Method for improving stability of chip test process on automatic test equipment

By positioning and adjusting the test conditions between test items on the automated test equipment, the problem of unstable chip test program flow is solved, and higher test stability and production efficiency are achieved, reducing costs and downtime.

CN119001404APending Publication Date: 2024-11-22CCID IND & INFORMATION TECH RES INST GRP (SUZHOU) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411125865.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-22

AI Technical Summary

Technical Problem

On automated testing equipment, the unstable chip test program flow leads to test failures and increased production costs, and the existing technology has failed to effectively solve this problem.

Method used

By setting the test items and their corresponding test conditions, perform functional tests on the chip, locate unstable test items, find out the conditions of the previous test item according to the order of the test program flow, and apply it to the unstable test items, and gradually check it And add the conditions affecting the test until the chip test program flow passes stably.

Benefits of technology

It improves the stability of the test program, shortens the development and debugging cycle, saves test time and cost, improves chip yield and production capacity, and reduces downtime.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119001404A_ABST
    Figure CN119001404A_ABST
Patent Text Reader

Abstract

The invention discloses a method for improving the stability of a chip testing process on automatic testing equipment, and belongs to the technical field of chip testing. Comprising the following steps: positioning an unstable test item Test Item (N), and finding out a previous test item Test Item (N-1) of the unstable test item according to an execution sequence of a test program flow; all test conditions of Test Item (N-1) are applied to test conditions of Test Item (N), and the whole test program process is executed again; the added test conditions are checked, and the test conditions influencing Test Item (N) are found; test conditions influencing the Test Item (N) are newly added in the test conditions of the Test Item (N); and the chip test program flow is passed. Compared with the prior art, the method has the advantages that after the signal pins with unstable connection states among the test items are found out, the states of the signal pins are set, so that the test items are tested after the chip stably enters the states, and the stability of a test program flow can be effectively improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of chip testing technology, and more specifically, to a method for improving the stability of a chip testing process on automated testing equipment. Background Art

[0002] Before semiconductor integrated circuits (wafers or ICs, chips for short) enter large-scale mass production testing, they usually need to go through a series of development steps to ensure the feasibility, functionality and reliability of the design. Among them, chip test program development, that is, writing test programs for automated test equipment (ATE for short), is an indispensable step. The stability of the test program flow is of great significance to the subsequent chip mass production: verifying the accuracy of chip functions, improving production efficiency, ensuring chip quality, reducing production costs, enhancing customer confidence, etc.

[0003] However, during the ATE test program development phase or the early mass production introduction phase, the test flow of the test program is often unstable, that is, the test flow test instability phenomenon of all ATE sites is exactly the same, that is, in the same test item, sometimes the test passes, sometimes the test fails. For example, for the same chip, when ATE executes a certain test item alone, it passes stably, but when executing the entire test flow, the test will be unstable (sometimes Pass, sometimes Fail), and the unstable test flow will cause the chip test program development cycle to be delayed or even the failure of the entire development project. If the program with unstable test flow is delivered for mass production, it may lead to an increase in test time cost and a decrease in yield, which directly affects the ATE utilization rate (Overall Equipment Effectiveness, referred to as OEE), and then affects production capacity.

[0004] At present, the current practice is usually to add a fail loop to unstable test items in the program flow during the test program development phase, or even add a fail loop to multiple test items together. The fail loop in chip testing refers to the process in which some chips need to be tested repeatedly due to test failures during the test process. In the early mass production introduction stage, the number of retests of defective chips will increase. However, both methods are only temporary solutions and will greatly increase the time cost of chip testing. They cannot even completely solve the abnormality of unstable program test flow, resulting in low product yield.

[0005] In the related art, for example, Chinese patent CN104237766A provides a chip testing method and device, wherein the method includes performing a first wafer-level test on the chip; if the first wafer-level test passes, writing a first identification information indicating that the first wafer-level test passes at a first designated position of the flash memory module of the chip; reading the first identification information, performing a second wafer-level test, if the second wafer-level test passes, writing a second identification information at a second designated position of the flash memory module of the chip; reading the second identification information, performing a finished product-level test, if the finished product-level test passes, writing a third identification information indicating that the finished product-level test passes at a third designated position of the flash memory module of the chip; reading the third identification information, and performing a warehouse-out test. The shortcoming of this scheme is that it does not propose a solution in the event of unstable testing.

