Double-hole tunnel shield tunneling construction simulation method based on BIM (Building Information Modeling) and digital twinning

By using BIM and digital twin technology in the tunnel shield machine excavation monitoring system, a three-dimensional model is established and digitally driven simulation is carried out, and the shortcomings of the existing system in three-dimensional visualization and progress planning display are solved, and efficient tunnel shield machine excavation construction management is achieved.

CN120145526APending Publication Date: 2025-06-13CHINA CIVIL ENG CONSTR CORP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202510298146.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2025-03-13
Publication Date
2025-06-13

AI Technical Summary

Technical Problem

The existing tunnel shield machine excavation monitoring system has poor three-dimensional visualization effect, cannot perform virtual simulation, cannot display pipe segments, formation modules, progress plans and actual progress using digital drive methods, and cannot accurately reflect the installation location and progress of each pipe segment.

Method used

A two-hole tunnel shield excavation construction simulation method based on BIM and digital twins is adopted to establish a three-dimensional model of a two-hole tunnel project, including a tunnel project model, a shield machine model, a prefabricated pipe segment model and a geological profile model. The shield excavation is simulated through digital-driven interactive software, and the progress plan and actual progress are interactively driven.

Benefits of technology

The visual display of pipe segments, geological profiles, progress plans and actual progress is realized, which accurately reflects the installation location and progress of each pipe segment, and reflects the tunnel shield machine excavation progress plan in vivid and intuitively, improving construction efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN120145526A_ABST
    Figure CN120145526A_ABST
Patent Text Reader

Abstract

The invention provides a double-hole tunnel shield tunneling construction simulation method based on BIM and digital twinning, and the method comprises the steps: building a double-hole tunnel BIM model, and importing the BIM model into a monitoring system platform; real-time tunneling physical data of the shield tunneling machine are imported into a monitoring system platform; the physical and mechanical data of the entity shield tunneling machine are endowed to the shield tunneling machine model, and dynamics simulation is carried out; linear engineering three-dimensional visual expression and display of double-hole tunnel shield tunneling construction are realized; and compiling a double-hole tunnel shield tunneling three-dimensional visual digital driving progress plan, and interactively displaying the construction progress plan by using a monitoring system platform. A three-dimensional model is established for a double-hole tunnel engineering project, a shield tunneling machine, a geological section and a duct piece by adopting digital technologies such as BIM and digital twinning, shield tunneling is simulated by adopting digital driving interaction software, a progress plan and an actual progress are interactively driven, the duct piece, the geological section, the progress plan and the actual progress are visually displayed, and the construction efficiency is improved. And the shield tunneling construction efficiency of the double-hole tunnel can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of shield tunneling construction simulation and visualization display for double-hole tunnels. Specifically, it relates to a method for simulating shield tunneling construction of double-hole tunnels based on BIM and digital twin. Background Art

[0002] With the advancement of large-scale infrastructure construction in China, the construction technology of tunnel shield machines has developed rapidly in the country. As the core technology of tunnel shield machine construction, the shield machine monitoring system has also developed rapidly. Various production manufacturers, application units, and research institutions have continuously developed various monitoring systems, with increasing automation and intelligence, including tunnel construction video monitoring systems, tunnel construction personnel positioning systems, tunnel emergency telephone systems, tunnel construction gas detection systems, tunnel entrance LED large screen display systems, shield machine construction safety management systems, etc. The shield machine monitoring system can call the real-time operation data of the shield machine, collect data such as earth pressure, displacement, thrust, oil pressure, stroke, and grouting, and can provide real-time feedback on the tunneling attitude, the state of the screw conveyor, and articulated data, enabling an intuitive understanding of the operation status of the shield machine.

[0003] With the development and popularization of the application of BIM technology, BIM technology has also been developed and applied in the shield monitoring system, such as the current tunnel shield machine tunneling monitoring system. This tunnel shield machine tunneling monitoring system has shown an intuitive and vivid effect, improving the on-site work efficiency, ensuring the accuracy of project data, reducing project expenses, and at the same time providing real-time risk alarms for the project site, real-time monitoring of the engineering safety quality and progress, effectively enhancing the project management ability.

