A boiler heating surface intermediate tube row replacement support device and method
By using support plates and fixtures to transfer load to pipe rows that do not need to be replaced during the replacement of the intermediate pipe row of the boiler heating surface, the safety and efficiency of the lifting of the reverse chain wire rope is solved, and the safety of pipe row replacement is achieved and improve installation efficiency.
Patent Information
- Application Number
- CN202010790370.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-08-07
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2040-08-07
AI Technical Summary
During the replacement of the intermediate pipe row of the boiler heating surface, the prior art uses inverted chain wire rope to lift the result that the safety factor is low, the labor and material consumption is large, the operation is dangerous, and the counterpart spacing is not easy to be unified when installing the new pipe row, which is prone to folding.
The support plate and fixtures are arranged. The load below the pipe row to be replaced is transferred to the pipe rows on both sides that do not need to be replaced. The fixed installation method ensures that the pipe row position does not shift and reduces the inverted chain. Use of wire rope.
It improves the safety and efficiency of pipe row replacement, reduces the demand for tools, ensures that the spacing between the suspended pipes is fixed when the new pipe row is installed, avoids collision between the pipe row and the wire rope, and simplifies the installation process.
Smart Images

Figure CN111981461B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of boiler maintenance, and in particular to a boiler heating surface intermediate tube row replacement support device and method. Background Art
[0002] The statements in this section merely provide background art related to the present disclosure and do not necessarily constitute prior art.
[0003] For units that have been running for many years, some of the heating surface tube banks need to be replaced due to corrosion and thinning. The tube banks of tower boilers are generally economizer tube banks, reheater tube banks, and superheater tube banks from top to bottom. The tube banks are suspended in the furnace by suspension pipes. When replacing the upper tube bank, in order to prevent the lower suspended tube bank from sinking and falling, before cutting off the upper suspension pipe, the existing technical solution is to use a fall chain wire rope to hang the lower tube panel to the upper rooting point.
[0004] The inventors have found that, at present, one screen of pipe row generally has four suspension pipes, that is, one screen of pipe row requires at least four fall chains and wire rope clamps. When the pipe row of the entire system is replaced, the demand for tools such as fall chain wire ropes is too large. When the fall chain wire ropes are used as lifting points, the upper pipe row in and out often rubs and collides with the lifting point wire ropes, and the overall safety factor is not high. The use of too many fall chain wire ropes has also become an obstacle to the entry and exit of new pipe rows. The manpower and material resources used for lifting and arrangement are large, and when the lifting points are hung high above, it is a high-altitude operation, and the operating environment is relatively dangerous. The pipe row is suspended by the fall chain wire rope, and after the new pipe row above is in place, the installation joint spacing is not uniform, and the mouth phenomenon is prone to folding. Summary of the invention
[0005] The purpose of the present invention is to address the defects of the prior art and to provide a support device and method for replacing the intermediate tube bank of the heating surface of a boiler. By arranging support plates and fixings, the load under the tube bank to be replaced is transferred to the tube banks on both sides that do not need to be replaced through the support plates, thereby avoiding the need to arrange hanging points from the outside to suspend the load under the tube bank to be replaced, and there is no need to configure tools such as fall chain wire ropes. In addition, the fixed installation method can fix the structural position under the tube bank to be replaced to keep it in its original position, thereby avoiding the displacement of the tube bank and improving the efficiency and safety of subsequent tube bank installation.
[0006] The first object of the present disclosure is to provide a boiler heating surface intermediate tube row replacement support device, which adopts the following technical solutions:
[0007] It includes a support plate and three groups of fixing parts, which are installed on the support plate in sequence. The second group of fixing parts is used to connect the suspension pipes of the pipe row cut off above. The first group of fixing parts and the third group of fixing parts are located on both sides of the second group of fixing parts, and are both used to connect the suspension pipes of the pipe row that has not been cut off to provide auxiliary support for the suspension pipes of the pipe row that has been cut off.
[0008] Furthermore, each set of fixing parts includes a plurality of fixing buckles which are sequentially arranged at intervals on the support plate, and the fixing buckles cooperate with the support plate to clamp the suspension pipe.
