A clamp-type prestressed cable-stayed foundation

Through the fastening mechanism and grouting pipe grouting technology of clip-type prestressed cable-stayed foundation, the force demand and construction quality problems of cable-stayed rods in flexible photovoltaic support systems are solved, and economical, safe and reliable construction results are achieved.

CN111335350BActive Publication Date: 2024-11-19NANJING GUANGXIANG NEW ENERGY TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010352664.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-04-29
Publication Date
2024-11-19
Estimated Expiration
2040-04-29

AI Technical Summary

Technical Problem

In the prior art, the basic form of the flexible photovoltaic support system cannot effectively meet the large crawl tension demand of the cable-stayed rod, resulting in high construction costs, poor safety, poor reliability and difficult to ensure construction quality.

Method used

It adopts a clamped prestressed cable-stayed foundation, including the lower anchor plate and the upper anchor plate, is connected by a fastening mechanism, uses fine-rolled rebar and prestressed nut to provide resistance to pulling, and is connected with the cable-stayed rod through a U-shaped adjustable mechanism. Grouting is combined with grouting pipes to enhance structural integrity.

Benefits of technology

It reduces construction costs, improves safety and reliability, simplifies construction machinery and processes, significantly improves economic advantages, reduces deformation, and controls the apex displacement of the end columns.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111335350B_ABST
    Figure CN111335350B_ABST
Patent Text Reader

Abstract

The present invention discloses a clamp-type prestressed cable-stayed foundation, comprising a lower anchor plate in a deep foundation pit, an upper anchor plate in a shallow foundation pit and fine-rolled threaded steel bars connected thereto. The fine-rolled threaded steel bars passing through the inclined holes of the upper and lower anchor plates are first tensioned by prestressed nuts, and then cement slurry is poured through a reserved grouting pipe until the cement slurry overflows from the top, and the grouting pipe is pulled out. The prestressed nuts, fine-rolled threaded steel bars and other parts of the upper and lower anchor plates that are not wrapped by cement slurry are treated with asphalt for corrosion protection. The foundation pits of the upper and lower anchor plates are backfilled and compacted. The present invention solves the technical problems of high construction cost, uneconomical, poor safety, and poor construction quality and reliability in the prior art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an inclined-stayed foundation, in particular to a clamped-type prestressed inclined-stayed foundation, which is mainly applicable to an inclined-stayed foundation of a photovoltaic flexible support. Background Art

[0002] The flexible photovoltaic support system is a new type of support system. It simplifies the support system by fixing the photovoltaic components on the steel strands tensioned between two columns. The axial tension of the tensioned steel strands is used to resist the deadweight of the components, snow load and wind load. It is a geometrically nonlinear force system with complex force and deformation characteristics. The axial force of the tensioned steel strands is ultimately shared by the diagonal rods and end columns at the ends (the diagonal rods are under tension and the end columns are under compression). Since the diagonal force of the diagonal rods is large, the general foundation form cannot meet the requirements.

[0003] At present, the main foundation methods used in the market are ① precast foundation of cast-in-place piles and ② anchor bolt enlarged head foundation (high-pressure jet enlarged head anchor bolt foundation). The shortcomings are: ① The precast foundation of cast-in-place piles has a large vertical bearing capacity, while the horizontal bearing capacity is generally less affected by the soil around the pile. If the horizontal bearing capacity is large, the cast-in-place piles need to have a larger pile diameter and burial depth, and the cost is relatively high. The construction machinery of cast-in-place piles is huge, and it is more difficult to construct in mountainous environments. ② Anchor bolt enlarged head foundation (high-pressure jet enlarged head anchor bolt foundation), most of the anchor bolt bearing capacity is provided by the end enlarged head, but the enlarged head is formed by cutting the soil by a high-pressure jet stream, and the size of the enlarged head and the pouring quality of concrete cannot be guaranteed. Summary of the invention

[0004] In view of the above-mentioned deficiencies in the prior art, the present invention provides a clamp-type prestressed cable-stayed foundation to solve the technical problems of high construction cost, uneconomical, poor safety, and unguaranteed construction quality and poor reliability in the prior art.

[0005] In order to solve the above technical problems and achieve the purpose of the present invention, the present invention adopts the following technical scheme: a clamp-type prestressed cable-stayed foundation, comprising a lower anchor plate and an upper anchor plate, the upper anchor plate is provided with anchor ears, the upper and lower anchor plates are respectively provided with inclined holes, the upper and lower anchor plates are respectively placed in shallow and deep foundation pits, and are connected into one by a fastening mechanism, and clamp the side walls of the shallow and deep foundation pits accordingly.

[0006] Furthermore, the fastening mechanism includes precision-rolled threaded steel and prestressed nuts. The upper and lower ends of the precision-rolled threaded steel pass through the inclined holes formed on the upper and lower anchor plates and are tightened and fixed by the prestressed nuts.