[0004] The current tunnel shield machine tunneling monitoring system is based on a technical route for monitoring physical and mechanical properties. Sensors with various physical parameter properties are installed on the shield machine. The data collected by these sensors are transmitted to the monitoring system through 4G / 5G networks. The changes in physical data can be viewed in real time through the monitoring system dashboard, providing a basis for the tunneling progress, positioning, and safety of the shield machine.

[0005] However, while the existing tunnel shield machine tunneling monitoring system has the above-mentioned functional advantages, it also has the following disadvantages and deficiencies: The three-dimensional visualization effect is not good. It is not possible to perform virtual simulation on the shield machine, and it is not possible to display segments, formation modules, progress plans, and actual progress using digital driving methods. It is not possible to accurately reflect the installation position and progress of each segment, and it is not possible to vividly and intuitively reflect the tunneling progress plan of the tunnel shield machine. Summary of the Invention

[0006] In view of this, the purpose of the present invention is to develop a new shield tunneling simulation and three-dimensional visualization digital driving method applied to the monitoring system for shield tunneling construction of double-hole tunnels. Based on digital technologies such as BIM and digital twin, a monitoring system platform for shield tunneling of double-hole tunnels is built. Three-dimensional models are established for double-hole tunnel engineering projects, shield machines, formation structures (geological profiles), segment linings, etc. A digital driving interactive software is used to simulate shield tunneling, and interactive driving is carried out for the progress plan and actual progress, so as to make up for the deficiencies of the current tunnel shield machine tunneling monitoring system, visually display segment linings, geological profiles, progress plans and actual progress, accurately reflect the installation position and progress of each segment lining, and vividly and intuitively reflect the shield tunneling progress plan of the tunnel, so as to improve the construction efficiency of shield tunneling of double-hole tunnels.

[0007] The present invention provides a method for simulating shield tunneling construction of double-hole tunnels based on BIM and digital twin, including the following steps: S1. Establish a BIM model of the double-hole tunnels of the double-hole tunnel engineering project, and import the BIM model of the double-hole tunnels into the monitoring system platform; the BIM double-hole tunnel model includes the following modules: tunnel engineering project model, shield machine model, precast segment model, geological profile model; S2. Import the real-time physical data of shield tunneling into the monitoring system platform; the real-time physical data of shield tunneling (important parameters during the operation of the shield machine) includes: propulsion speed, total thrust, torque, cutter head, shield slope, earth pressure; Specifically, the shield machine is composed of a cutter head device, a propulsion system, a screw conveyor, a tail seal device, etc. The real-time physical data of shield tunneling (important parameters during the operation of the shield machine) is connected to the monitoring system platform through an interface; S3. Endow the physical and mechanical data of the entity shield machine connected to the monitoring system platform to the shield machine model for dynamic simulation; S4. Realize the three-dimensional visualization expression and display of the linear project of shield tunneling construction of double-hole tunnels, including: realizing the three-dimensional real-time visualization expression of tunnel construction progress, realizing the three-dimensional visualization display of tunnel segment installation progress, and realizing the three-dimensional visualization interactive display of the shield machine structure decomposition function; Specifically, the shield machine structure decomposition function is to interactively display the structure composition, product description, construction technology, working principle, etc. of the shield machine through the monitoring system platform, and display the shield tunneling technology in the form of three-dimensional interactive animation, which is convenient for construction personnel to understand and master the technological performance and working conditions of the shield machine.

[0008] S5. Based on the three-dimensional visualization expression and display of the linear project in step S4, compile a three-dimensional visualization digital driving progress plan for shield tunneling of double-hole tunnels, and use the monitoring system platform to interactively display the construction progress plan.

[0009] Specifically, based on the data for the three-dimensional visualization expression and display achieved in step S4 of the linear project, a three-dimensional visualization digital drive is performed using a digital drive interactive drive engine software to prepare a three-dimensional visualization digital drive progress plan for the tunneling of a double-hole tunnel shield machine. By using the slider on the control panel, the construction progress plan for each day can be interactively displayed.