[0009] The second object of the present disclosure is to provide a method for replacing an intermediate tube row on a heating surface of a boiler, comprising the following steps:
[0010] Arrange the support plate and the fixings so that the support plate is located below the tube row to be replaced;
[0011] The middle part of the support plate is connected to the suspension pipe under the pipe row to be replaced through a fixing piece, and the two ends are connected to the suspension pipe of the pipe row that has not been replaced through fixing pieces respectively;
[0012] Cut off the suspension pipes between the pipe row to be replaced and the support plate, remove the pipe row to be replaced, and transfer the load on the suspension pipes below the pipe row to be replaced to the suspension pipes connected at both ends of the support plate.
[0013] Furthermore, after removing the tube row to be replaced, a new tube row is replaced at the original position, and the cut suspension pipes corresponding to the middle of the support plate are connected to the suspension pipes corresponding to the new tube row.
[0014] Furthermore, all corresponding suspension pipes below the pipe row to be replaced are connected to the support plate through fixing parts.
[0015] Compared with the prior art, the advantages and positive effects of the present disclosure are:
[0016] (1) By arranging support plates and fixings, the load under the pipe bank to be replaced is transferred to the pipe banks on both sides that do not need to be replaced through the support plates, avoiding the need to arrange hanging points from the outside to suspend the load under the pipe bank to be replaced, and no tools such as fall chain wire ropes are required;
[0017] (2) It meets the need for temporary fixed support of the lower tube row when replacing the middle tube row of the tower boiler heating surface, prevents the tube row from sinking and falling, and avoids the need to use chain wire ropes to set up multiple hanging points, which not only saves tools but also improves labor efficiency;
[0018] (3) When installing a new pipe row, the pipe row support and fixing device fixes the spacing between the suspended pipes, which is convenient for the welding joints of the new pipe row, saves manpower, avoids the collision between the pipe row and the wire rope, facilitates the installation and transportation of the pipe row, and improves the efficiency and safety of the pipe row installation. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] The accompanying drawings constituting a part of the present disclosure are used to provide a further understanding of the present disclosure. The illustrative embodiments of the present disclosure and their descriptions are used to explain the present disclosure and do not constitute an improper limitation on the present disclosure.
[0020] Figure 1It is a schematic longitudinal section diagram of the heating surface tube row of the boiler in Examples 1 and 2 of the present disclosure;
[0021] Figure 2 It is a top view schematic diagram of the heating surface tube array of the boiler in Embodiments 1 and 2 of the present disclosure;
[0022] Figure 3 It is a schematic diagram of the structure of the support plate in Embodiments 1 and 2 of the present disclosure;
[0023] Figure 4 It is a schematic diagram of the structure of the fixing buckle in Embodiments 1 and 2 of the present disclosure;
[0024] Figure 5 It is a schematic diagram of the structure of the support plate, the fixing buckle and the suspension tube in the embodiments 1 and 2 of the present disclosure. DETAILED DESCRIPTION
[0025] It should be noted that the following detailed descriptions are illustrative and intended to provide further explanation of the present disclosure. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present disclosure belongs.
[0026] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present disclosure. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "include" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or their combinations;
[0027] For the convenience of description, if the words "up", "down", "left" and "right" appear in the present disclosure, they only indicate that they are consistent with the up, down, left and right directions of the drawings themselves, and do not limit the structure. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present disclosure.
[0028] As introduced in the background technology, the prior art adopts the method of chain wire rope suspension to realize the replacement of the intermediate tube row of the heating surface. When the tube row of the entire system is replaced, the demand for tools such as chain wire rope is too large; the tube row is suspended by the chain wire rope, and after the new tube row above is in place, the installation joint spacing is not uniform and the folding phenomenon is easy to occur; in view of the above problems, the present disclosure proposes a replacement support device and method for the intermediate tube row of the heating surface of the boiler.
[0029] Example 1
[0030] In a typical embodiment of the present disclosure, Figure 1-Figure 5As shown, a boiler heating surface intermediate tube row replacement support device is proposed.
