calculated based on the environmental algorithm of the on-site electricity meter, and the distance threshold is 30cm. If the distance to two or more adjacent electricity meters is within 30cm, it is determined that the meter is in the meter container box, and then it is judged to belong to the residential area type based on the actual address and positioning, and the meter reading difficulty coefficient of the meter is evaluated as the first level coefficient.
[0066] For another example, for the meter to be read in large industrial electricity consumption: whether the word "charging pile" exists in the work order and electricity address in the system file is used to determine whether it is a charging pile user. If so, it is further judged based on the distance to the ground of the meter and whether the address is in a village or a building. If the distance to the ground is less than 1.5m and located in a building, it is evaluated as the first-level coefficient; when the distance to the ground is more than 1.5m and located in a building, it is evaluated as the first-level coefficient; when the distance to the ground is less than 1.5m and located in a village, it is evaluated as the first-level coefficient; when the distance to the ground is more than 1.5m and located in a village, it is evaluated as the second-level coefficient. In other cases, the first-level coefficient is evaluated by default.
[0067] As an optional implementation method, based on each map positioning point and the meter reading difficulty coefficient, the meter reading route of the meter to be read is determined, including: based on each map positioning point, determining the running time of the object to be read from the power supply station to each meter to be read; based on the meter reading difficulty coefficient, determining the meter reading time for the object to be read to read the meter to be read; summing the running time and the meter reading time to obtain the total meter reading time corresponding to each meter to be read, wherein the total meter reading time is used to indicate the time consumed to complete reading the meter to be read; based on the total meter reading time, determining the meter reading route of the meter to be read.
[0068] In this embodiment, the running time of the object to be read from the power supply station to each meter to be read is determined according to each map positioning point; and the meter reading time of the object to be read to read the meter to be read is determined according to the meter reading difficulty coefficient.
[0069] Optionally, after determining the meter reading time, the running time is summed with the meter reading time to obtain the total meter reading time corresponding to each meter to be read, wherein the total meter reading time is used to indicate the time consumed to complete reading the meter to be read, thereby determining the meter reading route of the meter to be read based on the total meter reading time.
[0070] Optionally, by determining the running time of the object to be read from the power supply station to each meter to be read and the meter reading time, the working route of the meter reader can be effectively arranged to ensure efficient meter reading.
[0071] As an optional implementation method, based on the total meter reading time, determining the meter reading route of the meter to be read includes: a comparison step, comparing the total meter reading times corresponding to multiple meters to be read respectively to obtain comparison results, and determining the nodes of the meter reading route based on the comparison results; a first determination step, in response to the comparison result being less than a preset threshold, determining the meter to be read corresponding to the total meter reading time as a node of the meter reading route, executing the comparison step until the total meter reading time is greater than the preset total time threshold; a second determination step, connecting each node in a target order to obtain the meter reading route of the meter to be read, executing the comparison step and the first determination step until the meters to be read are all determined as nodes, wherein the determination order is used to indicate the order in which the meters to be read are determined as nodes in the first determination step.
[0072] In this embodiment, in the comparison step, the total meter reading times corresponding to the multiple meters to be read are compared to obtain a comparison result. When the comparison result is less than a preset threshold, the meter to be read corresponding to the total meter reading time is determined as a node of the meter reading route.
[0073] For example, the total meter reading times are compared, and the meter to be read corresponding to the smallest total meter reading time is selected as the node of the meter reading route, that is, the first meter reading station T1.
[0074] Optionally, the comparison step is performed until the total meter reading time is greater than a preset total time threshold.
[0075] For example, after determining a meter reading node, the total meter reading times corresponding to the remaining meters to be read that have not been determined are compared again. When the comparison result is less than a preset threshold, the meter to be read corresponding to the total meter reading time is determined as the second node of the meter reading route, and so on, until the sum of all the total meter reading times corresponding to the determined nodes is greater than the preset total time threshold.
[0076] Optionally, in the second determination step, each node is connected in a target order to obtain a meter reading route of the meter to be read, and the comparison step and the first determination step are performed until all the meters to be read are determined as nodes.
[0077] For example, the nodes determined in the first determination step are connected in a target order, that is, in an order in which the nodes are determined, so as to obtain a meter reading route for the meter to be read. After the meter reading route is determined, the comparison step and the first determination step are continued for the remaining meters to be read until all the meters to be read are determined as nodes, that is, all the meters to be read are in the meter reading route.
[0078] It should be noted that the above embodiment can be executed by a device for determining a meter reading route.
