Construction safety risk analysis method of pumped storage power station based on energy transfer theory

Through the energy transfer theory, the construction safety risk model of pumped storage power stations is established, and the safety risks during the construction period are systematically identified and evaluated, which solves the problem of low risk identification efficiency caused by relying on expert experience in the existing technology, and realizes the scientific nature of construction safety risks. and standardize, providing effective risk prevention and control measures.

CN112036716BActive Publication Date: 2024-11-19ENG CONSTR MANAGEMENT BRANCH OF CHINA SOUTHERN POWERGRID POWER GENERATION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202010839541.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-08-19
Publication Date
2024-11-19
Estimated Expiration
2040-08-19

AI Technical Summary

Technical Problem

The existing engineering construction safety risk identification methods rely on expert experience and lack standardization and targetedness, resulting in low risk identification efficiency and lack of systematicity and scientificity.

Method used

Based on the energy transfer theory, establish a safety risk model and analysis method for pumped storage power station construction, and calculate the risk value, divide the risk level and determine the pre-control measures to form risks by decomposing engineering tasks, identifying hazard sources, establishing judgment matrix and evaluation sets. Database to realize the systematic identification and evaluation of safety risks during construction period.

Benefits of technology

It improves the standardization and pertinence of construction safety risks identification, reduces subjective impact, enhances the scientificity and reliability of construction safety risks, and provides effective risk prevention and control measures for construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112036716B_ABST
    Figure CN112036716B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for analyzing the construction safety risks of a pumped-storage power station based on the energy transfer theory, and is characterized in that the method comprises the following steps: step S1: establishing a safety risk analysis model, and preparing a safety risk database according to the established risk analysis model; step S2: performing risk analysis and assessment on energy or dangerous substances existing during the construction period that may be accidentally released according to the established risk analysis model, and obtaining risk results by searching the risk database; step S3: selecting preventive control measures for correction according to the risk results, tracking and detecting the construction project of the pumped-storage power station according to the risk assessment results and the preventive control measures, and conducting real-time risk analysis of the construction project in combination with the precision division of the divisions, sub-projects, and processes of the construction project and the implementation of the preventive control measures, thereby reducing the probability of the occurrence of risk events.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pumped storage power station construction risk management, and in particular to a pumped storage power station construction safety risk analysis method based on energy transfer theory. Background Art

[0002] At present, the focus of research on engineering construction safety risks is on how to conduct safety risk assessment and early warning. Risk identification is the key to troubleshooting safety hazards, and the existing identification methods are mostly based on expert experience and judgment. This method is greatly influenced by the operator's subjective influence and requires very high ability and experience of the operator, making risk identification inefficient, lacking standardization and pertinence. There are relatively few studies on engineering construction risk analysis based on risk identification.

[0003] Therefore, in order to reduce the subjective influence of personnel in the risk identification process, it is particularly important to enhance the standardization and pertinence of safety risk identification and analysis in the construction of pumped-storage power stations. Summary of the invention

[0004] In view of this, the present invention studies the identification and analysis of safety risks during the construction period of a pumped-storage power station from the perspective of the causation theory of energy transfer accidents, proposes a safety risk model and analysis method for the construction of a pumped-storage power station, and provides a basis for the establishment of a safety risk database during the construction period of a pumped-storage power station.

[0005] The technical solution adopted by the present invention is:

[0006] A safety risk analysis method for construction of pumped storage power stations based on energy transfer theory.

[0007] The method comprises the following steps:

[0008] Step S1: Establish a security risk analysis model, and create a risk database based on the established risk analysis model;

[0009] Step S2: Perform risk analysis and assessment on the energy or hazardous substances that are accidentally released during the construction period according to the established risk analysis model, and obtain risk results by searching the risk database;

[0010] Step S3: Select preventive control measures for correction based on the risk results.

