Self-balancing grouting system for subway tunnel reinforcement construction and subway tunnel reinforcement method

The self-balancing slurry return system solves the problems of cement soil slurry out and pressure control in high-pressure rotary spray pile construction, and achieves the clean and efficient reinforcement effect of subway tunnel reinforcement construction.

CN115370382BActive Publication Date: 2024-12-03ZHEJIANG DATONG CONSTR TECH CO LTD +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202211007988.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-22
Publication Date
2024-12-03
Estimated Expiration
2042-08-22

AI Technical Summary

Technical Problem

During the reinforcement of subway tunnels, underground cement soil slurry will emerge from the tunnel during the construction of high-pressure rotary sprinkler piles, and the pressure of underground cement soil cannot be effectively controlled, affecting the construction quality.

Method used

Adopt a self-balancing slurry return system, including an underground pressure balancer, slurry tank, slurry discharge valve and filter press. It is sealed and connected by a slurry return container and a rotary nozzle to detect and control the pressure of cement soil slurry to avoid emergence and conduct Mud and water separation.

Benefits of technology

Effectively prevent cement soil slurry from coming out of polluted tunnels, while ensuring the pressure of underground cement soil and improving the construction quality of high-pressure rotary spray piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115370382B_ABST
    Figure CN115370382B_ABST
Patent Text Reader

Abstract

The present invention discloses a self-balancing grouting system and a method for reinforcing a subway tunnel, aiming to provide a self-balancing grouting system and a method for reinforcing a subway tunnel, which can effectively solve the problem that the cement-soil slurry in the underground will emerge into the tunnel and pollute the tunnel during the construction of the high-pressure rotary jet piles without affecting the construction of the high-pressure rotary jet piles, and the problem that the pressure of the underground cement-soil cannot be controlled and the construction quality of the high-pressure rotary jet piles is affected due to low pressure. The self-balancing grouting system for reinforcing a subway tunnel includes: an underground pressure balancer, which includes a grouting container and a pressure detector; a grouting tank, the inner cavity of the grouting tank is connected to the closed inner cavity of the grouting container through a grouting pipe; a grouting valve, which is used to control the on and off of the grouting pipe; and a filter press, which includes a feed pump, and the inlet of the feed pump is connected to the inner cavity of the grouting tank through a feed pipe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of subway tunnel reinforcement construction, and in particular to a self-balancing slurry return system for subway tunnel reinforcement construction and a subway tunnel reinforcement method. Background Art

[0002] At present, after the construction of subway tunnels is completed, some sections of the tunnels need to be reinforced to improve the structural stability of the tunnels. At present, the technology of subway tunnel reinforcement construction equipment and construction methods is immature, and there are problems such as complex construction steps, low construction efficiency, and poor reinforcement effect of the completed subway tunnel reinforcement structure.

[0003] In order to solve this problem, some inventors have invented tunnel reinforcement construction equipment, using a high-pressure rotary jet pile machine to construct high-pressure rotary jet piles under the inner wall of the shield segment to support and reinforce a certain section of the tunnel. For example, Chinese patent application No. 2020103013757, the name of the invention is, multi-angle cement soil pile construction equipment and tunnel reinforcement construction method in the tunnel, the application discloses a high-pressure rotary jet pile machine to construct high-pressure rotary jet piles under the inner wall of the shield segment to support and reinforce a certain section of the tunnel. The equipment and method, specifically, a hole is drawn on the inner wall of the tunnel to form a through hole that penetrates the tunnel wall, and then the high-pressure rotary jet pile machine constructs high-pressure rotary jet piles under the inner wall of the shield segment. Although the equipment and method of using a high-pressure rotary jet pile machine to construct high-pressure rotary jet piles below the inner wall of the shield segment can reinforce the tunnel, it has the following shortcomings. First, during the construction of the high-pressure rotary jet piles, the underground cement soil slurry will emerge from the through holes in the inner wall of the shield segment into the tunnel, polluting the tunnel, which will cause great inconvenience in cleaning, especially for the tunnel in operation; second, during the construction of the high-pressure rotary jet piles, since the underground cement soil slurry will emerge from the through holes in the inner wall of the shield segment, the pressure of the underground cement soil cannot be controlled during the construction of the high-pressure rotary jet piles, and the construction quality of the high-pressure rotary jet piles is often affected by the low pressure. Summary of the invention

