Cooling device used after steel pipe smelting

By designing a cooling device for steel pipe smelting, a combined structure of a cooling box and a water pipe can achieve uniform cooling inside and outside the steel pipe, solving the problem of uneven cooling in the prior art, and improving the quality and cooling speed of the steel pipe.

CN222113056UActive Publication Date: 2024-12-06SHANGHAI JINGTENG METAL GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420851594.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2024-12-06
Estimated Expiration
2034-04-23

AI Technical Summary

Technical Problem

The existing steel pipe smelting and cooling methods lead to uneven cooling of the inside and outside of the steel pipe, affecting the performance and appearance of the steel pipe. The cold air cooling time is long and the site occupies a large amount, resulting in a low quality of the steel pipe.

Method used

A cooling device is designed, including a cooling box, water pipe and rotating assembly, which uniformly cools the inside and outside of the steel pipe through the water jet hole, and moves and places the steel pipes left and right through the conveying assembly, adapts to different pipe diameters and ensures the stability of the water pipes.

Benefits of technology

It realizes uniformity of internal and external cooling of steel pipes, improves the quality and cooling speed of steel pipes, and is convenient for the placement and removal of steel pipes, and is suitable for different pipe diameters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222113056U_ABST
    Figure CN222113056U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of steel pipe smelting, in particular to a cooling device used after steel pipe smelting, which comprises a cooling box, the top surface of the cooling box is fixedly connected with an outer protective shell, the inside of the outer protective shell is fixedly connected with a second water pipe, and the bottom surface of the cooling box is fixedly connected with a bottom connecting plate. Conveying assemblies are arranged on the front side and the rear side of the cooling box correspondingly, a rotating assembly is arranged on the rear side of the conveying assembly on the rear side, a placing round opening is formed in the upper portion of the interior of the cooling box, and a first water pipe is arranged in the placing round opening. According to the cooling device, the cooling box, the outer protective shell, the placing round opening, the first water pipe, the second water pipe, water spraying holes, a bearing block, a first bearing pipe, a second bearing pipe, a rotating assembly and a conveying assembly are arranged in a matched mode, the effect of internally and externally cooling a steel pipe placed in the placing round opening can be achieved, and the steel pipe is evenly cooled internally and externally; therefore, the influence on the performance and the appearance of the steel pipe caused by inconsistent internal and external temperature differences is well avoided, and the output quality is well improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of steel pipe smelting, in particular to a cooling device used for steel pipes after smelting. Background Art

[0002] In the technical production process of steel pipe smelting, the newly cast steel pipe needs to be cooled down, which we call hot rolling cooling, which is the process of cooling the hot rolled steel from the high temperature at the end of rolling to room temperature. Post-rolling cooling will affect the performance and appearance of the rolled material, and sometimes also affect the output of the rolling mill. In related technologies, cold water cooling and cold air cooling are generally used to cool the steel pipe. However, due to the disadvantages of slow cooling time and large site area occupied by cold air cooling, most companies generally use cold water cooling.

[0003] Some existing cold water cooling methods usually place the steel pipe on a rack and use water to cool the surface of the steel pipe. However, since the cold water method only cools the outer surface of the steel pipe, the temperature inside the steel pipe is inconsistent with the surface temperature, resulting in a temperature difference, which leads to uneven cooling inside and outside the steel pipe, which may affect the performance and appearance of the steel pipe after cooling to a certain extent, and may also make the quality of the output steel pipe lower. Therefore, in response to the above problems, we provide a new cooling device for steel pipes after smelting. Utility Model Content

[0004] The utility model aims to provide a cooling device for steel pipes after smelting, so as to solve the problems raised in the above-mentioned background technology.

