Crushed ore body first mining layer mechanical mining method

By dividing multiple panels within the first mining layer of crushed ore body mining and pre-supporting, the problems of inefficient mining efficiency and safety risks of crushed ore body in the existing technology are solved, and long-distance, continuous and efficient mining of mechanical mining is achieved, ensuring an efficient and safe mining process.

CN119712112AActive Publication Date: 2025-03-28BEIJING MINING & METALLURGICAL TECH GRP CO LTD
8 Cites 0 Cited by

Patent Information

Application Number
CN202510228857.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-02-28
Publication Date
2025-03-28
Estimated Expiration
2045-02-28

AI Technical Summary

Technical Problem

In the prior art, crushed ore body mining has inefficient efficiency and safety risks, and mechanical mining cannot exert its advantages in long-distance, continuity and efficient mining.

Method used

By dividing multiple panels within the first mining layer, setting up intraves connection channels, intraves mining quasi-progress routes and first mining routes, and providing advance pre-support for these roads, a large-scale advance pre-support system is achieved to ensure the safety and efficiency of mechanical mining.

Benefits of technology

Mechanical mining under the advanced pre-support system can effectively exert the advantages of long-distance, continuity and efficient mining, greatly ensuring the efficiency and safety of mechanical mining, and ensuring the smooth and efficient mining of crushed ore bodies.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention provides a mechanical mining method for a first mining layer of a broken ore body, and relates to the technical field of mining, the mechanical mining method for the first mining layer of the broken ore body comprises the steps that a plurality of panels are divided in the first mining layer, and each panel comprises an in-vein connection way, an in-vein accurate mining drift and a plurality of first stoping drift; an included angle is formed between each of the in-pulse accurate mining drift and the first stoping drift and the in-pulse connection way, and the in-pulse accurate mining drift and the first stoping drift are arranged in parallel; and performing advanced pre-support on the intra-pulse connection way and the intra-pulse accurate mining drift, performing advanced pre-support on each first stoping drift through the intra-pulse connection way and / or the intra-pulse accurate mining drift, performing mechanical stoping operation under the advanced pre-support, and performing filling after stoping is completed. According to the mechanical mining method for the first mining layer of the broken ore body, the problem of mechanical continuous mining of the first mining layer of the broken ore body can be solved, and the long-distance, continuous and efficient mining advantages of mechanical continuous mining are exerted.