[0004] The purpose of the present invention is to provide a self-balancing grouting system and a subway tunnel reinforcement method for subway tunnel reinforcement construction, which can effectively solve the problem that underground cement soil slurry will emerge into the tunnel and pollute the tunnel during the construction of high-pressure rotary jet piles without affecting the construction of high-pressure rotary jet piles, and the pressure of underground cement soil cannot be controlled, resulting in the construction quality of high-pressure rotary jet piles being affected due to low pressure.

[0005] The technical solution of the present invention is:

[0006] A self-balancing grouting system for subway tunnel reinforcement construction, which is used in subway tunnel reinforcement construction using high-pressure jet grouting piles, includes:

[0007] An underground pressure balancer is used to cooperate with the jet pipe of the high-pressure jet pile machine during the high-pressure jet pile construction process. The underground pressure balancer includes a slurry return container and a pressure detector. The slurry return container has a closed inner cavity. The top of the slurry return container is provided with a jet pipe upper through hole. The inner wall of the jet pipe upper through hole is provided with a sealing ring for cooperating with the jet pipe. The bottom of the slurry return container is provided with a slurry return container mounting seat. The slurry return container mounting seat is provided with a jet pipe lower through hole. The pressure detector is used to detect the pressure in the closed inner cavity of the slurry return container.

[0008] The inner cavity of the slurry storage tank is connected to the sealed inner cavity of the slurry return container through a slurry discharge pipe; the slurry discharge valve is used to control the on and off of the slurry discharge pipe;

[0009] The filter press comprises a feed pump, the inlet of the feed pump is connected to the inner cavity of the slurry storage tank through a feed pipeline.

[0010] The specific use of the self-balancing grouting system for subway tunnel reinforcement construction in this scheme is as follows:

[0011] A hole is drilled on the shield segment of the subway tunnel by a drilling machine. After the segment through-hole is formed on the shield segment, the slurry return container mounting seat is sealed and fixed on the inner wall of the shield segment. In actual operation, a sealing gasket is generally arranged between the slurry return container mounting seat and the inner wall of the shield segment, and the slurry return container mounting seat is fixed to the shield segment with an expansion screw; then, the lower end of the grouting pipe of the high-pressure grouting pile driver passes through the upper through-hole of the grouting pipe, the closed inner cavity, the lower through-hole of the grouting pipe and the segment through-hole in turn, and extends to the specified depth underground. At this time, the upper through-hole of the grouting pipe and the grouting pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through-hole of the grouting pipe and the grouting pipe; then The rotary jet pipe of the high-pressure rotary jet pile machine sprays grouting, thereby forming high-pressure rotary jet piles for reinforcing the subway tunnel on the outside of the shield segment of the subway tunnel. In this process, the cement soil slurry that emerges through the through holes of the segment will enter the closed inner cavity of the slurry return container through the slurry return gap. When the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the slurry discharge valve is closed to ensure the pressure of the underground cement soil and avoid the problem of affecting the construction quality of the high-pressure rotary jet pile due to low pressure; when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the slurry discharge valve is opened to discharge the cement soil slurry into the slurry storage tank through the slurry discharge pipe. The cement-soil slurry in the slurry storage tank is pumped into the filter press through the feed pipe and the feed pump, and the filter press is used to separate the mud and water in the cement-soil slurry; the water separated by the filter press is recovered into the recovery tank for recycling; of course, it is also discharged to a designated location outside the subway tunnel; the mud separated by the filter press is packaged and transported away; thereby preventing the cement-soil slurry from bubbling up into the tunnel and polluting the tunnel; therefore, it can effectively solve the problem that the underground cement-soil slurry will bubble up into the tunnel and pollute the tunnel during the construction of the high-pressure rotary jet piles without affecting the construction of the high-pressure rotary jet piles, as well as the problem that the pressure of the underground cement soil cannot be controlled, and the construction quality of the high-pressure rotary jet piles is affected by the low pressure.

