Blockchain-based construction waste management method, device, equipment and storage medium

By using blockchain technology to store and compare information on the chain in construction waste management, the problem of low manual information transmission efficiency is solved, the full life cycle management and environmental protection of construction waste is realized, and management accuracy and efficiency are improved.

CN114399187BActive Publication Date: 2024-11-26XIAN JIAOTONG LIVERPOOL UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210015289.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-01-07
Publication Date
2024-11-26
Estimated Expiration
2042-01-07

AI Technical Summary

Technical Problem

The existing construction waste recycling management methods rely on manual information transmission, resulting in low information accuracy and efficiency, resulting in construction waste being illegally landfilled, causing environmental pollution, and failing to achieve system management and auditing, affecting management efficiency and accuracy.

Method used

Adopt a blockchain-based construction waste management method, and obtain information from the demolition and construction party and garbage collector for on-chain storage, judge the qualified conditions for information comparison, ensure the integrity and safety of information, and realize the full life cycle management of construction waste. .

Benefits of technology

It effectively avoids information tampering and loss, realizes information supervision of the construction waste industry, reduces the risk of environmental pollution, eliminates illegal and disorderly behaviors, improves the efficiency and accuracy of construction waste management, and saves manpower and time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114399187B_ABST
    Figure CN114399187B_ABST
Patent Text Reader

Abstract

The embodiment of the present invention discloses a method, device, equipment and storage medium for construction waste management based on blockchain. The method includes: obtaining the initial construction waste information uploaded by the demolition party, and storing the initial construction waste information on the chain; obtaining the received construction waste information uploaded by the waste recycling party, and storing the received construction waste information on the chain; judging whether the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions; if so, obtaining the to-be-traded building materials information corresponding to the received construction waste information uploaded by the waste recycling party, and storing the to-be-traded building materials information on the chain, so as to manage the construction waste throughout its life cycle. The information of construction waste throughout its life cycle is recorded in time through the blockchain to avoid tampering or loss of information, realize the full life cycle management of construction waste, and improve the management efficiency and accuracy of construction waste.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] Embodiments of the present invention relate to blockchain technology, and in particular to a construction waste management method, device, equipment and storage medium based on blockchain. Background Art

[0002] Recycling construction waste is beneficial to protecting the environment and saving resources. In order to avoid the waste and random discard of construction waste, it is necessary to record information on construction waste.

[0003] The existing construction waste recycling management method relies on manual information transmission, which has low accuracy and efficiency. For example, when the demolition and construction party transports the construction waste to the waste recycling party, due to cost considerations, they will conceal the demolition and construction conditions and directly landfill the construction waste illegally, causing serious environmental problems. Moreover, the recycled construction waste resources have not been systematically managed and audited, which hinders the overall statistics of the environmental department on the entire life cycle of construction waste and affects the management efficiency and accuracy of construction waste. Summary of the invention

[0004] The embodiments of the present invention provide a construction waste management method, device, equipment and storage medium based on blockchain to achieve full life cycle management of construction waste.

[0005] In a first aspect, an embodiment of the present invention provides a construction waste management method based on blockchain, the method is executed by a blockchain node, and the method includes:

[0006] Obtaining the initial construction waste information uploaded by the demolition and construction party, and storing the initial construction waste information on the chain;

[0007] Obtaining the received construction waste information uploaded by the waste collector, and storing the received construction waste information on the chain;

[0008] Determining whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition;

[0009] If so, the information of building materials to be traded corresponding to the received construction waste information uploaded by the waste recycling party is obtained, and the information of building materials to be traded is stored on the chain to manage the construction waste throughout its life cycle.

[0010] In a second aspect, an embodiment of the present invention further provides a construction waste management device based on blockchain, the device is configured in a blockchain node, and the device includes:

[0011] The initial waste information acquisition module is used to acquire the initial construction waste information uploaded by the demolition and construction party, and store the initial construction waste information on the chain;

[0012] The received garbage information acquisition module is used to acquire the received construction garbage information uploaded by the garbage collector and store the received construction garbage information on the chain;

[0013] A garbage information determination module, used to determine whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition;

[0014] The module for determining the information of building materials to be traded is used to obtain the information of building materials to be traded corresponding to the received construction waste information uploaded by the waste recycling party, and store the information of building materials to be traded on the chain to manage the construction waste throughout its life cycle.

[0015] In a third aspect, an embodiment of the present invention further provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the program, the blockchain-based construction waste management method as described in any embodiment of the present invention is implemented.

[0016] In a fourth aspect, an embodiment of the present invention further provides a storage medium comprising computer executable instructions, which, when executed by a computer processor, are used to execute the blockchain-based construction waste management method as described in any embodiment of the present invention.

[0017] The embodiment of the present invention can obtain the information of the two parties in the construction waste management process by storing the initial construction waste information of the demolition party and the received construction waste information of the waste recycling party on the chain, thereby preventing the information from being tampered with or lost. By comparing the initial construction waste information and the received construction waste information, it is possible to achieve information-based supervision of the demolition and construction waste industry, prevent the demolition and construction party from illegally landfilling construction waste, effectively reduce the risk of environmental pollution, and eliminate illegal and disorderly behaviors. It solves the problem of manual exchange of construction waste information in the prior art, saves manpower and time, realizes information exchange of construction waste, and improves the efficiency and accuracy of construction waste management. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a flowchart of a construction waste management method based on blockchain in Embodiment 1 of the present invention;

[0019] Figure 2 This is a flowchart of a construction waste management method based on blockchain in Embodiment 2 of the present invention;

[0020] Figure 3 This is a structural block diagram of a construction waste management device based on blockchain in Embodiment 3 of the present invention;

[0021] Figure 4This is a structural diagram of a blockchain-based construction waste management device in Embodiment 4 of the present invention. DETAILED DESCRIPTION

[0022] The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.

