Soil body solidification and underground composite support integrated structure and construction method
By adopting integrated structure and construction methods of soil solidification and underground composite support in deep foundation pit projects in soft soil areas, combined with full-house reinforcement and implantation of engineering piles, the soil deformation and lateral direction of the enclosure structure are solved by solving the pit bottom soil deformation and the enclosure structure lateral direction of the pit bottom The problem of displacement has achieved the improvement of the stability of the foundation pit and the construction efficiency.
Patent Information
- Application Number
- CN202411193432.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-15
AI Technical Summary
In deep foundation pit projects in soft soil areas, it is difficult for the existing technology to effectively control the deformation of pit bottom soil and the lateral displacement of the enclosure structure, resulting in skirting damage and pit bottom bulge, and pit bottom reinforcement and support design are often Carry out separately, resulting in waste of resources and construction periods.
A integrated structure and construction method of soil solidification and underground composite support, including enclosure structure, reinforcement area and engineering piles. Through the full-house reinforcement of the reinforcement area and the implantation of engineering piles, an enclosure structure-reinforced soil body is formed. - The overall support system of the engineering piles reduces the embedding depth and internal support size of the enclosure structure, and reduces construction costs and construction period.
Effectively prevent kicking damage, control foundation pit deformation, improve the vertical load-bearing capacity of foundation pits, reduce soil bulge at the bottom of the pit, save construction space and reduce project cost, and achieve efficient utilization of resources.
Smart Images

Figure CN118958309A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of geotechnical engineering, and in particular to an integrated structure of soil solidification and underground composite support and a construction method. Background Art
[0002] Foundation pit engineering is a preliminary project for underground space structures. Currently, subways, shopping malls, stadiums, urban integrated pipeline corridors, municipal and other urban underground space developments involve a large number of foundation pit projects. Foundation pit engineering is developing in the direction of "deep, large and long".
[0003] There are a large number of deep and soft soil foundations distributed in coastal areas (such as the Bohai Sea Rim, the Yangtze River Delta, Fujian, and the Pearl River Delta). These soft soil foundations are mostly distributed in areas of silt, silty clay, silty sub-clay, etc., which are highly compressible, thixotropic, and low in strength when used as foundations. Therefore, for deep foundation pit projects in soft soil areas with complex environments, the foundation pit support design has shifted from strength control to deformation control. When the soil in the deep foundation pit in the soft soil area is excavated and unloaded, the ability of the soil at the bottom of the pit to resist the soil pressure outside the retaining structure is relatively small, and the silty clay below will undergo soft plastic or flow plastic deformation. The retaining structure is prone to excessive lateral displacement under the action of the pressure difference on both sides, which can easily cause problems such as kicking damage and upward bulging of the soil at the bottom of the pit, and then the soil around the foundation pit is deformed, affecting the safety of the support structure.
[0004] The two main methods used in engineering are design control and construction deformation control. The foundation pit design often uses measures such as increasing the stiffness of the supporting pile wall, deepening the wall embedding depth, enhancing the support stiffness or setting isolation piles to control the deformation of the foundation pit to meet the stability requirements. On-site construction can be handled by reinforcing the soil inside and outside the pit, zoning support and adding temporary support. Among them, reinforcing the soil at the bottom of the pit can greatly improve the properties of the soil, improve the soil's ability to resist deformation, and effectively suppress the uplift of the soil at the bottom of the pit, enhance the stability of the foundation pit support system, and create conditions for on-site construction and earth excavation.
[0005] Pit bottom reinforcement is usually used as an emergency measure. The increase in the strength of the pit bottom reinforcement soil and the strengthening effect on the pit bottom structure are not considered in the foundation pit support design, resulting in a certain degree of waste. At the same time, in the foundation engineering construction in soft soil areas, the implantation of pit bottom engineering piles can play a role in compacting and reinforcing the pit bottom reinforcement soil. However, in current projects, the two are often designed and constructed separately, which often results in a waste of resources and construction time.
[0006] At present, pit bottom reinforcement is mainly used to reinforce the soft soil layer during construction. The methods for strengthening the foundation pit soil include mixing pile method (single-axis, double-axis and three-axis mixing pile), high-pressure rotary jet grouting method, grouting method and other methods. In addition, there are also methods such as electro-osmosis chemical grouting method and extrusion grouting method that can also be used for soil reinforcement.