[0012] Preferably, during the high-pressure rotary jet pile construction process, the rotary jet pipe of the high-pressure rotary jet pile machine is inserted into the upper through hole and the lower through hole of the rotary jet pipe. At this time, the upper through hole and the rotary jet pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole of the rotary jet pipe and the rotary jet pipe.

[0013] Preferably, during the construction of high-pressure rotary jet piles, when the pressure detector detects that the pressure in the closed inner cavity of the return slurry container is greater than the set value, the slurry discharge valve opens; when the pressure detector detects that the pressure in the closed inner cavity of the return slurry container is less than the set value, the slurry discharge valve closes.

[0014] Preferably, the re-slurry container mounting seat includes a mounting base and a compensator connecting the mounting base and the bottom of the re-slurry container, and the lower through hole of the rotary spray pipe includes a compensator inner hole arranged in the compensator and a base through hole arranged in the mounting base.

[0015] The function of the compensator in the re-slurry container mounting seat of the present scheme is different from that of the compensator on the pipeline or container in the prior art, which is "used to absorb the axial, lateral and angular displacement changes of the pipeline, container, etc. caused by thermal expansion and contraction". The problem to be solved by the compensator in the re-slurry container mounting seat of the present scheme is that before the rotary spraying pipe is inserted into the through hole on the rotary spraying pipe, it is difficult to adjust to ensure that the rotary spraying pipe is coaxial with the through hole on the rotary spraying pipe, resulting in a gap between the sealing ring and the rotary spraying pipe, which cannot be sealed, resulting in the problem of the underground pressure balancer. Specifically, before the rotary jet pipe is inserted into the through hole on the rotary jet pipe, it is necessary to adjust the rotary jet pipe to be coaxial with the through hole on the rotary jet pipe, and then the rotary jet pipe is inserted into and passes through the through hole on the rotary jet pipe to ensure that the through hole on the rotary jet pipe and the rotary jet pipe are sealed and connected through the sealing ring; if the rotary jet pipe and the through hole on the rotary jet pipe are not coaxial, then after the rotary jet pipe passes through the through hole on the rotary jet pipe, there may be a gap between the sealing ring and the rotary jet pipe, and it cannot be sealed, which leads to problems with the underground pressure balancer; especially when constructing inclined high-pressure rotary jet piles (high-pressure rotary jet piles used to reinforce tunnels ensure vertically distributed high-pressure rotary jet piles and inclined high-pressure rotary jet piles), since the rotary jet pipe and the through hole on the rotary jet pipe are both inclinedly distributed, in actual construction, before the rotary jet pipe is inserted into the through hole on the rotary jet pipe, it is often difficult to adjust to ensure that the rotary jet pipe and the through hole on the rotary jet pipe are coaxial, which is prone to problems with the underground pressure balancer due to the gap between the sealing ring and the rotary jet pipe, which cannot be sealed.

[0016] In order to solve this problem, this scheme specially designs a re-slurry container mounting seat. Since the re-slurry container mounting seat includes a mounting base and a compensator connecting the mounting base and the bottom of the re-slurry container, after the mounting base is fixed on the inner wall of the shield segment, the through hole on the rotary spray pipe on the re-slurry container can swing at a certain angle relative to the mounting base. In this way, before the rotary spray pipe is inserted into the through hole on the rotary spray pipe, even if the rotary spray pipe and the through hole on the rotary spray pipe are not coaxial, after the rotary spray pipe is inserted into and passes through the through hole on the rotary spray pipe, the re-slurry container will automatically swing around the mounting base to adjust the position of the through hole on the rotary spray pipe so that the sealing ring is sealed and connected to the rotary spray pipe.

