Intelligent circulating water cooling system for coal mine hoisting shaft tower

Through the intelligent circulating water cooling system, the combination of water supply and return water pipes, sensors and control terminals is used to automatically adjust the flow rate and circulation rate of the coolant, which solves the problem of low efficiency of the cooling system in the coal mine lifting tower and improves the operation of the equipment Safety and health of the working environment.

CN222089412UActive Publication Date: 2024-11-29YANKUANG ENERGY GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323178947.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-11-23
Publication Date
2024-11-29
Estimated Expiration
2033-11-23

AI Technical Summary

Technical Problem

The cooling system in the coal mine lifting well tower is inefficient, causing equipment to overtemperature, affecting safe and reliable operation and causing harm to the health of the operators.

Method used

An intelligent circulating water cooling system is designed, including water supply pipes, return water pipes, water cooling units, meter coolers, temperature sensors, flow sensors and control terminals. By automatically controlling the water pump and electric butterfly valve, the flow and circulation of coolant are intelligently adjusted. speed, improve the working efficiency of the system.

Benefits of technology

It effectively improves the working efficiency of the system, reduces the probability of equipment overtemperature shutdown, and ensures a safe and healthy production environment in the coal mine lifting well tower.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222089412U_ABST
    Figure CN222089412U_ABST
Patent Text Reader

Abstract

The utility model provides an intelligent circulating water cooling system for a coal mine hoisting shaft tower. The intelligent circulating water cooling system comprises a water supply pipeline, a water return pipeline, a water cooling unit, a surface air cooler, a temperature sensor, a flow sensor and a control terminal. The water supply pipeline comprises a main water supply pipeline, a branch water supply pipeline and a surface air cooler water supply pipeline. The water return pipeline comprises a main water return pipeline, a branch water return pipeline and a surface air cooler water return pipeline. Water pumps are arranged on the main water supply pipeline and the main water return pipeline respectively, and electric butterfly valves are arranged on the branch water return pipelines. The temperature sensor and the flow sensor are arranged on the pipeline, the temperature sensor and the flow sensor send collected data to the control terminal for processing, and the control terminal can automatically control connection and disconnection of the water pump and the electric butterfly valve and the flow according to data results and can control the working state of the water chilling unit. The working efficiency of the system can be improved, and the probability of overtemperature shutdown of equipment in the hoisting shaft tower is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of refrigeration and cooling technology, and in particular to an intelligent circulating water cooling system for a coal mine hoisting tower. Background Art

[0002] The power motor of the coal mine hoisting tower transmission equipment is a DC rotary motor, and the motor is cooled by natural air cooling. Due to the long operation time of the cooling air duct, the dust in the air is not completely filtered and falls on the surface of the motor, which will cause scaling on the surface of the motor and affect the effect of air cooling. The motor can operate normally when the ambient temperature is low. However, when the ambient temperature is high in summer, the maximum temperature in the coal mine hoisting tower can reach above 40°C. At this time, the cooling and heat dissipation of the mine hoist motor decreases, which will cause the temperature of the motor to be higher than the normal operating temperature, and then the equipment is forced to shut down for cooling, affecting the safe and reliable operation of the equipment. At the same time, it will also cause great harm to the health of the operators.

[0003] In order to ensure the health and safety of workers in the coal mine hoisting tower, it is necessary to cool the coal mine hoisting tower. In some cooling systems, the system efficiency is low and the equipment is prone to overheating. Utility Model Content

[0004] The present application provides an intelligent circulating water cooling system for a coal mine hoisting tower to solve the problem of low efficiency of the cooling system in the coal mine hoisting tower.

[0005] The present application provides an intelligent circulating water cooling system for a coal mine hoisting tower, characterized in that it comprises: a water supply pipe, a return pipe, a water cooling unit, a surface cooler, a temperature sensor, a flow sensor and a control terminal;

[0006] The water supply pipeline includes a main water supply pipeline, a branch water supply pipeline, and a water supply pipeline for a surface cooler; one end of several water supply pipelines for the surface cooler is connected to the surface cooler, the other end of several water supply pipelines for the surface cooler is connected in parallel to one end of the branch water supply pipeline, the other end of several water supply pipelines for the surface cooler is connected in parallel to one end of the main water supply pipeline, and the other end of the main water supply pipeline is connected to the water cooling unit;