[0023] Embodiment 1

[0024] Figure 1 This is a flowchart of a method for managing construction waste based on blockchain provided in the first embodiment of the present invention. This embodiment is applicable to the supervision of the entire life cycle of construction waste. The method can be executed by a construction waste management device configured on a blockchain node. Figure 1 As shown, the method specifically comprises the following steps:

[0025] Step 110: Obtain the initial construction waste information uploaded by the demolition and construction party, and store the initial construction waste information on the chain.

[0026] Among them, the demolition party is the party that dismantles abandoned buildings into construction waste during the management of construction waste. The demolition party can be a demolition company that mainly engages in building demolition and maintenance, and is responsible for the transportation and processing of construction waste. For example, the demolition company performs demolition activities, obtains construction waste, and transports the construction waste to a designated location. After the demolition party obtains the construction waste, it determines the information of the construction waste as the initial construction waste information, and can store the initial construction waste information in the blockchain through a preset client. For example, the client can be an SDK (Software Development Kit) based on Linux, Windows or MacOS (an operating system) system. The parties involved in the construction waste can log in to their respective accounts to achieve different permissions. The SDK encapsulates data acquisition, data review and node request functions, as well as user information interaction interface, etc.; for the on-chain storage of information, the initial construction waste information can be temporarily stored in the AMDB (Advanced Mass Database, distributed storage) table of the blockchain node.

[0027] The initial construction waste information may include the transportation starting point, end point, weight, type and transportation time of the construction waste.

[0028] In an embodiment of the present invention, the underlying architecture of the system for implementing the construction waste management method can be a consortium chain system based on the Ethereum blockchain, and the registration and authorization of each participant in the consortium chain need to be reviewed. After the review, each participant can upload relevant information about construction waste in the system. For example, the system can be a public service application based on the open source financial management architecture FISCO-BCOS, which is a consortium chain solution based on the Ethereum virtual machine. For another example, the system can be based on the open source Hyperledger fabric, which is a hyperledger framework developed by IBM (International Business Machines Corporation). With the encryption mechanism provided by the consortium chain architecture, as well as the consensus process and anti-tampering mechanism, the information security on the chain can be effectively protected. By identifying the wrong information nodes, some attempts to illegally tamper with the data can also be effectively avoided, further ensuring the security of the information.

[0029] In the present embodiment, optionally, after obtaining the initial construction waste information uploaded by the demolition and construction party and storing the initial construction waste information on the chain, it also includes: sending an initial construction waste information review instruction to the construction waste supervisor, so that the construction waste supervisor can judge whether the initial construction waste information meets the preset preliminary review conditions based on the pre-stored estimated construction waste information; receiving the preliminary review pass information fed back by the construction waste supervisor, and sending an initial construction waste transportation instruction to the demolition and construction party, so that the demolition and construction party can transport the initial construction waste to the waste recycling party.

[0030] Specifically, the participants in construction waste management may also include construction waste supervisors and waste recyclers. Construction waste supervisors may be local regulatory authorities, which are mainly responsible for the supervision of demolition and construction waste, sustainable development and environmental protection, and can also authorize, supervise and manage other participants in the system. Waste recyclers may be construction waste recycling companies that own construction waste treatment plants, which are mainly responsible for harmlessly treating construction waste and producing building materials. For example, construction waste recycling companies can receive waste, treat waste, produce green building materials, and transport building materials to designated locations.

[0031] After confirming that the demolition and construction party has uploaded the initial construction waste information, an initial construction waste information review instruction can be sent to the construction waste supervisor, instructing the construction waste supervisor to review the initial construction waste information. Before the demolition and construction party obtains the construction waste, the construction waste supervisor predicts the construction waste that can be generated by the building to be demolished and estimates the construction waste that may be obtained as the estimated construction waste information. The estimated construction waste information may include the estimated type and weight of construction waste, etc. After receiving the initial construction waste information review instruction, the construction waste supervisor judges the initial construction waste information based on the pre-stored estimated construction waste information. Determine whether the initial construction waste information meets the preset preliminary review conditions. If so, send a preliminary review pass message to the blockchain node; if not, send a preliminary review failure message.

[0032] The preset preliminary review condition may be that if the estimated construction waste information is consistent with the initial construction waste information, it is determined that the initial construction waste information meets the preliminary review condition; if they are inconsistent, it is determined that the initial construction waste information does not meet the preliminary review condition. A difference threshold may also be preset, for example, the difference threshold may be a weight difference threshold. If the difference between the weight of the construction waste in the estimated construction waste information and the weight of the construction waste in the initial construction waste information is within the weight difference threshold, it is determined that the initial construction waste information meets the preliminary review condition; if it is not within the weight difference threshold, it is determined that the initial construction waste information does not meet the preliminary review condition.