[0017] Preferably, a negative pressure pump and a slurry pump are further included. The slurry storage tank includes a negative pressure suction tank and a mixing tank. The negative pressure pump vacuums the top of the inner cavity of the negative pressure suction tank. The slurry discharge pipe includes a first slurry discharge pipe connecting the closed inner cavity of the return slurry container and the negative pressure suction tank, and a second slurry discharge pipe connecting the bottom of the negative pressure suction tank and the mixing tank. The slurry discharge pump is used to pump the slurry in the negative pressure suction tank into the mixing tank through the second slurry discharge pipe. The slurry discharge valve includes a first slurry discharge valve for controlling the on and off of the first slurry discharge pipe and a second slurry discharge valve for controlling the on and off of the second slurry discharge pipe; the feed pipe connects the inlet of the feed pump and the inner cavity of the mixing tank. In this way, the top of the inner cavity of the negative pressure suction tank can be evacuated by the negative pressure pump, so that the inner cavity of the negative pressure suction tank is in a negative pressure environment; when the pressure detector detects that the pressure in the closed inner cavity of the return slurry container is greater than the set value, the slurry discharge valve is opened, and the cement soil slurry in the closed inner cavity of the return slurry container can be quickly sucked into the negative pressure suction tank through the slurry discharge pipe.

[0018] Preferably, an air inlet is provided on the top of the negative pressure suction tank, and a switch valve is provided on the air inlet.

[0019] Preferably, a slurry agitator is provided in the mixing tank, and the slurry agitator includes a stirring shaft rotatably arranged on the mixing tank, a stirring paddle arranged on the stirring shaft, and a driving motor for driving the stirring shaft to rotate. In this way, the cement soil slurry in the mixing tank can be stirred by the slurry agitator to avoid the sedimentation of the cement soil slurry in the mixing tank, which is beneficial to the subsequent separation of mud and water.

[0020] Preferably, a traveling vehicle capable of traveling in a subway tunnel is further included, the traveling vehicle being provided with a mounting platform, and the slurry storage tank, the filter press and the high-pressure rotary jet pile driver are all mounted on the mounting platform.

[0021] A subway tunnel reinforcement method using a self-balancing grouting system for subway tunnel reinforcement construction comprises the following steps in sequence:

[0022] First, use a drilling machine to drill holes on the shield segments of the subway tunnel to form segment holes on the shield segments;

[0023] Second, install the underground pressure balancer, and use expansion screws to fix the slurry return container mounting base to the shield segment where the segment through hole is located. The through hole under the rotary jet pipe is directly opposite to the through hole of the segment. A sealing gasket is arranged between the slurry return container mounting base and the shield segment to ensure that the through hole under the rotary jet pipe is sealed and connected with the through hole of the segment.

[0024] Third, adjust the jetting pipe of the high-pressure jetting pile machine to make the jetting pipe coaxial with the through hole on the jetting pipe;

[0025] Next, the jet pipe passes through the upper through hole of the jet pipe, the closed inner cavity, the lower through hole of the jet pipe and the through hole of the pipe segment in sequence. At this time, the upper through hole of the jet pipe and the jet pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole of the jet pipe and the jet pipe.

[0026] Next, the high-pressure rotary jet pile machine constructs high-pressure rotary jet piles on the outside of the shield segment of the subway tunnel through the rotary jet pipe, so as to form high-pressure rotary jet piles for reinforcing the subway tunnel on the outside of the shield segment of the subway tunnel. In this process, the cement soil slurry that emerges through the through holes of the segment will enter the closed inner cavity of the slurry return container through the slurry return gap; when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the slurry discharge valve is closed to ensure the pressure of the underground cement soil and avoid the problem of affecting the construction quality of the high-pressure rotary jet piles due to low pressure; when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the slurry discharge valve is opened to discharge the cement soil slurry into the slurry storage tank through the slurry discharge pipe; thereby avoiding the problem of cement soil slurry escaping into the tunnel and polluting the tunnel.

[0027] As a preferred method, the method further includes the following steps: the cement soil slurry in the slurry storage tank is pumped into the filter press through the feed pipe and the feed pump, and the cement soil slurry is separated into mud and water by the filter press. The water separated by the filter press is recovered into the recovery tank for recycling; of course, it is also discharged to a designated location outside the subway tunnel. The mud separated by the filter press is packaged and transported away; thereby avoiding the problem of cement soil slurry bubbling into the tunnel and polluting the tunnel.

[0028] The beneficial effects of the present invention are: it can effectively solve the problem that underground cement soil slurry will emerge into the tunnel and pollute the tunnel during the construction of high-pressure rotary jet piles without affecting the construction of high-pressure rotary jet piles, and the problem that the pressure of underground cement soil cannot be controlled, and the construction quality of high-pressure rotary jet piles is affected due to low pressure. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a structural schematic diagram of the self-balancing slurry return system for subway tunnel reinforcement construction in the specific embodiment 1 of the present invention during actual use.

