Electric heating orderly power utilization system and method

By designing an orderly power consumption system for electric heating, using components such as the system main station, 4G gateway, broadband carrier communication main gateway and intelligent Internet of Things circuit breaker, intelligent and automatic flexible adjustment of heavy load and low voltage in the station area is achieved, and the solution is solved The electrical power consumption problem of electric heating that cannot be controlled by the prior art has been improved, and the applicability and efficiency of the system have been improved.

CN119071341APending Publication Date: 2024-12-03CHINA POWER HUARUI TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411256202.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

The existing electric heating monitoring terminal equipment (electricity meter and TTU) can only conduct electricity monitoring, cannot be controlled and adjusted, and cannot solve the heavy overload and low voltage problems in the station area, and its applicability is limited.

Method used

An ordered electricity system for electric heating is designed, including the system main station, 4G gateway, broadband carrier communication main gateway, station area transformer, intelligent IoT circuit breaker and flexible control device. By monitoring user load in real time, an orderly use is formulated. Electrical strategy, and flexible control is carried out through broadband carrier communication and RS485 communication, temporarily stop power consumption or reset power consumption, to solve the problem of heavy overload or low voltage of transformers.

Benefits of technology

It realizes intelligent and automatic flexible adjustment of heavy load or voltage overlimiting problems in the station area, monitors and adjusts user load in real time, solves heavy overload and low voltage problems in the station area, and improves the applicability of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119071341A_ABST
    Figure CN119071341A_ABST
Patent Text Reader

Abstract

The invention discloses an electric heating orderly power utilization system and method in the technical field of electric heating, and the system comprises a system master station, the system master station is electrically connected with a 4G gateway, the 4G gateway is electrically connected with a broadband carrier communication master gateway, the broadband carrier communication master gateway is electrically connected with a transformer area transformer, and the transformer area transformer is electrically connected with a power supply. The system comprises an area transformer, the area transformer is electrically connected with an area JP cabinet, the area JP cabinet is electrically connected with a plurality of groups of carrier communication units and a plurality of groups of intelligent instrumented circuit breakers, and the intelligent instrumented circuit breakers are electrically connected with a flexible control device and a boiler control module. The two devices have extremely high metering accuracy, can monitor and meter the power consumption condition of each heating user, but can only perform monitoring and cannot perform control adjustment, and cannot solve the heavy overload and low voltage of the current transformer area, so that the applicability is limited.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of electric heating, and in particular to an orderly electricity consumption system and method for electric heating. Background Art

[0002] In winter, the electric heating load in the northern bungalow distribution network area surges, resulting in the reported capacity and operating capacity far exceeding the allowable values ​​of the equipment. Some substations, lines and substations are frequently severely overloaded.

[0003] The main monitoring terminals of the existing technical solutions are electricity meters and concentrators or TTUs. These two devices have extremely high measurement accuracy and can monitor and measure the electricity consumption of each heating user. However, they can only monitor but not control and adjust, and cannot solve the heavy overload and low voltage in the current area, so their applicability is limited. Summary of the invention

[0004] The purpose of this section is to summarize some aspects of the embodiments of the present invention and briefly introduce some preferred embodiments. Some simplifications or omissions may be made in this section and the specification abstract and the invention title of the present invention to avoid blurring the purpose of this section, the specification abstract and the invention title, and such simplifications or omissions cannot be used to limit the scope of the present invention.

[0005] Therefore, the purpose of the present invention is to provide an orderly electricity consumption system and method for electric heating, which can solve the problem that the main monitoring terminals of the existing technical solutions are electricity meters and concentrators or TTUs. These two devices have extremely high metering accuracy and can complete the monitoring and metering of electricity consumption of each heating user, but can only monitor and cannot control and adjust, and cannot solve the heavy overload and low voltage in the current area, and have limited applicability.

[0006] In order to solve the above technical problems, the present invention provides an electric heating orderly electricity consumption system and method, adopting the following technical scheme: including a system main station, the system main station is electrically connected to a 4G gateway, the 4G gateway is electrically connected to a broadband carrier communication main gateway, the broadband carrier communication main gateway is electrically connected to a substation transformer, the substation transformer is electrically connected to a substation JP cabinet, the substation JP cabinet is electrically connected to multiple groups of carrier communication units and multiple groups of intelligent Internet of Things circuit breakers, the intelligent Internet of Things circuit breaker is electrically connected to a flexible control device and a boiler control module, and the boiler control module is electrically connected to an electric boiler.

[0007] Optionally, the system main station is electrically connected to a 4G gateway via 4G.

[0008] By adopting the above technical solution, the system main station transmits the signal to the 4G gateway.

[0009] Optionally, the 4G gateway is electrically connected to the broadband carrier communication main gateway via RS485 communication.

[0010] By adopting the above technical solution, the 4G gateway transmits the signal to the broadband carrier communication main gateway.

[0011] Optionally, the carrier communication unit is electrically connected to the JP cabinet in the substation area via wideband carrier communication.

[0012] By adopting the above technical solution, the JP cabinet in the substation transmits the signal to the carrier communication unit.

