Electric power peak and frequency modulation system for IGCC power station coupling compressed air energy storage
By introducing compressed air energy storage components, including gas storage chambers and molten salt heat storage systems, the problem of insufficient flexible regulation capabilities of IGCC generator sets under variable load operation is solved, and the effect of peak and frequency regulation of power is achieved, and the effect of power is enhanced. The grid is responsive and reduces equipment load.
Patent Information
- Application Number
- CN202323386809.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-13
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2033-12-13
AI Technical Summary
Under variable load operation conditions, the system's flexible regulation capability is weak, which cannot meet the requirements of peak regulating and frequency regulation of the power grid, resulting in limited peak regulating depth and response rate. The single compressed air energy storage application scenario has a large investment but is closely integrated with IGCC. Small degree.
Introduced compressed air energy storage components, including gas storage chambers and molten salt heat storage systems, to store rich compressed air potential energy and convert them into electrical energy when needed, and realize power regulation through coordinated control of gasification islands and power islands Peak frequency modulation.
Effectively combining the air-divided compression system and compressed air energy storage system has enhanced the peak-shaving capability of IGCC, reduced the load of gasifiers, gas turbines and other equipment, and achieved the purpose of peak-shaving of power.
Smart Images

Figure CN222029656U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of IGCC energy storage and electric power regulation and control, and specifically relates to an electric power peak regulation and frequency regulation system of an IGCC power station coupled with compressed air energy storage. Background Art
[0002] IGCC is a new, efficient clean coal power generation technology with the characteristics of high efficiency, cleanliness, water saving, and wide fuel adaptability. However, when the IGCC generator set is operating under variable load conditions, the system will be limited by the safe and stable operation capabilities of equipment such as the gasification unit and the air separation unit, causing the IGCC generator set to be unable to respond to the peak-shaving and frequency-regulating auxiliary service requirements of the power grid. The peak-shaving depth and response rate cannot meet the requirements of the power grid, and the frequency regulation response rate and depth are very limited.
[0003] The IGCC power generation system is mainly composed of two parts, namely the gasification island part and the power island part; the coal is gasified into medium and low calorific value coal gas, which is purified to remove pollutants such as sulfides, nitrides, and dust in the coal gas and becomes a clean gas fuel. It is then sent to the combustion chamber of the gas turbine for combustion, heating the gas working medium to drive the gas turbine to do work. The exhaust gas of the gas turbine enters the waste heat boiler to heat the feed water, generating superheated steam to drive the steam turbine to do work.
[0004] The main problems are: the integrated coal gasification combined cycle power generation system (IGCC) is mainly used for power generation, there is a mismatch between the gasification island and the power island, and at the same time, it is affected by the dispatch of the national grid, resulting in weak flexible regulation of the entire IGCC power generation system, which cannot operate at full load, has low power generation income and poor economic benefits. The application scenarios of single compressed air energy storage are limited, the investment is large, and the close integration with IGCC is not close. Utility Model Content
[0005] The purpose of the utility model is to provide an IGCC power plant coupled with compressed air energy storage power peak-shaving and frequency-regulating system, by adding a compressed air energy storage component (energy storage peak-shaving system) in the IGCC system, to achieve coordinated control of the overall coal gasification combined cycle power plant.
[0006] The technical solution adopted by the utility model is an electric peak-shaving and frequency-regulating system of an IGCC power station coupled with compressed air energy storage, comprising three parts: a gasification island, a power island and a compressed air energy storage component; the compressed air energy storage component comprises a gas storage chamber and a molten salt heat storage system, the input ends of the gas storage chamber and the molten salt heat storage system are connected to the gasification island, the output ends of the gas storage chamber and the molten salt heat storage system are respectively connected to the input ends of the gas heat exchange system, the output end of the gas heat exchange system is connected to the expansion power generation system, and the output end of the expansion power generation system is connected to the power island for power output.
[0007] Furthermore, the gasification island includes a coal pretreatment device connected to the gasifier, the output end of the gasifier is connected to the waste heat boiler, and the raw coal gas of the waste heat boiler is purified by the dust removal and desulfurization components and then transported to the power island.