[0010] In an embodiment of the present invention, according to the contract construction period requirements, node construction period requirements, and contract requirements in the tender documents, a construction organization design and a bar chart plan for the double-hole tunnel are prepared. On this basis, a three-dimensional visualization digital drive progress plan for the tunneling of the double-hole tunnel shield machine is prepared using a digital drive interactive drive engine software. The progress plan shows the double-line data of the left and right shield tunneling, including the mileage of the section, the length of the section, the number of rings, the shield tunneling time, the number of rings in the progress plan, etc. The construction progress plan for each day can be interactively displayed by using the slider at the lower part of the control panel.

[0011] The three-dimensional visualization digital drive construction progress plan for the tunneling of the double-hole tunnel shield machine in the present invention has the following advantages: First, it can visually display the arrangement of project work and the sequence of completion of a linear engineering project over time, and intuitively feel whether the project construction arrangement is reasonable; Second, it can display the input quantity, working time, and running track of the main construction machinery and equipment; Third, the sub-projects on the critical path are decomposed into processes. By the construction processes and equipment input, the operation time of the smallest construction unit is determined, and then the overall construction period is determined; the construction period is optimized by backward scheduling the construction period, and resources are reasonably allocated to avoid resource waste; Fourth, through the time slider, the construction progress plan can be freely simulated forward or backward, and by parametrically setting the process construction period, the construction period date can be conveniently adjusted to achieve digital drive.

[0012] Furthermore, the method for establishing the geological profile model in step S1 includes: segmenting the model along the tunnel direction according to the length of each segment of the segment ring and assigning mechanical properties; modularizing the geological strata at the segment ring, with the size of each module being the same as that of each segment ring, and each module reflecting the mechanical properties and stratum type of the geology where the module is located; based on the module, a three-dimensional geological profile is made, and the three-dimensional geological profile uses different scales in the horizontal and vertical directions to focus on reflecting the change of geological properties in terms of mileage of the strata.

[0013] Furthermore, the tunnel engineering project model in step S1 includes the tunnel itself, the surrounding environment, the launch shaft, the receiving shaft, and the auxiliary structures; The method for establishing the tunnel engineering project model includes: importing the CAD design drawings of the tunnel engineering project into 3D modeling software (preferably Revit), and modeling according to a 1:1 ratio to ensure the accuracy of the model.

[0014] Further, the method for establishing the precast segment model in step S1 includes: modeling each segment in detail, assigning a separate identification number to each segment, and using two-dimensional code recognition technology to identify the production date, segment size, and installation position information of each segment by scanning the two-dimensional code.

[0015] Further, the method for establishing the shield machine model in step S1 includes: establishing a 3D model using 3D software (preferably Revit) according to the CAD drawings provided by the shield machine manufacturer, and performing hierarchical division according to the components and functions of the shield machine.

[0016] Further, the method for dynamic simulation in step S3 includes: after assigning the physical and mechanical data of the physical shield machine to the shield machine model, placing it in a geological profile model containing geomechanical parameters, performing dynamic simulation of the shield machine tunneling in a virtual environment, and comparing it with the tunneling construction of the physical shield machine; when it is found that the tunneling of the physical shield machine and the shield machine model is inconsistent, check whether the problem lies in the tunneling parameters of the shield machine model or the tunneling parameters of the physical shield machine, and determine whether to adjust the tunneling parameters of the physical shield machine or the data of the shield machine model.

[0017] The present invention assigns various physical and mechanical parameters to the shield machine model, integrates it with the stratum containing mechanical properties, and simulates the shield machine tunneling in a virtual environment, providing technical support for the tunneling of the physical shield machine.

[0018] Further, the method for realizing the three-dimensional real-time visualization expression of the tunnel construction progress in step S4 includes: Install a positioning instrument at the head of the shield machine. During the tunneling process of the shield machine, transmit the positioning instrument data to the shield machine model in the monitoring system platform in real time. The shield machine model is driven by the positioning instrument data and moves forward in real time with the positioning instrument data. Cooperating with the surrounding geological profile and mileage data, the tunneling position of the shield machine and the completed quantity of the tunnel construction are obtained in real time.

[0019] Further, the method for realizing the three-dimensional visualization display of the tunnel segment installation progress in step S4 includes: Paste corresponding two-dimensional code labels on each segment, realize two-dimensional code management during the production, transportation, and installation processes. After the segment installation is completed, identify the segment identification position by scanning the two-dimensional code, automatically transmit the segment identification position information to the monitoring system platform, and the monitoring system platform automatically displays the status of the completed segment identification position and displays the two-dimensional code number of the segment.