[0013] Optionally, the carrier communication unit is electrically connected to the intelligent IoT circuit breaker via RS485 communication.

[0014] By adopting the above technical solution, the carrier communication unit transmits the signal to the intelligent IoT circuit breaker.

[0015] Optionally, the flexible control device is electrically connected to the intelligent IoT circuit breaker via wideband carrier communication.

[0016] By adopting the above technical solution, the intelligent IoT circuit breaker transmits the signal to the flexible control device.

[0017] Optionally, the flexible control device is electrically connected to the boiler control module via RS485 communication.

[0018] By adopting the above technical solution, the flexible control device transmits the signal to the boiler control module.

[0019] Optionally, a method for orderly electricity use of electric heating is also included, and the specific steps are as follows:

[0020] S1: The power consumption and importance of each branch node of the master station communication platform and platform system, as well as the current power consumption status and over-limit situation, formulate an orderly power consumption strategy, and send the orderly power consumption strategy to the 4G gateway;

[0021] S2: The 4G gateway converts the orderly power consumption strategy signal into a carrier signal through the transparent transmission of the broadband carrier gateway and sends it to the flexible control devices and intelligent IoT circuit breakers at each branch node for strategy control;

[0022] S3: The flexible control device performs flexible power control on the branch nodes that need to be controlled according to the flexible control strategy;

[0023] S4: The intelligent IoT circuit breaker performs necessary strategy control to temporarily stop power consumption at nodes and reset or restart power consumption according to the strategy, thereby ultimately solving the problem of transformer overload or low voltage in the current substation in an economical way.

[0024] By adopting the above technical solution, the problem of transformer heavy overload or low voltage in the current substation area can be solved.

[0025] To summarize, the present invention includes at least one of the following beneficial effects: by real-time monitoring of user load conditions and adopting a load flexible adjustment device, intelligent and automatic flexible adjustment of low-voltage load is achieved for heavy load or voltage over-limit problems in the substation, thereby solving the problem of heavy overload and low voltage in the substation. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0027] Figure 1 It is a structural schematic diagram of the present invention.

[0028] Explanation of the accompanying drawings: 1. System main station; 2. 4G gateway; 3. Broadband carrier communication main gateway; 4. Substation transformer; 5. Substation JP cabinet; 6. Carrier communication unit; 7. Intelligent IoT circuit breaker; 8. Flexible control device; 9. Boiler control module; 10. Electric boiler. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1 The present invention is described in further detail.

[0030] Embodiment 1, refer to Figure 1In this embodiment, in order to solve the existing technical solutions, the main monitoring terminals are electric energy meters and concentrators or TTUs. These two devices have extremely high metering accuracy and can complete the monitoring and metering of the electricity consumption of each heating user, but can only monitor but not control and adjust, and cannot solve the heavy overload and low voltage of the current area, and have limited applicability. The present invention discloses an electric heating orderly power consumption system and method, including a system master station 1, the system master station 1 is electrically connected to a 4G gateway 2, and the 4G gateway 2 is electrically connected to a broadband carrier communication main network The broadband carrier communication main gateway 3 is electrically connected to the substation transformer 4, the substation transformer 4 is electrically connected to the substation JP cabinet 5, the substation JP cabinet 5 is electrically connected to multiple groups of carrier communication units 6 and multiple groups of intelligent IoT circuit breakers 7, the intelligent IoT circuit breaker 7 is electrically connected to the flexible control device 8 and the boiler control module 9, the boiler control module 9 is electrically connected to the electric boiler 10, the system master station 1 is electrically connected to the 4G gateway 2 through 4G, the 4G gateway 2 is electrically connected to the broadband carrier communication main gateway 3 through RS485 communication, the carrier communication unit 6 is electrically connected to the broadband The carrier communication is electrically connected to the JP cabinet 5 in the substation area through the wideband carrier communication, the carrier communication unit 6 is electrically connected to the intelligent IoT circuit breaker 7 through the RS485 communication, the flexible control device 8 is electrically connected to the intelligent IoT circuit breaker 7 through the wideband carrier communication, and the flexible control device 8 is electrically connected to the boiler control module 9 through the RS485 communication. It also includes an orderly power consumption method for electric heating, and the specific steps are as follows: S1: The power consumption and importance of each branch node of the master station communication platform and the platform system, as well as the current power consumption status and over-limit situation, formulate an orderly power consumption strategy, and The strategy is sent to the 4G gateway; S2: The 4G gateway converts the orderly power consumption strategy signal into a carrier signal through the transparent transmission of the broadband carrier gateway and sends it to the flexible control device and intelligent IoT circuit breaker of each branch node for strategy control; S3: The flexible control device performs flexible power consumption control on the branch nodes that need to be controlled according to the flexible control strategy; S4: The intelligent IoT circuit breaker performs necessary strategy control of temporarily stopping power consumption of nodes and resetting or restarting power consumption according to the strategy, thereby ultimately solving the problem of heavy overload or low voltage of transformers in the current substation in an economical way.