[0007] The return water pipeline includes a main return water pipeline, a branch return water pipeline, and a surface cooler return water pipeline; one end of several surface cooler return water pipelines is connected to the surface cooler, the other end of several surface cooler return water pipelines is connected in parallel to one end of the branch return water pipeline, the other end of several branch return water pipelines is connected in parallel to one end of the main return water pipeline, and the other end of the main return water pipeline is connected to the water cooling unit;

[0008] The main water supply pipe and the main water return pipe are respectively provided with water pumps, the water inlet of the water pump of the main water supply pipe faces the water cooling unit, and the water outlet of the water pump of the main water return pipe faces the water cooling unit;

[0009] The temperature sensors are respectively arranged on the main water supply pipe, the main water return pipe, the branch water return pipe, and the water return pipe of the surface cooler; the flow sensors are respectively arranged on the main water return pipe, the branch water return pipe, and the water return pipe of the surface cooler;

[0010] The branch water return pipe is provided with an electric butterfly valve, and the electric butterfly valve, the water cooling unit, the water pump, the flow sensor and the temperature sensor are electrically connected to the control terminal respectively.

[0011] Optionally, the water cooling units are in parallel structure.

[0012] Optionally, a water inlet of the water pump of the main water supply pipe faces the water cooling unit, and a water outlet of the water pump of the main return water pipe faces the water cooling unit.

[0013] Optionally, it also includes an automatic exhaust valve, which is respectively arranged at the highest point of the main water supply pipe and the main water return pipe.

[0014] Optionally, a static balancing valve is also included, and the static balancing valve is arranged on the branch water supply pipeline.

[0015] Optionally, the main water supply pipeline is also provided with a butterfly valve, a dirt remover, a gate valve, a pressure gauge, a flow meter and a check valve; the butterfly valve, the dirt remover, the gate valve and the pressure gauge are arranged in sequence at the water inlet of the water pump along the direction of liquid flow, and the pressure gauge, the flow meter, the check valve and the butterfly valve are arranged in sequence at the water outlet of the water pump along the direction of liquid flow.

[0016] Optionally, the main return water pipe is also provided with a butterfly valve, a dirt remover, a gate valve, a pressure gauge and a check valve; the butterfly valve, the dirt remover, the gate valve and the pressure gauge are arranged in sequence at the water inlet of the water pump along the direction of liquid flow, and the pressure gauge, the check valve and the butterfly valve are arranged in sequence at the water outlet of the water pump along the direction of liquid flow.

[0017] Optionally, a butterfly valve, a flow meter, a gate valve, a thermometer and a pressure gauge are also provided on the water supply pipeline of the surface cooler, and the butterfly valve, flow meter, gate valve, thermometer and pressure gauge are arranged in sequence along the flow direction of the liquid.

[0018] Optionally, a pressure gauge, a thermometer and a butterfly valve are further provided on the return water pipe of the surface cooler, and the pressure gauge, the thermometer and the butterfly valve are arranged in sequence along the flow direction of the liquid.

[0019] Optionally, several of the temperature sensors on the main water supply pipe, the main return pipe, the branch return pipe, and the cooler return pipe are connected end to end; several of the flow sensors on the main return pipe, the branch return pipe, and the cooler return pipe are connected end to end.

[0020] It can be seen from the above technical scheme that the present application provides an intelligent circulating water cooling system for a coal mine hoisting tower, including: a water supply pipeline, a return pipeline, a water cooling unit, a surface cooler, a temperature sensor, a flow sensor and a control terminal. The water supply pipeline includes a main water supply pipeline, a branch water supply pipeline and a surface cooler water supply pipeline. The return pipeline includes a main return pipeline, a branch return pipeline and a surface cooler return pipeline. A water pump is provided on the main water supply pipeline and the main return pipeline, respectively, and an electric butterfly valve is provided on the branch return pipeline. The temperature sensor is provided on the main water supply pipeline, the main return pipeline, the branch return pipeline and the surface cooler return pipeline, and the flow sensor is provided on the main return pipeline, the branch return pipeline and the surface cooler return pipeline. The temperature sensor and the flow sensor send the collected data to the control terminal for processing, and the control terminal can automatically control the on and off of the water pump and the electric butterfly valve and the flow rate according to the data results, and can control the working state of the water cooling unit. It can improve the working efficiency of the system and reduce the probability of over-temperature shutdown of equipment in the hoisting tower. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solution of the present application, the drawings required for use in the embodiments are briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.