[0079] In this embodiment, multiple meters to be read are determined; the geographical location of each meter to be read is obtained; according to the geographical location of each meter to be read, the map positioning point and the meter reading difficulty coefficient of each meter to be read are determined, wherein the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; based on each map positioning point and the meter reading difficulty coefficient, the meter reading route of the meter to be read is determined, and the meter reading difficulty coefficient is marked in the meter reading route. That is to say, the present invention determines the map positioning point and the meter reading difficulty coefficient of each meter to be read through the geographical location of each meter to be read, thereby determining the meter reading route of the meter to be read according to each map positioning point and the meter reading difficulty coefficient, and by using the actual geographical location of the meter to be read and the meter reading difficulty degree, the purpose of rationally planning the meter reading route according to the actual situation is achieved, thereby solving the technical problem of low meter reading efficiency and achieving the technical effect of improving meter reading efficiency.
[0080] Example 2
[0081] The technical solution of the embodiment of the present invention is illustrated below in conjunction with preferred implementation modes.
[0082] At present, meter reading is one of the basic management and operation means of the power industry. Through meter reading, users' electricity consumption can be monitored in real time, users' electricity demand can be understood in a timely manner, and data support and decision-making basis can be provided for the power industry. The accuracy and timeliness of meter reading are crucial to the operation and management of the power industry. Only through accurate meter reading data can the reasonable planning and resource allocation of the power industry be realized, and the safe and stable operation of the power grid be ensured.
[0083] In the related art, manual meter reading is time-consuming and laborious, and its accuracy and timeliness cannot be guaranteed. In addition, because the meters are installed in different locations, the difficulty coefficient of meter reading is different, and it is difficult for meter readers to predict the time it takes to read the meters. If the traditional method of dividing the area into sections and reading the meters according to the concentrator or transformer is used, it is difficult to achieve the goal of efficient meter reading. Therefore, there is a technical problem of low meter reading efficiency. For the above-mentioned technical problem of low meter reading efficiency, no effective solution has been proposed yet.
[0084] However, an embodiment of the present invention proposes a method for optimizing meter reading routes, which matches the corresponding electricity usage address through the asset number of the meter, generates map positioning points based on the existing operating meter positioning, and intelligently plans the optimal time-saving meter reading route and meter reading sequence based on the positioning points and the departure point; solves the technical problem of low meter reading efficiency and achieves the technical effect of improving meter reading efficiency.
[0085] The embodiments of the present invention are further described below.
[0086] Figure 2is a flow chart of a method for optimizing an electric meter line according to an embodiment of the present invention. The target detection method comprises the following steps:
[0087] Step S201, grouping the electric meters to be read.
[0088] In this embodiment, users who need to read meters are divided into different groups according to meter readers.
[0089] Step S202, determining the first meter reading station.
[0090] In this embodiment, the power supply station is used as the base point B, and the time required from the power supply station to each meter reading address is derived using AutoNavi Map. The required time is added to the meter reading time rated by each user to obtain the total meter reading time A. A is compared and the minimum value is selected as the first meter reading station T1.
[0091] Optionally, the total meter reading time can be calculated by the following formula:
[0092]
[0093] Among them, T n It indicates the time taken for meter reading, and Treturn indicates the time taken to return from the meter reading location to the power supply station.
[0094] Step S203, determining the meter reading route.
[0095] In this embodiment, the remaining meters are judged in the same way with T1 as the starting point to confirm the second meter reading station T2, and the whole meter reading route is confirmed by repeating this process.
[0096] Step S204, determining the meter reading end point.
[0097] In this embodiment, considering that the working time of the master is about 150 minutes at a time, the time S is introduced. After each confirmation of the meter reading location, the total time of all meter readings is added up, and the time for the meter reading location to return to the power station is added. If it is greater than 150 minutes, this meter reading location is taken as the end point and this meter reading is completed.
[0098] Step S205: Check whether meter reading is completed.
[0099] In this embodiment, it is determined whether the meter reading of all the meters to be read has been completed. If so, step S206 is executed; if not, step S202 is executed.
[0100] Step S206, completing meter reading.
[0101] In this embodiment, meter reading of all the electricity meters to be read is completed.
[0102] In this embodiment, a primary identification classification is performed based on the electricity usage category in the user file corresponding to the electricity meter. The system's electricity usage category is divided into non-industrial, wholesale, residential, non-residential, agricultural production, agricultural irrigation and drainage, other electricity usage, large industrial electricity usage, general industry, and commerce. A representative symbol is compiled for each category and written into the subsequent evaluation algorithm.