[0033] If the preliminary review information is received from the construction waste supervisor, the initial construction waste transportation instructions can be sent to the demolition and construction party, instructing the demolition and construction party to transport the initial construction waste to the waste recycling party. If the preliminary review information is received from the construction waste supervisor, it is considered that there may be violations such as discarding or landfilling of the construction waste information, and a prompt message is sent to the construction waste supervisor to prompt the construction waste supervisor to conduct an on-site inspection. The beneficial effect of this setting is that the initial construction waste information uploaded by the demolition and construction party can be supervised by the construction waste supervisor, preventing the demolition and construction party from privately landfilling or discarding the obtained construction waste, thereby avoiding damage to the environment. The audit results can be stored on the chain with a timestamp, which is convenient for subsequent review and improves the management accuracy of construction waste.

[0034] Step 120: Obtain the received construction waste information uploaded by the waste collector, and store the received construction waste information on the chain.

[0035] Among them, the garbage recycling party receives the construction waste transported by the demolition party, counts the information of the received construction waste, and uses the information of the received construction waste as the received construction waste information. The received construction waste information may include the weight, type, receiving location and receiving time of the construction waste. The garbage recycling party can upload the received construction waste information to the blockchain through the client, and the blockchain node stores the received construction waste information on the chain. For example, the received construction waste information can be uploaded to the AMDB table of the blockchain node for temporary storage.

[0036] Step 130: Determine whether the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions.

[0037] Among them, after obtaining the received construction waste information, the initial construction waste information can be compared with the received construction waste information to determine whether the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions. For example, the preset information comparison qualification condition is the time difference threshold between the start time of transportation and the receiving time of the construction waste. The time when the demolition and construction party starts transportation in the initial construction waste information and the receiving time of the waste recycling party in the received construction waste information are obtained to determine the time difference between the start time of transportation and the receiving time. If the time difference is within the preset time difference threshold, it can be considered that the initial construction waste information and the received construction waste information meet the information comparison qualification conditions; if the time difference is not within the preset time difference threshold, it can be considered that the demolition and construction party has violated the regulations on the construction waste during transportation, resulting in delays, such as discarding or landfilling, etc., and a prompt message can be sent to the construction waste supervision party to prompt the construction waste supervision to conduct an inspection.

[0038] In this embodiment, optionally, it is determined whether the initial construction waste information and the received construction waste information satisfy the preset information comparison qualification conditions, including: determining whether the initial construction waste information and the received construction waste information are consistent, and if so, determining whether the initial construction waste information and the received construction waste information satisfy the preset information comparison qualification conditions.

[0039] Specifically, the preset information comparison qualification condition may be to compare the initial construction waste information with the received construction waste information one by one to determine whether the initial construction waste information is consistent with the received construction waste information. For example, the type of waste in the initial construction waste information may be compared with the type of waste in the received construction waste information, and the weight of waste in the initial construction waste information may be compared with the weight of waste in the received construction waste information. If the initial construction waste information is consistent with the received construction waste information, it is determined that the initial construction waste information and the received construction waste information meet the preset information comparison qualification condition; if they are inconsistent, it is determined that the initial construction waste information and the received construction waste information do not meet the preset information comparison qualification condition. The beneficial effect of such a setting is to ensure that the construction waste received by the waste recycling party is the construction waste obtained by the demolition and construction party, avoid the loss of construction waste, realize the automation of construction waste management, and improve the efficiency and accuracy of construction waste management.

[0040] Step 140: If yes, obtain the building materials information to be traded corresponding to the received construction waste information uploaded by the waste recycling party, and store the building materials information to be traded on the chain to manage the construction waste throughout its life cycle.

[0041] Among them, if the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions, the waste recycling party is allowed to process the received construction waste, convert the construction waste into building materials, and use them as the building materials to be traded corresponding to the received construction waste, and obtain the building materials information to be traded of the building materials to be traded. The building materials information to be traded may include the type, quantity and weight of the building materials to be traded. The waste recycling party can upload the building materials information to be traded through the client, and the blockchain node will store the building materials information to be traded on the chain to achieve the management of construction waste from generation to disappearance. The information of construction waste in various processes such as production and transportation is stored in the blockchain to prevent information tampering, improve the security and accuracy of information storage, and thus improve the efficiency and accuracy of construction waste management.

[0042] In this embodiment, optionally, before obtaining the building materials information to be traded corresponding to the received construction waste information uploaded by the waste recycler, it also includes: if it is determined that the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions, a building materials manufacturing permission instruction is sent to the waste recycler, so that the waste recycler can convert the received construction waste into building materials to be traded, and upload the building materials information to be traded to the blockchain.

[0043] Specifically, if it is determined that the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions, it is determined that there is no error in the construction waste received by the waste recycler, and the waste recycler can be allowed to process the construction waste into building materials.

[0044] Send a building material manufacturing permission instruction to the waste recycling party. After receiving the building material manufacturing permission instruction, the waste recycling party converts the received construction waste into building materials to be traded, and uploads the information of the building materials to be traded to the blockchain. The building materials to be traded are obtained by processing the received construction waste, and are waiting for the waste recycling party to trade with the building material demander. The building material demander is also a participant in the construction waste management process. It can be a building material company or a building material purchaser, etc., who is mainly responsible for purchasing and receiving recycled building materials from the waste recycling party. The beneficial effect of this setting is that it can indicate whether the waste recycling party processes the construction waste, realize the supervision of all nodes of construction waste management, and avoid the waste recycling party processing it by itself. By storing the information of the building materials to be traded, it is helpful to check whether the waste recycling party has completely processed the construction waste, avoid the loss of building materials, and improve the management efficiency and accuracy of construction waste.