[0022] Figure 1 A schematic diagram of the structure of the intelligent circulating water cooling system provided in this application;

[0023] Figure 2 A control schematic diagram of the intelligent circulating water cooling system provided for this application;

[0024] Figure 3 This is a connection diagram for the control terminal.

[0025] Illustration Description:

[0026] Among them, 1-water cooling unit; 2-butterfly valve; 3-decontaminant remover; 4-gate valve; 5-water pump; 6-press; 7-flow meter; 8-check valve; 9-temperature sensor; 10-automatic exhaust valve; 11-static balancing valve; 12-thermometer; 13-cooler; 14-flow sensor; 15-electric butterfly valve; 16-main water supply pipeline; 17-main return pipeline; 18-branch water supply pipeline; 19-branch return pipeline; 20-cooler water supply pipeline; 21-cooler return pipeline. DETAILED DESCRIPTION

[0027] The following embodiments are described in detail, and examples thereof are shown in the accompanying drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The implementations described in the following embodiments do not represent all implementations consistent with the present application. They are only examples of systems and methods consistent with some aspects of the present application as detailed in the claims.

[0028] When the ambient temperature is high in summer, the maximum temperature in the coal mine hoisting tower can reach above 40°C. Due to the decrease in cooling and heat dissipation of the working motor in the tower at high temperature, the temperature of the motor will be higher than the normal operating temperature, which will force the equipment to shut down and cool down, affecting the safe and reliable operation of the equipment. At the same time, it will also cause great harm to the health of the operators. In order to ensure the health and safety of the operators in the coal mine hoisting tower, the coal mine hoisting tower needs to be cooled. In some cooling systems, the system has low working efficiency and is prone to equipment overheating.

[0029] In order to solve the above problems, the present application provides an intelligent circulating water cooling system for a coal mine hoisting tower. Figure 1 This is a schematic diagram of the structure of the intelligent circulating water cooling system provided in this application. Figure 3 This is a connection diagram of the control terminal, such as Figure 1 and Figure 3 As shown, the intelligent circulating water cooling system for the coal mine hoisting tower provided in the present application includes a water supply pipe, a return pipe, a water cooling unit 1, a surface cooler 13, a temperature sensor 9, a flow sensor 14 and a control terminal.

[0030] The control terminal is electrically connected to the water cooling unit 1, and can intelligently control the water cooling machine of the water cooling unit 1. The water cooling unit 1 is a parallel structure, and even if a single water cooling machine in the group fails, the intelligent circulating water cooling system can continue to operate. In some embodiments, in order to improve the working efficiency of the system, a coolant is used to cool the system, so the liquid in the water cooling machine of the water cooling unit 1 is a coolant.

[0031] The surface cooler 13 is a cooler. After the coolant flows through the inner cavity of the metal pipe of the surface cooler 13, it can exchange heat with the outside through the outer wall of the metal pipe, thereby achieving the purpose of cooling the air.

[0032] The water supply pipeline includes a main water supply pipeline 16, a plurality of branch water supply pipelines 18, and a surface cooler water supply pipeline 20 connected to the branch water supply pipeline 18. One end of the plurality of surface cooler water supply pipelines 20 is connected to the surface cooler 13, the other end of the plurality of surface cooler water supply pipelines 20 is connected in parallel to one end of the branch water supply pipeline 18, the other end of the plurality of branch water supply pipelines 18 is connected in parallel to one end of the main water supply pipeline 16, and the other end of the main water supply pipeline 16 is connected to the water cooling unit 1. The water cooling unit 1 transports cooling liquid to the main water supply pipeline 16, so that the main water supply pipeline 16 can provide cooling liquid to the branch water supply pipelines 18 on each floor in the lifting shaft tower, thereby evenly cooling the entire lifting shaft tower.

[0033] The return water pipeline includes a main return water pipeline 17, a plurality of branch return water pipelines 19 and a surface cooler return water pipeline 21. One end of the plurality of surface cooler return water pipelines 21 is connected to the surface cooler 13, the other end of the plurality of surface cooler return water pipelines 21 is connected in parallel to one end of the branch return water pipeline 19, the other end of the plurality of branch return water pipelines 19 is connected in parallel to one end of the main return water pipeline 17, and the other end of the main return water pipeline 17 is connected to the water cooling unit 1.

[0034] It can be understood that the coolant flows to the surface cooler 13 through the main water supply pipe 16, the branch water supply pipe 18, and the surface cooler water supply pipe 20, exchanges heat with the external high temperature environment in the surface cooler 13, and then returns to the water-cooled unit 1 for cooling through the surface cooler return pipe 21, the branch return pipe 19, and the main return pipe 17, thereby completing a complete water cooling cycle.

