Method and system for quickly partitioning power network after power failure based on coherent Isin machine
By applying coherent Isin machines in the power system to quickly partition the power network after power outage, the problem of long solution time for partitioning methods in the existing technology, manual selection of results and model cannot be directly solved, and fast and accurate network partitioning of the power system is achieved.
Patent Information
- Application Number
- CN202411950764.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-12-27
- Publication Date
- 2025-04-04
- Estimated Expiration
- 2044-12-27
AI Technical Summary
After the existing power system has a major power outage, it is difficult to perform network partitioning methods quickly and accurately, resulting in a prolonged power outage time and the model cannot be directly solved. The solution results require manual selection and computing power limitation of computing equipment.
Using the fast partitioning method after power network power outage based on coherent Isin machine, a parallel recovery sub-region division model is established by constructing the Laplace matrix of the power network, and the model is converted into a binary quadratic unconstrained optimization model, and the model is solved using coherent Isin machine to obtain network partitioning results.
It realizes fast network partitioning after power outage, avoids the "dimensional disaster" that classic computers may suffer during the solution process, and effectively expands the application scale of the model through the qubit expansion method, ensuring the accuracy and real-timeness of partition results.