[0011] Preferably, in the above step S1, the process of establishing the security risk analysis model is as follows:

[0012] Step S101: Decomposing the construction tasks of the pumped storage power station project to determine the hazard sources;

[0013] Step S102: Identify the hazard sources and divide them into two categories, namely, the first category hazard sources and the second category hazard sources; identify the first category hazard source set U1 = {X1, X2, X3, ..., X15}, refine the first category hazard sources to identify the second category hazard source set U2 = {Y1, Y2, Y3, ..., Y98};

[0014] Step S103: Establish a judgment matrix G. According to the danger sources U1 and U2 determined in step S102, use the 1-9 scaling method to compare the factors in the same criterion layer in pairs and assign corresponding scores to obtain the judgment matrix G, where i is the criterion layer number and n is the number of influencing factors in the criterion layer;

[0015]

[0016] Step S104: Establish an evaluation set V, which is a set of various risk assessment results, V = {v1, v2, ..., vk}, and the evaluation set V is expressed as "very high, high, medium, low, acceptable", and each expression corresponds to a corresponding evaluation scale value;

[0017] Step S105: Calculate the maximum eigenvalue λmax of the judgment matrix G. First, calculate the product M of the elements in each row of the judgment matrix. j , and then find M j The nth root of Normalized processing is recorded as Get the feature vector W = [W1, W2, ..., W m ], the eigenvector W i That is, weight ωi;

[0018] Using the formula The calculated maximum eigenvalue λmax, (GW) i is the product of the i-th row element of the judgment matrix G and the eigenvector W, n is the number of influencing factors in the criterion layer, and i is the criterion layer number;

[0019] Step S106: Calculate the consistency CG of the judgment matrix and check whether its value is valid, using the following formula:

[0020]

[0021]

[0022] In the above formula, n is the number of influencing factors in the criterion layer; GI is the average random consistency CG index; the value of GI is as follows:

[0023] n 1 2 3 4 5 6 7 8 9 GI 0 0 0.58 0.90 1.12 1.24 1.32 1.41 1.45

[0024] When the consistency value CG < 0.1, the inconsistency of the judgment matrix is ​​within an acceptable range and passes the consistency test; if CG > 0.1, the consistency fails and the weight value obtained should be discarded and re-evaluated and calculated;

[0025] Step S107: Determine the level matrix Gi of each factor in the single criterion layer by using the trapezoidal membership function. By integrating the level matrix Gi of all factors in the single criterion layer, calculate the first-level fuzzy evaluation matrix Ri of the single criterion layer. The calculation formula is as follows:

[0026] Ri = ωi × Gi, where i is the order of the criterion layer, ω is the weight set of the criterion layer;

[0027]

[0028] Step S108: Perform secondary fuzzy comprehensive evaluation on the factors of all criterion layers to obtain the risk assessment result; the influence of a single criterion layer on the evaluation object is calculated in step S105, and the secondary fuzzy comprehensive evaluation is used to comprehensively consider the overall influence of the factors of all criterion layers on the evaluation result. The evaluation result is F, and the calculation formula is as follows:

[0029] R=ω×G;F=R×V T

[0030] Where ω is the weight distribution set of the main criterion layer, which is composed of the weights of each criterion layer; G is the evaluation matrix of the main criterion layer, which is composed of the evaluation matrix of each criterion layer; V is the evaluation set;

[0031] Step S109: Through the above analysis of the hazard source, the hazard of the operation step is evaluated, that is, D = L × E × C × B, where D represents the hazard value, L represents the probability value of an accident, E represents the frequency of human exposure to a hazardous environment or the influencing factors of equipment and devices, C represents the severity of the hazard; and B represents the management factor;

[0032] Step S110: Based on the calculation results, risk levels are classified and then preventive control measures for the operation steps are determined.

[0033] Based on the theory of energy transfer accident causation, the present invention studies the safety risk identification and assessment analysis during the construction period of a pumped-storage power station, proposes a safety risk analysis model for the construction period of a pumped-storage power station, analyzes and assesses the safety risks during the construction period of a pumped-storage power station, achieves the purpose of risk prevention and control, and provides reference and support for the safe construction of a pumped-storage power station. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.