[0020] Preferably, after the segment is produced in the prefabrication factory, a two-dimensional code label is attached, and it is transported to the site by transportation equipment, then transported into the tunnel by a special tunnel transport vehicle, and the segment is installed in place by a manipulator. To install a circular tunnel wall, approximately 5-7 such support segments are needed. After the manipulator installs a segment, it is compacted and fixed by a hydraulic pipe.

[0021] The present invention establishes a complete three-dimensional model, including permanent works, temporary works, and main construction machinery and equipment, which can reflect the construction process and construction status; decomposes the sub-projects on the critical path that affect the overall construction progress into processes, and each process is equipped with relevant machinery and equipment, and determines the process duration plan according to the machinery and equipment parameters; the process duration plan is the key to determining the entire duration plan; uses professional three-dimensional visualization digital driving software to compile the overall construction progress plan, parametrically designs the process plan, sub-project plan, and sub-division project plan, and integrates all plans together using the vertical axis (Y-axis) time slider to form a three-dimensional visualization construction progress plan that can be repeatedly manipulated and interlinked.

[0022] The present invention also provides a computer-readable storage medium, on which a computer program is stored, and when the program is executed by a processor, the steps of the double-tunnel shield tunneling construction simulation method based on BIM and digital twin as described above are implemented.

[0023] The present invention also provides a computer device, which includes a memory, a processor, and a computer program stored on the memory and operable on the processor. When the processor executes the program, the steps of the double-tunnel shield tunneling construction simulation method based on BIM and digital twin as described above are implemented.

[0024] Compared with the prior art, the beneficial effects of the present invention are as follows: The double-tunnel shield tunneling construction simulation method based on BIM and digital twin provided by the present invention adopts digital technologies such as BIM and digital twin to build a monitoring system platform for double-tunnel shield tunneling, establishes three-dimensional models for double-tunnel engineering projects, shield machines, stratum structures (geological profiles), segments, etc., simulates shield tunneling using digital-driven interactive software, and interactively drives the progress plan and actual progress, making up for the deficiencies of the current tunnel shield machine tunneling monitoring system, being able to visually display segments, geological profiles, progress plans, and actual progress, accurately reflecting the installation position and progress of each segment, and vividly and intuitively reflecting the tunnel shield machine tunneling progress plan, which is beneficial to improving the construction efficiency of double-tunnel shield tunneling. Description of the Drawings

[0025] Various other advantages and benefits will become apparent to those of ordinary skill in the art by reading the following detailed description of the preferred embodiments. The drawings are only for the purpose of showing the preferred embodiments and are not considered to be a limitation of the present invention.

[0026] In the drawings: Figure 1 is the BIM model diagram of the double - hole tunnel established in the embodiment of the present invention; Figure 2 is the 3D model diagram of the shield machine established in the embodiment of the present invention; Figure 3 is the geological section diagram of the embodiment of the present invention; Figure 4 is the control panel diagram of the real - time monitoring data of the shield machine in the embodiment of the present invention; Figure 5 is the tunnel shield tunneling progress diagram of the embodiment of the present invention; Figure 6 is the tunneling progress plan diagram of the double - hole tunnel shield machine in the embodiment of the present invention; Figure 7 is the structural decomposition diagram of the shield machine in the embodiment of the present invention; Figure 8 is the flow chart of the double - hole tunnel shield tunneling construction simulation method based on BIM and digital twin of the present invention; Figure 9 is the schematic diagram of the composition of the computer device in the embodiment of the present invention. Detailed Embodiments

[0027] Here, the exemplary embodiments will be described in detail, and the examples are shown in the drawings. When the following description refers to the drawings, unless otherwise indicated, the same numbers in different drawings represent the same or similar elements. The embodiments described in the following exemplary embodiments do not represent all embodiments consistent with the present disclosure. On the contrary, they are only examples of devices and products consistent with some aspects of the present disclosure as detailed in the appended claims.