[0005] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0006] A cooling device for steel pipe after smelting comprises a cooling box, the top surface of the cooling box is fixedly connected to an outer protective shell, the interior of the outer protective shell is fixedly connected to a water pipe 2, the bottom surface of the cooling box is fixedly connected to a bottom connecting plate, the front and rear sides of the cooling box are provided with conveying components, and the rear side of the rear conveying component is provided with a rotating component, the upper part of the cooling box is provided with a placement circular opening, the interior of the placement circular opening is provided with a water pipe 1, the front end of the water pipe 1 is fixedly connected to a receiving block, the rear end of the water pipe 1 is fixedly connected to a receiving pipe 1, the interior of the receiving pipe 1 is provided with a receiving pipe 2, a plurality of water spray holes are equidistantly arranged on the opposite surfaces of the water pipe 2 and the water pipe 1, the outer wall of the top surface of the water pipe 2 is fixedly connected to an external pipe 2, one end of the external pipe 2 passes through the top surface of the outer protective shell and is fixedly connected to a mounting plate, a water storage cavity is provided at the lower part of the interior of the cooling box, and a drain hole is provided on one side of the water storage cavity.

[0007] Furthermore, empty grooves are provided on the outer walls of the upper and lower sides of the receiving block. A load-bearing block is slidably connected inside the empty groove. An arc-shaped plate is fixedly connected to the side of the load-bearing block away from the first water pipe. Springs are provided inside both of the empty grooves. One end of the spring is connected to the inner side of the corresponding load-bearing block, and the other end of the spring is connected to the inner side of the corresponding empty groove.

[0008] Furthermore, four limiting grooves are equidistantly arranged on the outer wall of the second receiving pipe. A limiting block is fixedly connected to the rear of the inner side of the first receiving pipe. The limiting block is slidably connected to the limiting groove.

[0009] Furthermore, conveying components are provided on both the front and rear sides of the cooling box. The conveying component includes a conveying connection frame. Hydraulic cylinders are installed inside the upper and lower sides of the conveying connection frame. The driving end of the hydraulic cylinder is fixedly connected to a U-shaped connection plate. Rotating rods are rotatably connected to both sides inside the U-shaped connection plate. Conveying wheels are fixedly connected to the adjacent ends of the two rotating rods. A support plate is fixedly connected to the outer wall of one side of the lower U-shaped connection plate. A servo motor two is fixedly connected to the top of the support plate. The driving end of the servo motor two is fixedly connected to one end of the corresponding rotating rod.

[0010] Furthermore, the rotating component includes a movable block. The movable block is located behind the rear conveying connection frame. A rotating block is rotatably connected to the upper part inside the movable block. The front end of the rotating block is fixedly connected to the rear end of the second receiving pipe. A rotating coiled pipe is rotatably connected inside the rotating block. The rear end of the rotating coiled pipe is fixedly connected to an outer connecting pipe one. The rear end of the outer connecting pipe one penetrates through the rear sides of the rotating block and the movable block and is fixedly connected to an installation disc. An L-shaped connecting frame is fixedly connected to the outer wall of the movable block. A servo motor one is fixedly connected to the top of the L-shaped connecting frame. A toothed ring is fixedly connected to the middle side of the outer wall of the rotating block. A gear is meshed with the lower outer wall of the toothed ring. The two sides of the gear are rotatably connected to the inner wall of the movable block through rotating rods. The driving end of the servo motor one is fixedly connected to the rotating rod on the gear.

[0011] Furthermore, a sliding plate is fixedly connected to the lower part of the front outer wall of the movable block. The front end of the sliding plate penetrates through the inside of the rear conveying connection frame and is slidably connected to the inside of the bottom connection plate.

[0012] Furthermore, water receiving seats are fixedly connected to the top surfaces of the bottom connection plate, the movable block, and the two conveying connection frames.

[0013] Compared with the prior art, the beneficial effects of the present utility model are:

[0014] 1. In the utility model, through the coordinated arrangement of the cooling box, the outer protective shell, the placement circular port, the water pipe 1, the water pipe 2, the water spray hole, the receiving block, the receiving pipe 1, the receiving pipe 2, the rotating assembly and the conveying assembly, the steel pipe placed in the placement circular port can be cooled inside and outside, so that the steel pipe is cooled evenly inside and outside, thereby better avoiding the inconsistent temperature difference between the inside and outside that affects the performance and appearance of the steel pipe, better improving the output quality, and at the same time further accelerating the cooling speed of the steel pipe.