[0030] Figure 2 It is a structural schematic diagram of the underground pressure balancer of the present invention.

[0031] Figure 3 It is a partial structural schematic diagram of the underground pressure balancer of the present invention during actual use.

[0032] Figure 4 It is a structural schematic diagram of the self-balancing slurry return system for subway tunnel reinforcement construction in the specific embodiment 3 of the present invention during actual use.

[0033] In the figure:

[0034] Underground pressure balancer 1, slurry return container 1.0, slurry return container mounting seat 1.1, mounting base 1.11, compensator 1.12, arc steel plate 1.13, sealing gasket 1.14, base valve 1.15, through hole on rotary spray pipe 1.2, sealing ring 1.3, pressure detector 1.4, pressure sensor 1.41, pressure gauge 1.42, slurry discharge interface 1.5;

[0035] Filter press 2, feed pump 2.1;

[0036] Slurry storage tank 3, negative pressure suction tank 3.1, mixing tank 3.2;

[0037] Slurry discharge pipe 4, first row slurry pipe 4.1, second row slurry pipe 4.2;

[0038] Feeding pipeline 5;

[0039] High-pressure jet grouting machine 6, jet grouting pipe 6.1;

[0040] Traveling vehicle 7;

[0041] Negative pressure pump 8;

[0042] Slurry pump 9;

[0043] Shield segment 10, segment through hole 10.1. DETAILED DESCRIPTION

[0044] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments:

[0045] Specific embodiment 1: Figure 1 , Figure 2 , Figure 3 As shown, a self-balancing grouting system for subway tunnel reinforcement construction is used in the reinforcement construction of subway tunnels using high-pressure rotary jet piles. The self-balancing grouting system for subway tunnel reinforcement construction includes an underground pressure balancer 1, a slurry storage tank 3, a slurry discharge valve and a filter press 2.

[0046] The underground pressure balancer 1 is used to cooperate with the jet pipe 6.1 of the high-pressure jet pile machine 6 during the high-pressure jet pile construction process. The underground pressure balancer includes a slurry return container 1.0 and a pressure detector 1.4. The slurry return container has a closed inner cavity. The top of the slurry return container is provided with a jet pipe upper through hole 1.2, and the jet pipe upper through hole is connected to the closed inner cavity. A sealing ring 1.3 for cooperating with the jet pipe is provided on the inner wall of the jet pipe upper through hole. The bottom of the slurry return container is provided with a slurry return container mounting seat 1.1, and the slurry return container mounting seat is provided with a jet pipe lower through hole, and the jet pipe lower through hole is connected to the closed inner cavity. A slurry discharge interface 1.5 is also provided on the side wall of the slurry return container. The slurry discharge interface is connected to the closed inner cavity. The pressure detector is used to detect the pressure in the closed inner cavity of the slurry return container.

[0047] The inner cavity of the slurry storage tank 3 is connected to the sealed inner cavity of the slurry return container through a slurry discharge pipe 4. Specifically, one end of the slurry discharge pipe is connected to the slurry discharge interface, and the other end of the slurry discharge pipe is connected to the upper part of the inner cavity of the slurry storage tank. The slurry discharge valve is used to control the on and off of the slurry discharge pipe. The slurry discharge valve is set on the slurry discharge pipe or on the slurry discharge interface.

[0048] The filter press 2 includes a feed pump 2.1. The inlet of the feed pump is connected to the bottom of the inner cavity of the slurry storage tank through a feed pipe 5. In this embodiment, a feed valve is provided on the feed pipe to control the on and off of the feed pipe. The feed valve is a solenoid valve or a manual valve.