[0006] It can be seen from the above that the relevant technology does not provide any technical inspiration on how to improve the stability of the test program process. Summary of the invention

[0007] 1. Technical issues to be solved

[0008] In response to the problem in the prior art of how to improve the stability of the test program flow when unstable situations occur during chip testing, the present invention provides a method for improving the stability of the chip test flow on an automated testing device, which can find out the signal pins with unstable connection states between test items and then set their states, so that the chip can enter a stable state before performing test item testing, thereby effectively improving the stability of the test program flow.

[0009] 2. Technical solution

[0010] The purpose of the present invention is achieved through the following technical solutions.

[0011] A method for improving the stability of a chip test process on an automated test device comprises the following steps: setting test items and test conditions corresponding to each test item, and performing functional tests on all functions of a chip; locating an unstable test item Test Item (N), and finding the previous test item Test Item (N-1) of the unstable test item according to the execution order of a test program flow; applying all test conditions of Test Item (N-1) to the test conditions of Test Item (N), and executing the entire test program flow again; checking the added test conditions to find the test conditions that affect Test Item (N); adding the test conditions that affect Test Item (N) to the test conditions of Test Item (N); until the chip test program flow passes.

[0012] Furthermore, a test condition is a test parameter or a collection of multiple test parameters in a test item.

[0013] Furthermore, all the test conditions of Test Item (N-1) are added to the test conditions of Test Item (N), and the entire test procedure flow is executed again;

[0014] If the test program flow passes, the execution status of Test Item (N) is stable;

[0015] The added test conditions are checked to find the test conditions that affect Test Item (N) among all the test conditions of the added Test Item (N-1).

[0016] Furthermore, the steps of adding all the test conditions of Test Item (N-1) to the test conditions of Test Item (N) and executing the entire test program flow again are specifically as follows:

[0017] Add the codes corresponding to all the test conditions of Test Item (N-1) before the test conditions in Test Item (N), and then execute the entire test program flow to obtain new test results.

[0018] Furthermore, the steps to troubleshoot the added test conditions to find the test conditions that affect Test Item (N) are as follows:

[0019] In Test Item (N), each test condition in all the test conditions of the added Test Item (N-1) is set one by one and the entire test program flow is executed until the test condition that affects the stability of Test Item (N) in all the test conditions of the added Test Item (N-1) is found.

[0020] Furthermore, the test conditions that affect the stability of Test Item (N) refer to the test conditions that enable Test Item (N) to pass when executing the entire test program flow.

[0021] Furthermore, the troubleshooting process is: all the test conditions of Test Item (N-1) are added one by one to the test conditions of TestItem (N), and then the entire test program flow is executed until the test program flow passes.

[0022] Furthermore, the troubleshooting process is: add all the test conditions of Test Item (N-1) to the test conditions of Test Item (N), then delete the added test conditions one by one, and execute the entire test program flow at the same time until the test program flow passes.

[0023] Furthermore, adding the test condition of Test Item (N-1) to the test condition of Test Item (N) means setting the state of each pin in the added test condition.

[0024] Furthermore, the method for improving the stability of the chip testing process on the automated testing equipment also includes: applying the test conditions of Test Item (N-1) to the test conditions of Test Item (N), and then executing the entire test program flow; if the test program flow fails, applying the test conditions of the previous test item Test Item (N-2) of the previous test item to the test conditions of Test Item (N), and then executing the entire test program flow.

[0025] 3. Beneficial effects

[0026] Compared with the prior art, the advantages of the present invention are: it can solve the problem of unstable chip test flow and improve the stability of the test program; it can greatly shorten the program development and debugging cycle in the test program development stage; it can save test time costs in the early mass production introduction stage and improve the chip test yield. The high stability of the test program Test Flow means that ATE can run efficiently, reducing downtime (Machine Down) time, thereby effectively improving production capacity. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 A schematic flow chart of a method for improving the stability of a chip testing process on an automated testing device in one embodiment of the present invention;

[0028] Figure 2 Another flowchart of a method for improving chip testing process stability on automated testing equipment according to an embodiment of the present invention is shown. DETAILED DESCRIPTION

[0029] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0030] like Figure 1 to Figure 2 As shown, a method for improving the stability of a chip test process on an automated test device of the present invention comprises the following steps:

[0031] Set test items and the test conditions corresponding to each test item to perform functional tests on all functions of the chip;

[0032] Locate the unstable test item and find the previous test item of the unstable test item according to the execution order of the test program flow;

[0033] Before applying all the test conditions of the previous test item of the unstable test item to the test conditions in the unstable test item, executing the entire test program flow again;

[0034] Check the added test conditions to find the test conditions that affect unstable test items;

[0035] In the test conditions of unstable test items, add test conditions that affect unstable test items;

[0036] Ultimately, the unstable test items make the chip test program flow pass stably after adding test conditions, and the test items are tested after the chip enters a stable state, thereby improving the stability of the test program flow.

