By generating CNC marking files, the different wooden structure components in the framework structure are automatically processed, which solves the problem of inability to automatically process and improves construction accuracy and efficiency.
Patent Information
- Application Number
- CN202411120227.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-12-03
AI Technical Summary
The existing wood structure processing technology requires special design shapes based on a single wood structure, and it is impossible to automatically process different wood structures in the overall construction construction, and the operation is cumbersome and inconvenient to use.
By establishing a structural model of the framework structure, combining the marker database to automatically generate CNC mark files of any component in the framework structure, use the model processing module, storage module, selection module, mapping module and translation module to generate CNC mark files to achieve no Paper-based construction, automated processing of different wooden structure components.
Paperless construction is realized, construction errors caused by human marking are avoided, construction accuracy and construction efficiency are improved, and defects in the existing technology that cannot be automatically handled different wooden structures.
Smart Images

Figure CN119066854A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of structural processing, and in particular to a paperless construction system and a construction method for a frame structure. Background Art
[0002] The traditional “cane pole” instrument (called “gaochi” in Fujian) laid the foundation for the precise and skilled marking of structural carpentry. The “cane pole” instrument realizes the construction system and frame system through the symbolic language of full-size marking, which is essential for the precise coordination and component manufacturing during the wood structure construction process.
[0003] During the construction of wooden structures, the connection relationship between wooden structure components is usually summarized by mortise and tenon structures. Existing mortise and tenon structure processing devices usually use heavy workbenches and combine computer numerical control technology (CNC) to achieve wooden structure processing. The existing technology has the following problems: the existing wooden structure processing technology usually requires a special shape design based on a single wooden structure, cannot be programmed on site, and cannot automatically process different wooden structures (such as columns, beams, and purlins) in the overall construction. Summary of the invention
[0004] The present invention provides a paperless construction system and method for a frame structure, in order to solve the problems that the existing wood structure processing technology needs to be based on the special design shape of a single wood structure, cannot automatically process different wood structures in the overall construction, and is cumbersome to operate and inconvenient to use. The system realizes paperless construction by automatically generating CNC marking files of the frame structure through a machine.
[0005] According to one aspect of the present invention, a paperless construction system for a frame structure is provided, comprising: a model processing module, for generating a construction structure model according to custom parameters of the frame structure, and calculating interface data of different components based on the construction structure model; wherein the custom parameters include at least one of the following: structural dimension data, construction scene data and structural unit data; a storage module, for configuring and storing a marking symbol database; a selection module, for selecting components to be marked, and adding component labels to the components to be marked; a mapping module, respectively connected to the model processing module, the storage module and the component selection module, for matching corresponding marking content to the components to be marked based on the mapping relationship between the marking symbol database, the interface data and the component labels; and a translation module, for translating the marking content and the component labels into a numerical control marking file.
[0006] Optionally, the model processing module includes: a model generation unit, used to generate a construction structure model according to the custom parameters; a logic calculation unit, connected to the model generation unit, used to calculate the number of intersections at any point in the construction structure model, the centerline direction of intersecting components and the limit position of structural components, and calculate the interface data based on the number of intersections, the centerline direction and the limit position.
[0007] Optionally, the logic calculation unit is also used to check whether the geometry of any cross interface is within the set domain of the framework structure, and to check whether there is a symbol conflict in the tag content of any cross interface.
[0008] Optionally, the frame structure paperless construction system further includes: a marking device connected to the translation module, used to fix the component to be marked, receive the numerical control marking file, and process and mark the component to be marked according to the numerical control marking file.
[0009] Optionally, the marking device comprises: a fixing component for fixing the component to be marked; and a marking component for processing and marking the component to be marked.
[0010] Optionally, the fixing assembly includes: a bracket body, a turntable tool and an alignment tool; the turntable tool is arranged at one end of the bracket body, and the turntable tool is used to clamp and fix the component to be marked, and drive the component to be marked to rotate circumferentially; the alignment tool can be moved along the extension direction of the bracket body, and is used to fix the component to be marked so that the component to be marked is aligned with the center of the turntable tool.
[0011] Optionally, the paperless construction system for the frame structure also includes: a detection module and a data configuration module; the detection module and the data configuration module are detachably fixed to the marking device; wherein the detection module is at least used to detect the structural dimension data of the component to be marked; the data configuration module is used to configure the construction scene data and the structural unit data of the frame structure.
[0012] Optionally, the detection module includes at least a first detection unit and a second detection unit; the first detection unit can be detachably fixed to the marking device, and is used to collect the external dimension data of the component to be marked; the second detection unit can be detachably fixed to the bracket body of the marking device, and can move along the bracket body, and the second detection unit is used to detect the length dimension of the component to be marked.