[0015] 2. In the utility model, the rotating assembly provided can drive the water pipe to rotate, so that the water spray holes on the water pipe can spray around the inner wall of the steel pipe. The conveying assembly provided can drive the steel pipe to move left and right, so as to facilitate the placement or removal of the steel pipe. The cooperation of the receiving blocks, empty grooves, load-bearing blocks, arc plates and springs provided can adapt to the inner walls of different pipe diameters and can also play a role in supporting and stabilizing the steel pipe and the water pipe. The overall design has a certain practical effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 It is a three-dimensional schematic diagram of a cooling device for steel pipes after smelting proposed by the utility model;

[0017] Figure 2 It is a cross-sectional schematic diagram of a cooling box of a cooling device for cooling steel pipes after smelting, which is proposed by the utility model;

[0018] Figure 3 This is a structural schematic diagram of a conveying assembly for a cooling device after steel pipe smelting proposed by the utility model;

[0019] Figure 4 It is a cross-sectional schematic diagram of a movable block of a cooling device for steel pipe after smelting proposed by the utility model;

[0020] Figure 5 It is a cross-sectional schematic diagram of a receiving pipe 1 of a cooling device for steel pipe after smelting proposed by the utility model;

[0021] Figure 6 The utility model discloses a cross-sectional schematic diagram of a receiving block of a cooling device for steel pipes after smelting.

[0022] Legend:

[0023] 1. Cooling box; 2. Outer protective shell; 3. Rotating assembly; 31. Movable block; 32. Rotating block; 33. Rotating coiled pipe; 34. First external connecting pipe; 35. L-shaped connecting frame; 36. First servo motor; 37. Tooth ring; 38. Gear; 4. Placing round opening; 5. Conveying assembly; 51. Conveying connecting frame; 52. Hydraulic cylinder; 53. C-shaped connecting plate; 54.转接杆; 55. Conveying wheel; 56. Support plate; 57. Second servo motor; 6. Water receiving seat; 7. Bottom connecting plate; 8. First water pipe; 9. Second water pipe; 10.承接块; 11. First receiving pipe; 12. Second receiving pipe; 13. Empty slot; 14. Load-bearing block; 15. Arc-shaped plate; 16. Spring; 17. Limit slot; 18. Limit block; 19. Spraying hole; 20. Second external connecting pipe; 21. Sliding plate; 22. Water storage cavity; 23. Water discharge hole. Detailed implementation manner

[0024] Next, the technical solutions in the embodiments of the present invention will be clearly and completely described in conjunction with the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

[0025] Please refer to Figures 1 to 6In the embodiment of the utility model, a cooling device for steel pipe after smelting includes a cooling box 1, the top surface of the cooling box 1 is fixedly connected with an outer protective shell 2, the inside of the outer protective shell 2 is fixedly connected with a water pipe 9, the bottom surface of the cooling box 1 is fixedly connected with a bottom connecting plate 7, the front and rear sides of the cooling box 1 are provided with conveying components 5, the rear side of the rear conveying component 5 is provided with a rotating component 3, the upper part of the interior of the cooling box 1 is provided with a placement circular opening 4, the inside of the placement circular opening 4 is provided with a water pipe 8, the front end of the water pipe 8 is fixedly connected with a receiving block 10, the upper and lower outer walls of the receiving block 10 are provided with empty grooves 13, the inside of the empty grooves 13 is slidably connected with a bearing block 14, the side of the bearing block 14 away from the water pipe 8 is fixedly connected with an arc plate 15, and the inside of the two empty grooves 13 are provided with springs 16 One end of the spring 16 is connected to the inner side of the corresponding load-bearing block 14, and the other end of the spring 16 is connected to the inner side of the corresponding empty groove 13. The rear end of the rear water pipe 8 is fixedly connected with the receiving pipe 11, and the receiving pipe 12 is arranged inside the receiving pipe 11. The outer wall of the receiving pipe 12 is equidistantly provided with four limiting grooves 17, and the inner side of the receiving pipe 11 is fixedly connected with a limiting block 18 at the rear, and the limiting block 18 is slidably connected to the limiting groove 17. A plurality of water spray holes 19 are equidistantly arranged on the opposite surfaces of the water pipe 29 and the water pipe 18. The outer wall of the top surface of the water pipe 29 is fixedly connected with an external pipe 20, and one end of the external pipe 20 passes through the top surface of the outer casing 2 and is fixedly connected with a mounting plate. A water storage cavity 22 is arranged at the lower part of the interior of the cooling box 1, and a drain hole 23 is opened on one side of the water storage cavity 22.