[0035] The temperature sensors 9 are respectively arranged on the main water supply pipe 16, the main water return pipe 17, the branch water return pipe 19, and the cooler water return pipe 21, and are respectively used to measure the temperature of the main water supply pipe 16, the main water return pipe 17, each branch water return pipe 19, and each cooler water return pipe 21. The flow sensors 14 are respectively arranged on the main water return pipe 17, the branch water return pipe 19, and the cooler water return pipe 21, and are respectively used to measure the flow of the main water return pipe 17, the branch water return pipe 19, and the cooler water return pipe 21. The temperature sensor 9 and the flow sensor 14 are respectively electrically connected to the control terminal to transmit data to the control terminal, and the control terminal can process the received data and judge the working status of each pipeline through the sensor data.

[0036] In some embodiments, several temperature sensors 9 on the main water supply pipe 16, the main return pipe 17, the branch return pipe 19, and the surface cooler return pipe 21 are electrically connected to the control terminal in an end-to-end connection manner. Several flow sensors 14 on the main return pipe 17, the branch return pipe 19, and the surface cooler return pipe 21 are electrically connected to the control terminal in an end-to-end connection manner. The end-to-end connection method can prevent the sensor data from stopping the system's monitoring function due to the failure of a certain information line of a flow sensor or temperature sensor, so that the system can continue to intelligently cool the coal mine hoisting tower. At the same time, the system will not stop correcting work due to lack of data, so that the power change of the water-cooling unit 1 is not timely, resulting in reduced system efficiency or the machine over-temperature self-locking.

[0037] In some embodiments, a temperature sensor 9 may also be provided on the equipment in the hoisting tower to collect the temperature of the equipment. The control terminal may display the initial temperature of the coolant, the coolant temperature and flow rate of each floor and the entire system, and the temperature of the equipment in the hoisting tower. By collecting these data, the working state of the coal mine hoisting tower at different times and under different working conditions and the temperature change curve of each part of the system may be obtained, and based on this, appropriate corrections may be made to the system according to corresponding conditions, so that the temperature curve of each part of the system tends to be stable. It should be noted that the temperature collected by the temperature sensor 9 on the main water supply pipe 16 is the initial temperature of the coolant.

[0038] See also Figure 1 A water pump 5 is provided on the main water supply pipe 16 and the main water return pipe 17, respectively. The water inlet of the water pump 5 of the main water supply pipe 16 faces the water cooling unit 1, and the water outlet of the water pump 5 of the main water return pipe 17 faces the water cooling unit 1, so that the flow of the coolant in the main water supply pipe 16 and the main water return pipe 17 can be controlled by the water pump 5. The two water pumps 5 are electrically connected to the control terminal respectively, and the control terminal can intelligently control the on and off and flow size of the water pump 5 according to the data received from the sensor.

[0039] An electric butterfly valve 15 is provided on the branch return pipe 19 , and the electric butterfly valve 15 is electrically connected to the control terminal so that the control terminal can intelligently control the on-off and flow rate of the electric butterfly valve 15 according to the received sensor data, thereby controlling the flow rate of the coolant in the branch return pipe 19 .

[0040] According to the collected data, the power variation law of the equipment in the coal mine hoisting tower can be obtained. When the power rises and the heat release increases, the flow of the coolant can be controlled by controlling the electric butterfly valve 15, the water pump 5 of the main return water pipe 17 and the water pump 5 of the main water supply pipe 16, thereby regulating the cooling power of the system. When the heat release is too much, the circulation rate of the coolant is controlled by controlling the electric butterfly valve 15 and the water pump 5, the operation mode of the water cooling unit 1 is changed, and the refrigeration power is increased.

[0041] Figure 2 The control schematic diagram of the intelligent circulating water cooling system provided for this application is as follows: Figure 2 As shown, in some embodiments, the temperature can be set as follows: when the initial temperature and return water temperature of the coolant change by more than 5°C, the flow of the coolant is controlled by controlling the electric butterfly valve 15, thereby controlling the local cooling power; when the initial temperature and return water temperature of the coolant change by more than 10°C or the equipment temperature in the well tower is greater than 80°C, the working mode of the water cooling unit 1 is changed, and the cooling power is increased by lowering the initial temperature of the coolant and increasing the circulation rate of the coolant; when the initial temperature and return water temperature of the coolant change by more than 15°C or the equipment temperature in the well tower is greater than 90°C, the control terminal issues an alarm.