[0037] In chip testing, it is common to encounter unstable test program flow, which means that when each test item is executed separately, the test program flow can pass; but when the entire test program flow is executed, it cannot pass stably, that is, a test item or multiple test items sometimes pass and sometimes fail (fail) during the execution of the entire test program flow. Such a situation indicates that the test program flow is an unstable test program flow, and the test item or multiple test items are unstable test items.

[0038] In a specific embodiment, the steps of the method for improving the stability of the chip testing process on the automated testing equipment are as follows:

[0039] S1. Prepare the chip to be tested, set several test items and the test conditions corresponding to each test item, and perform functional testing on the chip;

[0040] The ATE executes the test flow to perform functional testing on the chip. In a specific scenario, the ATE referred to here refers to an automated testing equipment and is not a limitation.

[0041] Specifically, after the test is completed, ATE will output a Datalog to display the test results. Datalog is a data query language used to record test results. The Datalog file contains specific information about the test results, such as yield, test time, etc. By analyzing these data, it is decided whether to enter the mass production stage.

[0042] In a specific embodiment, the following situation often occurs during the test process: for the same chip, when a certain test item is executed alone, it passes stably, but when the entire test flow is executed, it sometimes passes and sometimes fails, that is, the test is unstable, and the unstable test fails are all in the same test item. At this time, the test item is located as an unstable test item.

[0043] Among them, in chip testing, Pass and Fail refer to two states of test results, representing test passing and test failing respectively.

[0044] S2. When test instability occurs during the execution of the test program flow, the automated test equipment locates the unstable test item and finds the previous test item of the unstable test item according to the execution order of the test program flow.

[0045] In a specific embodiment, the unstable test item is named "Test Item (N)", and the previous test item of the unstable test item Test Item (N) is found according to the test flow execution order and named "Test Item (N-1)".

[0046] S3. Apply the test conditions of the previous test item Test Item (N-1) of the unstable test item to the test conditions of the unstable test item Test Item (N), and execute the entire test program flow again. If the test program flow passes at this time, it means that the execution status of Test Item (N) is stable, which means that the unstable test is affected by the status of a pin of TestItem (N-1).

[0047] In a specific embodiment, since the test process is executed in the order of the test program flow, when the execution state is unstable, the unstable test item Test Item (N) is usually affected by the state of the previous test item TestItem (N-1); however, it may also be affected by the pin state of the previous test item. At this time, the same method is used to find the test conditions that affect the execution state of Test Item (N), that is, the test conditions of the previous test item of the previous test item, such as Test Item (N-2), are applied to the test conditions of the unstable test item Test Item (N), and then the entire test program flow is executed. At this time, if the execution state of Test Item (N) is stable, it means that the test instability is affected by the state of a pin of Test Item (N-2). In addition, if the instability is excluded from the situation that it is affected by the previous test item, it is affected by the hardware state of the ATE test machine. At this time, the hardware is replaced, such as changing the machine test to achieve a stable execution state.

[0048] Specifically, applying the test conditions of the previous test item Test Item (N-1) of the unstable test item to the test conditions of the unstable test item Test Item (N) means: applying the test condition voltage Level (N-1) and timing Timing (N-1) of Test Item (N-1) to the test conditions of Test Item (N) to configure the chip pin status.

[0049] Execute the entire test program flow again to get a new test result. Determine whether the current Test Item (N) can stably pass. If it can stably pass, it means that it is affected by the state of a chip digital pin IO Pin of the previous test item Test Item (N-1).

[0050] More specifically, the test conditions of the previous test item Test Item (N-1) of the unstable test item are applied to the test conditions of the unstable test item Test Item (N) by adding the codes corresponding to the test conditions Level (N-1) and Timing (N-1) of Test Item (N-1) before the original test conditions in Test Item (N), and then executing the entire Test flow to obtain new test results.