[0026] In specific implementation, the rotating assembly 3 is extended by the receiving tube 1 11, the receiving tube 2 12, the limiting groove 17 and the limiting block 18, so as to be adjusted to a certain extent according to the length of the steel pipe, so as to facilitate the subsequent forward removal of the steel pipe by the conveying assembly 5 on the rear side, and to prevent the receiving tube 2 12 from being pulled out of the receiving tube 1 1 by the limiting groove 17 and the limiting block 18. In addition, it can usually cooperate with the following rotating assembly 3, and the steel pipe to be cooled is placed in the cooling box 1 through the placement circular opening 4, which is set with a larger diameter, and can be applied to a certain extent. For steel pipes of different diameters, the conveying assembly 5 provided at the rear side can move the cooled steel pipes out. When in use, the hollow part of the steel pipe is aligned with the arc plate 15 through the front conveying assembly 5 and inserted into the outside of the water pipe 8 provided. Then, the external pipe 20 and the external pipe 34 described below can be connected to the external water pipeline through the mounting plate, and cooling water is input into the water pipe 2 9 and the water pipe 8. The water is sprayed through the water spray holes 19 provided on the outer walls of one side of the water pipe 8 and the water pipe 2 9, thereby spraying and cooling the inner and outer walls of the steel pipe, so that the cooling of the inner and outer walls of the steel pipe is better. The steel pipe is uniformly cooled, thereby better avoiding the inconsistent temperature difference between the inside and outside that affects the performance and appearance of the steel pipe, and better improving the quality of the output. At the same time, the cooling speed of the steel pipe is further accelerated by spraying cooling inside and outside. The arc plate 15 is provided to facilitate the insertion of the steel pipe. Combined with the setting of the receiving block 10, the empty slot 13, the bearing block 14 and the spring 16, it can be well applied to the placement of steel pipes with different inner diameters. It can also support and stabilize the steel pipe and the water pipe 8. The rotating assembly 3 can be used to carry the receiving pipe 11 and the receiving pipe 2 12. The moving water pipe 8 rotates to spray the inner wall of the steel pipe all around, increasing the spraying area to a certain extent. Notches are provided on the upper and lower sides of the circular opening 4. The upper notch facilitates the water pipe 9 to cool the outer wall of the steel pipe by pouring. Water can flow along the outer wall of the steel pipe into the lower notch provided on the inner bottom surface of the circular opening 4 and enter the water storage cavity 22. Through the water storage cavity 22, the water sprayed by the water pipe 9 can be collected, and the water outlet pipe can be connected to the outside through the drain hole 23, so as to facilitate the recycling of the water after cooling, which has a certain practical effect.

[0027] Embodiment 1

[0028] like Figure 3As shown in the figure, in this embodiment, conveying components 5 are arranged on both the front and rear sides of the cooling box 1. The conveying component 5 includes a conveying connection frame 51. Hydraulic cylinders 52 are installed inside the upper and lower sides of the conveying connection frame 51. The driving ends of the hydraulic cylinders 52 are fixedly connected with U-shaped connection plates 53. Both sides inside the U-shaped connection plates 53 are rotatably connected with transfer rods 54. Conveying wheels 55 are fixedly connected to the adjacent ends of the two transfer rods 54. A support plate 56 is fixedly connected to the outer wall of one side of the lower U-shaped connection plate 53. A second servo motor 57 is fixedly connected to the top of the support plate 56. The driving end of the second servo motor 57 is fixedly connected to one end of the corresponding transfer rod 54.