[0049] like Figure 1 , Figure 3 As shown, during the high-pressure jet grouting pile construction process, the jet grouting pipe of the high-pressure jet grouting pile machine is simultaneously inserted into the upper through hole of the jet grouting pipe, the closed inner cavity of the slurry return container and the lower through hole of the jet grouting pipe. At this time, the upper through hole of the jet grouting pipe and the jet grouting pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole of the jet grouting pipe and the jet grouting pipe. In this embodiment, the upper through hole of the jet grouting pipe and the lower through hole of the jet grouting pipe are coaxially distributed. Of course, the upper through hole of the jet grouting pipe and the lower through hole of the jet grouting pipe can also be non-coaxially distributed, as long as the jet grouting pipe passes through the upper through hole of the jet grouting pipe, the closed inner cavity and the lower through hole of the jet grouting pipe in sequence, the upper through hole of the jet grouting pipe and the jet grouting pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole of the jet grouting pipe and the jet grouting pipe. The inner diameter of the lower through hole of the jet grouting pipe is larger than the outer diameter of the jet grouting pipe.

[0050] During the high-pressure jet grouting pile construction process, when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the slurry discharge valve opens. When the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the slurry discharge valve closes.

[0051] The specific use of the self-balancing grouting system for subway tunnel reinforcement construction of this embodiment is as follows. In the reinforcement construction of subway tunnels using high-pressure rotary jet piles, holes are drilled on the shield segments 10 of the subway tunnel by a drilling machine. After the segment through-holes 10.1 are formed on the shield segments, the grouting container mounting seat is sealed and fixed on the inner wall of the shield segment. In actual operation, a sealing gasket is generally arranged between the grouting container mounting seat and the inner wall of the shield segment, and the grouting container mounting seat is fixed to the inner wall of the shield segment with expansion screws; then, the lower end of the rotary jet pipe of the high-pressure rotary jet pile driver passes through the upper through-hole of the rotary jet pipe, the closed inner cavity, the lower through-hole of the rotary jet pipe and the segment through-hole in turn, and extends to a specified depth underground. At this time, a sealing ring is passed between the upper through-hole of the rotary jet pipe and the rotary jet pipe. Sealed connection, there is a slurry gap between the inner wall of the lower through-hole of the rotary jet pipe and the rotary jet pipe; then, the rotary jet pipe of the high-pressure rotary jet pile machine sprays grouting, thereby forming a high-pressure rotary jet pile for reinforcing the subway tunnel on the outside of the shield pipe segment of the subway tunnel. In this process, the cement soil slurry emerging from the through-hole of the pipe segment will enter the closed inner cavity of the slurry container through the slurry gap. When the pressure detector detects that the pressure in the closed inner cavity of the slurry container is less than the set value, the slurry discharge valve is closed to ensure the pressure of the underground cement soil and avoid the problem of affecting the construction quality of the high-pressure rotary jet pile due to low pressure; when the pressure detector detects that the pressure in the closed inner cavity of the slurry container is greater than the set value, the slurry discharge valve is opened to discharge the cement soil slurry into the slurry storage tank through the slurry discharge pipe. The cement-soil slurry in the slurry storage tank is pumped into the filter press through the feed pipe and the feed pump, and the filter press is used to separate the mud and water in the cement-soil slurry; the water separated by the filter press is recovered into the recovery tank for recycling; of course, it is also discharged to a designated location outside the subway tunnel; the mud separated by the filter press is packaged and transported away; thereby preventing the cement-soil slurry from bubbling up into the tunnel and polluting the tunnel; therefore, it can effectively solve the problem that the underground cement-soil slurry will bubble up into the tunnel and pollute the tunnel during the construction of the high-pressure rotary jet piles without affecting the construction of the high-pressure rotary jet piles, as well as the problem that the pressure of the underground cement soil cannot be controlled, and the construction quality of the high-pressure rotary jet piles is affected by the low pressure.

[0052] Specifically, Figure 1 As shown, the self-balancing grouting system for subway tunnel reinforcement construction also includes a traveling vehicle 7 capable of traveling in the subway tunnel. The traveling vehicle is provided with an installation platform. The slurry storage tank, filter press and high-pressure rotary jet pile machine are all installed on the installation platform.

[0053] Specific embodiment 2: The rest of the structure of this embodiment refers to the specific embodiment 1, except that:

[0054] like Figure 2As shown, the slurry return container 1.0 is cylindrical, spherical, square or other shapes. In this embodiment, the slurry return container is spherical. The slurry return container is an integrated structure or is made in parts and then sealed and connected as one.