[0051] Among them, Level refers to the voltage applied by ATE to the chip pins (including power pins and digital IO pins). During the chip testing process, the Level in the test conditions is crucial to ensure the normal operation and functional testing of the chip; Level (N-1) is the test voltage condition of the test item Test Item (N-1). In chip testing, Timing in the test conditions refers to the test timing. Timing in chip testing involves the timing and timing control of test signals, which mainly refers to the timing setting of test signals. Specifically, Timing refers to the signal waveform output from the ATE Test Head (test head) after the input signal is created by the data combination provided by various areas of the test system. This timing setting is crucial to ensure the accuracy and efficiency of chip functional testing; Timing (N-1) is the test timing condition of the test item Test Item (N-1). IO Pin refers to the input / output pins on the chip, which can also be called digital pins. These pins are connected to the digital channels of the ATE test machine digital board module (PPMU) via the probe card peripheral circuit to realize the data input and output functions. Usually, before a chip is functionally tested, it is necessary to put the chip into a specific state (Enter Mode) and then perform the functional test. The correct IO Pin state is crucial to ensure the test stability of the chip.

[0052] S4. In the unstable test items, each test condition in all the test conditions of the added Test Item (N-1) is set one by one and the entire test program flow is executed until the test condition that affects the stability of Test Item (N) in all the test conditions of the added Test Item (N-1) is found.

[0053] Specifically, the status of each pin in the test condition of the added Test Item (N-1) is set one by one and the entire test program flow is checked until the test condition that can ensure that Test Item (N) can pass when executing the entire test program flow is found.

[0054] Specifically, in unstable test items, the level state and timing state of each signal pin in Level (N-1) and Timing (N-1) are set one by one and the entire test program flow is executed for troubleshooting until it is found that it is affected by the timing state of one or several signal pins. For example, it is necessary to keep the timing waveform of a certain IO pin unchanged before correctly entering the test state of the next test item.

[0055] In a specific embodiment, in the unstable test item Test Item (N), the level state and timing state of each IO Pin in Level (N-1) and Timing (N-1) are set one by one and the entire test program flow is checked until it is found that the timing state of one or several IO Pins needs to be maintained first, for example: the Timing waveform of a certain IO needs to be maintained unchanged in order to correctly enter the state of the next test item. That is, after determining in S3 that the unstable test item TestItem (N) is affected by the state of a certain IO Pin of the previous test item Test Item (N-1), the test conditions of the previous test item Test Item (N-1) added are checked until the test condition that plays an influential role in ensuring that the unstable test item can pass stably when executing the entire test program flow is found.

[0056] Specifically, the troubleshooting can be performed by adding the test conditions of the previous test item Test Item (N-1) one by one before the test conditions in the unstable test item Test Item (N); or it can be performed by adding the test conditions of the previous test item Test Item (N-1) before the test conditions in the unstable test item Test Item (N), and then deleting the added IO pin states (Level or Timing) one by one and performing test screening to find the test condition in the test condition that can ensure that the unstable test item can pass stably when executing the entire test program flow.

[0057] In a specific embodiment, for example, the state of IO Pin "RX" in the test item TestItem(N-1) is: Waveformat = NRZ, test frequency = 10Mhz; after the test item TestItem(N-1) is finished, before entering the test item TestItem(N) with a test frequency f = 2MHz, it is necessary to pre-set the Timing state of TestItem(N-1) to: initial (default) state DefaultState = Z (High-Z high impedance state), Waveformat = NRZ, frequency = 10Mh, so that the entire Testflow can pass stably. Thus, it is confirmed that the state of IO Pin "RX": Waveformat = NRZ (Non Return to Zero), frequency = 10Mhz plays a role in affecting the test stability in the test conditions of the test item TestItem(N).

[0058] Among them, RX is the pin name; Waveformat = NRZ means that the input signal format used in chip testing is non-return-to-zero encoding (NRZ), indicating that the use of NRZ encoding in chip test timing means that the transmission of the test signal does not rely on returning to the zero level to define the boundary of the Timing time edge, but is consistent with the input vector data from the beginning (T0) to the end (T0) of each cycle, thereby achieving the maintenance of the vector signal, and frequency = 10Mhz means the frequency is 10 megahertz.

[0059] S5. Add test conditions that affect Test Item (N) to the test conditions of unstable test items.