[0007] There are various arrangements for reinforcement of soft soil foundation. Common pit bottom reinforcement plane arrangements can be divided into: full-chamber type, skirt type, strip type and grid type. Full-chamber reinforcement is suitable for small pits, but the cost is the highest; grid / strip reinforcement is suitable for narrow and long pits, but the cost is medium; skirt reinforcement is suitable for large pits with high protection level and low cost. In terms of reinforcement effect, full-chamber reinforcement is the best, followed by grid reinforcement and skirt reinforcement, and strip reinforcement is the worst. Summary of the invention
[0008] To solve the above problems, the present invention provides an integrated construction method for soil solidification and underground composite support in soft soil areas, which can effectively prevent skirting damage and control foundation pit deformation; reduce costs by reducing the embedding depth of the retaining structure, reducing the size of the internal support, and reducing the workload of internal support installation and removal, and can free up construction space and shorten the construction period.
[0009] To achieve the above-mentioned purpose, the present invention provides an integrated structure of soil solidification and underground composite support, including a retaining structure, a reinforcement area and engineering piles, wherein the retaining structure, the reinforcement area and the engineering piles form an integrated support system of "retaining structure-reinforcement area-engineering piles";
[0010] The reinforcement area includes a first reinforcement area, a second reinforcement area and a third reinforcement area. The first reinforcement area is distributed along the outer side of the enclosure structure, and the second reinforcement area is distributed along the inner side of the enclosure structure. The third reinforcement area is located inside the second reinforcement area, and the reinforcement form of the third reinforcement area is full-hall reinforcement.
[0011] Preferably, the first reinforcement zone has a first reinforcement depth, and the first reinforcement depth is 0.6 times the foundation pit excavation depth below the pit bottom and not less than 5m below the pit bottom.
[0012] Preferably, the second reinforcement zone has a second reinforcement depth, and the second reinforcement depth is 0.6 times the foundation pit excavation depth below the pit bottom and not less than 6m below the pit bottom.
[0013] Preferably, the width of the first reinforcement area and the second reinforcement area is greater than or equal to 6m.
[0014] Preferably, the third reinforcement zone has a third reinforcement depth, and the third reinforcement depth is 0.2 to 0.4 times the foundation pit excavation depth below the pit bottom.
[0015] A construction method of the above-mentioned soil solidification and underground composite support integrated structure comprises the following steps:
[0016] S1. Excavate the guide trench. First, excavate the foundation pit to the support position, and then excavate the guide trench at the location of the support piles. The center line of the guide trench is consistent with the center line of the SMW construction method pile of the support pile construction.
[0017] S2, curing agent delivery;
[0018] S3, reinforce the third reinforcement area; after the third reinforcement area is reinforced, the engineering piles are planted by bored cast-in-place piles before the curing agent begins to set;
[0019] S4. Reinforce the first reinforcement area and the second reinforcement area, and implant support piles before the solidified soil begins to set.
[0020] The soil solidification and underground composite support integrated structure and construction method of the present invention have the following beneficial effects:
[0021] (1) The underground composite support system connects the independent engineering piles in the pit vertically and horizontally through the solidified soil reinforced at the bottom of the pit, expanding to form an underground load-bearing body, changing the vertical single load-bearing form of the previous engineering piles and giving full play to the horizontal restraint role of the soil between the piles;
[0022] (2) Pit bottom reinforcement can effectively reduce the uplift of the pit bottom soil, avoid slippage between piles and soil, and ensure the bearing capacity of engineering piles. Under normal use conditions, the overall support system of retaining structure-reinforced soil-engineering piles can improve the vertical bearing capacity and reduce the overall settlement of the pile group.
[0023] (3) The overall structure of connecting engineering piles, reinforced soil, and retaining structures can also increase its ability to resist deformation and avoid damage to the retaining structure. Compared with adding retaining structures, it does not need to increase the design size to improve the safety and stability of the foundation pit, thereby saving construction space and reducing project costs.
[0024] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a plan view of the integrated structure of soil solidification and underground composite support in the first embodiment of the present invention;
[0026] Figure 2 This is a cross-sectional view of the integrated structure of soil solidification and underground composite support in the first embodiment of the present invention;
[0027] Figure 3 The present invention is a flow chart of the soil solidification and underground composite support integrated structure construction method in Example 1 of the present invention.
[0028] Reference numerals
[0029] 1. Support piles; 2. First reinforcement area; 3. Second reinforcement area; 4. Third reinforcement area; 5. Engineering piles. DETAILED DESCRIPTION
[0030] In order to make the purpose, technical scheme and advantages disclosed in the embodiments of the present invention clearer, the embodiments of the present invention are further described in detail in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the embodiments of the present invention and are not intended to limit the embodiments of the present invention. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application. Examples of the embodiments are shown in the accompanying drawings, where the same or similar reference numerals throughout represent the same or similar elements or elements with the same or similar functions.