[0103] Optionally, residential life can be divided into two types: village residence and residential community. After identifying the electricity consumption category, the distance is calculated based on the environmental algorithm of the on-site electric meter. If the distance to two or more adjacent electric meters is within 30cm, the meter is judged to be in the meter container. Then, according to the actual address and location, it is judged to belong to the residential community type, and the meter reading difficulty level is assessed as low. If the above distance judgment is not met and the actual address and location are in the village, it is assessed as medium difficulty. Then, according to whether the height of the electric meter location is greater than 1.5m from the ground and the shape and newness of the village, further assessment is made, and these electric meters are given a medium difficulty or a high difficulty assessment.
[0104] Optionally, agricultural production, agricultural irrigation and drainage: after being identified as this category, since it is difficult to find the electric meters of this category on site, and they are generally installed on poles in farmland, most of which are higher than 1.5m, the rating of this type of electric meters starts from medium difficulty, and the difficulty is maintained at medium if the distance from the ground is within 1.5m-2m and the distance from the site to the actual available driving path is within 100m; if any of the evaluation indicators is exceeded, it is rated as high difficulty.
[0105] Optionally, non-industrial, wholesale, non-residential, and other electricity use: generally public services such as schools, hospitals, power supply, offices or temporary electricity use. The judgment is based on whether there are recent general temporary electricity use work orders in the work order archive in the system. If the work order filing date is within 6 months, it is judged as a temporary electricity meter installation. Since temporary electricity use generally belongs to the repair or reconstruction of buildings, there are certain safety risks on site, so the difficulty is rated as medium. The rest of the situations are rated as low difficulty.
[0106] Optionally, for large industrial electricity use: determine whether it is a charging pile user based on whether the word "charging pile" exists in the work order and electricity use address in the system file. If so, further determine based on the distance to the ground located in the table and whether the address is in a village or a building. If the distance to the ground is less than 1.5m and located in a building, it is assessed as low difficulty; when the distance to the ground is more than 1.5m and located in a building, it is assessed as medium difficulty; when the distance to the ground is less than 1.5m and located in a village, it is assessed as medium difficulty; when the distance to the ground is more than 1.5m and located in a village, it is assessed as high difficulty. In other cases, the default assessment is low difficulty.
[0107] Optionally, general industry and commerce: general industry can be divided into industrial parks and village individual households, which can refer to the classification of residential categories. The commercial category can directly refer to the classification of residential categories.
[0108] Optionally, after the meter reading difficulty rating is carried out according to the above-mentioned categories, an efficient meter reading path is generated according to the difficulty and spatial distance of meter reading through an algorithm to improve the meter reading efficiency.
[0109] Optionally, the meter reading difficulty coefficient is set based on the altitude, and the difficulty coefficient of each route is marked, so that the meter readers can prepare climbing tools in advance, etc., to reduce the time spent by the meter readers in meter reading, improve the meter reading efficiency, and increase the timeliness of electricity bill issuance.
[0110] In this embodiment, the corresponding electricity usage address is matched by the asset number of the electricity meter, and a map positioning point is generated based on the existing operating electricity meter positioning. Based on the positioning point and the departure point, the optimal time-saving meter reading route and meter reading sequence are intelligently planned, thereby solving the technical problem of low meter reading efficiency and achieving the technical effect of improving meter reading efficiency.
[0111] Example 3
[0112] According to an embodiment of the present invention, a device for determining a meter reading route is also provided. It should be noted that the device for determining a meter reading route can be used to execute the method for determining a meter reading route in Example 1.
[0113] Figure 3 Schematic diagram of a device for determining a meter reading route according to an embodiment of the present invention. Figure 3 As shown, the device 300 for determining a meter reading route may include: a first determining unit 301 , an acquiring unit 302 , a second determining unit 303 and a third determining unit 304 .
[0114] The first determining unit 301 is used to determine a plurality of electricity meters to be read.
[0115] The acquisition unit 302 is used to acquire the geographical location of each electricity meter to be read.
[0116] The second determining unit 303 is used to determine the map positioning point and meter reading difficulty coefficient of each meter to be read based on the geographical location of each meter to be read, wherein the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read.
[0117] The third determining unit 304 is used to determine a meter reading route of the meter to be read based on each map positioning point and the meter reading difficulty coefficient, and mark the meter reading difficulty coefficient in the meter reading route.
[0118] Optionally, the acquisition unit 302 may include: a first acquisition module, used to acquire the asset number of each meter to be read; a first determination module, used to match the asset number with the electricity usage address of the meter to be read, and determine the electricity usage address of each meter to be read; a second determination module, used to determine the location of the operating meter in the electricity usage address; and a third determination module, used to determine the location of the operating meter as the geographical location of the meter to be read.