[0007] Furthermore, the anchor ear is connected to the inclined tie rod connected to the end column through a U-shaped adjustable mechanism.

[0008] Furthermore, the upper anchor plate oblique hole is arranged at the overlapping part of the upper anchor plate and the anchor ear seat, and the lower anchor plate oblique hole is arranged on the convex ridge thereon.

[0009] Furthermore, a grouting port is provided on the upper anchor plate.

[0010] Furthermore, the grouting port can be inserted with a PVC grouting pipe.

[0011] Compared with the prior art, the present invention has the following beneficial effects:

[0012] The present invention uses the resistance of the soil at the front end of the lower anchor plate to provide pull-out resistance, which is similar to the force-bearing principle of the anchor bolt enlarged head foundation. However, the present invention overcomes the shortcomings of the anchor bolt enlarged head foundation, which has complex construction technology and is difficult to ensure the construction quality. It also overcomes the shortcomings of the high construction cost of the cast-in-place pile prefabricated foundation. In short, the present invention is safe and reliable, uses simple construction machinery, and has simple and easy-to-operate technical processes, and has significant economic advantages. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 It is a schematic diagram of the structure of the present invention.

[0014] Figure 2 It is a front view of the main structure of the present invention.

[0015] Figure 3 It is the right view of the main structure of the present invention.

[0016] Figure 4 for Figure 3 Enlarged view of area A in the middle.

[0017] In the figure: 1-upper anchor plate, 2-lower anchor plate, 3-anchor ear, 4-shallow foundation pit, 5-deep foundation pit, 6-fine-rolled threaded steel bar, 7-prestressed nut, 8-U-shaped adjustable mechanism, 9-end column, 10-inclined tie rod, 11-grouting port, 12-PVC grouting pipe. DETAILED DESCRIPTION

[0018] The present invention is further described below with reference to the accompanying drawings and examples.

[0019] like Figures 1 to 4As shown, the present invention provides a clamp-type prestressed inclined-stayed foundation, including a lower anchor plate 1 and an upper anchor plate 2. The upper anchor plate 1 is provided with an anchor ear 3, and the anchor ear 3 is connected to the inclined tie rod 10 connected to the end column 9 through a U-shaped adjustable mechanism 8. The upper and lower anchor plates 1, 2 are respectively provided with inclined holes. Preferably, the inclined hole of the upper anchor plate 1 is provided at the overlap of the upper anchor plate 1 and the anchor ear seat, and the inclined hole of the lower anchor plate 2 is provided on the convex ridge thereon. The upper and lower anchor plates 1, 2 are respectively placed in the shallow and deep foundation pits 4, 5, and are connected into one body through a fastening mechanism, and correspondingly clamp the side walls of the shallow and deep foundation pits 4, 5. The fastening mechanism includes a fine-rolled threaded steel bar 6 and a prestressed nut 7. The upper and lower ends of the fine-rolled threaded steel bar 6 pass through the inclined holes provided on the upper and lower anchor plates 1, 2, and are tightened and fixed by the prestressed nut 7. The upper and lower anchor plates 1, 2 respectively placed in the shallow and deep foundation pits 4, 5 are made to be close to the foundation pit wall and clamp the soil. During the tensioning and fixing process of the prestressed nut 7, the prestressed steel bar 6 is prestressed by the tensioning equipment, and then the prestressed nut 7 is tightened and fixed. The tensioning equipment can select a jack, and the jack is used to apply pre-tension to the fine-rolled threaded steel bar 6 at the upper anchor plate 1 so that the lower anchor plate 2 fits tightly with the side wall of the foundation pit, eliminating the influence of the gap between the lower anchor plate 2 and the foundation pit on the overall deformation. The pre-tension is applied to make the fine-rolled threaded steel bar 6 deform in advance. When the subsequent tension value acting on the upper anchor plate 1 is not greater than this pre-tension, the clamp-type prestressed inclined-stayed foundation will not deform; when the subsequent tension value acting on the upper anchor plate 1 is greater than this pre-tension, the clamp-type prestressed inclined-stayed foundation will deform to a certain extent, but this deformation will be much smaller than the deformation of the ordinary anchor rod under the same working condition, and the control of the vertex displacement of the end column 9 is extremely important. The size of the initial pre-tension can be taken as the tension value of the inclined tie rod 10 of the end column of the flexible bracket under the working condition of deadweight.