[0028] The terms used in the present disclosure are only for the purpose of describing specific embodiments and are not intended to limit the present disclosure. The singular forms "a", "the" and "said" used in the present disclosure and the appended claims are also intended to include the plural forms unless the context clearly indicates otherwise. It should also be understood that the term "and / or" as used herein refers to and includes any and all possible combinations of one or more of the associated listed items.

[0029] It should be understood that although the terms first, second, third, etc. may be used in this disclosure to describe various information, such information should not be limited to these terms. These terms are only used to distinguish information of the same type from each other. For example, without departing from the scope of this disclosure, the first information may also be referred to as the second information, and similarly, the second information may also be referred to as the first information. Depending on the context, the word "if" as used herein may be interpreted as "when" or "while" or "in response to a determination".

[0030] The embodiments of the present invention will be further described in detail below.

[0031] The embodiments of the present invention provide a simulation method for shield tunneling construction of a double - hole tunnel based on BIM and digital twin, as Figure 8 shown, including the following steps: S1. Establish a BIM model of the double - hole tunnel for the double - hole tunnel engineering project, and import the BIM model of the double - hole tunnel into the monitoring system platform; the BIM double - hole tunnel model includes the following modules: a tunnel engineering project model, a shield machine model, a precast segment model, and a geological profile model, as Figures 1-3 shown; The tunnel engineering project model includes the tunnel itself, the surrounding environment, the launching shaft, the receiving shaft, and the ancillary structures (see Figure 1 shown); The method for establishing the tunnel engineering project model includes: importing the CAD design drawings of the tunnel engineering project into the Revit 3D modeling software, and modeling according to a 1:1 ratio to ensure the accuracy of the model.

[0032] The method for establishing the precast segment model includes: modeling each segment in detail, assigning a separate identification number to each segment, and using two - dimensional code recognition technology to identify the production date, segment size, and installation location information of each segment by scanning the two - dimensional code.

[0033] The method for establishing the geological profile model includes: segmenting the model along the tunnel direction according to the length of each segment and assigning mechanical properties; modularizing the geological strata at the segment location, with the size of each module being the same as that of each segment, and each module reflecting the mechanical properties and stratum type of the geology where the module is located; based on the module, making a three - dimensional geological profile diagram (see Figure 3 shown), and the three - dimensional geological profile diagram uses different scales in the horizontal and vertical directions to focus on reflecting the change in geological properties along the mileage of the stratum.

[0034] The method for establishing the shield machine model includes: establishing a 3D model using the Revit 3D software according to the CAD drawings provided by the shield machine manufacturer (see Figure 2 shown), and hierarchically dividing according to the components and functions of the shield machine.

[0035] S2. Import the real-time physical data of the shield tunneling machine into the monitoring system platform; the real-time physical data of the shield tunneling machine includes: propulsion speed, total thrust, torque, cutterhead, shield slope, and soil pressure. See Figure 4 As shown, the shield tunneling machine consists of a cutterhead device, a propulsion system, a screw conveyor, a tail seal device, etc. The real-time physical data of the shield tunneling machine (important parameters during the operation of the shield tunneling machine) is connected to the monitoring system platform through an interface. S3. Assign the physical and mechanical data of the physical shield tunneling machine imported into the monitoring system platform to the shield tunneling machine model for dynamic simulation. The method of dynamic simulation includes: after assigning the physical and mechanical data of the physical shield tunneling machine to the shield tunneling machine model, putting it into a geological profile model containing geomechanical parameters, and conducting dynamic simulation of the shield tunneling machine tunneling in a virtual environment and comparing it with the tunneling construction of the physical shield tunneling machine. When it is found that the tunneling of the physical shield tunneling machine and the shield tunneling machine model is inconsistent, check whether the problem lies in the tunneling parameters of the shield tunneling machine model or the tunneling parameters of the physical shield tunneling machine, and determine whether to adjust the tunneling parameters of the physical shield tunneling machine or the data of the shield tunneling machine model. In this embodiment, various physical and mechanical parameters are assigned to the shield tunneling machine model and integrated with the formation containing mechanical properties to simulate the shield tunneling machine tunneling in a virtual environment, providing technical support for the tunneling of the physical shield tunneling machine.