[0029] During specific implementation, by starting the second servo motor 57, the transfer rod 54 connected thereto is used to drive the conveying wheel 55 to rotate. The steel pipe can be driven to be conveyed back and forth through the provided conveying wheel 55. The distance between the two conveying wheels 55 can be adjusted according to the diameter of the steel pipe through the provided hydraulic cylinder 52, so as to facilitate adapting to steel pipes of different diameters. An activity slot is provided on one side of the conveying connection frame 51 to facilitate the second servo motor 57 connected to the lower side through the support plate 56 and the U-shaped connection plate 53 to move up and down a certain distance following the corresponding hydraulic cylinder 52.

[0030] As Figure 2 、 4 As shown in the figure, in this embodiment, the rotating component 3 includes a movable block 31. The movable block 31 is located behind the rear conveying connection frame 51. A rotating block 32 is rotatably connected above the inside of the movable block 31. The front end of the rotating block 32 is fixedly connected to the rear end of the second receiving pipe 12. A rotating coiled pipe 33 is rotatably connected inside the rotating block 32. The rear end of the rotating coiled pipe 33 is fixedly connected to an outer connecting pipe 34. The rear end of the outer connecting pipe 34 penetrates through the rear sides of the rotating block 32 and the movable block 31 and is fixedly connected to a mounting plate. An L-shaped connecting frame 35 is fixedly connected to the outer wall of the movable block 31. A first servo motor 36 is fixedly connected to the top of the L-shaped connecting frame 35. A toothed ring 37 is fixedly connected to the middle side of the outer wall of the rotating block 32. A gear 38 is meshed with the lower outer wall of the toothed ring 37. Both sides of the gear 38 are rotatably connected to the inner wall of the movable block 31 through rotating rods. The driving end of the first servo motor 36 is fixedly connected to the rotating rod on the gear 38.

[0031] During specific implementation, by starting the first servo motor 36, the first servo motor 36 drives the gear 38 connected thereto to rotate through the rotating rod. Through the cooperative setting of the gear 38 and the toothed ring 37, the rotating block 32 fixed to the inner wall of the toothed ring 37 is driven to rotate. The rotation of the rotating block 32 drives the second receiving pipe 12 and the first receiving pipe 11 to rotate. The rotation of the first receiving pipe 11 drives the water pipe 8 fixed to the first receiving pipe 11 to rotate, so that the water pipe 8 can spray the inner wall of the steel pipe all around through the provided spray holes 19.

[0032] Embodiment Two

[0033] like Figure 1 , 2 As shown, in the present embodiment, a sliding plate 21 is fixedly connected to the lower portion of the front outer wall of the movable block 31, and the front end of the sliding plate 21 passes through the interior of the rear conveying frame 51 and is slidably connected to the interior of the bottom connecting plate 7, and the top surfaces of the bottom connecting plate 7, the movable block 31 and the two conveying frames 51 are all fixedly connected to a water receiving seat 6.

[0034] During specific implementation, through the cooperation between the bottom connecting plate 7 and the sliding plate 21 provided on the bottom side of the movable block 31, the movable block 31 can cooperate with the extension and retraction of the receiving tube 1 11 and the receiving tube 2 12, and the cooling water flowing out of the steel pipe can be stored through the water receiving seat 6 for subsequent processing.

[0035] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.