[0119] Optionally, the second determining unit 303 may include: a mapping module, configured to map the geographical location of each to-be-read electricity meter on a map to obtain a map positioning point of each to-be-read electricity meter.
[0120] Optionally, the second determination unit 303 may include: a second acquisition module, used to acquire a target distance of the meter to be read, wherein the target distance is used to indicate the distance between the meter to be read and the ground or the distance between the meters to be read; a fourth determination module, used to determine that the meter reading difficulty coefficient of the meter to be read is a first-level coefficient in response to the target distance being less than a distance threshold; and a fifth determination module, used to determine that the meter reading difficulty coefficient of the meter to be read is a second-level coefficient in response to the target distance being greater than the distance threshold, wherein the meter reading difficulty corresponding to the second-level coefficient is greater than the meter reading difficulty corresponding to the first-level coefficient.
[0121] Optionally, the third determination unit 304 may include: a sixth determination module, used to determine the running time of the object to be read from the power supply station to each meter to be read based on each map positioning point; a seventh determination module, used to determine the meter reading time for the object to be read to read the meter to be read based on the meter reading difficulty coefficient; a calculation module, used to sum the running time with the meter reading time to obtain the total meter reading time corresponding to each meter to be read, wherein the total meter reading time is used to indicate the time consumed to complete the reading of the meter to be read; an eighth determination module, used to determine the meter reading route of the meter to be read based on the total meter reading time.
[0122] Optionally, the eighth determination module may include: a comparison submodule, used for the comparison step, respectively comparing the total meter reading times corresponding to multiple meters to be read, obtaining a comparison result, and determining the nodes of the meter reading route based on the comparison result; a first determination submodule, used for the first determination step, in response to the comparison result being less than a preset threshold, determining the meter to be read corresponding to the total meter reading time as a node of the meter reading route, executing the comparison step until the total meter reading time is greater than the preset total time threshold; a second determination submodule, used for the second determination step, connecting each node in a target order to obtain the meter reading route of the meter to be read, executing the comparison step and the first determination step until all the meters to be read are determined as nodes, wherein the determination order is used to indicate the order in which the meters to be read are determined as nodes in the first determination step.
[0123] In this embodiment, multiple meters to be read are determined; the geographical location of each meter to be read is obtained; according to the geographical location of each meter to be read, the map positioning point and the meter reading difficulty coefficient of each meter to be read are determined, wherein the map positioning point is used to indicate the position of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; based on each map positioning point and the meter reading difficulty coefficient, the meter reading route of the meter to be read is determined, and the meter reading difficulty coefficient is marked in the meter reading route. That is to say, the present invention determines the map positioning point and the meter reading difficulty coefficient of each meter to be read through the geographical location of each meter to be read, thereby determining the meter reading route of the meter to be read according to each map positioning point and the meter reading difficulty coefficient, and by using the actual geographical location of the meter to be read and the meter reading difficulty degree, the purpose of rationally planning the meter reading route according to the actual situation is achieved, thereby solving the technical problem of low meter reading efficiency and achieving the technical effect of improving meter reading efficiency.
[0124] Example 4
[0125] According to an embodiment of the present invention, a computer-readable storage medium is further provided. The storage medium includes a stored program, wherein the program executes the method for determining a meter reading route in Embodiment 1.
[0126] Example 5
[0127] According to an embodiment of the present invention, a processor is further provided. The processor is used to run a program. When the program is run, the method for determining a meter reading route in Embodiment 1 is executed.
[0128] According to an embodiment of the present invention, a computer program product is further provided. The computer program product includes computer instructions. When the computer instructions are executed by a processor, the method for determining a meter reading route in Embodiment 1 is implemented.
[0129] The serial numbers of the above embodiments of the present invention are only for description and do not represent the advantages or disadvantages of the embodiments.
[0130] In the above embodiments of the present invention, the description of each embodiment has its own emphasis. For parts that are not described in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.
[0131] In the several embodiments provided in this application, it should be understood that the disclosed technical content can be implemented in other ways. Among them, the device embodiments described above are only schematic. For example, the division of units can be a logical function division. There may be other division methods in actual implementation. For example, multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of units or modules, which can be electrical or other forms.
[0132] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed over multiple units. Some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.
[0133] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.
[0134] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent functional component, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, in essence, or the part that contributes to the prior art, or all or part of the technical solution can be embodied in the form of a software functional component, which is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, server or network device, etc.) to perform all or part of the steps of the methods of each embodiment of the present invention. The aforementioned storage medium includes: U disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), mobile hard disk, disk or optical disk, etc., which can store program codes.