[0008] Furthermore, the gasification island also includes a compression system, a precooling component, a purification component and a distillation component connected in sequence; the air from the power island is transported to the gasifier through the compression system, the precooling component, the purification component and the distillation component in sequence.
[0009] Furthermore, part of the air compressed by the compression system is sent to the air storage chamber of the compressed air energy storage component and the molten salt heat storage system.
[0010] Furthermore, the power island includes a gas turbine, a waste heat boiler and a steam turbine; the gas turbine receives the synthesis gas from the gasification island and outputs electricity, and the exhaust gas of the gas turbine is transported to the waste heat boiler. Part of the hot steam from the waste heat boiler is used for heating, and the other part drives the steam turbine to generate electricity.
[0011] The beneficial effects of the utility model are:
[0012] 1. After using this system, the air separation compression system and compressed air energy storage system in IGCC can be organically combined, which not only overcomes the disadvantage of poor grid peak-shaving capacity of IGCC power generation system, but also reduces the rapid load change burden of gasifier, gas turbine, waste heat boiler, steam turbine and other equipment.
[0013] 2. After using this system, the compressed air energy storage system and the IGCC system operate in parallel to achieve the purpose of power peak regulation by storing the surplus compressed air potential energy. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is the overall intention of the utility model IGCC power station coupled with compressed air energy storage power peak load and frequency regulation system;
[0015] In the figure: 1. Coal pretreatment device, 2. Gasification furnace, 3. Waste heat boiler, 4. Dust removal and desulfurization component, 5. Gas turbine, 6. Waste heat boiler, 7. Steam turbine, 8. Compression system, 9. Precooling component, 10. Purification component, 11. Distillation component, 12. Lava heat storage system, 13. Gas storage chamber, 14. Gas heat exchange system, 15. Expansion power generation system. DETAILED DESCRIPTION
[0016] The utility model is described in detail below with reference to the accompanying drawings and specific implementation modes.
[0017] like Figure 1As shown, an IGCC power plant coupled with compressed air energy storage has an electric peak-shaving and frequency-regulating system, comprising a gasification island, a power island and a compressed air energy storage assembly; the compressed air energy storage assembly comprises a gas storage chamber 13 and a molten salt heat storage system 12, the input ends of the gas storage chamber 13 and the molten salt heat storage system 12 are connected to the gasification island, the output ends of the gas storage chamber 13 and the molten salt heat storage system 12 are respectively connected to the input ends of a gas heat exchange system 14, the output end of the gas heat exchange system 14 is connected to an expansion power generation system 15, and the output end of the expansion power generation system 15 is connected to the power island for power output.
[0018] The gasification island includes a coal pretreatment device 1 connected to a gasifier 2. The output end of the gasifier 2 is connected to a waste heat boiler 3. The raw coal gas of the waste heat boiler 3 is purified by a dust removal and desulfurization component 4 and then transported to the power island.
[0019] The gasification island also includes a compression system 8, a precooling component 9, a purification component 10 and a distillation component 11 connected in sequence; the air from the power island is transported to the gasifier 2 through the compression system 8, the precooling component 9, the purification component 10 and the distillation component 11 in sequence.
[0020] A portion of the air compressed by the compression system 8 is sent to the air storage chamber 13 of the compressed air energy storage component and the molten salt heat storage system 12.
[0021] The power island includes a gas turbine 5, a waste heat boiler 6 and a steam turbine 7; the gas turbine 5 receives the synthesis gas from the gasification island and outputs electricity, and the exhaust gas of the gas turbine 5 is transported to the waste heat boiler 6, a part of the hot steam of the waste heat boiler 6 is used for heating, and the other part drives the steam turbine 7 to generate electricity.