[0045] The technical solution of this embodiment can obtain the information of the participants in the construction waste management process by storing the initial construction waste information of the demolition party and the received construction waste information of the waste recycling party on the chain, so as to prevent the information from being tampered with or lost. By comparing the initial construction waste information and the received construction waste information, it is possible to realize the information-based supervision of the demolition and construction waste industry, prevent the demolition and construction party from illegally landfilling construction waste, effectively reduce the risk of environmental pollution, and eliminate illegal and disorderly behaviors. It solves the problem of manual exchange of construction waste information in the prior art, saves manpower and time, realizes the information exchange of construction waste, and improves the efficiency and accuracy of construction waste management.

[0046] Embodiment 2

[0047] Figure 2 The flowchart of a construction waste management method based on blockchain provided by the second embodiment of the present invention is as follows. This embodiment is an optional embodiment based on the above embodiment. The method can be executed by a construction waste management device based on blockchain. Figure 2 As shown, the method specifically comprises the following steps:

[0048] Step 210: Obtain the initial construction waste information uploaded by the demolition and construction party, and store the initial construction waste information on the chain.

[0049] Step 220: Obtain the received construction waste information uploaded by the waste collector, and store the received construction waste information on the chain.

[0050] Step 230: Determine whether the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions.

[0051] Step 240: If yes, obtain the building materials information to be traded corresponding to the received construction waste information uploaded by the waste recycling party, and store the building materials information to be traded on the chain.

[0052] Step 250: Send a review instruction for the building materials to be traded to the construction waste supervisor, so that the construction waste supervisor can determine whether the information of the building materials to be traded meets the preset building materials information qualification conditions.

[0053] Among them, after receiving the information of building materials to be traded uploaded by the waste recycling party, a review instruction for building materials to be traded can be sent to the construction waste supervisor, instructing the construction waste supervisor to determine whether the information of building materials to be traded meets the preset building materials information qualification conditions. The construction waste supervisor can pre-set the building materials information qualification conditions. The building materials information qualification conditions can be that the construction waste supervisor obtains the received construction waste information in the blockchain, and predicts the building materials to be traded that can be produced based on the received construction waste information to obtain the estimated building materials information. The building materials information to be traded is compared with the estimated building materials information. If the building materials information to be traded is consistent with the estimated building materials information, it is determined that the building materials information to be traded meets the preset building materials information qualification conditions. For example, the types of building materials in the building materials information to be traded and the estimated building materials information can be compared, and the weight of building materials in the building materials information to be traded and the estimated building materials information can also be compared.

[0054] Step 260: If qualified building material information is received from the construction waste supervisor, a building material transaction permission instruction is sent to the waste recycling party, so that the waste recycling party can publish building material transaction requirements and wait for the building material demander to trade with the waste recycling party.

[0055] Among them, if the construction waste supervisor determines that the information of the building materials to be traded meets the preset building materials information qualification conditions, feedback information of qualified building materials information will be issued; if the construction waste supervisor determines that the information of the building materials to be traded does not meet the building materials information qualification conditions, feedback information of unqualified building materials information will be issued. If the qualified building materials information feedback from the construction waste supervisor is received, it is determined that there is no problem in the production of building materials by the waste recycling party, and an instruction to allow building materials trading can be sent to the waste recycling party, that is, the waste recycling party is allowed to trade with the building materials demander for the building materials to be traded. The waste recycling party receives the instruction to allow building materials trading, publishes the building materials trading demand on the blockchain, and waits for the building materials demander to trade with the waste recycling party. The building materials trading demand can be an invitation to trade building materials, which can indicate the type, quantity and unit price of the building materials to be traded.

[0056] If the construction waste supervisor receives unqualified building material information, the waste recycler will not be allowed to publish building material trading needs. It can be considered that the waste recycler made an error in generating the building materials to be traded, or privately occupied the building materials to be traded. A prompt message can be sent to the construction waste supervisor to prompt the staff of the construction waste supervisor to check and review the waste recycler.

[0057] In the present embodiment, optionally, after sending a building materials transaction permission instruction to the waste recycling party so that the waste recycling party can publish building materials transaction requirements and wait for the building materials demander to conduct transactions with the waste recycling party, it also includes: responding to the building materials transaction request sent by the building materials demander, determining the building materials information to be acquired and the building materials information allowed to be acquired of the building materials demander; judging whether the building materials information to be acquired meets the building materials acquisition qualification requirements based on the building materials information allowed to be acquired; if so, sending the building materials transaction instruction to the waste recycling party to realize the building materials transaction between the waste recycling party and the building materials demander.

[0058] Specifically, after seeing the building materials transaction demand issued by the waste recycling party, the building materials demander can establish a transaction with the waste recycling party according to actual needs. The building materials demander can issue a building materials transaction request in response to the building materials transaction demand. The building materials transaction request can include the building materials information to be obtained and the building materials information allowed to be obtained. The building materials information to be obtained can be the types and quantities of building materials required by the building materials demander, and the building materials information allowed to be obtained can be the types and quantities of building materials that the building materials demander can obtain. The building materials information allowed to be obtained is determined by the building materials demander when it is established, and is the qualification of the building materials demander to obtain building materials. In response to the building materials transaction request sent by the building materials demander, the building materials information to be obtained and the building materials information allowed to be obtained of the building materials demander are determined.