[0031] Based on the above characteristics, the working principle of this embodiment is: the flexible control device 8 has built-in broadband carrier communication and RS485 communication, the RS485 communication line is connected to the boiler control module 9, and receives the flexible control strategy sent by the main station platform through the broadband carrier communication signal to realize flexible and orderly power control and regulation of the heating electric boiler 10 at each branch node. The intelligent IoT circuit breaker 7 has the functions of line equipment over-store protection, over-voltage and under-voltage protection, and leakage protection. At the same time, it has fault identification, judgment, current, voltage, power collection, over-limit warning, alarm and protection functions. The power consumption, power over-limit and abnormal conditions of each branch node can be collected, recorded and transmitted to the broadband carrier communication main gateway 3 through RS485 communication. The broadband carrier communication unit at each branch node uploads the branch node abnormal conditions and related status information collected and uploaded by the intelligent IoT circuit breaker 7 to the broadband carrier communication main gateway 3 through the broadband carrier communication method. The broadband carrier communication method can save the communication line laying cost from the side of the substation transformer 4 to each branch node or the real-time communication traffic cost of wireless 4G communication. The broadband carrier communication main gateway 3 collects and identifies the information of each branch node intelligent IoT circuit breaker 7 received through the downlink broadband carrier communication signal and transmits the signal uplink to the 4G gateway 2 through the device RS485 port. The 4G gateway 2 uploads the power consumption information of the branch node electric boiler 10 and the status information of the intelligent IoT circuit breaker 7 uploaded through the RS485 communication to the system master station 1 through the uplink 4G communication method. The system master station 1 and the platform system formulate an orderly power consumption strategy for the power consumption and importance of each branch node, the current power consumption status and the over-limit situation. The orderly power consumption strategy is sent to the 4G gateway 2. The 4G gateway 2 converts the orderly power consumption strategy signal into a carrier signal through the transparent transmission mode of the broadband carrier gateway and sends it to the flexible control device 8 and the intelligent IoT circuit breaker 7 of each branch node for strategy control. The flexible control device 7 performs flexible power consumption control on the branch nodes that need to be controlled according to the flexible control strategy. The intelligent IoT circuit breaker 7 performs necessary strategy control of temporarily stopping power consumption of nodes and resetting or restarting power consumption according to the strategy, thereby ultimately solving the problem of heavy transformer overload or low voltage in the current substation in an economical way.

[0032] The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. An orderly electric heating power consumption system, comprising a system master station (1), characterized in that: The system master station (1) is electrically connected to a 4G gateway (2), the 4G gateway (2) is electrically connected to a broadband carrier communication main gateway (3), the broadband carrier communication main gateway (3) is electrically connected to a substation transformer (4), the substation transformer (4) is electrically connected to a substation JP cabinet (5), the substation JP cabinet (5) is electrically connected to multiple groups of carrier communication units (6) and multiple groups of intelligent IoT circuit breakers (7), the intelligent IoT circuit breaker (7) is electrically connected to a flexible control device (8) and a boiler control module (9), and the boiler control module (9) is electrically connected to an electric boiler (10).

2. The electric heating orderly power consumption system according to claim 1, characterized in that: The system main station (1) is electrically connected to the 4G gateway (2) via 4G.

3. The electric heating orderly power consumption system according to claim 1, characterized in that: The 4G gateway (2) is electrically connected to the broadband carrier communication main gateway (3) via RS485 communication.

4. The electric heating orderly power consumption system according to claim 1, characterized in that: The carrier communication unit (6) is electrically connected to the station area JP cabinet (5) through wideband carrier communication.

5. The electric heating orderly power consumption system according to claim 1, characterized in that: The carrier communication unit (6) is electrically connected to the intelligent IoT circuit breaker (7) via RS485 communication.

6. The electric heating orderly power consumption system according to claim 1, characterized in that: The flexible control device (8) is electrically connected to the intelligent IoT circuit breaker (7) via wideband carrier communication.

7. The electric heating orderly power consumption system according to claim 1, characterized in that: The flexible control device (8) is electrically connected to the boiler control module (9) via RS485 communication.

8. An orderly electric heating power system according to any one of claims 1 to 7, characterized in that: The invention also includes a method for orderly using electricity for electric heating, and the specific steps are as follows: S1: The power consumption and importance of each branch node of the master station communication platform and platform system, as well as the current power consumption status and over-limit situation, formulate an orderly power consumption strategy, and send the orderly power consumption strategy to the 4G gateway; S2: The 4G gateway converts the orderly power consumption strategy signal into a carrier signal through the transparent transmission of the broadband carrier gateway and sends it to the flexible control devices and intelligent IoT circuit breakers at each branch node for strategy control; S3: The flexible control device performs flexible power control on the branch nodes that need to be controlled according to the flexible control strategy; S4: The intelligent IoT circuit breaker performs necessary strategy control to temporarily stop power consumption at nodes and reset or restart power consumption according to the strategy, thereby ultimately solving the problem of transformer overload or low voltage in the current substation in an economical way.