[0013] Optionally, the mapping relationship of the mapping module includes: a first mapping relationship between the marking symbol and the structural component; a second mapping relationship between the axis or surface of any structural component and the marking symbol; the mapping module is configured to: filter the marking symbols belonging to the component to be marked according to the first mapping relationship and the second mapping relationship, and combine all the marking symbols together to form a symbol string.
[0014] According to another aspect of the present invention, a paperless construction method for a frame structure is provided, comprising: generating a construction structure model according to custom parameters of the frame structure, and calculating interface data of different components based on the construction structure model; wherein the custom parameters include at least one of the following: structural dimension data, construction scene data, and structural unit data; selecting components to be marked, and adding component labels to the components to be marked; matching corresponding marking content to the components to be marked based on a mapping relationship between the marking symbol database, the interface data, and the component labels; and translating the marking content and the component labels to generate a CNC marking file.
[0015] Optionally, after translating the marking symbol and the component label to generate a CNC marking file, the paperless construction method of the frame structure further includes: turning on a marking device, sending the CNC marking file to the marking device, and allowing the marking device to process and mark the component to be marked according to the CNC marking file.
[0016] The technical solution of the embodiment of the present invention is provided with a model processing module, a storage module, a selection module, a mapping module and a translation module. The model processing module generates a construction structure model according to user-defined parameters such as structural dimension data, construction scene data and structural unit data of the frame structure, and calculates interface data of different components based on the construction structure model; the component to be marked is selected based on the selection module, and a component label is added to the component to be marked; the mapping module matches the corresponding marking content to the component to be marked based on the mapping relationship between the marking symbol database, the interface data and the component label; the translation module translates the marking content and the component label into a numerical control marking file, which solves the problem that the existing wood structure processing technology is based on the special design shape of a single wood structure, cannot automatically process different wood structures in the overall construction, and is cumbersome to operate and inconvenient to use. By establishing a construction structure model of the frame structure, the numerical control marking file corresponding to any component in the frame structure is automatically generated in combination with the marking symbol database. The numerical control marking file uses the structural material as the matrix of the marking, can realize paperless construction, avoid construction errors caused by human marking, and improve construction accuracy and efficiency.
[0017] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0019] Figure 1 A schematic structural diagram of a paperless construction system for a frame structure provided in Embodiment 1 of the present invention;
[0020] Figure 2 A schematic structural diagram of another paperless construction system with a frame structure provided in the first embodiment of the present invention;
[0021] Figure 3 A three-dimensional diagram of a frame structure processing and marking device provided in Embodiment 1 of the present invention;
[0022] Figure 4 A schematic diagram of a frame structure provided in the first embodiment of the present invention;
[0023] Figure 5 for Figure 4 Exploded diagram of
[0024] Figure 6 A schematic diagram of another frame structure provided in the first embodiment of the present invention;
[0025] Figure 7 for Figure 6 Exploded diagram of
[0026] Figure 8 A schematic diagram of a marking symbol of a frame structure processing marking device provided in Embodiment 1 of the present invention;
[0027] Fig. 9 A schematic diagram of marking symbols of another frame structure processing marking device provided in the first embodiment of the present invention;
[0028] Fig.10 This is a flow chart of a paperless construction method for a frame structure provided in Example 2 of the present invention. DETAILED DESCRIPTION
[0029] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
[0030] It should be noted that the terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequence. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present invention described herein can be implemented in an order other than those illustrated or described herein. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device that includes a series of steps or units is not necessarily limited to those steps or units that are clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0031] Embodiment 1
[0032] Figure 1 A schematic diagram of a paperless construction system for a frame structure provided in Embodiment 1 of the present invention is provided. This embodiment can be applied to application scenarios of frame structure construction on special terrain. Typically, the frame structure includes but is not limited to: an interlocking frame, a balloon frame, and a tilt frame. The structural components of the present application can be any wooden structure, steel structure, or bamboo structure located at different positions of the frame structure.
[0033] See also Figure 1 As shown, the paperless construction system of the frame structure of the present application includes: a model processing module 101, a storage module 102, a selection module 103, a mapping module 104 and a translation module 105. The functions of the model processing module 101, the storage module 102, the selection module 103, the mapping module 104 and the translation module 105 can be implemented by a software program on a microcontroller.
[0034] Among them, the model processing module 101 is used to generate a construction structure model according to the custom parameters of the frame structure. In this embodiment, the construction structure model can be a single-line model. Optionally, the custom parameters include at least one of the following: structural dimension data, construction scene data and structural unit data. In this embodiment, the custom parameters can be input through external devices such as sensors, switches or interactive devices. Optionally, the structural dimension data includes but is not limited to: material dimensions of columns, beams and secondary component structures, such as shape, thickness, width and length; construction scene data includes but is not limited to at least one of the following: ground topography, eaves height or roof slope of the roof or middle layer; structural unit data includes but is not limited to at least one of the following: the number of structural components of the frame structure, the number of purlins or a combination of secondary elements.