[0059] The building material acquisition qualification requirements are pre-set. The building material acquisition qualification requirements may be to compare the building material information to be acquired with the building material information that is allowed to be acquired, determine whether the building material to be acquired is the building material that is allowed to be acquired, and if so, determine that the building material acquisition qualification requirements are met. For example, based on the building material information to be acquired and the building material information that is allowed to be acquired, determine the types of building materials to be acquired and the types of building materials that are allowed to be acquired. If the type of building materials to be acquired is not in the types of building materials that are allowed to be acquired, then determine that the building material information to be acquired does not meet the building material acquisition qualification requirements, that is, the building material demander cannot acquire building materials that are not in the types of building materials that are allowed to be acquired. The building material acquisition qualification requirements may also be to compare whether the quantity of building materials to be acquired exceeds the quantity of building materials that are allowed to be acquired. If not, determine that the building material information to be acquired meets the building material acquisition qualification requirements.

[0060] If the building materials information to be acquired meets the building materials acquisition qualification requirements, the building materials demander is allowed to trade with the garbage recycling party, and a building materials transaction instruction can be sent to the garbage recycling party to establish interaction between the garbage recycling party and the building materials demander. The garbage recycling party can communicate with the building materials demander to realize the transaction of building materials. If the building materials information to be acquired does not meet the building materials acquisition qualification requirements, a prompt message can be sent to the building materials demander to prompt the building materials demander to change the building materials transaction request so that the building materials demander can obtain building materials that meet its own qualification requirements. The beneficial effect of such a setting is that it can realize the interaction between the various participants and review the transaction to avoid the building materials demander who does not meet the qualification requirements from obtaining the wrong building materials, improve the legitimacy of the building materials transaction, and the building materials transaction request is in the blockchain to avoid being tampered with by humans, improve the entire process from production to transaction of construction waste, and improve the reliability of construction waste management.

[0061] In this embodiment, optionally, after sending the building materials transaction instruction to the waste recycling party and realizing the building materials transaction between the waste recycling party and the building materials demander, it also includes: obtaining the received building materials information uploaded by the building materials demander, and storing the received building materials information on the chain; judging whether the building materials information to be obtained is consistent with the received building materials information; if so, determining that the building materials transaction between the waste recycling party and the building materials demander is completed, thereby realizing the full life cycle management of construction waste.

[0062] Specifically, after the building materials demander and the waste recycling party conduct a transaction, the building materials demander determines the received building materials information based on the received building materials, and the received building materials information may include the types and quantities of the received building materials, etc. The received building materials information is stored on the chain. It is determined whether the received building materials information is the building materials information to be obtained uploaded by the building materials demander before the transaction. If so, it is determined that the building materials transaction between the waste recycling party and the building materials demander is completed, and the full life cycle management of this batch of construction waste is completed; if not, it is determined that the waste recycling party and the building materials demander can continue to trade. The beneficial effect of this setting is that the entire process of construction waste from generation to the final transaction as building materials is supervised and audited on the blockchain, and the relevant data of construction waste can be summarized and counted, including the amount of garbage generated, the amount of recycled construction waste, the newly generated green building materials, and the acquisition destination, etc., to achieve the full life cycle management of construction waste, which is convenient for subsequent viewing of each node of construction waste management. For example, tracking the entire life cycle of construction waste can calculate carbon emissions and carbon neutrality capabilities. All participants can achieve sustainable development of the industry by reliably counting the construction waste treatment behaviors and quantifying the behaviors into carbon neutrality points.

[0063] The embodiment of the present invention can obtain the information of the participants in the construction waste management process by storing the initial construction waste information of the demolition party and the received construction waste information of the waste recycling party on the chain, so as to prevent the information from being tampered with or lost. By comparing the initial construction waste information and the received construction waste information, the information-based supervision of the demolition and construction waste industry can be realized, and the demolition and construction party can be prevented from illegally landfilling the construction waste, effectively reducing the risk of environmental pollution and eliminating illegal and disorderly behaviors. After the construction waste is converted, the supervision continues until the building materials transaction is completed. The problem of manual recording of construction waste information in the prior art is solved, saving manpower and time. Through the alliance chain architecture of blockchain technology, strong information-based supervision of the demolition and construction waste industry is realized. The integration of industry information can motivate the enthusiasm of the entire industry, reduce the cost of waste building materials recycling and processing plants and improve efficiency. The information exchange of construction waste is realized, the efficiency and accuracy of construction waste management are improved, and the full life cycle management of construction waste is realized.

[0064] Embodiment 3

[0065] Figure 3 This is a structural block diagram of a construction waste management device based on blockchain provided in the third embodiment of the present invention, which can execute the construction waste management method based on blockchain provided in any embodiment of the present invention. The device is configured on a blockchain node and has the functional modules and beneficial effects corresponding to the execution method. Figure 3 As shown, the device specifically includes:

[0066] The initial waste information acquisition module 301 is used to acquire the initial construction waste information uploaded by the demolition and construction party, and store the initial construction waste information on the chain;

[0067] The received garbage information acquisition module 302 is used to acquire the received construction garbage information uploaded by the garbage collector and store the received construction garbage information on the chain;

[0068] The garbage information determination module 303 is used to determine whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition;

[0069] The module 304 for determining the information of building materials to be traded is used to obtain the information of building materials to be traded corresponding to the received construction waste information uploaded by the waste recycling party, and store the information of building materials to be traded on the chain to manage the construction waste throughout its life cycle.