[0036] S4. Realize the three-dimensional visualization expression and display of the linear project of the double-tunnel shield tunneling construction, including: realizing the three-dimensional real-time visualization expression of the tunnel construction progress, realizing the three-dimensional visualization display of the tunnel segment installation progress, and realizing the three-dimensional visualization interactive display of the shield tunneling machine structure decomposition function. Install a locator at the head of the shield tunneling machine. During the tunneling process of the shield tunneling machine, transmit the locator data to the shield tunneling machine model in the monitoring system platform in real time. The shield tunneling machine model is driven by the locator data and moves forward in real time with the locator data. Cooperating with the surrounding geological profile and mileage data, the tunneling position of the shield tunneling machine and the completed quantity of the tunnel construction are obtained in real time (see Figure 5 shown).

[0037] In this embodiment, after the segment is produced in the prefabrication factory, a QR code label is attached to it and transported to the site by transportation equipment. Then it is transported into the tunnel by a special tunnel transport vehicle, and a manipulator is used to install the segment in place. It takes about 5 - 7 such support segments to install a circle of tunnel wall. After the manipulator installs a segment, a hydraulic pipe is used to compact and fix it. A corresponding QR code label is pasted on each segment to realize QR code management during the production, transportation, and installation processes. After the segment installation is completed, the segment identification position is identified by scanning the QR code, and the segment identification position information is automatically transmitted to the monitoring system platform. The monitoring system platform automatically displays the status of the segment identification position of the installed segment and shows the QR code number of the segment.

[0038] As Figure 7 shown, the structural composition, product description, construction technology, working principle, etc. of the shield machine are interactively displayed through the monitoring system platform, and the tunneling technology of the shield machine is displayed in the form of three-dimensional interactive animation, which is convenient for construction personnel to understand and master the technological performance and working conditions of the shield machine.

[0039] S5. Based on the three-dimensional visualization expression and display of the linear project in step S4 as the data basis, compile a three-dimensional visualization digital-driven progress plan for the shield tunneling of the double-hole tunnel, and use the monitoring system platform to interactively display the construction progress plan.

[0040] Based on the data obtained from the three-dimensional visualization expression and display of the linear project in step S4, a three-dimensional visualization digital-driven progress plan for the shield tunneling of the double-hole tunnel is compiled using a digital-driven interactive drive engine software (see Figure 6 shown). By using the slider on the control panel (as Figure 4 shown), the construction progress plan for each day can be interactively displayed.

[0041] In this embodiment, according to the contract construction period, node construction period requirements in the bidding documents, and contract requirements, a construction organization design and bar chart plan for the double-hole tunnel are compiled. On this basis, a three-dimensional visualization digital-driven progress plan for the shield tunneling of the double-hole tunnel is compiled using a digital-driven interactive drive engine software (see Figure 6 shown). The progress plan shows the double-line data of the left and right shield tunneling, including the section mileage, section length, number of rings, shield tunneling time, number of rings in the progress plan, etc. By using the slider at the lower part of the control panel, the construction progress plan for each day can be interactively displayed.

[0042] The shield tunneling construction simulation method for double - hole tunnels based on BIM and digital twin in this embodiment uses digital technologies such as BIM and digital twin to build a monitoring system platform for shield tunneling of double - hole tunnels. Three - dimensional models are established for double - hole tunnel engineering projects, shield machines, stratum structures (geological profiles), segment linings, etc. A digital - driven interaction software is used to simulate shield tunneling, and interactive driving is performed on the progress plan and actual progress, making up for the deficiencies of the current tunnel shield machine tunneling monitoring system. It can visually display segment linings, geological profiles, progress plans, and actual progress, accurately reflect the installation position and progress of each segment lining, and vividly and intuitively reflect the shield tunneling progress plan of the tunnel, which is conducive to further improving the construction efficiency of shield tunneling for double - hole tunnels.

[0043] An embodiment of the present invention also provides a computer device. Figure 9 It is a schematic structural diagram of a computer device provided by an embodiment of the present invention; see the attached drawings Figure 9 As shown, the computer device includes: an input system 23, an output system 24, a memory 22, and a processor 21; the memory 22 is used to store one or more programs; when the one or more programs are executed by the one or more processors 21, the one or more processors 21 implement the shield tunneling construction simulation method for double - hole tunnels based on BIM and digital twin as provided in the above - mentioned embodiment; among them, the input system 23, the output system 24, the memory 22, and the processor 21 can be connected through a bus or other means. Figure 9 Taking connection through a bus as an example.