[0055] like Figure 2 As shown, the pressure detector 1.4 includes a pressure sensor 1.41 for the pressure in the closed inner cavity. The slurry discharge valve is a solenoid valve. In this way, when the pressure sensor detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the slurry discharge valve can be automatically controlled to close; when the pressure sensor detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the slurry discharge valve can be automatically controlled to open.

[0056] Of course, the slurry discharge valve can also be a manual valve, and the opening and closing of the slurry discharge valve can be manually controlled.

[0057] The pressure detector also includes a pressure gauge 1.42 for the pressure in the sealed inner cavity, and the operator can directly check the pressure in the sealed inner cavity through the pressure gauge.

[0058] Further, such as Figure 2 , Figure 3 As shown, the re-slurry container mounting seat 1.1 includes a mounting base 1.11 and a compensator 1.12 connecting the mounting base and the bottom of the re-slurry container. The lower through hole of the rotary spray pipe includes a bottom through hole arranged at the bottom of the re-slurry container, a compensator inner hole arranged in the compensator, and a base through hole arranged in the mounting base. In this embodiment, the bottom through hole, the compensator inner hole and the base through hole are coaxially distributed. The compensator is connected to the outer wall of the bottom of the re-slurry container by a flange seal or a welding seal. The compensator is connected to the mounting base by a flange seal or a welding seal. The compensator is a bellows compensator or a metal hose or a rubber hose. In this embodiment, the compensator is a bellows compensator.

[0059] The function of the compensator in the re-slurry container mounting seat of this embodiment is different from that of the compensator on the pipeline or container in the prior art, which is "used to absorb the axial, lateral and angular displacement changes of the pipeline, container, etc. caused by thermal expansion and contraction". The problem to be solved by the compensator in the re-slurry container mounting seat of this scheme is that before the rotary spraying pipe is inserted into the through hole on the rotary spraying pipe, it is difficult to adjust to ensure that the rotary spraying pipe is coaxial with the through hole on the rotary spraying pipe, resulting in a gap between the sealing ring and the rotary spraying pipe, which cannot be sealed, resulting in the problem of the underground pressure balancer. Specifically, during the construction of high-pressure rotary jet piles, before the rotary jet pipe is inserted into the through hole on the rotary jet pipe, it is necessary to adjust the rotary jet pipe to be coaxial with the through hole on the rotary jet pipe, and then the rotary jet pipe is inserted into and passes through the through hole on the rotary jet pipe to ensure that the through hole on the rotary jet pipe and the rotary jet pipe are sealed and connected through the sealing ring; if the rotary jet pipe and the through hole on the rotary jet pipe are not coaxial, then after the rotary jet pipe passes through the through hole on the rotary jet pipe, there may be a gap between the sealing ring and the rotary jet pipe, and it cannot be sealed, which leads to problems with the underground pressure balancer; especially, when constructing inclined high-pressure rotary jet piles (high-pressure rotary jet piles used to reinforce tunnels to ensure vertically distributed high-pressure rotary jet piles and inclined high-pressure rotary jet piles), since the rotary jet pipe and the through hole on the rotary jet pipe are both inclinedly distributed, in actual construction, before the rotary jet pipe is inserted into the through hole on the rotary jet pipe, it is often difficult to adjust to ensure that the rotary jet pipe is coaxial with the through hole on the rotary jet pipe, which is prone to problems with the underground pressure balancer due to the gap between the sealing ring and the rotary jet pipe, which cannot be sealed. In order to solve this problem, the present embodiment specially designs a re-slurry container mounting seat. Since the re-slurry container mounting seat includes a mounting base and a compensator connecting the mounting base and the bottom of the re-slurry container, after the mounting base is fixed on the inner wall of the shield segment, the through hole on the rotary spray pipe on the re-slurry container can also swing relative to the mounting base. In this way, before the rotary spray pipe is inserted into the through hole on the rotary spray pipe, even if the rotary spray pipe and the through hole on the rotary spray pipe are not coaxial, after the rotary spray pipe is inserted into and passes through the through hole on the rotary spray pipe, the re-slurry container will automatically swing around the mounting base to adjust the position of the through hole on the rotary spray pipe so that the sealing ring is sealed and connected to the rotary spray pipe.