[0070] Optionally, the device further comprises:

[0071] The initial construction waste information review module is used to obtain the initial construction waste information uploaded by the demolition and construction party, store the initial construction waste information on the chain, and then send an initial construction waste information review instruction to the construction waste supervisor, so that the construction waste supervisor can judge whether the initial construction waste information meets the preset preliminary review conditions based on the pre-stored estimated construction waste information;

[0072] The transport instruction sending module is used to receive the preliminary review pass information fed back by the construction waste supervisor, and send an initial construction waste transport instruction to the demolition and construction party, so that the demolition and construction party can transport the initial construction waste to the waste recycling party.

[0073] Optionally, the spam information determination module 303 is specifically used to:

[0074] Determine whether the initial construction waste information is consistent with the received construction waste information. If so, determine whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition.

[0075] Optionally, the device further comprises:

[0076] The module for sending a building material manufacturing permission instruction is used to send a building material manufacturing permission instruction to the waste recycling party before obtaining the building material information to be traded corresponding to the received building waste information uploaded by the waste recycling party. If it is determined that the initial building waste information and the received building waste information meet the preset information comparison qualification conditions, the module enables the waste recycling party to convert the received building waste into building materials to be traded and upload the building materials information to be traded to the blockchain.

[0077] Optionally, the device further comprises:

[0078] The pending traded building materials review module is used to obtain the pending traded building materials information corresponding to the received building waste information uploaded by the waste recycling party, store the pending traded building materials information on the chain, and then send a pending traded building materials review instruction to the building waste supervisor, so that the building waste supervisor can judge whether the pending traded building materials information meets the preset building materials information qualification conditions;

[0079] The module for sending instructions for allowing building material transactions is used to send instructions for allowing building material transactions to the waste recycling party if qualified building material information feedback from the construction waste supervision party is received, so that the waste recycling party can publish building material transaction needs and wait for the building material demand party to trade with the waste recycling party.

[0080] Optionally, the device further comprises:

[0081] A building material information acquisition module is used to send a building material transaction permission instruction to the waste recycling party, so that the waste recycling party can publish building material transaction requirements, wait for the building material demand party to trade with the waste recycling party, and then respond to the building material transaction request sent by the building material demand party to determine the building material information to be acquired and the building material information allowed to be acquired of the building material demand party;

[0082] A building material information judgment module, used to judge whether the building material information to be obtained and the building material information allowed to be obtained meet the building material acquisition qualification requirements;

[0083] The building materials transaction instruction sending module is used to send the building materials transaction instruction to the garbage recycling party, so as to realize the building materials transaction between the garbage recycling party and the building materials demander.

[0084] Optionally, the device further comprises:

[0085] The received building materials information storage module is used to obtain the received building materials information uploaded by the building materials demander after sending the building materials transaction instruction to the waste recycling party to realize the building materials transaction between the waste recycling party and the building materials demander, and store the received building materials information on the chain;

[0086] A received building material information determination module is used to determine whether the building material information to be obtained is consistent with the received building material information;

[0087] The building materials transaction completion module is used to determine that the building materials transaction between the garbage recycling party and the building materials demander is completed, thereby realizing the full life cycle management of construction waste.

[0088] The embodiment of the present invention can obtain the information of each participant in the construction waste management process by storing the initial construction waste information of the demolition party and the received construction waste information of the waste recycling party on the chain, thereby preventing the information from being tampered with or lost. By comparing the initial construction waste information and the received construction waste information, it is possible to achieve information-based supervision of the demolition and construction waste industry, prevent the demolition and construction party from illegally landfilling construction waste, effectively reduce the risk of environmental pollution, and eliminate illegal and disorderly behaviors. It solves the problem of manual recording of construction waste information in the prior art, saves manpower and time, realizes the information exchange of construction waste, and improves the efficiency and accuracy of construction waste management.

[0089] Embodiment 4

[0090] Figure 4 This is a schematic diagram of the structure of a blockchain-based construction waste management device provided by the fourth embodiment of the present invention. The blockchain-based construction waste management device is an electronic device. Figure 4A block diagram of an exemplary electronic device 400 suitable for implementing embodiments of the present invention is shown. Figure 4 The electronic device 400 shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.

[0091] like Figure 4 As shown, the electronic device 400 is in the form of a general computing device. The components of the electronic device 400 may include but are not limited to: one or more processors or processing units 401, a system memory 402, and a bus 403 connecting different system components (including the system memory 402 and the processing unit 401).

[0092] Bus 403 represents one or more of several types of bus structures, including a memory bus or memory controller, a peripheral bus, an accelerated graphics port, a processor or a local bus using any of a variety of bus structures. For example, these architectures include but are not limited to Industry Standard Architecture (ISA) bus, Micro Channel Architecture (MAC) bus, Enhanced ISA bus, Video Electronics Standards Association (VESA) local bus and Peripheral Component Interconnect (PCI) bus.

