Prefabricated part for loading bridge supporting bracket
A technology of prefabricated components and support frames, applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., can solve the problems of prolonged traffic closure time, small sand proportion, long lines, etc., to reduce traffic time, reduce the number of installation parts, The effect of low stack height
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2010-01-13
- Estimated Expiration
- Not applicable · inactive patent
Smart Images
Figure 1 Figure 2 Figure 3
Abstract
Description
technical field
[0001] The invention belongs to the fields of civil engineering and bridge engineering, and in particular relates to a prefabricated component used for loading a bridge support frame. Background technique
[0002] In order to ensure that the bridge support frame does not sink when the bridge slab is poured with concrete, it is often necessary to load the bridge support frame first after the bridge support frame is erected. The traditional method of loading the bridge support frame is to use the method of artificially stacking sand bags, which is simple and convenient. But there are also the following problems: 1. The bridge support frame is generally high, and the labor intensity of manual sand bagging is high; 2. The bridge support frame is characterized by long lines and large area, and the efficiency of manual sand bag stacking is low; 3. The specific gravity is small, so the sandbags occupy a lot of land and need to be stacked at a high height, making it...
Examples
Embodiment 1
[0028] Such as figure 1 , figure 2 , image 3 As shown, the prefabricated component used to load the bridge support frame includes a block-shaped prefabricated component 1; the upper surface of the prefabricated component is provided with vertical and horizontal grooves 2, and the intersection of the horizontal grooves 2 is fixed with a first The hook 3; the side of the prefabricated component is provided with a vertical groove 4, and the second hook 5 is fixed in the vertical groove 4.
[0029] The material of the prefabricated component is concrete; it is prefabricated according to existing conventional methods. The length of the prefabricated component is 1.2m, the width is 1.2m, and the height is 0.8m.
[0030] Application: A method for loading a bridge support frame with prefabricated components, which includes the following steps:
[0031] 1) if figure 1 , figure 2 , image 3 As shown, the prefabricated component 1 is made, and the prefabricated component is blo...
Embodiment 2
[0037] Such as Figure 4 , Figure 5 As shown, it is basically the same as Embodiment 1, except that the lower surface of the prefabricated component is provided with a first chute 6 and a second chute 8, and the first chute 6 and the second chute 8 are arranged in parallel , the first chute 6 and the second chute 8 are equipped with at least two rollers 7; the upper surface of the prefabricated component is provided with a first guide bar 9 and a second guide bar 10, and the first guide bar 9 and the first slide The position of the groove 6 is corresponding, and the second guide bar 10 is corresponding to the position of the second chute 8 (the spacing between the first guide bar 9 and the second guide bar 10 is the same as that of the first chute 6 on the lower surface of the prefabricated component. Consistent with the spacing between the second chute 8; the roller 7 in the first chute 6 on the lower surface of the prefabricated component of the upper layer falls on the fi...