[0035] Figure 1 This is a flow chart of risk analysis of the transportation step during blasting operation during construction of a pumped-storage power station according to an embodiment of the present invention. DETAILED DESCRIPTION

[0036] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0037] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0038] like Figure 1 As shown, the present invention specifically proposes a pumped storage power station construction safety risk analysis method based on energy transfer theory, the method comprising the following steps:

[0039] Step S1: Establish a security risk analysis model, and create a risk database based on the established risk analysis model;

[0040] Step S101: Decomposing the construction tasks of the pumped storage power station project to determine the hazard sources;

[0041] Step S102: Identify the hazard sources and divide them into two categories, namely, the first category hazard sources and the second category hazard sources; identify the first category hazard source set U1 = {X1, X2, X3, ..., X15}, refine the first category hazard sources to identify the second category hazard source set U2 = {Y1, Y2, Y3, ...Y98};

[0042] Step S103: Establish a judgment matrix G. According to the danger sources U1 and U2 determined in step S102, use the 1-9 scaling method to compare the factors in the same criterion layer in pairs and assign corresponding scores to obtain the judgment matrix G, where i is the criterion layer number and n is the number of influencing factors in the criterion layer;

[0043]

[0044] Step S104: Establish an evaluation set V, which is a set of various risk assessment results, V = {v1, v2, ..., vk}, and the evaluation set V is expressed as "very high, high, medium, low, acceptable", and each expression corresponds to a corresponding evaluation scale value;

[0045] Step S105: Calculate the maximum eigenvalue λmax of the judgment matrix G. First, calculate the product M of the elements in each row of the judgment matrix. j , and then find M j The nth root of Normalized processing is recorded as Get the feature vector W = [W1, W2, ..., W m ], the eigenvector W i That is, weight ωi;

[0046] Using the formula The calculated maximum eigenvalue λmax, (GW) i is the product of the i-th row element of the judgment matrix G and the eigenvector W, n is the number of influencing factors in the criterion layer, and i is the criterion layer number;

[0047] Step S106: Calculate the consistency CG of the judgment matrix and check whether its value is valid, using the following formula:

[0048]

[0049]

[0050] In the above formula, n is the number of influencing factors in the criterion layer; GI is the average random consistency CG index; the value of GI is as follows:

[0051] n 1 2 3 4 5 6 7 8 9 GI 0 0 0.58 0.90 1.12 1.24 1.32 1.41 1.45

[0052] When the consistency value CG < 0.1, the inconsistency of the judgment matrix is ​​within an acceptable range and passes the consistency test; if CG > 0.1, the consistency fails and the weight value obtained should be discarded and re-evaluated and calculated;

[0053] Step S107: Determine the level matrix Gi of each factor in the single criterion layer by using the trapezoidal membership function. By integrating the level matrix Gi of all factors in the single criterion layer, calculate the first-level fuzzy evaluation matrix Ri of the single criterion layer. The calculation formula is as follows:

[0054] Ri = ωi × Gi, where i is the order of the criterion layer, ω is the weight set of the criterion layer;

[0055]

[0056] Step S108: Perform secondary fuzzy comprehensive evaluation on the factors of all criterion layers to obtain risk assessment results; the influence of a single criterion layer on the evaluation object is calculated in step S105, and the secondary fuzzy comprehensive evaluation is used to comprehensively consider the overall influence of the factors of all criterion layers on the evaluation results. The evaluation result is F, and the calculation formula is as follows:

[0057] R=ω×G;F=R×V T

[0058] Where ω is the weight distribution set of the main criterion layer, which is composed of the weights of each criterion layer; G is the evaluation matrix of the main criterion layer, which is composed of the evaluation matrix of each criterion layer; V is the evaluation set;

[0059] Step S109: Through the above analysis of the hazard source, the hazard of the operation step is evaluated, that is, D = L × E × C × B, where D represents the hazard value, L represents the probability value of an accident, E represents the frequency of human exposure to the hazardous environment or the influencing factors of equipment and devices, and C represents the severity of the hazard;

[0060] Step S110: Based on the calculation results, risk levels are divided, and then preventive control measures for the operation steps are determined, wherein the preventive control measures include technical control measures, management control measures and individual protection control measures, wherein the management control measures include administrative management measures and emergency management measures.

[0061] Step S2: Perform risk analysis and assessment on the energy or hazardous substances that may be accidentally released during the construction period according to the established risk analysis model, and obtain risk results by searching the risk database;

[0062] Step S3: According to the risk results, preventive control measures are selected for correction. According to the risk assessment results and preventive control measures, the pumped storage power station construction project is tracked and detected. Combined with the division of the construction project's divisions, sub-projects, and precision division of processes as well as the implementation of preventive control measures, a real-time risk assessment of the construction project is conducted to reduce the probability of risk events.