[0036] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A cooling device for steel pipe after smelting, comprising a cooling box, characterized in that: The top surface of the cooling box is fixedly connected with an outer protective shell. Inside the outer protective shell, a second water pipe is fixedly connected. The bottom surface of the cooling box is fixedly connected with a bottom connecting plate. On both the front and rear sides of the cooling box, a conveying assembly is arranged. Behind the conveying assembly at the rear side, a rotating assembly is arranged. Above the interior of the cooling box, a placing round opening is formed. Inside the placing round opening, a first water pipe is arranged. The front end of the first water pipe is fixedly connected with a receiving block, and the rear end of the first water pipe is fixedly connected with a first receiving pipe. Inside the first receiving pipe, a second receiving pipe is arranged. On the opposite surfaces of the second water pipe and the first water pipe, a plurality of water spraying holes are arranged at equal intervals. On the outer wall of the top surface of the second water pipe, an outer connecting pipe two is fixedly connected. One end of the outer connecting pipe two penetrates through the top surface of the outer protective shell and is fixedly connected with an installation plate. Below the interior of the cooling box, a water storage cavity is arranged. On one side of the water storage cavity, a water discharge hole is formed.

2. The cooling device for steel pipe after smelting according to claim 1 is characterized in that: On the outer walls of the upper and lower sides of the receiving block, empty slots are arranged. Inside the empty slots, load-bearing blocks are slidably connected. On the side of the load-bearing block away from the first water pipe, an arc-shaped plate is fixedly connected. Inside both of the empty slots, springs are arranged. One end of the spring is connected to the inner side of the corresponding load-bearing block, and the other end of the spring is connected to the inner side of the corresponding empty slot.

3. The cooling device for steel pipe after smelting according to claim 1 is characterized in that: On the outer wall of the second receiving pipe, four limiting slots are arranged at equal intervals. At the rear of the inner side of the first receiving pipe, a limiting block is fixedly connected. The limiting block is slidably connected with the limiting slot.

4. The cooling device for steel pipe after smelting according to claim 1 is characterized in that: On both the front and rear sides of the cooling box, a conveying assembly is arranged. The conveying assembly includes a conveying connecting frame. Inside the upper and lower sides of the conveying connecting frame, hydraulic cylinders are installed. The driving end of the hydraulic cylinder is fixedly connected with a U-shaped connecting plate. On both sides inside the U-shaped connecting plate, transfer rods are rotatably connected. At the adjacent ends of the two transfer rods, conveying wheels are fixedly connected. On one outer wall of the lower U-shaped connecting plate, a support plate is fixedly connected. At the top end of the support plate, a second servo motor is fixedly connected. The driving end of the second servo motor is fixedly connected with one end of the corresponding transfer rod.

5. The cooling device for steel pipe after smelting according to claim 4 is characterized in that: The rotating assembly includes a movable block. The movable block is located behind the conveying connecting frame at the rear side. Inside the upper part of the movable block, a rotating block is rotatably connected. The front end of the rotating block is fixedly connected with the rear end of the second receiving pipe. Inside the rotating block, a rotating coiled pipe is rotatably connected. The rear end of the rotating coiled pipe is fixedly connected with an outer connecting pipe one. The rear end of the outer connecting pipe one penetrates through the rear sides of the rotating block and the movable block and is fixedly connected with an installation plate. On the outer wall of the movable block, an L-shaped connecting frame is fixedly connected. At the top end of the L-shaped connecting frame, a first servo motor is fixedly connected. In the middle of the outer wall of the rotating block, a toothed ring is fixedly connected. Below the outer wall of the toothed ring, a gear is meshed and connected. The two sides of the gear are rotatably connected to the inner wall of the movable block through rotating rods. The driving end of the first servo motor is fixedly connected with the rotating rod on the gear.

6. The cooling device for steel pipe after smelting according to claim 5, characterized in that: Below the front outer wall of the movable block, a sliding plate is fixedly connected. The front end of the sliding plate penetrates through the interior of the rear conveying connecting frame and is slidably connected with the interior of the bottom connecting plate.

7. The cooling device for steel pipe after smelting according to claim 6, characterized in that: On the top surfaces of the bottom connecting plate, the movable block and the two conveying connecting frames, water receiving seats are fixedly connected.