[0044] The memory 22, as a readable and writable storage medium of a computing device, can be used to store software programs and computer - executable programs, such as the program instructions corresponding to the shield tunneling construction simulation method for double - hole tunnels based on BIM and digital twin described in the embodiment of the present invention; the memory 22 mainly includes a program storage area and a data storage area. Among them, the program storage area can store an operating system and application programs required for at least one function; the data storage area can store data created according to the use of the device, etc.; in addition, the memory 22 can include high - speed random - access memory, and can also include non - volatile memory, such as at least one magnetic disk storage device, a flash memory device, or other non - volatile solid - state storage devices; in some instances, the memory 22 can further include a memory remotely set relative to the processor 21, and these remote memories can be connected to the device through a network. Examples of the above - mentioned network include, but are not limited to, the Internet, an enterprise intranet, a local area network, a mobile communication network, and their combinations.

[0045] The input system 23 can be used to receive input digital or character information, and generate key signal inputs related to the user settings and function control of the device; the output system 24 can include display devices such as a display screen.

[0046] The processor 21 executes various functional applications and data processing of the device by running software programs, instructions, and modules stored in the memory 22, that is, implements the above-mentioned double-hole tunnel shield tunneling construction simulation method based on BIM and digital twin.

[0047] The computer device provided above can be used to execute the double-hole tunnel shield tunneling construction simulation method based on BIM and digital twin provided in the above embodiment, and has corresponding functions and beneficial effects.

[0048] The embodiment of the present invention also provides a storage medium containing computer-executable instructions. The computer-executable instructions are used to execute the double-hole tunnel shield tunneling construction simulation method based on BIM and digital twin provided in the above embodiment when executed by a computer processor. The storage medium is any of various types of memory devices or storage devices, including: installation media such as CD-ROM, floppy disk or magnetic tape system; computer system memory or random access memory such as DRAM, DDR RAM, SRAM, EDO RAM, Rambus RAM, etc.; non-volatile memory such as flash memory, magnetic medium (such as hard disk or optical storage); registers or other similar types of memory elements, etc.; the storage medium can also include other types of memory or their combinations; in addition, the storage medium can be located in the first computer system in which the program is executed, or can be located in a different second computer system, and the second computer system is connected to the first computer system through a network (such as the Internet); the second computer system can provide program instructions to the first computer for execution. The storage medium includes two or more storage media that can reside in different locations (such as in different computer systems connected through a network). The storage medium can store program instructions (such as specifically implemented as a computer program) executable by one or more processors.

[0049] Of course, the computer-executable instructions of the storage medium containing computer-executable instructions provided in the embodiment of the present invention are not limited to the double-hole tunnel shield tunneling construction simulation method based on BIM and digital twin described in the above embodiment, and can also execute related operations in the double-hole tunnel shield tunneling construction simulation method provided in any embodiment of the present invention.

[0050] So far, the technical solution of the present invention has been described in combination with the preferred embodiments. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will all fall within the protection scope of the present invention.

[0051] The above are only the preferred embodiments of the present invention and are not intended to limit the present invention; for those skilled in the art, various modifications and variations can be made to the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims

1. A double-hole tunnel shield excavation construction simulation method based on BIM and digital twins, characterized in that: The following steps are involved: S1. Establish a double-hole tunnel BIM model of the double-hole tunnel project, and import the double-hole tunnel BIM model into the monitoring system platform; The BIM double-hole tunnel model includes the following modules: tunnel engineering project model, shield machine model, prefabricated segment model, and geological profile model; S2. Import the real-time physical data of shield machine excavation into the monitoring system platform; The real-time physical data of the shield machine excavation includes: propulsion speed, total thrust, torque, cut, shield slope, and soil pressure; S3, assigning the physical mechanical data of the actual shield machine connected to the monitoring system platform to the shield machine model to perform dynamic simulation; S4. Realize the three-dimensional visualization and display of the linear engineering of the shield tunneling construction of the double-hole tunnel, including: realize the three-dimensional real-time visualization of the tunnel construction progress, realize the three-dimensional visualization display of the tunnel segment installation progress, and realize the three-dimensional visualization interactive display of the shield machine structure decomposition function; S5. Based on the three-dimensional visualization and display of the linear engineering in step S4, a three-dimensional visualization digitally driven progress plan for the shield excavation of the double-hole tunnel is compiled, and the monitoring system platform is used to interactively display the construction progress plan.