[0022] The process flow of this system is as follows: coal passes through the coal pretreatment device 1, and then enters the gasifier 2 and the oxygen of the distillation component 11 of the air separation device to be gasified and hardened to generate medium and low calorific value coal gas, first passes through the waste heat boiler 3 to extract the heat of the raw coal gas to generate steam and send it to the waste heat boiler 6, the raw coal gas passes through the dust removal and desulfurization component 4 to remove pollutants such as sulfides, nitrides, dust and other pollutants in the coal gas, and becomes a clean gas fuel, and then is sent to the combustion chamber of the gas turbine 5 for combustion, heating the gas working medium to drive the gas turbine to do work, the exhaust gas of the gas turbine 5 enters the waste heat boiler 6 to heat the feed water, and generates superheated steam to drive the steam turbine 7 to do work, wherein the air compressed by the compression system 8 of the air separation device, a part of which enters the subsequent precooling component 9, purification component 10, and distillation component 11 for a series of treatments, and the finally separated oxygen is sent to the gasifier 2 to participate in the front-end reaction, and the other part of the compressed air is sent to the gas storage chamber 13 for compression to store energy.
[0023] When the power grid does not need the IGCC power plant to peak, the air separation system is in normal working condition, and the air intake of the air compressor can be increased to 120-140% compared with normal working conditions. At this time, the surplus 20-50% of compressed air can be sent to the air storage room for potential energy storage.
[0024] When the power grid needs the IGCC power plant to peak-shave, 20-50% of the compressed air stored in the energy storage peak-shaving system can be first sent to the gas heat exchange system 14 for heating, wherein the heat of the gas heat exchange system 14 can pass through the molten salt heat storage system 12, and the heat of the molten salt heat storage system 12 can be directly obtained by the steam of the waste heat boiler 6 or obtained before the inter-stage heat exchanger of the air compression system compressor. The heated compressed air then enters the expansion power generation system 15, and the potential energy is converted into electrical energy and sent to the power grid to participate in peak-shaving.
Claims
1. An IGCC power plant coupled with compressed air energy storage power peak load and frequency regulation system, It is characterized in that The invention comprises three parts: a gasification island, a power island and a compressed air energy storage component; the compressed air energy storage component comprises a gas storage chamber (13) and a molten salt heat storage system (12); the input ends of the gas storage chamber (13) and the molten salt heat storage system (12) are connected to the gasification island; the output ends of the gas storage chamber (13) and the molten salt heat storage system (12) are respectively connected to the input ends of a gas heat exchange system (14); the output end of the gas heat exchange system (14) is connected to an expansion power generation system (15); and the output end of the expansion power generation system (15) is connected to the power island for power output.
2. The power peak load and frequency regulation system of an IGCC power station coupled with compressed air energy storage according to claim 1, It is characterized in that The gasification island comprises a coal pretreatment device (1) connected to a gasifier (2); the output end of the gasifier (2) is connected to a waste heat boiler (3); the raw coal gas of the waste heat boiler (3) is purified by a dust removal and desulfurization component (4) and then transported to the power island.
3. The power peak load and frequency modulation system of an IGCC power plant coupled with compressed air energy storage according to claim 2, It is characterized in that The gasification island further comprises a compression system (8), a precooling component (9), a purification component (10) and a distillation component (11) connected in sequence; air from the power island is transported to the gasifier (2) through the compression system (8), the precooling component (9), the purification component (10) and the distillation component (11) in sequence.
4. The power peak load and frequency modulation system of an IGCC power station coupled with compressed air energy storage according to claim 3, It is characterized in that A portion of the air compressed by the compression system (8) is sent to the air storage chamber (13) of the compressed air energy storage component and the molten salt heat storage system (12).
5. The power peak load and frequency regulation system of an IGCC power station coupled with compressed air energy storage according to claim 1, It is characterized in that The power island comprises a gas turbine (5), a waste heat boiler (6) and a steam turbine (7); the gas turbine (5) receives the synthesis gas from the gasification island and outputs electricity, the exhaust gas of the gas turbine (5) is transported to the waste heat boiler (6), part of the hot steam of the waste heat boiler (6) is used for heating, and the other part drives the steam turbine (7) to generate electricity.