[0020] In order to prevent the fine-rolled threaded steel bars that penetrate into the soil from being corroded and to enhance the integrity of the structure, a grouting port 11 is opened on the upper anchor plate 1. The PVC grouting pipe 12 is inserted into the grouting port 11 to inject cement slurry into the drilled hole in the soil until the cement slurry overflows from the top, so that the fine-rolled threaded steel bars 6 that penetrate into the drilled hole are wrapped by the cement slurry, and then the PVC grouting pipe 12 is pulled out. The prestressed nuts 7, fine-rolled threaded steel bars 6, etc. at the upper and lower anchor plates 1, 2 that are not wrapped by cement slurry are treated with asphalt for corrosion protection. The foundation pit of the upper and lower anchor plates 1, 2 is backfilled and compacted, leaving only the upper anchor plate 1 connected to the U-shaped adjustable mechanism 8 and the inclined tie rod 10.

[0021] According to the required tension and the soil conditions of the site (cohesion, internal friction angle), refer to the "Technical Code for High-Pressure Jet Enlarged Head Anchors" (JGJ / T 282-2012) (4.6.3-1) to determine the cross-sectional dimensions of the foundation, the burial depth and the inclination angle of the drill hole to the soil.

[0022] The ultimate pull-out resistance of the clamp-type prestressed cable-stayed foundation is related to the soil quality, the burial depth of the lower anchor plate (enlarged head) and the inclination angle of the drill hole to the soil, and should be determined through basic on-site tests. When there is no test data, it can be estimated according to the "Technical Code for High-Pressure Jet Enlarged Head Anchors" formula (4.6.3-1) (only considering the contribution of the soil at the end of the lower anchor plate (enlarged head) to the resistance of the lower anchor plate (enlarged head)), but it must be verified and determined through basic on-site tests during actual construction.

[0023] Taking the flexible bracket case as an example, an economic comparison is made. It is obvious that the high-pressure jet enlarged head anchor foundation is cheaper than the bored pile foundation (precast bored pile foundation). It is only necessary to compare the economic efficiency of the present invention and the high-pressure jet enlarged head anchor foundation.

[0024] Project scale 1MW photovoltaic power station: 200m long from east to west, 14 rows from north to south, and 4m between rows. Each load-bearing cable at the east and west ends of the flexible bracket needs to be equipped with a diagonal tie rod, which is at a 45° angle to the ground, and the axial tension of the tie rod is about 250KN.

[0025] To set up the prestressed cable-stayed foundation, two foundation pits of about 50m long, 1.2m wide and 4.5m deep are needed, totaling about 100m long; 56 inclined holes with a 45° inclination and a depth of 6m are drilled. Φ26 fine-rolled threaded steel 6.5x56=364m; prestressed nuts: 56x2=112 sets; upper and lower anchor plates: 28x2=56 sets; the average cost of each prestressed cable-stayed foundation is 635 yuan, and the cost of 56 foundations per megawatt is 35,560 yuan;

[0026] High-pressure jet enlarged head anchor foundation, 450 yuan / m, each cable-stayed foundation is about 4,000 yuan, and the cost of 56 foundations per MW is 224,000 yuan;

[0027] In summary, the present invention has obvious economic advantages.

[0028] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed by the present invention should be covered within the protection scope of the present invention.

Claims

1. A clamp-type prestressed cable-stayed foundation, comprising an upper anchor plate (1) and a lower anchor plate (2), characterized in that: The upper anchor plate (1) is provided with an anchor ear (3), and the upper anchor plate (1) and the lower anchor plate (2) are respectively provided with an inclined hole. The upper anchor plate (1) and the lower anchor plate (2) are respectively placed in a shallow foundation pit (4) and a deep foundation pit (5), and are connected into one body through a fastening mechanism, and correspondingly clamp the side walls of the shallow foundation pit (4) and the deep foundation pit (5); The fastening mechanism comprises a precision-rolled threaded steel bar (6) and a prestressed nut (7); the upper and lower ends of the precision-rolled threaded steel bar (6) respectively pass through the inclined holes provided on the upper anchor plate (1) and the lower anchor plate (2), and are tensioned and fixed by the prestressed nut (7); During the tensioning and fixing process of the prestressed nut (7), prestress is applied to the fine-rolled threaded steel bar (6) by a tensioning device, and then the prestressed nut (7) is tightened and fixed; Applying a pre-tensioning force causes the finished rolled threaded steel bar (6) to be deformed to a certain extent in advance; The anchor ear (3) is connected to a diagonal tie rod (10) connected to the end column (9) via a U-shaped adjustable mechanism (8); The upper anchor plate (1) is provided with a grouting opening (11); The grouting port (11) is capable of inserting a PVC grouting pipe (12).

2. The clamp-type prestressed cable-stayed foundation according to claim 1, characterized in that: The upper anchor plate oblique hole is formed at the overlapping portion of the upper anchor plate (1) and the anchor ear seat, and the lower anchor plate oblique hole is formed on the convex edge of the lower anchor plate (2).