[0063] In the above step S1, the risk database specifically includes information such as environmental characteristics, overall process, process, operation steps, accident category, first-category hazardous source, second-category hazardous source, hazard name, hazard category, hazard distribution, characteristics and risk conditions, possible risk consequences, risk scope, risk type, management factor, risk level analysis, risk level, control measures, etc. The above-mentioned types of information are sorted and tabulated according to the risk analysis model.

[0064] In the above step S102, the first type of hazard source set U = {X1, X2, X3, ..., X15} is identified, as shown in Table 1:

[0065] Table 1 The first category of hazardous sources in the construction of pumped storage power stations

[0066]

[0067]

[0068] The first type of hazard source is refined to identify the second type of hazard source set U1 = {Y1, Y2, Y3, ... Y98}, as shown in Table 2:

[0069] Table 2 Second category of hazards in construction of pumped storage power stations

[0070]

[0071] In the above step S109, the probability L of an accident or dangerous event is related to the type of work and the working environment, with the highest score being 10 points and the lowest score being 0.1 points. Please refer to the table below for score distribution.

[0072] Table 3 Comparison table of the probability L value of accidents or dangerous events

[0073]

[0074]

[0075] Exposure is the frequency of the first unintended event in the accident sequence that causes the most likely consequence of the hazard. See the table below for the distribution of points.

[0076] Table 4 Comparison table of frequency factors E values ​​for exposure to hazardous environments

[0077] Serial number The frequency of the first unexpected event that triggers an accident sequence Points a Continuous (many times a day) 10 b Often (about once a day) 6 c Sometimes (from once a week to once a month) 3 d Occasionally (from once a month to once a year) 2 e Rarely (said to have happened) 1 f Very rare (never happened, but there is a possibility of it happening) 0.5

[0078] The C value of the hazard severity factor is related to the severity of the consequences when an accident occurs under the action of the triggering factor. See the table below for the distribution of points.

[0079] Table 5 Comparison table of C values ​​of risk severity factors

[0080]

[0081]

[0082]

[0083] The management factor B value is related to the project's management measures and the implementation of the management measures. Comprehensively review the clauses corresponding to each score and list all the problems for each score. If there are several problems in both high-scoring and low-scoring areas, the B value should be the score of the high-scoring area. See the table below for score distribution.

[0084] Table 6 Management factor B value comparison table

[0085]

[0086]

[0087] In the above step S103, an evaluation set V is established, which is represented by "very high", "high", "medium", "low" and "acceptable".

[0088] Table 7 Hazard Assessment Set V

[0089] Risk Level D value Countermeasures Very high risk D≥400 Consider giving up, stopping High risk 200≤D<400 Immediate corrective action required Medium risk 70≤D<200 Corrective action is needed Low risk 20≤D<70 Need to pay attention Acceptable risk D<20 tolerate

[0090] In the above step S110, the technical control measures include the following:

[0091] 1) Elimination

[0092] Through reasonable design and scientific management, we can eliminate dangerous and harmful factors as fundamentally as possible, such as replacing unsafe energy with safe energy, adopting harmless process technology, replacing harmful substances with harmless substances in production, and realizing automation and remote control operations.

[0093] 2) Prevention

[0094] When the disaster-causing body (energy source or energy carrier) cannot be eliminated, preventive technical measures can be taken to limit the size and speed of accidental energy release, set safety limits, and use low-energy processes or equipment as much as possible in the production process. For example, use safety valves, safety shields, leakage protection devices, safety voltages, fuses, explosion-proof membranes, accident discharge devices, etc. In this way, even if accidental energy release occurs, serious injuries will not occur.

[0095] 3) Weakened

[0096] When it is impossible to eliminate or prevent dangerous and harmful factors, measures can be taken to reduce the danger and harm. From the energy perspective, these can be divided into four aspects:

[0097] Prevent energy accumulation. A large amount of energy accumulation will lead to sudden energy release. Therefore, it is necessary to release excess energy in time to prevent energy accumulation. For example, use low-altitude potential to control the concentration of explosive gases, eliminate static electricity accumulation through grounding, and use lightning rod discharge to protect important facilities.