[0042] See again Figure 1 On the main water supply pipe 16, between the temperature sensor 9 and the water cooling unit 1, a butterfly valve 2, a dirt remover 3, a gate valve 4, a pressure gauge 6, a flow meter 7 and a check valve 8 are also provided. The butterfly valve 2, the dirt remover 3, the gate valve 4, and the pressure gauge 6 are sequentially provided at the water inlet of the water pump 5 along the flow direction of the coolant, and the pressure gauge 6, the flow meter 7, the check valve 8, and the butterfly valve 2 are sequentially provided at the water outlet of the water pump 5 along the flow direction of the coolant.

[0043] A butterfly valve 2, a dirt remover 3, a gate valve 4, a pressure gauge 6 and a check valve 8 are also provided on the main return water pipe 17 between the flow sensor 14 and the water cooling unit 1. The butterfly valve 2, the dirt remover 3, the gate valve 4 and the pressure gauge 6 are sequentially provided at the water inlet of the water pump 5 along the flow direction of the coolant, and the pressure gauge 6, the check valve 8 and the butterfly valve 2 are sequentially provided at the water outlet of the water pump 5 along the flow direction of the coolant.

[0044] The surface cooler water supply pipe 20 is also provided with a butterfly valve 2, a flow meter 7, a gate valve 4, a thermometer 12 and a pressure gauge 6. The butterfly valve 2, the flow meter 7, the gate valve 4, the thermometer 12 and the pressure gauge 6 are arranged in sequence along the flow direction of the coolant.

[0045] The return water pipe 21 of the surface cooler is also provided with a pressure gauge 6, a thermometer 12 and a butterfly valve 2, and the pressure gauge 6, the thermometer 12 and the butterfly valve 2 are arranged in sequence along the flow direction of the coolant.

[0046] The butterfly valve 2 is used to manually adjust the flow of the coolant in the pipeline, the decontaminant 3 can remove impurities in the pipeline, the gate valve 4 is used to connect or cut off the coolant flowing to the pressure gauge 6 in the pipeline, the pressure gauge 6 can measure the pressure in the pipeline, the check valve 8 can prevent the coolant in the pipeline from being withdrawn, and the thermometer 12 can measure the temperature of the coolant in the pipeline.

[0047] See again Figure 1 The intelligent circulating water cooling system provided in the present application also includes an automatic exhaust valve 10, which is respectively arranged at the highest points of the main water supply pipe 16 and the main return water pipe 17, and can be exhausted when gas enters the pipe.

[0048] The intelligent circulating water cooling system provided in the present application also includes a static balancing valve 11, which is arranged on the branch water supply pipe 18. The static balancing valve 11 can reasonably distribute the flow, and can solve the problem of uneven cold and hot in the system. At the same time, it can accurately adjust the pressure drop and flow, and can improve the liquid flow state in the system to achieve liquid balance.

[0049] It can be seen from the above technical scheme that the embodiment of the present application provides an intelligent circulating water cooling system for a coal mine hoisting tower, including: a water supply pipeline, a return water pipeline, a water cooling unit 1, a surface cooler 13, a temperature sensor 9, a flow sensor 14 and a control terminal. The water supply pipeline includes a main water supply pipeline 16, a branch water supply pipeline 18 and a surface cooler water supply pipeline 20. The return water pipeline includes a main return water pipeline 17, a branch return water pipeline 19 and a surface cooler return water pipeline 21. A water pump 5 is respectively provided on the main water supply pipeline 16 and the main return water pipeline 17, and an electric butterfly valve 15 is provided on the branch return water pipeline 19. The temperature sensor 9 and the flow sensor 14 are arranged on the pipeline. The temperature sensor 9 and the flow sensor 14 send the collected data to the control terminal for processing. The control terminal can automatically control the on and off of the water pump 5 and the electric butterfly valve 15 and the flow size according to the data results, and can control the working state of the water cooling unit 1. The working efficiency of the system can be improved and the probability of over-temperature shutdown of the equipment in the hoisting tower can be reduced.

[0050] Similar parts between the embodiments provided in this application can be referenced to each other. The specific implementation methods provided above are only a few examples under the general concept of this application and do not constitute a limitation on the protection scope of this application. For those skilled in the art, any other implementation methods expanded based on the scheme of this application without creative work belong to the protection scope of this application.