[0035] The model processing module 101 of the present application is also configured to calculate the interface data of different components based on the constructed structural model. Optionally, the interface data includes but is not limited to at least one of the following: interface position, interface type, connection method and subsequent construction activities of the interface. Among them, the interface position characterizes the position of the cross interface of the component in the overall frame structure. The interface position includes but is not limited to: the position of the cross interface along the extension direction of the current component, and the spacing size relative to the end of the component or other cross interfaces. The interface type characterizes the connection method between the cross interface and other structural components and characterizes the subsequent construction method. The marking symbol corresponds to the interface type determined according to the number of intersections. Typically, the interface type includes but is not limited to: column-main beam interface, column-secondary beam interface, secondary beam-main beam interface, support member interface. In this embodiment, the interface connection method is determined by the interface position and interface type. Typically, the interface connection method includes but is not limited to half-mortise and tenon connection and cross-carved half-mortise connection. In this embodiment, the subsequent construction activities of the interface are determined by the interface position and interface type. Typically, the subsequent construction activities of the interface include but are not limited to: drilling tool processing or mortise and tenon processing.
[0036] The storage module 102 is used to configure and store a marking symbol database. In this embodiment, the marking symbol database is a collection of symbols that characterize the interface position, interface type, connection mode, and subsequent construction activities of the cross interface. In this embodiment, the symbols in the marking symbol database are scalable symbols, and the symbols can be updated. The position of the symbols in the marking symbol database is determined by the model processing module 101.
[0037] The selection module 103 is used to select the component to be marked and add a component label to the component to be marked. The component label is a number that represents the identity of the component. The component label corresponds to the component one by one.
[0038] The mapping module 104 is connected to the model processing module, the storage module and the component selection module respectively, and is used to match the corresponding marking content to the component to be marked based on the mapping relationship between the marking symbol database, the interface data and the component label. In this embodiment, the marking content of the marking component includes: a marking position and a marking symbol. Among them, the marking position is used to characterize the position of the intersection interface of the component to be marked in the overall frame structure. The marking position includes but is not limited to: the position of the intersection interface along the extension direction of the current component, and the spacing size relative to the end of the component or other intersection interfaces. The marking symbol is used to characterize the connection method between the intersection interface and other structural components and to characterize the subsequent construction method. The marking symbol corresponds to the intersection type determined according to the number of intersections. Typically, the height of the marking symbol corresponds to the spacing between the top limit position and the bottom limit position of the intersection interface between the structural components, and the center line is used to mark the center of the top limit position and the bottom limit position. An inclined line terminating at the center line or centered on the center line is used to distinguish the end of the marking symbol. The type of the end of the marking symbol indicates the subsequent construction activities of the marked location, which helps to align tools when processing components. For example, the cross interface of bolt connection or pin connection will have a first angle line, which is used to define the information of the drill diameter (drill diameter equals the center line length) and the center of the drill; the cross interface of the mortise and tenon connection will have a second angle line, which is used to define the information of the chisel (chain saw or other mortise and tenon processing tools) width; the cross interface of the welded connection will have a third angle line, which is used to define the size information of the welding construction location. The direction indicator symbol in the marking symbol points to the center line or the midpoint of the center line corresponding to the alignment direction of the structural component, usually indicating the direction of its span.
[0039] The translation module 105 is used to translate the marking content and the component label into a numerical control marking file. The numerical control marking file of the present application can be a G-code numerical control programming language.
[0040] Specifically, before the construction of the frame structure, the model processing module generates a construction structure model according to the custom parameters such as the structural dimension data, construction scene data and structural unit data of the frame structure, and calculates the interface data (such as interface position and interface type) of different components based on the construction structure model. Then, based on the selection module, the component to be marked is selected, and the component label is added to the component to be marked. The mapping module matches the corresponding marking content to the component to be marked based on the mapping relationship between the marking symbol database, the interface data and the component label; the marking content and the component label are translated into a numerical control marking file through the translation module, and the numerical control marking file uses the structural material as the matrix of the mark for processing and marking. By establishing a construction structure model of the frame structure, the numerical control marking file corresponding to any component in the frame structure is automatically generated in combination with the marking symbol database, so that paperless construction can be realized, which solves the problem that the existing wood structure processing technology is based on the special design shape of a single wood structure, and cannot automatically process different wood structures in the overall construction, and the operation is cumbersome and inconvenient to use, avoiding construction errors caused by human marking, and improving construction accuracy and efficiency.