[0093] The electronic device 400 typically includes a variety of computer system readable media. These media can be any available media that can be accessed by the electronic device 400, including volatile and non-volatile media, removable and non-removable media.

[0094] System memory 402 may include computer system readable media in the form of volatile memory, such as random access memory (RAM) 404 and / or cache memory 405. Electronic device 400 may further include other removable / non-removable, volatile / non-volatile computer system storage media. By way of example only, storage system 406 may be used to read and write non-removable, non-volatile magnetic media ( Figure 4 not shown, usually called a "hard drive"). Although Figure 4 Not shown in the figure, a disk drive for reading and writing to a removable non-volatile disk (e.g., a "floppy disk"), and an optical disk drive for reading and writing to a removable non-volatile optical disk (e.g., a CD-ROM, a DVD-ROM, or other optical media) may be provided. In these cases, each drive may be connected to bus 403 via one or more data medium interfaces. Memory 402 may include at least one program product having a set (e.g., at least one) of program modules that are configured to perform the functions of various embodiments of the present invention.

[0095] A program / utility 408 having a set (at least one) of program modules 407 may be stored, for example, in memory 402, such program modules 407 including, but not limited to, an operating system, one or more application programs, other program modules, and program data, each of which or some combination may include an implementation of a network environment. Program modules 407 generally perform the functions and / or methods of the embodiments described herein.

[0096] The electronic device 400 may also communicate with one or more external devices 409 (e.g., keyboard, pointing device, display 410, etc.), one or more devices that enable a user to interact with the electronic device 400, and / or any device that enables the electronic device 400 to communicate with one or more other computing devices (e.g., network card, modem, etc.). Such communication may be performed through an input / output (I / O) interface 411. Furthermore, the electronic device 400 may also communicate with one or more networks (e.g., local area network (LAN), wide area network (WAN) and / or public network, such as the Internet) through a network adapter 412. Figure 4 As shown, the network adapter 412 communicates with other modules of the electronic device 400 via the bus 403. It should be understood that although Figure 4 Not shown, other hardware and / or software modules may be used in conjunction with electronic device 400, including but not limited to: microcode, device drivers, redundant processing units, external disk drive arrays, RAID systems, tape drives, and data backup storage systems.

[0097] The processing unit 401 executes various functional applications and data processing by running the program stored in the system memory 402, for example, implementing a construction waste management method based on blockchain provided in an embodiment of the present invention, including:

[0098] Obtaining the initial construction waste information uploaded by the demolition and construction party, and storing the initial construction waste information on the chain;

[0099] Obtaining the received construction waste information uploaded by the waste collector, and storing the received construction waste information on the chain;

[0100] Determining whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition;

[0101] If so, the information of building materials to be traded corresponding to the received construction waste information uploaded by the waste recycling party is obtained, and the information of building materials to be traded is stored on the chain to manage the construction waste throughout its life cycle.

[0102] Embodiment 5

[0103] Embodiment 5 of the present invention further provides a storage medium containing computer executable instructions, on which a computer program is stored. When the program is executed by a processor, a construction waste management method based on blockchain as provided in the embodiment of the present invention is implemented, including:

[0104] Obtaining the initial construction waste information uploaded by the demolition and construction party, and storing the initial construction waste information on the chain;

[0105] Obtaining the received construction waste information uploaded by the waste collector, and storing the received construction waste information on the chain;

[0106] Determining whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition;

[0107] If so, the information of building materials to be traded corresponding to the received construction waste information uploaded by the waste recycling party is obtained, and the information of building materials to be traded is stored on the chain to manage the construction waste throughout its life cycle.

[0108] The computer storage medium of the embodiment of the present invention can adopt any combination of one or more computer-readable media. The computer-readable medium can be a computer-readable signal medium or a computer-readable storage medium. The computer-readable storage medium can be, for example, but not limited to, a system, device or device of electricity, magnetism, light, electromagnetic, infrared, or semiconductor, or any combination of the above. More specific examples (non-exhaustive list) of computer-readable storage media include: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In this document, a computer-readable storage medium can be any tangible medium containing or storing a program, which can be used by an instruction execution system, a device or a device or used in combination with it.

[0109] Computer-readable signal media may include data signals propagated in baseband or as part of a carrier wave, which carry computer-readable program code. Such propagated data signals may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. Computer-readable signal media may also be any computer-readable medium other than a computer-readable storage medium, which may send, propagate, or transmit a program for use by or in conjunction with an instruction execution system, apparatus, or device.

[0110] The program code embodied on the computer readable medium may be transmitted using any appropriate medium, including but not limited to wireless, wireline, optical fiber cable, RF, etc., or any suitable combination of the foregoing.

[0111] Computer program code for performing the operations of the present invention may be written in one or more programming languages ​​or a combination thereof, including object-oriented programming languages ​​such as Java, Smalltalk, C++, and conventional procedural programming languages ​​such as "C" or similar programming languages. The program code may be executed entirely on the user's computer, partially on the user's computer, as a separate software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer may be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or may be connected to an external computer (e.g., through the Internet using an Internet service provider).

[0112] Note that the above are only preferred embodiments of the present invention and the technical principles used. Those skilled in the art will understand that the present invention is not limited to the specific embodiments described herein, and that various obvious changes, readjustments and substitutions can be made by those skilled in the art without departing from the scope of protection of the present invention. Therefore, although the present invention has been described in more detail through the above embodiments, the present invention is not limited to the above embodiments, and may include more other equivalent embodiments without departing from the concept of the present invention, and the scope of the present invention is determined by the scope of the appended claims.