Claims

1. An intelligent circulating water cooling system for a coal mine hoisting tower, characterized in that: include: A water supply pipe, a water return pipe, a water cooling unit (1), a surface cooler (13), a temperature sensor (9), a flow sensor (14) and a control terminal; The water supply pipeline comprises a main water supply pipeline (16), a branch water supply pipeline (18), and a water supply pipeline for a cooling device (20); one end of a plurality of the water supply pipelines for the cooling device (20) is connected to the cooling device (13), the other end of a plurality of the water supply pipelines for the cooling device (20) is connected in parallel to one end of the branch water supply pipeline (18), the other end of a plurality of the branch water supply pipelines (18) is connected in parallel to one end of the main water supply pipeline (16), and the other end of the main water supply pipeline (16) is connected to the water cooling unit (1); The return water pipeline comprises a main return water pipeline (17), a branch return water pipeline (19), and a water cooler return water pipeline (21); one end of a plurality of the water cooler return water pipelines (21) is connected to the water cooler (13), the other end of a plurality of the water cooler return water pipelines (21) is connected in parallel to one end of the branch return water pipelines (19), the other end of a plurality of the branch return water pipelines (19) is connected in parallel to one end of the main return water pipeline (17), and the other end of the main return water pipeline (17) is connected to the water cooling unit (1); The main water supply pipe (16) and the main water return pipe (17) are respectively provided with water pumps (5); The temperature sensors (9) are respectively arranged on the main water supply pipe (16), the main water return pipe (17), the branch water return pipe (19), and the condenser water return pipe (21); the flow sensors (14) are respectively arranged on the main water return pipe (17), the branch water return pipe (19), and the condenser water return pipe (21); The branch water return pipe (19) is provided with an electric butterfly valve (15), and the electric butterfly valve (15), the water cooling unit (1), the water pump (5), the temperature sensor (9) and the flow sensor (14) are electrically connected to the control terminal respectively.

2. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The water cooling unit (1) is a parallel structure.

3. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The water inlet of the water pump (5) of the main water supply pipe (16) faces the water cooling unit (1), and the water outlet of the water pump (5) of the main water return pipe (17) faces the water cooling unit (1).

4. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: It also comprises an automatic air exhaust valve (10), which is respectively arranged at the highest point of the main water supply pipe (16) and the main water return pipe (17).

5. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: It also comprises a static balancing valve (11), wherein the static balancing valve (11) is arranged on the branch water supply pipeline (18).

6. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The main water supply pipeline (16) is also provided with a butterfly valve (2), a dirt remover (3), a gate valve (4), a pressure gauge (6), a flow meter (7) and a check valve (8); the butterfly valve (2), the dirt remover (3), the gate valve (4) and the pressure gauge (6) are arranged in sequence at the water inlet of the water pump (5) along the direction of liquid flow, and the pressure gauge (6), the flow meter (7), the check valve (8) and the butterfly valve (2) are arranged in sequence at the water outlet of the water pump (5) along the direction of liquid flow.

7. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The main water return pipe (17) is also provided with a butterfly valve (2), a dirt remover (3), a gate valve (4), a pressure gauge (6) and a check valve (8); the butterfly valve (2), the dirt remover (3), the gate valve (4) and the pressure gauge (6) are arranged in sequence at the water inlet of the water pump (5) along the direction of liquid flow, and the pressure gauge (6), the check valve (8) and the butterfly valve (2) are arranged in sequence at the water outlet of the water pump (5) along the direction of liquid flow.

8. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The surface cooler water supply pipeline (20) is also provided with a butterfly valve (2), a flow meter (7), a gate valve (4), a thermometer (12) and a pressure gauge (6), and the butterfly valve (2), the flow meter (7), the gate valve (4), the thermometer (12) and the pressure gauge (6) are arranged in sequence along the flow direction of the liquid.

9. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The surface cooler water return pipe (21) is also provided with a pressure gauge (6), a thermometer (12) and a butterfly valve (2), and the pressure gauge (6), the thermometer (12) and the butterfly valve (2) are arranged in sequence along the flow direction of the liquid.

10. The intelligent circulating water cooling system for coal mine hoisting tower according to claim 1 is characterized in that: The plurality of temperature sensors (9) on the main water supply pipe (16), the main water return pipe (17), the branch water return pipe (19), and the condenser water return pipe (21) are connected end to end; the plurality of flow sensors (14) on the main water return pipe (17), the branch water return pipe (19), and the condenser water return pipe (21) are connected end to end.