[0098] Controlling the release of energy. For example, building sluice walls to prevent the sudden outburst of high-potential groundwater.

[0099] Delay the release of energy. Slowly releasing energy can reduce the energy released per unit time and reduce the effect of energy on the human body. For example, use safety valves and escape valves to control high-pressure gas; use the full collapse method to manage the coal roadway roof and control ground pressure; use various vibration reduction devices to absorb impact energy and prevent personnel from being injured.

[0100] Open up channels for releasing energy. For example, safe grounding can prevent electric shock, water exploration and drainage in mines can prevent water seepage, and extracting gas from coal bodies can prevent gas accumulation and explosion.

[0101] 4) Isolation

[0102] When it is impossible to eliminate, prevent or reduce the energy, the physical entity that contacts the energy should be separated from the personnel, i.e. shielding in a narrow sense. Shielding facilities can be installed on the energy source, such as a protective cover installed outside the rotating part of the machine; they can also be installed between the personnel and the energy source, such as a safety fence.

[0103] Individual protection measures are essentially shielding facilities installed on personnel, such as personal protective equipment (protective clothing, various gas masks), etc. In theory, individual protection measures are the last isolation measure for energy transmission to the affected body (human body). Whether from the perspective of intrinsic safety or accidental energy release, they are not the top priority technical control measures, but they are the last line of defense to protect operators.

[0104] Management and control measures include safety management system, safety management organization and personnel, safety training and education, safety investment and safety facilities, and safety supervision and inspection; emergency management measures mainly include emergency management system, emergency response plan for sudden accidents, emergency warning, emergency response, emergency drills, etc.

[0105] Example 1

[0106] Blasting is a common process in the construction of pumped storage power stations, and it is also one of the processes with relatively high risks. The blasting process can be divided into 8 steps according to the construction process, which are: ① transportation; ② warning; ③ on-site storage; ④ charging; ⑤ networking; ⑥ detonation; ⑦ ventilation and smoke dispersion; ⑧ blind shot treatment.

[0107] Taking step transport as an example, apply the model to analyze the results.

[0108] According to the transportation operation steps, the specific conditions of the operation are determined from five aspects: "people, machines, materials, methods, and environment". The personnel involved in the operation include the transport vehicle driver and blaster; the machinery and equipment involved include the transport vehicle; the materials involved include explosives and detonators; and the environmental factors involved include weather and road conditions.

[0109] The identification of hazardous sources is carried out on the basis of the specific conditions of the operation determined by the operation steps. The materials involved in the transportation step, explosives and detonators, are disaster-causing objects and are the first type of hazardous sources. After analysis and judgment of the operation process, it was determined that there were factors in the operation process that led to the accidental release of energy from explosives and detonators. Human factors include mixed loading of detonators and explosives, overloaded transportation, simultaneous loading and unloading, use of mobile phones, carrying fire, etc.; machine factors include vehicles without anti-static measures, etc.; material factors include unqualified blasting materials, etc.; environmental factors include rainy and snowy weather, slippery roads, etc.

[0110] Risk assessment is to calculate the size of the risk through the possibility of risk occurrence, the frequency of personnel exposure, the size of the accident consequences and the influence of management factors. From the table, we can see that the value of the possibility of occurrence (L) is 0.5, the value of the exposure frequency (E) is 3, the value of the accident consequence (C) is 50, and the management factor is 1 considering the industry average level. The calculated result of the risk size (D) is 0.5×3×50×1=75, which is a medium risk and needs to be corrected.

[0111] Control measures are considered from four aspects: technical control measures, administrative control measures, individual protection measures and emergency management measures. The technical control measures that can be taken include: using a special detonator box to place detonators during transportation; setting up a storage box to put mobile phones and fire starters in; detonators and explosives are loaded and unloaded separately by blasters and stored separately on site. Administrative management measures can provide training and education for employees, requiring relevant personnel to hold certificates before taking up their posts. Emergency management measures include the preparation and improvement of corresponding accident emergency plans, etc.