Claims

1. A construction waste management method based on blockchain, characterized in that: The method is performed by a blockchain node, and the method includes: Obtaining the initial construction waste information uploaded by the demolition and construction party, and storing the initial construction waste information on the chain; Obtaining the received construction waste information uploaded by the waste collector, and storing the received construction waste information on the chain; Determine whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition; wherein the preset information comparison qualification condition includes a time difference threshold between the construction waste start transportation time and the reception time; If so, the information of the building materials to be traded corresponding to the received construction waste information uploaded by the waste recycling party is obtained, and the information of the building materials to be traded is stored on the chain to manage the construction waste throughout its life cycle; Sending a review instruction of the building materials to be traded to the construction waste supervisor, so that the construction waste supervisor can determine whether the information of the building materials to be traded meets the preset building materials information qualification conditions; If the qualified building material information feedback from the construction waste supervisor is received, an instruction to allow building material trading is sent to the waste recycling party, so that the waste recycling party can publish building material trading demand and wait for the building material demand party to trade with the waste recycling party; In response to the building material transaction request sent by the building material demander, determining the building material information to be acquired and the building material information allowed to be acquired of the building material demander; According to the building material information that is allowed to be obtained, determining whether the building material information to be obtained meets the building material acquisition qualification requirements; If yes, the building materials transaction instruction is sent to the waste recycling party to realize the building materials transaction between the waste recycling party and the building materials demander; Obtaining the received building materials information uploaded by the building materials demander, and storing the received building materials information on the chain; Determining whether the building material information to be obtained is consistent with the received building material information; If so, it is determined that the building materials transaction between the waste recycling party and the building materials demander is completed, thus realizing the full life cycle management of construction waste.

2. The method according to claim 1, characterized in that: After obtaining the initial construction waste information uploaded by the demolition and construction party and storing the initial construction waste information on the chain, the method further includes: Sending an initial construction waste information review instruction to a construction waste supervisor, so that the construction waste supervisor can determine whether the initial construction waste information meets the preset preliminary review conditions based on the pre-stored estimated construction waste information; Receive the preliminary review information fed back by the construction waste supervisor, and send an initial construction waste transportation instruction to the demolition and construction party, so that the demolition and construction party can transport the initial construction waste to the waste recycling party.

3. The method according to claim 1, characterized in that Determining whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition includes: Determine whether the initial construction waste information is consistent with the received construction waste information. If so, determine whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition.

4. The method according to claim 1, characterized in that Before obtaining the to-be-traded building material information corresponding to the received construction waste information uploaded by the waste recycling party, the method further includes: If it is determined that the initial construction waste information and the received construction waste information meet the preset information comparison qualification conditions, a building material manufacturing permission instruction is sent to the waste recycling party, so that the waste recycling party can convert the received construction waste into building materials to be traded, and upload the information of the building materials to be traded to the blockchain.

5. A construction waste management device based on blockchain, characterized in that: The device is configured in a blockchain node, and the device includes: The initial waste information acquisition module is used to acquire the initial construction waste information uploaded by the demolition and construction party, and store the initial construction waste information on the chain; The received garbage information acquisition module is used to acquire the received construction garbage information uploaded by the garbage collector and store the received construction garbage information on the chain; A garbage information judgment module is used to judge whether the initial construction waste information and the received construction waste information meet a preset information comparison qualification condition; wherein the preset information comparison qualification condition includes a time difference threshold between the construction waste start transportation time and the reception time; The module for determining the information of building materials to be traded is used to obtain the information of building materials to be traded corresponding to the received building waste information uploaded by the waste recycling party, and store the information of building materials to be traded on the chain to manage the whole life cycle of building waste; The pending trade building materials review module is used to send a pending trade building materials review instruction to the construction waste supervisor, so that the construction waste supervisor can determine whether the pending trade building materials information meets the preset building materials information qualification conditions; A module for sending a building material transaction instruction is used to send a building material transaction instruction to the waste recycling party if the building material information feedback from the construction waste supervision party is qualified, so that the waste recycling party can publish a building material transaction demand and wait for the building material demand party to trade with the waste recycling party; A building material information acquisition module, for responding to a building material transaction request sent by the building material demander, and determining the building material information to be acquired and the building material information allowed to be acquired of the building material demander; A building material information judgment module, used to judge whether the building material information to be obtained and the building material information allowed to be obtained meet the building material acquisition qualification requirements; A building materials transaction instruction sending module is used to send the building materials transaction instruction to the waste recycling party to realize the building materials transaction between the waste recycling party and the building materials demander; The received building materials information storage module is used to obtain the received building materials information uploaded by the building materials demander and store the received building materials information on the chain; A received building material information determination module is used to determine whether the building material information to be obtained is consistent with the received building material information; The building materials transaction completion module is used to determine that the building materials transaction between the garbage recycling party and the building materials demander is completed, thereby realizing the full life cycle management of construction waste.

6. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the blockchain-based construction waste management method as described in any one of claims 1-4 is implemented.

7. A storage medium containing computer executable instructions, characterized in that: The computer executable instructions, when executed by a computer processor, are used to execute the blockchain-based construction waste management method as described in any one of claims 1-4.