[0135] The above are only preferred embodiments of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for determining a meter reading route, characterized in that: include: Determine multiple electricity meters to be read; Obtaining the geographical location of each of the electricity meters to be read; Based on the geographical location of each of the electricity meters to be read, determining a map positioning point and a meter reading difficulty coefficient of each of the electricity meters to be read, wherein the map positioning point is used to indicate the location of the electricity meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the electricity meter to be read; Based on each of the map positioning points and the meter reading difficulty coefficient, a meter reading route of the meter to be read is determined, and the meter reading difficulty coefficient is marked in the meter reading route.
2. The method according to claim 1, characterized in that Obtaining the geographical location of each of the electricity meters to be read includes: Obtaining the asset number of each of the electricity meters to be read; Matching the asset number with the electricity usage address of the electricity meter to be read, and determining the electricity usage address of each electricity meter to be read; Determine the location of the operated electric meter in the electric usage address; The location of the operated electric meter is determined as the geographical location of the electric meter to be read.
3. The method according to claim 1, characterized in that Based on the geographical location of each of the electricity meters to be read, determining a map location point of each of the electricity meters to be read includes: The geographical location of each of the electricity meters to be read is mapped on a map to obtain a map positioning point of each of the electricity meters to be read.
4. The method according to claim 1, characterized in that: Determining the meter reading difficulty coefficient of each of the electricity meters to be read based on the geographical location of each of the electricity meters to be read, including: Acquire a target distance of the meter to be read, wherein the target distance is used to indicate the distance between the meter to be read and the ground or the distance between the meters to be read; In response to the target distance being less than a distance threshold, determining the meter reading difficulty coefficient of the to-be-read electricity meter to be a first-level coefficient; In response to the target distance being greater than a distance threshold, the meter reading difficulty coefficient of the to-be-read electricity meter is determined to be a second-level coefficient, wherein the meter reading difficulty corresponding to the second-level coefficient is greater than the meter reading difficulty corresponding to the first-level coefficient.
5. The method according to claim 1, characterized in that Based on each of the map positioning points and the meter reading difficulty coefficient, determining a meter reading route of the meter to be read includes: Based on each of the map positioning points, determining the running time of the object to be read from the power supply station to each of the electric meters to be read; Based on the meter reading difficulty coefficient, determining the meter reading time for the object to be read to read the meter to be read; The running time and the meter reading time are summed to obtain the total meter reading time corresponding to each meter to be read, wherein the total meter reading time is used to indicate the time consumed to complete reading the meter to be read; Based on the total meter reading time, the meter reading route of the meter to be read is determined.
6. The method according to claim 5, characterized in that Determining the meter reading route of the meter to be read based on the total meter reading time includes: A comparison step of comparing the total meter reading times corresponding to the plurality of meters to be read to obtain a comparison result, and determining the nodes of the meter reading route based on the comparison result; A first determination step, in response to the comparison result being less than a preset threshold, determining the to-be-read electricity meter corresponding to the total meter reading time as a node of the meter reading route, and executing the comparison step until the total meter reading time is greater than the preset total time threshold; The second determination step is to connect each of the nodes in a target order to obtain the meter reading route of the meter to be read, and to perform the comparison step and the first determination step until all the meters to be read are determined as the nodes, wherein the determination order is used to indicate the order in which the meters to be read are determined as the nodes in the first determination step.
7. A method for determining a meter reading route, characterized in that: include: A first determining unit, used for determining a plurality of electricity meters to be read; An acquisition unit, used for acquiring the geographical location of each of the electricity meters to be read; A second determining unit is used to determine a map positioning point and a meter reading difficulty coefficient of each of the meters to be read based on the geographical location of each of the meters to be read, wherein the map positioning point is used to indicate the location of the meter to be read on the map, and the meter reading difficulty coefficient is used to indicate the difficulty of reading the meter to be read; The third determining unit is used to determine the meter reading route of the meter to be read based on each of the map positioning points and the meter reading difficulty coefficient, and mark the meter reading difficulty coefficient in the meter reading route.
8. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed by a processor, the device where the storage medium is located is controlled to execute the method according to any one of claims 1 to 6.
9. A processor, characterized in that: The processor is used to run a program, wherein the program executes the method according to any one of claims 1 to 6 when running.
10. A computer program product, characterized in that The computer program product comprises computer instructions, which implement the method according to any one of claims 1 to 6 when executed by a processor.