[0031] It should be noted that the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or server that includes a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or units that are not explicitly listed or inherent to these processes, methods, products or devices.
[0032] Like reference numerals and letters denote similar items in the following drawings, and thus, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0033] Embodiment 1
[0034] An integrated structure of soil solidification and underground composite support, such as Figures 1-2 As shown, it includes support piles 1, which are arranged at the edge of the foundation pit and serve as the foundation pit retaining structure during the foundation pit construction phase, playing the role of retaining soil and stopping water; and during the main project use phase, it also serves as the structural outer wall of the main basement and becomes a part of the main structure.
[0035] The reinforcement area includes a first reinforcement area 2, a second reinforcement area 3 and a third reinforcement area 4, and the pit bottom reinforcement form is full-floor reinforcement.
[0036] Among them, the first reinforcement area 2 (also called active reinforcement area) is distributed along the outer side of the support pile 1, and has a first reinforcement depth. The first reinforcement depth is preferably 0.6 times the excavation depth of the foundation pit below the pit bottom. If the excavation depth of the foundation pit is small, the reinforcement thickness should also be ensured to be not less than 5m below the pit bottom.
[0037] The second reinforcement zone 3 (also called passive reinforcement zone) is distributed along the inner side of the support pile 1 and has a second reinforcement depth. The second reinforcement depth should be 0.6 times the excavation depth of the foundation pit below the pit bottom. If the excavation depth of the foundation pit is small, the reinforcement thickness should also be ensured to be no less than 6m below the pit bottom.
[0038] The width of the first reinforcement area 2 and the second reinforcement area 3 should be greater than or equal to 6m, and the specific width should be determined according to the supporting piles 1 and the properties of the soil layer.
[0039] The third reinforcement area 4 is all areas inside the foundation pit except the second reinforcement area 3, and has a third reinforcement depth. The third reinforcement depth is preferably 0.2 to 0.4 times the foundation pit excavation depth below the pit bottom. Engineering piles 5 are set in the third reinforcement area 4.
[0040] The reinforcement area uses early-strength fly ash-based solidifying agent to reinforce the soil. The soil reinforced with this solidifying agent has the characteristics of early strength and stability. When the solidifying agent dosage is 10% to 20%, the soil reinforcement effect is the best and can meet the requirements of foundation pit reinforcement. The specific dosage of the solidifying agent should be determined according to the properties of the soil layer.
[0041] The soil reinforcement adopts deep mixing pile reinforcement technology. After drilling to the predetermined depth using a mixing drill, an early-strength fly ash-based curing agent is injected, the slurry is fully mixed with the soil, and after solidification, a cylindrical consolidated body is formed.
[0042] Embodiment 2
[0043] A soil solidification and underground composite support integrated construction method, the process is as follows Figure 3 As shown, the following steps are included:
[0044] S1. The site is level.
[0045] S2. Measurement and layout.
[0046] S3. Dig a guide ditch.
[0047] First, the foundation pit is excavated to the support position, and then the guide ditch is excavated at the location of the designed support pile 1. The center line of the guide ditch is consistent with the center line of the designed SMW method pile.
[0048] After the excavation of the guide trench is completed, two positioning steels are placed in the direction perpendicular to the trench and parallel to the trench respectively. The length and cross-sectional side length of the positioning steels should be determined according to the length and width of the foundation pit. The longitudinal and transverse steels should be fixed by spot welding. The steel at the corner should be inserted with the web aligned with the angle bisector on the angle between the two side lines.
[0049] S4. Equipment is in place. The equipment includes three-shaft mixer, pile drilling rig, aggregate hopper, mortar mixer, mortar pump, etc.
[0050] S5. Delivery of curing agent. Choose an early-strength curing agent and follow the principle of mixing and using. During the mixing process, it is necessary to ensure that the mixing is uniform and there are no lumps. If the curing agent begins to solidify after mixing, it cannot be used.
[0051] When the curing agent is used, the mixer needs to sink to the bottom of the designed reinforcement depth to start spraying reinforcement. When the mixer is stirring and lifting, the bottom of the designed reinforcement depth needs to be continuously sprayed for 30 seconds, then it is lifted to the predetermined slurry stopping surface while stirring, and the top of the designed reinforcement depth needs to be continuously sprayed for 30 seconds.
[0052] The reverse rotation is carried out while the grouting is being carried out, and the lifting speed is about 0.3m / min-0.5m / min, and when grouting is being carried out, the grouting amount must be ensured to be uniform. When the mixer completes the reinforcement of the designed depth, the mixer should be sunk to the bottom of the designed depth again, and the mixing and lifting should be carried out again to ensure the construction quality.