2. The double-hole tunnel shield excavation construction simulation method based on BIM and digital twin according to claim 1 is characterized in that: The method for establishing the geological profile model in step S1 includes: modeling in sections according to the length of each segment along the tunnel direction and assigning mechanical properties; modularizing the geological strata at the segments, with the size of each module being consistent with that of each segment, and each module reflecting the mechanical properties and stratum type of the geology in which the module is located; and making a three-dimensional geological profile map based on the modules, wherein the three-dimensional geological profile map adopts different horizontal and vertical scales, focusing on reflecting the changes in the geological properties of the strata over the mileage.

3. The double-hole tunnel shield excavation construction simulation method based on BIM and digital twin according to claim 1 is characterized in that: The tunnel engineering project model in step S1 includes the tunnel itself, the surrounding environment, the starting shaft, the receiving shaft and the auxiliary structures; The method for establishing the tunnel engineering project model comprises: according to the CAD design drawings of the tunnel engineering project, the CAD design drawings are imported into three-dimensional modeling software, and modeling is performed in a 1:1 ratio.

4. The method for simulating double-hole tunnel shield excavation construction based on BIM and digital twin according to claim 1, characterized in that: The method for establishing the prefabricated segment model in step S1 includes: modeling each segment in detail, assigning a separate identification number to each segment, and using QR code recognition technology to identify the production date, segment size, and installation location information of each segment by scanning the QR code.

5. The double-hole tunnel shield excavation construction simulation method based on BIM and digital twin according to claim 1 is characterized in that: The method for establishing the shield machine model in step S1 includes: establishing a three-dimensional model using three-dimensional software according to the CAD drawings provided by the shield machine manufacturer, and dividing the model into levels according to the components and functions of the shield machine.

6. The method for simulating double-hole tunnel shield excavation construction based on BIM and digital twin according to claim 1, characterized in that: The method for dynamic simulation in step S3 includes: after assigning the physical and mechanical data of the physical shield machine to the shield machine model, putting it into a geological profile model containing geomechanical parameters, dynamically simulating the shield machine excavation in a virtual environment, and comparing it with the excavation construction of the physical shield machine; when it is found that the excavation of the physical shield machine is inconsistent with the excavation of the shield machine model, checking whether the problem lies in the excavation parameters of the shield machine model or the excavation parameters of the physical shield machine, and determining whether to adjust the excavation parameters of the physical shield machine or the shield machine model data.

7. The method for simulating double-hole tunnel shield excavation construction based on BIM and digital twin according to claim 1, characterized in that: The method for realizing three-dimensional real-time visualization of tunnel construction progress in step S4 includes: A locator is installed on the head of the shield machine. During the tunneling process of the shield machine, the locator data is transmitted in real time to the shield machine model in the monitoring system platform. The shield machine model is driven by the locator data and moves forward in real time with the locator data. In conjunction with the surrounding geological profiles and mileage data, the shield machine excavation position and the number of completed tunnel construction can be obtained in real time.

8. The method for simulating double-hole tunnel shield excavation construction based on BIM and digital twin according to claim 1, characterized in that: The method for realizing the three-dimensional visualization display of the tunnel segment installation progress in step S4 includes: A corresponding QR code label is pasted on each segment to implement QR code management during the production, transportation and installation processes. When the segment is installed, the segment identification position is identified by scanning the QR code, and the segment identification position information is automatically transmitted to the monitoring system platform. The monitoring system platform automatically displays the status of the segment identification position that has been installed and displays the QR code number of the segment.

9. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by the processor, the steps of the double-hole tunnel shield excavation construction simulation method based on BIM and digital twins as described in any one of claims 1 to 8 are implemented.

10. A computer device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, it implements the steps of the double-hole tunnel shield excavation construction simulation method based on BIM and digital twin as described in any one of claims 1 to 8.