Claims

1. A pumped storage power station construction safety risk analysis method based on energy transfer theory, characterized in that: The method comprises the following steps: Step S1: Establish a risk analysis model, and create a risk database based on the established risk analysis model; Step S2: Conduct risk assessment on energy or hazardous substances that may be accidentally released during the construction period according to the established risk analysis model, and obtain risk results by searching the risk database; Step S3: Select preventive measures for correction according to the risk results, track and detect the pumped storage power station construction project according to the risk assessment results and preventive measures, and conduct real-time risk assessment of the construction project in combination with the division, sub-project, and process precision of the construction project and the implementation of preventive measures, thereby reducing the probability of risk events; In the above step S1, the risk analysis model establishment process is as follows: Step S101: Decomposing the construction tasks of the pumped storage power station project to determine the hazard sources; Step S102: Identify the hazard sources and divide them into two categories, namely, the first category hazard sources and the second category hazard sources; identify the first category hazard source set U1 = {X1, X2, X3, ..., X15}, refine the first category hazard sources to identify the second category hazard source set U2 = {Y1, Y2, Y3, ..., Y98}; Step S103: Through the above analysis of the hazard source, the hazard of the operation step is evaluated, that is, D = L × E × C × B, where D represents the hazard value, L represents the probability value of an accident, E represents the frequency of human exposure to a hazardous environment or the influencing factors of equipment and devices, C represents the severity of the hazard; and B represents the management factor; Step S104: Establish an evaluation set V, which is a set of various risk assessment results, V = {v1, v2, ..., vk}, and the evaluation set V is expressed as "very high, high, medium, low, acceptable", and each expression corresponds to a corresponding risk value D; The specific steps of step S104 include: Step S105: Establish a judgment matrix G. According to the danger sources U1 and U2 determined in step S102, use the 1-9 scaling method to compare the factors in the same criterion layer in pairs and assign corresponding scores to obtain the judgment matrix G, where i is the criterion layer sequence number and n is the number of influencing factors in the criterion layer; Step S106: Calculate the maximum eigenvalue λmax of the judgment matrix G. First, calculate the product M of the elements in each row of the judgment matrix. j , and then find M j The nth root of Normalized processing is recorded as Get the feature vector W = [W1, W2, ..., W m ], the eigenvector W i That is, weight ωi; Using the formula The calculated maximum eigenvalue λmax, (GW) i is the product of the i-th row element of the judgment matrix G and the eigenvector W, n is the number of influencing factors in the criterion layer, and i is the criterion layer number; Step S107: Calculate the consistency CG of the judgment matrix and check whether its value is valid, using the following formula: In the above formula, n is the number of influencing factors in the criterion layer; GI is the average random consistency CG index; the value of GI is as follows: When the consistency value CG < 0.1, the inconsistency of the judgment matrix is ​​within an acceptable range and passes the consistency test; if CG > 0.1, the consistency fails and the weight value obtained should be discarded and re-evaluated and calculated; Step S108: Determine the level matrix Gi of each factor in the single criterion layer by using the trapezoidal membership function. By integrating the level matrix Gi of all factors in the single criterion layer, calculate the first-level fuzzy evaluation matrix Ri of the single criterion layer. The calculation formula is as follows: Ri = ωi × Gi, where i is the order of the criterion layer, ω is the weight set of the criterion layer; Step S109: Perform secondary fuzzy comprehensive evaluation on the factors of all criterion layers to obtain the risk assessment result; the influence of a single criterion layer on the evaluation object is calculated in step S105, and the secondary fuzzy comprehensive evaluation is used to comprehensively consider the overall influence of the factors of all criterion layers on the evaluation result. The evaluation result is F, and the calculation formula is as follows: R=ω×G;F=R×V T Where ω is the weight distribution set of the main criterion layer, which is composed of the weights of each criterion layer; G is the evaluation matrix of the main criterion layer, which is composed of the evaluation matrix of each criterion layer; V is the evaluation set; Step S110: According to the calculation results, risk levels are classified, and then the preventive control measures for the operation steps are determined; The risk database specifically includes environmental characteristics, overall process, process, operation steps, accident category, first category hazard source, second category hazard source, hazard name, hazard category, hazard distribution, characteristics and risk conditions, possible risk consequences, risk scope, risk type, management factor, risk level analysis, risk level, control measures information, and the above-mentioned information is organized and tabulated according to the risk analysis model.