[0041] Figure 2 This is a structural diagram of another frame structure paperless construction system provided by the first embodiment of the present invention. Figure 2 As shown, the model processing module 101 includes: a model generation unit 1011, which is used to generate a construction structure model according to custom parameters; a logic calculation unit 1012, which is connected to the model generation unit 1011, and is used to calculate the number of intersections at any point in the construction structure model, the center line direction of the intersecting components and the limit position of the structural components, and calculate the interface data according to the number of intersections, the center line direction and the limit position.
[0042] Optionally, the logic calculation unit 1012 is further used to check whether the geometry of any cross interface is within the range of the set domain of the framework structure, and to check whether there is a symbol conflict in the marking content of any cross interface. The set domain represents the threshold range of the positional relationship between different components in the framework structure. The symbol conflict indicates that the marking symbol does not match the actual interface type.
[0043] Specifically, after the model generation unit 1011 generates the construction structure model, the logic calculation unit 1012 confirms the situation around the intersection interface by testing the geometric figures, such as the number of intersections, the centerline direction of the intersecting components and the limit position of the structural components, and then determines the interface type (such as the column-main beam interface, the column-secondary beam interface, the secondary beam-main beam interface or the support member interface) and the interface position (such as the spacing size relative to the end of the component or other intersection interfaces) according to the number of intersections, the centerline direction and the limit position. After the construction structure model is generated, the logic calculation unit 1012 is also used to check whether the geometric figures of any intersection interface are within the range of the set domain of the frame structure, and to check whether there is a symbol conflict in the marking content of any intersection interface. If the geometric figures are not within the range of the set domain of the frame structure, or there is a symbol conflict in the marking content of any intersection interface, a model correction warning is issued. By setting logic gates, data processing and checking of the single-line model can improve the modeling accuracy.
[0044] Optionally, the mapping relationship of the mapping module 104 includes: a first mapping relationship between a marking symbol and a structural member; a second mapping relationship between an axis or a surface of any structural member and a marking symbol; the mapping module 104 is configured to: filter the marking symbols belonging to the component to be marked according to the first mapping relationship and the second mapping relationship, and combine all the marking symbols together to form a symbol string. Among them, the marking content includes but is not limited to: labels, marking symbols and center lines. The first mapping relationship and the second mapping relationship are established based on empirical data calibration. Specifically, the mapping module 104 is used to determine which main component each marking symbol belongs to, determine which axis or surface each marking symbol belongs to, and filter all symbols (labels, symbols and center lines) belonging to any surface or axis of any component in any component to be marked, and then combine all symbols of the same surface or axis to form a surface or axis symbol string, and finally, combine all symbol strings in the component to be marked to form a final symbol string. By calibrating the mapping relationship, the matching speed and accuracy of the marking symbol are improved.
[0045] Optionally, the paperless construction system for frame structures further includes: a marking device connected to the translation module 105, the marking device being used to fix the component to be marked, receive the numerical control marking file, and process and mark the component to be marked according to the numerical control marking file.
[0046] Optionally, the marking device of the present application includes: a marking component and a fixing component. Among them, the marking component is used to add processing marks to the component to be marked. Optionally, the marking component of the present application may be a laser marking component, that is, the marking component generates a high-energy laser beam through a laser generator. When the laser beam acts on the material surface of the component to be marked, the surface material changes color and displays the marking content. The fixing component is used to fix the component to be marked. In this embodiment, taking the component to be marked as a wooden structure as an example, the component to be marked includes but is not limited to: columns (such as columns, eaves columns, middle columns, mountain columns, gold columns, corner columns), beams (such as main beams, secondary beams, single-step beams, double-step beams, cantilever beams, and head beams) and secondary component structures, wherein the secondary component structure includes but is not limited to: purlins (such as central purlins, cantilever eaves purlins, ridge purlins, and gold purlins), beams (such as eaves beams, ridge beams, gold beams, and interlaced beams).
[0047] The frame structure processing and marking equipment of the present application also includes: a power supply module, which is used to supply power to the power load of the frame structure processing and marking equipment. In the present embodiment, the power supply module includes but is not limited to: a DC-DC voltage conversion module and / or an energy storage module. Among them, the DC-DC voltage conversion module can output a DC voltage of one or more voltage levels based on the rated working voltage of different power loads. Specifically, the power supply module can be integrated with the control module of the frame structure paperless construction system on the same circuit board, and the circuit board is provided with wiring lines, power supply output interfaces and input / output interfaces, and the wiring lines can at least realize the electrical connection between the power supply module and the power load and related interfaces on the circuit board. By setting up a power supply module, independent power supply of the marking equipment is realized, and the convenience of using the equipment is improved.
[0048] Figure 3 A three-dimensional diagram of a frame structure processing and marking device provided in Example 1 of the present invention.