[0031] It mainly includes a support plate and fixings. The fixings are divided into three groups. The three groups of fixings are sequentially installed on the support plate. Among them, the second group of fixings is used to connect the suspension pipes of the upper cut-off pipe row. The first group of fixings and the third group of fixings are located on both sides of the second group of fixings, and are both used to connect the suspension pipes of the uncut pipe row to provide auxiliary support for the suspension pipes of the cut-off pipe row.
[0032] The three sets of fixings are arranged according to the distribution of the tube banks. The tube bank in the middle of the heating surface is the tube bank to be replaced, and the tube banks on both sides are the tube banks that have not been replaced. The load is connected to the tube bank to be replaced through a suspension pipe. Figure 1 , Figure 2 As shown, there are multiple layers of pipe rows below the pipe row to be replaced as its load. When the pipe row to be replaced is repaired and replaced, the pipe row corresponding to the load below needs to be suspended or supported to maintain its original position;
[0033] The tube row that has not been replaced is the adjacent tube row of the middle tube row to be replaced, which is also suspended by the suspension pipe. Since it does not need to be replaced, the tube row is connected to the corresponding suspension pipe in sequence;
[0034] The middle part of the support plate is connected to the suspension pipes below the pipe row to be cut off, and the two ends are connected to the suspension pipes of the pipe row that has not been cut off. After the pipe row to be cut off is removed, the corresponding suspension pipes are cut off, and the load below is applied to the middle part of the support plate longitudinally. The support plate transfers the load to the two ends, thereby applying it to the suspension pipes of the pipe row that has not been cut off, and the suspension pipes on both sides are used to support the middle suspension pipe and the load below.
[0035] Each set of fixing members includes a plurality of fixing buckles arranged sequentially and spaced apart on the support plate, and the fixing buckles cooperate with the support plate to clamp the suspension pipe;
[0036] Since the fixing buckle and the suspension pipe are fixedly connected instead of suspended by flexible rope, the position of the suspension pipes is fixed, thus avoiding the friction and collision caused by wire rope suspension. In addition, there is no need to use chain wire rope, which will not block the new pipe row from entering the installation position.
[0037] When installing new pipe rows, the pipe row support and fixing device fixes the spacing between the suspended pipes, which is convenient for the new pipe row welding joint assembly, saves manpower, avoids the collision between the pipe row and the wire rope, facilitates the installation and transportation of the pipe row, and improves the efficiency and safety of the pipe row installation.
[0038] Example 2
[0039] In another typical embodiment of the present disclosure, Figure 1-Figure 5 As shown, a method for replacing the intermediate tube row of the boiler heating surface is proposed.
[0040] like Figure 1 , Figure 2 As shown, the tube banks of tower boilers are generally arranged from top to bottom, including economizer tube banks, reheater tube banks, and superheater tube banks. The tube banks in the furnace are suspended from top to bottom using hanging pipes. When replacing the upper tube bank, it is necessary to prevent the lower tube bank from sinking and falling, and facilities are used to constrain the position of the lower tube bank.
[0041] The traditional method is to fix the lower pipe row with the fall chain wire rope and then cut off the upper pipe row. The fall chain wire rope uses the upper hanging pipe as the rooting point;
[0042] However, this method has the problems described in the background technology, and cannot meet the existing demand for fast, accurate and safe replacement of pipe banks.
[0043] In this embodiment, a method for replacing a support that is convenient for disassembly and assembly and safe is provided, comprising the following steps:
[0044] Arrange the support plate and the fixings so that the support plate is located below the tube bank to be replaced and there are tube banks that have not been replaced on both sides of the tube bank to be replaced;
[0045] The middle part of the support plate is connected to the suspension pipes under the pipe row to be replaced through fixings, and the two ends are connected to the suspension pipes of the pipe row that has not been replaced through fixings; all the corresponding suspension pipes under the pipe row to be replaced are connected to the support plate through fixings, and the multiple suspension pipes corresponding to the pipe row that has not been replaced are connected to the support plate through fixings;
[0046] Cut off the suspension pipes between the pipe row to be replaced and the support plate, remove the pipe row to be replaced, and transfer the load on the suspension pipes under the pipe row to be replaced to the suspension pipes connected at both ends of the support plate;
[0047] After removing the pipe row to be replaced, replace the new pipe row in the original position, and connect the cut suspension pipe corresponding to the middle of the support plate with the suspension pipe corresponding to the new pipe row.