[0060] Specifically, in the test conditions of Test Item (N), a signal pin preset state condition is added to enable the pin states between the unstable test item Test Item (N) and the previous test item Test Item (N-1) of the unstable test item to be correctly connected, thereby allowing the chip to enter a correct working state suitable for the functional test of Test Item (N). Such chip pin state setting can effectively solve the problem of unstable chip test program flow.

[0061] In a specific embodiment, after obtaining the test conditions that affect the unstable test item Test Item (N) through investigation in S4, an IO Pin preset state condition is added to the test conditions of Test Item (N), that is, the test conditions that affect Test Item (N) obtained through investigation in S4, so that the states of the pins between the test item Test Item (N-1) and the test item TestItem (N) can be correctly connected, so that the chip can enter the correct working state suitable for functional testing of Test Item (N), thereby solving the problem of unstable test program flow.

[0062] For example: the state of IO Pin "RX" in the test item Test Item (N) is frequency = 2Mhz; the state of IO Pin "RX" in the test item TestItem (N-1) is Waveformat = NRZ, frequency = 10Mhz; in the test conditions of the unstable test item Test Item (N), a new IO Pin preset state condition is added, that is, the state of IO Pin "RX" is Waveformat = NRZ, frequency = 10Mhz, so that the state of pin RX between the test item Test Item (N-1) and the test item Test Item (N) can be correctly connected.

[0063] Another example: the test item "POWER_ON_RESET_Func" is unstable during the test. Through step S3, it is confirmed that it is affected by the timing of the previous test item. Then through step S4, the voltage and timing status of each pin is verified and checked, and finally it is confirmed that the test item "POWER_ON_RESET_Func" is affected by the timing (Timing) of the pin "RX". Therefore, by adding a preset state condition to set the timing Timing state of RX (frequency, signal waveform format, sampling time point) before the test condition of the test item "POWER_ON_RESET_Func", and then running the Test flow, the preset state condition will be executed first during the running process, and then the test condition of the test item "POWER_ON_RESET_Func" itself (applying pin voltage Level, timing waveform Timing) will be executed, and the test result is stable, and the abnormal situation is successfully eliminated.

[0064] like Figure 2 As shown, the method for improving the stability of the chip testing process on the automated testing equipment includes:

[0065] S10, perform functional testing on the chip to be tested and execute the test program flow.

[0066] S20, determining whether the test program flow can be stably passed when being executed;

[0067] If it can pass stably, the process ends;

[0068] If it cannot be passed stably, continue to execute S30.

[0069] S30, locate the unstable test item Test Item (N), and find the previous test item Test Item (N-1) before the unstable test item according to the execution order of the test program flow, apply the test conditions of the previous test item TestItem (N-1) of the unstable test item to the test conditions of the unstable test item Test Item (N), and then execute the entire test program flow.

[0070] S40, determining whether the test program flow can be stably passed when being executed;

[0071] If it can pass stably, continue to execute S50;

[0072] If it cannot pass stably, Test Item (N-1) is replaced with the previous test item Test Item (N-2) of Test Item (N-1) and S30 is executed.

[0073] S50. In the unstable test item Test Item (N), the status of each pin in the test condition of the previous test item Test Item (N-1) added is set one by one and the entire test program flow is checked until the test condition is found that can have an impact on ensuring that the unstable test item Test Item (N) can pass stably when executing the test program flow.

[0074] Specifically, in step S20, whether the test program flow can be stably passed can be determined by LoopTest x50 times.

[0075] Loop Test x50 (loopback test) in chip testing is a method to verify chip performance and stability by repeating loopback tests. Specifically, the loopback test verifies the chip's loopback function by sending test data packets to the chip and then checking whether these data packets can be correctly returned from the chip's receiving circuit. If the chip supports loopback testing and the test passes, it means that the chip's receiving circuit and logic functions are normal. Loop Test x50 refers to performing 50 repeated loopback tests. The purpose of this repeated test is to increase the reliability and accuracy of the test. By repeating the test multiple times, the performance stability of the chip under long-term use or high load conditions can be better evaluated.

[0076] The method for improving the stability of the chip test flow on the automated test equipment of the present invention can completely solve the problem of instability of most chip test flows and improve the stability of the test program. In the test program development stage, the program development and debugging cycle can be greatly shortened; in the early mass production introduction stage, the test time cost is saved and the chip test yield rate is improved. The high stability of the test program Test Flow means that ATE can run efficiently, reducing the downtime (Machine Down) time, thereby effectively improving the production capacity.