[0049] See also Figure 3 As shown, the fixing assembly includes: a bracket body 210, a turntable tool 220 and an alignment tool 230; the turntable tool 220 is arranged at one end of the bracket body 210, and the turntable tool 220 is used to clamp and fix the component to be marked, and drive the component to be marked to rotate circumferentially; the alignment tool 230 can move along the extension direction of the bracket body 210, and is used to fix the component to be marked so that the component to be marked is aligned with the center of the turntable tool 220.
[0050] See also Figure 3 As shown, the turntable tool 220 of the present application includes: a turntable body 221, and a self-centering adjustable vise 222 and a first drive motor 223 fixed to the turntable body 221, and the first drive motor 223 is used to drive the self-centering adjustable vise 222 to generate radial movement.
[0051] Optionally, the paperless construction system for the frame structure also includes: a detection module and a data configuration module; the detection module and the data configuration module are respectively connected to the model generation unit 1011, and the detection module and the data configuration module are detachably fixed to the marking device; wherein the detection module is at least used to detect the structural dimension data of the component to be marked (including but not limited to the material dimensions of columns, beams and secondary component structures, such as shape, thickness, width and length), and transmit the structural dimension data to the model generation unit 1011; the data configuration module is used to configure the construction scene data of the frame structure (including but not limited to the ground topographic map, the eaves height or roof slope of the roof or middle layer) and the structural unit data (including but not limited to the number of structural components of the frame structure, the number of purlins or the combination of secondary elements), and transmit the construction scene data and the structural unit data to the model generation unit 1011, so that the model generation unit 1011 generates a construction structure model according to the above-mentioned custom parameters.
[0052] See also Figure 3 As shown, the detection module at least includes a first detection unit 301 and a second detection unit 302; the first detection unit 301 is arranged on the turntable tool 220, and is used to collect the external dimension data of the component to be marked, typically, the external dimension data includes material width or material thickness; the second detection unit 302 is arranged on the bracket body 210, and can move along the bracket body 210, and the second detection unit 302 is used to detect the length dimension of the component to be marked, such as the height of the roof and the beam, wherein the length dimension of the component to be marked represents the construction scale. In this embodiment, the first detection unit 301 can be a position sensor, and the second detection unit 302 can adopt a movable limit switch. See. Figure 3 As shown, the first detection unit 301 can be arranged below the adjustable bracket of the self-centering adjustable vise 222 of the turntable tool 220. The second detection unit 302 is fixed to the bracket body 210 by a slider, and the slider can drive the second detection unit 302 to translate along the extension direction of the bracket body 210. Specifically, when the frame structure processing and marking device of the present application is used for processing and marking, the first drive motor 223 is used to drive the self-centering adjustable vise 222 to produce radial movement, so that the self-centering adjustable vise 222 fixes the component to be marked. The alignment tool 230 is moved to align the component to be marked with the center of the turntable tool 220, and the slider connected to the second detection unit 302 is moved to align the second detection unit 302 with the top of the component to be marked. The first detection unit 301 calculates the external dimension data (for example, material thickness) of the component to be marked by reading the position of the adjustable bracket of the self-centering adjustable vise 222; the length dimension of the component to be marked, such as the height of the roof and the beam, is collected by the second detection unit 302 to determine the construction scale.
[0053] See also Figure 3As shown, the data configuration module of the present application includes an interactive unit 401; the interactive unit 401 is detachably fixed to the fixed component, and is used to respond to the interactive instruction to configure the construction scene data and the structural unit data. Typically, the interactive unit 401 is a touch screen or an intelligent mobile terminal, such as a smart phone or an intelligent wearable device. Specifically, the interactive unit 401 can at least display the building scene operation interface and the structural unit operation interface. Before starting the mark, the construction personnel can input the ground topographic map, the eaves height of the roof or the middle layer, or the roof slope and other construction scene data through the building scene operation interface, and input the number of structural components, the number of purlins, or the combination of secondary elements and other structural unit data through the structural unit operation interface, and send the above-mentioned construction scene data and structural unit data to the control module 500, so that the control module 500 can generate a construction structure model adapted to irregular terrain, and match the corresponding marking content (such as marking position and marking symbol) to different components in the construction structure model. By setting the interactive unit 401, it is convenient to configure or modify the structural parameters on site, and the operation is convenient.
[0054] See also Figure 3 As shown, the fixing assembly of the present application also includes: a base 240 and a leveling leg 250; the bracket body 210 is detachably mounted on the top surface of the base 240 along a first direction Y, and the first direction Y is perpendicular to the plane where the base 240 is located; the turntable body 221 is detachably mounted on the top surface of the base 240 along a second direction X, and the second direction X is parallel to the plane where the base 240 is located; the leveling leg 250 is detachably mounted on the bottom surface of the base 240.