[0048] By arranging support plates and fixings, the load under the pipe bank to be replaced is transferred to the pipe banks on both sides that do not need to be replaced through the support plates, avoiding the need to arrange hanging points from the outside to suspend the load under the pipe bank to be replaced, and there is no need to configure tools such as fall chain wire ropes.
[0049] Further, the lower part of the middle of the support plate contacts the tube row below the tube row to be replaced, and the lower parts of both ends of the support plate contact and press against the tube row that has not been replaced;
[0050] The load on the suspended pipes below the pipe row to be replaced is transferred to the corresponding pipe rows not replaced at both ends of the support plate through the support plate, and is also transferred to the corresponding suspended pipes at both ends of the support plate through the fixings cooperating with the support plate;
[0051] On the one hand, the load is directly applied to the pipe row through the support plate, and on the other hand, it is applied to the suspension pipe through the fixing parts in conjunction with the pipe row, thereby realizing double load bearing, improving the load-bearing capacity of the support plate, avoiding stress concentration caused by the connection parts and the support plate cooperating position bearing the entire load, and evenly distributing the load to the uncut suspension pipe and the uncut pipe row.
[0052] Combined with the solution in Example 1, in this embodiment, each set of fixing members in Example 1 includes a plurality of fixing buckles, a plurality of suspension pipes are correspondingly arranged below the tube row to be replaced, a plurality of suspension pipes are correspondingly connected to the tube row not replaced, and the fixing members connect the suspension pipes to the support plate accordingly;
[0053] There are multiple support plates, each row of suspension pipes corresponds to one support plate, and multiple rows of suspension pipes below the pipe row to be replaced are connected to multiple support plates accordingly.
[0054] Combination Figure 3-Figure 5 , the tube bank replacement method in this embodiment is described in detail:
[0055] Step 1: Use a 20mm thick steel plate as the support plate, and punch holes according to the spacing of the pipes in the pipe row suspension pipes. The holes will serve as the installation holes for the connecting fixings.
[0056] Step 2: Make a U-shaped bolt clip as a fixing buckle. Both ends of the U-shaped bolt clip are provided with threads and are matched with corresponding nuts respectively;
[0057] Step 3: Before cutting the suspended pipe, first support the steel plate to the top of the lower pipe row, use the U-bolt clamp to clamp the suspended pipe under the pipe row to be cut and the suspended pipe of the pipe row that has not been cut, insert the U-bolt clamp into the corresponding steel plate hole, tighten the nut, and then cut the suspended pipe under the pipe row to be replaced in the middle position of the fixed support device. In this embodiment, the number of suspended pipes cut is 3-5 rows, and the middle load is transferred to the pipe rows on both sides of the suspended pipe that has not been cut;
[0058] After removing the pipe row to be replaced, replace the new pipe row in the original position, and connect the cut suspension pipe corresponding to the middle of the support plate with the suspension pipe corresponding to the new pipe row.
[0059] When installing new pipe banks, it not only ensures that the spacing between the suspended pipes remains unchanged, but also avoids the obstruction of too many chain wire ropes hanging above, making it convenient for the reverse transportation and installation of the pipe banks and improving their safety. The U-bolt clips are very convenient to fix and install, and are easy to disassemble and can be reused.
[0060] It fills the gap of temporary fixed support for the lower tube row when replacing the middle tube row of the heating surface of the tower boiler. A set of convenient temporary fixed support devices for the tube row is developed and combined with the corresponding replacement method. It can be implemented when replacing the middle tube row of the heating surface of the boiler and achieves good application results.
[0061] During the entire replacement process, the use of the chain wire rope is avoided, thereby avoiding the potential safety hazard of the chain wire rope rubbing against the pipe bank during the reverse transportation process, and improving the safety of pipe bank replacement;
[0062] It should be pointed out that after the suspended pipes are fixed with support plates and fixings, the spacing and position remain unchanged, which facilitates the installation of the new pipe row and avoids the occurrence of folding.