[0053] The mixer is in place and is mixing, sinking and lifting. During this process, the prepared cement slurry needs to be continuously injected, and it must be ensured that the sinking rate of the drilling rig is no more than 1m / min, and the lifting rate is no more than 2m / min.
[0054] S6, reinforce the third reinforcement area 4, the location of the third reinforcement area 4 is as follows Figure 2 The initial setting time of the solidified soil is 250-285 minutes, and the final setting time of the solidified soil is 415-455 minutes. The setting time will be shortened as the amount of curing agent added increases.
[0055] After the third reinforcement area 4 is reinforced, before the curing agent initially sets, the engineering piles 5 are implanted in the corresponding positions by means of bored cast-in-place piles.
[0056] S7, reinforce the first reinforcement area 2 and the second reinforcement area 3. The initial setting time of the solidified soil is 250-285 minutes, and the final setting time of the solidified soil is 415-455 minutes. The setting time will be shortened as the amount of curing agent added increases.
[0057] After the first reinforcement area 2 and the second reinforcement area 3 are reinforced, the support piles 1 are implanted in the corresponding positions before the solidified soil is initially set. The implantation of the support piles 1 is carried out by SMW (soil-cement mixing pile) construction method.
[0058] Since the reinforcement area is constructed first, the soil in the first reinforcement area 2 and the second reinforcement area 3 forms a close connection with the surrounding structure, which has an integrated feature. Therefore, the required embedding depth of the support pile 1 can be reduced by about 20% compared with the embedding depth required by the traditional construction method, and the construction difficulty is reduced.
[0059] After the supporting piles 1 are implanted, internal supports are erected between the supporting piles 1 on both sides. Since the soil in the foundation pit has been reinforced at this time, the corresponding internal support structure is also reduced, thereby reducing the construction cost; at the same time, the workload of dismantling the internal support is reduced, thereby achieving the effect of freeing up construction space and shortening the construction period.
[0060] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.
Claims
1. A soil solidification and underground composite support integrated structure, characterized in that: It includes the retaining structure, reinforcement area and engineering piles, which form an integrated support system of "retaining structure-reinforcement area-engineering piles"; The reinforcement area includes a first reinforcement area, a second reinforcement area and a third reinforcement area. The first reinforcement area is distributed along the outer side of the enclosure structure, and the second reinforcement area is distributed along the inner side of the enclosure structure. The third reinforcement area is located inside the second reinforcement area, and the reinforcement form of the third reinforcement area is full-hall reinforcement.
2. The soil solidification and underground composite support integrated structure according to claim 1, characterized in that: The first reinforcement area has a first reinforcement depth, which is 0.6 times the foundation pit excavation depth below the pit bottom and is not less than 5m below the pit bottom.
3. The soil solidification and underground composite support integrated structure according to claim 1, characterized in that: The second reinforcement area has a second reinforcement depth, which is 0.6 times the foundation pit excavation depth below the pit bottom and is not less than 6m below the pit bottom.
4. The soil solidification and underground composite support integrated structure according to claim 1, characterized in that: The width of the first reinforcement area and the second reinforcement area is greater than or equal to 6m.
5. The soil solidification and underground composite support integrated structure according to claim 1, characterized in that: The third reinforcement area has a third reinforcement depth, and the third reinforcement depth is 0.2 to 0.4 times the foundation pit excavation depth below the pit bottom.
6. A construction method for the soil solidification and underground composite support integrated structure according to any one of claims 1 to 5, characterized in that: The steps include: S1. Excavate the guide trench. First, excavate the foundation pit to the support position, and then excavate the guide trench at the location of the support piles. The center line of the guide trench is consistent with the center line of the SMW construction method pile of the support pile construction. S2, curing agent delivery; S3, reinforce the third reinforcement area; after the third reinforcement area is reinforced, the engineering piles are planted by bored cast-in-place piles before the curing agent initially sets; S4. Reinforce the first reinforcement area and the second reinforcement area, and implant support piles before the solidified soil begins to set.
7. The construction method of the soil solidification and underground composite support integrated structure according to claim 6, characterized in that: In step S1, after the guide trench is excavated, positioning steel is set at the reserved position of the support pile, and is removed before the support pile is planted in step S4.
Citation Information
Cited By
Permanent supporting structure capable of reducing built-in depth and enhancing foundation rigidity and construction method
CN122466858A
Permanent support structure with reduced embedment depth and increased foundation stiffness and method of construction
CN122466858B