[0055] Optionally, the fixing assembly of the present application may adopt a vertical structure or a horizontal structure. Specifically, in the vertical structure, the bracket body 210 is placed in the vertical direction (i.e., the first direction Y), the base 240 is placed in the horizontal direction (i.e., the second direction X), and the clamping surface of the turntable tool 220 is parallel to the base 240 in the horizontal direction (i.e., the second direction X). After the turntable tool 220 clamps and fixes the component to be marked, the component to be marked is placed in a vertical position. In the horizontal structure, the bracket body 210 is placed horizontally, the base 240 is placed vertically, and the clamping surface of the turntable tool 220 is installed on the base 240 in the vertical direction. After the turntable tool 220 clamps and fixes the component to be marked, the component to be marked is placed in a horizontal position. It should be noted that in the vertical structure and the horizontal structure, the installation angles of the components of the frame structure processing and marking equipment are adaptively adjusted to facilitate the marking operation.
[0056] See also Figure 3As shown, the fixing component also includes: a slide rail 261, a second drive motor 262, a slide 263, a marking component fixing portion 264 and a shield 265; the slide rail 261 is arranged parallel to the bracket body 210, and the length of the slide rail 261 is less than or equal to the length of the bracket body 210; the second drive motor 262 is used to drive the slide 263 to move along the extension direction of the slide rail 261; the marking component fixing portion 264 is fixed to the slide 263, and is used to fix the marking component so that the marking component faces the to-be-marked surface of the component to be marked, and the marking component fixing portion 264 can move along the extension direction of the slide rail 261 with the slide 263; the shield 265 is fixed to the slide 263, and is used to provide safety protection for the marking component.
[0057] Specifically, after the component to be marked is fixed to the fixed assembly, the material dimensional data (such as material thickness or width) is collected based on the detection module and the construction scale (such as the height of the roof and beams) is configured, and the construction scene data (such as ground topography, eaves height or roof slope of the roof or middle layer) and structural unit data (the number of structural components, the number of purlins or a combination of secondary elements) are configured based on the data configuration module. After completing the configuration of structural construction related data such as structural dimension data, construction scene data and structural unit data, the model processing module 101 builds a corresponding construction structure model according to the structural dimension data, construction scene data and structural unit data. For example, the construction structure model can be a single-line model; then, combined with the overall frame structure of the construction structure model, the interface data of the cross interface in the component to be marked is estimated, such as the interface position (such as the spacing size relative to the end of the component or other cross interfaces), interface type (such as column-main beam interface, column-secondary beam interface, secondary beam-main beam interface, support member interface), connection method (such as half-mortise and tenon connection, cross-engraved half-mortise connection) and subsequent construction activities (such as drilling tool processing or mortise and tenon processing). Then, the mapping module 104 combines the mapping relationship between the marking symbol database, interface data and component labels to match the corresponding marking content to the component to be marked. For example, the four quadrants of the column (quadrant A, quadrant B, quadrant C and quadrant D) are used as the index of its connected structural components to parse the marking content of different quadrants, and the marking content includes the marking position and marking symbol used to characterize the subsequent construction operation. After obtaining the marking content, the control module 500 outputs a fixed component driving signal to the fixed component to drive the fixed component to translate and rotate the component to be marked, so that the specific quadrant faces the marking component, and controls the marking component fixing part 264 to drive the marking component to move to the marking position, and add the corresponding marking symbol on the cylindrical surface or polyhedral surface of the component to be marked. By designing a light, slender, and modular structure, the marking equipment can be easily transported to the construction site, the material construction scale is configured on site, and the component material is directly used to mark the component on site, realizing paperless design marking, which is convenient for on-site processing, eliminates the distance between the processing site and the construction site, and reduces the corresponding transportation cost and time cost.
[0058] For example, Figure 4 A schematic diagram of a frame structure provided in the first embodiment of the present invention; Figure 5 for Figure 4 Exploded diagram of Figure 6 A schematic diagram of another frame structure provided in the first embodiment of the present invention; Figure 7 for Figure 6 Exploded diagram.
[0059] See also Figures 4 to 7As shown, taking the application scenario of the frame structure processing and marking equipment as a through-beam wooden frame with a bracket (dougong) as an example, the wooden structure in the through-beam wooden frame with a bracket (dougong) includes a column 1, a main beam 2, a secondary beam 3 and an additional support (a first member 4 connecting the column 1 and a second member 5 connecting the secondary beam 3). Among them, the column 1 is a supporting element that bears vertical loads and is vertically fixed on the ground. The main beam 2 is perpendicular to the column 1 and is connected to the column 1 by a half-mortise and tenon connection. The secondary beam 3 is perpendicular to the column 1 and the main beam 2, respectively, and is connected to the main beam 2 by a cross-engraved half-mortise connection. The additional support includes a first member 4 connecting the column 1 and a second member 5 connecting the secondary beam 3. The first member 4 is perpendicular to the column 1 and the main beam 2, respectively, and is parallel to the secondary beam 3. It is connected to the column 1 by a half-mortise and tenon connection, and is connected to the second member 5 connecting the secondary beam 3 by a cross-engraved half-mortise connection. The second component 5 is perpendicular to the column 1 and the secondary beam 3 respectively, parallel to the main beam 2, connected to the secondary beam 3 by a cross-cut half-mortise connection, connected to the first component 4 connected to the column 1 by a cross-cut half-mortise connection, and connected to the rest of its structure by a cross-cut half-mortise connection.