[0063] The above description is only a preferred embodiment of the present disclosure and is not intended to limit the present disclosure. For those skilled in the art, the present disclosure may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present disclosure shall be included in the protection scope of the present disclosure.
Claims
1. A boiler heating surface intermediate tube row replacement support device, characterized in that: It includes a support plate and three sets of fixings, which are sequentially mounted on the support plate. The second set of fixings is used to connect the suspension pipes of the upper cut-off pipe row. The first set of fixings and the third set of fixings are located on both sides of the second set of fixings, and are both used to connect the suspension pipes of the uncut-off pipe row to provide auxiliary support for the suspension pipes of the cut-off pipe row. The three groups of fixings are arranged according to the distribution of the tube rows. The tube row in the middle of the heating surface is the tube row to be replaced, and the tube rows on both sides are the tube rows that have not been replaced. The tube row to be replaced is connected to its load through a suspension pipe, and there are multiple layers of tube rows below the tube row to be replaced as its load; the tube row that has not been replaced is the adjacent tube row to the middle tube row to be replaced, and the tube rows are connected to the corresponding suspension pipes in sequence; The support plate is located below the tube row to be replaced; The middle part of the support plate is connected to the suspension pipes below the pipe row to be cut off, and the two ends are connected to the suspension pipes of the pipe row that has not been cut off. After the pipe row to be cut off is removed, the corresponding suspension pipes are cut off, and the load below is applied to the middle part of the support plate longitudinally. The support plate transfers the load to the two ends and applies it to the suspension pipes of the pipe row that has not been cut off. The suspension pipes on both sides are used to support the middle suspension pipe and the load below.
2. The boiler heating surface intermediate tube row replacement support device according to claim 1, characterized in that: Each set of fixing members includes a plurality of fixing buckles which are sequentially arranged at intervals on the support plate, and the fixing buckles cooperate with the support plate to clamp the suspension pipe.
3. A method for replacing an intermediate tube row of a boiler heating surface, characterized in that: The following steps are involved: Arrange the support plate and the fixings so that the support plate is located below the tube row to be replaced; The middle part of the support plate is connected to the suspension pipe under the pipe row to be replaced through a fixing piece, and the two ends are connected to the suspension pipe of the pipe row that has not been replaced through fixing pieces respectively; Cut off the suspension pipes between the pipe row to be replaced and the support plate, remove the pipe row to be replaced, and transfer the load on the suspension pipes below the pipe row to be replaced to the suspension pipes connected at both ends of the support plate.
4. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 3, characterized in that: After removing the pipe row to be replaced, replace the new pipe row in the original position, and connect the cut suspension pipe corresponding to the middle of the support plate with the suspension pipe corresponding to the new pipe row.
5. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 4, characterized in that: All corresponding suspended pipes below the pipe row to be replaced are connected to the support plate through fixings.
6. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 3, characterized in that: There are unreplaced tube rows on both sides of the tube row to be replaced, and multiple suspension pipes corresponding to the unreplaced tube rows are connected to the support plate through fixing parts.
7. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 3, characterized in that: The lower part of the middle of the support plate contacts the tube row below the tube row to be replaced, and the lower parts of both ends of the support plate contact and press against the tube row that has not been replaced.
8. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 7, characterized in that: The load on the suspended pipes below the pipe row to be replaced is transferred to the corresponding unreplaced pipe rows at both ends of the support plate through the support plate, and is also transferred to the corresponding suspended pipes at both ends of the support plate through the fixings cooperating with the support plate.
9. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 3, characterized in that: There are multiple suspension pipes correspondingly under the pipe row to be replaced, and there are multiple suspension pipes correspondingly connected to the pipe row that has not been replaced. The fixing parts connect the suspension pipes to the support plates accordingly.
10. The method for replacing the intermediate tube bank of the boiler heating surface according to claim 9, characterized in that: There are multiple support plates, each row of suspension pipes corresponds to one support plate, and multiple rows of suspension pipes below the pipe row to be replaced are connected to multiple support plates accordingly.