[0077] The above schematically describes the invention and its implementation methods, which is not restrictive. Without departing from the spirit or basic features of the invention, the invention can be implemented in other specific forms. What is shown in the accompanying drawings is only one of the implementation methods of the invention. The actual structure is not limited to this, and any figure mark in the claims should not limit the claims involved. Therefore, if a person of ordinary skill in the art is inspired by it, without departing from the purpose of the invention, a structural method and an embodiment similar to the technical solution are designed without creativity, which should all fall within the scope of protection of this patent. In addition, the word "including" does not exclude other elements or steps, and the word "one" before the element does not exclude the inclusion of "multiple" elements. The multiple elements stated in the product claim can also be implemented by one element through software or hardware. The words first, second, etc. are used to indicate names, and do not indicate any specific order.

Claims

1. A method for improving the stability of a chip test process on an automated test device, comprising the following steps: Set test items and test conditions corresponding to each test item to perform functional tests on all functions of the chip; Locate the unstable test item Test Item (N), and find the previous test item Test Item (N-1) of the unstable test item according to the execution order of the test program flow; Apply all the test conditions of Test Item (N-1) to the test conditions of Test Item (N) and execute the entire test procedure flow again; Check the added test conditions to find the test conditions that affect Test Item (N); Add test conditions that affect Test Item(N) to the test conditions of Test Item(N); Until the chip test program flow passes.

2. The method for improving the stability of chip testing process on automated testing equipment according to claim 1, characterized in that: A test condition is a test parameter or a collection of multiple test parameters in a test item.

3. The method for improving the stability of chip testing process on automated testing equipment according to claim 1, characterized in that: Add all the test conditions of Test Item (N-1) to the test conditions of Test Item (N) and execute the entire test procedure flow again; If the test program flow passes, the execution status of Test Item (N) is stable; The added test conditions are checked to find the test conditions that affect TestItem(N) among all the test conditions of the added Test Item(N-1).

4. The method for improving the stability of chip testing process on automated testing equipment according to claim 1 or 3, characterized in that: in, Add all the test conditions of Test Item (N-1) to the test conditions of Test Item (N) and execute the entire test program flow again. The specific steps are: Add the codes corresponding to all the test conditions of Test Item (N-1) before the test conditions in Test Item (N), and then execute the entire test program flow to obtain new test results.

5. The method for improving the stability of chip testing process on automated testing equipment according to claim 1, characterized in that: The steps to troubleshoot the added test conditions to find the test conditions that affect Test Item (N) are as follows: In Test Item (N), each test condition in all the test conditions of the added Test Item (N-1) is set one by one and the entire test program flow is executed until the test condition that affects the stability of Test Item (N) in all the test conditions of the added Test Item (N-1) is found.

6. The method for improving the stability of chip testing process on automated testing equipment according to claim 5, characterized in that: The test conditions that affect the stability of Test Item (N) refer to the test conditions that enable Test Item (N) to pass when executing the entire test program flow.

7. The method for improving the stability of chip testing process on automated testing equipment according to claim 5, characterized in that: The troubleshooting process is: add all the test conditions of Test Item (N-1) one by one to the test conditions of Test Item (N), and then execute the entire test program flow until the test program flow passes.

8. The method for improving the stability of chip testing process on automated testing equipment according to claim 5, characterized in that: The troubleshooting process is: add all the test conditions of Test Item (N-1) to the test conditions of Test Item (N), then delete the added test conditions one by one, and execute the entire test program flow at the same time until the test program flow passes.

9. The method for improving the stability of chip testing process on automated testing equipment according to claim 5, characterized in that: Adding the test conditions of Test Item (N-1) to the test conditions of Test Item (N) means setting the status of each pin in the added test conditions.

10. The method for improving the stability of chip testing process on automated testing equipment according to claim 1, characterized in that: The method for improving the stability of the chip testing process on the automated testing equipment also includes: Apply the test conditions of Test Item (N-1) to the test conditions of Test Item (N), and then execute the entire test procedure flow; If the test program flow fails, the test conditions of the previous test item Test Item (N-2) of the previous test item are applied to the test conditions of Test Item (N), and then the entire test program flow is executed.