[0060] Figure 8 A schematic diagram of a marking symbol of a frame structure processing marking device provided in Embodiment 1 of the present invention; Fig. 9 A schematic diagram of marking symbols of another frame structure processing marking device provided in Embodiment 1 of the present invention. Figure 8 and Fig. 9As shown in the figure, the marking symbols for the connecting part of the main beam 2 and the column 1 are defined as "king" or "worker". The height of the marking symbol corresponds to the top limit position and the bottom limit position at the intersection of the column 1 and the main beam 2. Insert the main beam 2 on the axis of the column 1 facing the center of the structure (for example, in quadrant A). If the main beam 2 does not pass through the column 1 but steps at different heights corresponding to the irregular roof or terrain, on the other side of the column 1, that is, the side背离 the center of the structure (quadrant C), the marking symbol is "worker", indicating that half of the beam protrudes through. On the side facing the center of the structure where the main beam 2 is inserted, the marking symbol is "king", with the ends of the symmetric angular lines intersecting at the center, which helps to center the chisel or chainsaw required for carving mortises and aligning the crossbeams. The secondary beam 3 is connected to the main beam 2 by a half-lap (mortise and tenon) connection. The marking symbol for the connecting part (inserted arch) of the secondary beam 3 and the column 1 is defined as "Z". The height of the marking symbol corresponds to the top limit position and the bottom limit position at the intersection of the secondary beam 3 and the column. The (inserted arch) can be inserted on the column axis perpendicular to the main beam 2 (for example, quadrant B or quadrant D). In the case where the main beam 2 does not pass through the column 1, the opposite side of the column 1 is marked with "Z", indicating that half of the component protrudes through the column 1. The "Z" on the inserted (inserted arch) side has an inclined line indicating the upward direction. These angled lines are located at the center of the projected distance between the top of the main beam 2 and the bottom of the inserted (inserted arch), which keeps them visible after the column and beam are formed and connected to help assemble and align the structural components. If there are symmetric brackets of the same height on both sides of the column 1, the direction indication symbol will be a rhombus. The "Z" on the inserted (inserted arch) side has symmetric angular lines intersecting at the center of the end, which helps to center the chisel or chainsaw required for carving mortises and aligning the beam. Finally, a horizontal mark intersecting with "Z" will be added to the marking symbol representing the lap depth.
[0061] The marking device provided by the embodiment of the present invention sets a marking component and a fixing component. After obtaining the numerical control marking file, it controls the marking component to process and mark the component to be marked, solving the problems that the existing wood structure processing technology needs to be specifically designed for a single wood structure, cannot perform automated processing on different wood structures in the overall construction, and is cumbersome to operate and inconvenient to use. By machine identifying the interface position and connection type of the component to be marked, it automatically adds processing marks, avoiding marking errors caused by manual marking and improving marking accuracy and efficiency.
[0062] Embodiment Two
[0063] The second embodiment of the present invention provides a paperless construction method for a frame structure, which is implemented based on the paperless construction system for a frame structure provided in the above embodiment, and has the corresponding beneficial effects of the paperless construction system for a frame structure. The same parts will not be described in detail.
[0064] Fig.10This is a flow chart of a paperless construction method for a frame structure provided in Example 2 of the present invention.
[0065] like Fig.10 As shown, the paperless construction method of the frame structure of the present application specifically includes the following steps:
[0066] S101: Generate a construction structure model according to the custom parameters of the frame structure, and calculate interface data of different components based on the construction structure model.
[0067] The custom parameters include at least one of the following: structure dimension data, construction scene data and structure unit data.
[0068] S102: Select a component to be marked, and add a component label to the component to be marked.
[0069] S103: Matching corresponding marking contents to the components to be marked based on the mapping relationship between the marking symbol database, the interface data and the component labels.
[0070] S104: Translate the marking content and component labels to generate a numerical control marking file.
[0071] See also Fig.10 As shown, after the above step S104, the paperless construction method of the frame structure of the present application further includes:
[0072] S105: Turn on the marking device, send the numerical control marking file to the marking device, and enable the marking device to process and mark the component to be marked according to the numerical control marking file.
[0073] Optionally, a construction structure model is generated according to custom parameters of the frame structure, and interface data of different components are calculated based on the construction structure model, including: generating a construction structure model according to custom parameters; calculating the number of intersections at any point in the construction structure model, the centerline direction of intersecting components and the limit position of the structural components, and calculating the interface data based on the number of intersections, the centerline direction and the limit position.
[0074] Optionally, generating a construction structure model according to the custom parameters of the framework structure, and calculating the interface data of different components based on the construction structure model also includes: checking whether the geometry of any cross-interface is within the set domain of the framework structure, and checking whether there is a symbol conflict in the marking content of any cross-interface.
[0075] Optionally, the mapping relationship includes: a first mapping relationship between the marking symbol and the structural component; and a second mapping relationship between the axis or surface of any structural component and the marking symbol. Based on the mapping relationship between the marking symbol database, the interface data and the component label, matching the corresponding marking content to the component to be marked includes: screening the marking symbols belonging to the component to be marked according to the first mapping relationship and the second mapping relationship, and combining all the marking symbols together to form a symbol string.
[0076] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0077] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A paperless construction system for frame structures, It is characterized in that include: A model processing module, used to generate a construction structure model according to the custom parameters of the frame structure, and calculate the interface data of different components based on the construction structure model; wherein the custom parameters include at least one of the following: structure size data, construction scene data and structure unit data; A storage module, used for configuring and storing a marking symbol database; A selection module, used for selecting a component to be marked and adding a component label to the component to be marked; A mapping module, connected to the model processing module, the storage module and the component selection module respectively, for matching corresponding marking content to the component to be marked based on the mapping relationship between the marking symbol database, the interface data and the component label; The translation module is used to translate the marking content and the component label into a numerical control marking file.
2. According to claim 1, the paperless construction system for frame structure, It is characterized in that The model processing module includes: A model generation unit, used to generate a construction structure model according to the custom parameters; A logic calculation unit is connected to the model generation unit, and is used to calculate the number of intersections at any point in the constructed structural model, the centerline direction of the intersecting components and the limit position of the structural components, and calculate the interface data based on the number of intersections, the centerline direction and the limit position.
3. According to claim 2, the paperless construction system for frame structure, It is characterized in that The logic calculation unit is also used to check whether the geometry of any cross interface is within the set domain of the framework structure, and to check whether there is a symbol conflict in the tag content of any cross interface.
4. According to claim 1, the paperless construction system for frame structure, It is characterized in that Also includes: The marking device is connected to the translation module, and is used to fix the component to be marked, receive the numerical control marking file, and perform processing marking on the component to be marked according to the numerical control marking file.
5. According to claim 4, the paperless construction system for frame structure, It is characterized in that The marking device comprises: A fixing assembly, used for fixing the component to be marked; The marking component is used to perform processing marking on the component to be marked.
6. The paperless construction system for frame structure according to claim 5, It is characterized in that The fixing assembly comprises: a bracket body, a turntable tool and an alignment tool; The turntable tool is arranged at one end of the bracket body, and is used to clamp and fix the component to be marked, and drive the component to be marked to rotate circumferentially; The alignment tool can be moved along the extension direction of the bracket body, and is used to fix the component to be marked so that the component to be marked is aligned with the center of the turntable tool.
7. The paperless construction system for frame structure according to claim 4, It is characterized in that Also includes: Detection module and data configuration module; The detection module and the data configuration module are detachably fixed to the marking device; Wherein, the detection module is at least used to detect the structural dimension data of the component to be marked; The data configuration module is used to configure the construction scene data and the structural unit data of the framework structure.
8. The paperless construction system for frame structure according to claim 7, It is characterized in that The detection module at least includes a first detection unit and a second detection unit; The first detection unit is detachably fixed to the marking device and is used to collect the external dimension data of the component to be marked; The second detection unit is detachably fixed to the support body of the marking device and can move along the support body. The second detection unit is used to detect the length dimension of the component to be marked.
9. The paperless construction system for frame structures according to any one of claims 1 to 8, It is characterized in that The mapping relationship of the mapping module includes: a first mapping relationship between marking symbols and structural components; a second mapping relationship between an axis or a surface of any structural component and the marking symbol; The mapping module is configured to: screen the marking symbols belonging to the component to be marked according to the first mapping relationship and the second mapping relationship, and combine all the marking symbols together to form a symbol string.
10. A paperless construction method for a frame structure, It is characterized in that include: Generate a construction structure model according to the custom parameters of the frame structure, and calculate interface data of different components based on the construction structure model; wherein the custom parameters include at least one of the following: structure size data, construction scene data and structure unit data; Select a component to be marked, and add a component label to the component to be marked; Based on the mapping relationship between the marking symbol database, the interface data and the component label, matching the corresponding marking content to the component to be marked; The marking content and the component label are translated to generate a numerical control marking file.