[0060] In one implementation of this embodiment, Figure 2 As shown, an arc-shaped steel plate 1.13 is provided on the end surface of the mounting base, the curvature of the arc-shaped steel plate matches the curvature of the inner wall of the shield segment, and a sealing gasket 1.14 is installed on the surface of the arc-shaped steel plate. The arc-shaped steel plate of the mounting base uses expansion screws to fix the slurry return container mounting seat on the inner wall of the shield segment, so as to realize the sealing installation of the mounting base on the inner wall of the shield segment.

[0061] In another implementation of this embodiment, a straight steel plate is provided on the end surface of the mounting base, a sealing gasket is installed on the surface of the straight steel plate, and the end surface of the sealing gasket facing away from the straight steel plate is an arc surface, and the curvature of the arc surface matches the curvature of the inner wall of the shield segment. The straight steel plate of the mounting base uses expansion screws to fix the slurry return container mounting seat on the inner wall of the shield segment, and the mounting base is sealed and connected to the inner wall of the shield segment through the sealing gasket.

[0062] Furthermore, a base valve is provided on the installation base to control the opening and closing of the base through hole. In this embodiment, the base valve is a gate valve. During the construction of the high-pressure rotary jet pile, the base valve is opened to allow the rotary jet pipe to pass smoothly; after the high-pressure rotary jet pile construction is completed and the rotary jet pipe is moved out of the slurry return container, the base valve can be closed to prevent the cement soil slurry in the ground from bubbling into the tunnel.

[0063] Specific embodiment 3: The rest of the structure of this embodiment refers to specific embodiment 1 or specific embodiment 2, and the difference is that:

[0064] like Figure 4 As shown, the self-balancing slurry return system for subway tunnel reinforcement construction also includes a negative pressure pump 8 and a slurry pump 9. The slurry storage tank 3 includes a negative pressure suction tank 3.1 and a mixing tank 3.2. The negative pressure pump vacuums the top of the inner cavity of the negative pressure suction tank. Specifically, the air inlet of the negative pressure pump is connected to the top of the inner cavity of the negative pressure suction tank through a connecting rod. An air inlet is provided at the top of the negative pressure suction tank, and a switch valve is provided on the air inlet.

[0065] The slurry discharge pipe 4 includes a first slurry discharge pipe 4.1 and a second slurry discharge pipe 4.2. The first slurry discharge pipe connects the closed inner cavity of the return slurry container and the inner cavity of the negative pressure suction tank. Specifically, one end of the first slurry discharge pipe is connected to the slurry discharge interface, and the other end of the first slurry discharge pipe is connected to the upper or lower part of the negative pressure suction tank. The second slurry discharge pipe connects the bottom of the negative pressure suction tank and the upper part of the mixing tank. The slurry pump is used to pump the slurry in the negative pressure suction tank into the mixing tank through the second slurry discharge pipe; specifically, a slurry outlet is provided at the bottom of the negative pressure suction tank, the inlet of the slurry pump is sealedly connected to the slurry outlet, one end of the second slurry discharge pipe is sealedly connected to the outlet of the slurry discharge pipe, and the other end of the second slurry discharge pipe is connected to the upper or lower part of the mixing tank. The feed pipe connects the inlet of the feed pump and the inner cavity of the mixing tank. Specifically, one end of the feed pipe is connected to the inlet of the feed pump, and the other end of the feed pipe is connected to the bottom of the inner cavity of the mixing tank.

[0066] The slurry discharge valve includes a first slurry discharge valve for controlling the on and off of the first slurry discharge pipe and a second slurry discharge valve for controlling the on and off of the second slurry discharge pipe. The first slurry discharge valve is a solenoid valve or a manual valve. The second slurry discharge valve is a solenoid valve or a manual valve. The first slurry discharge valve is arranged on the first slurry discharge pipe, or on the slurry discharge interface. When the pressure sensor detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the first slurry discharge valve is closed; when the pressure sensor detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the first slurry discharge valve is opened. The second slurry discharge valve is arranged on the second slurry discharge pipe.

[0067] In actual work, the top of the inner cavity of the negative pressure suction tank can be evacuated by a negative pressure pump to put the inner cavity of the negative pressure suction tank in a negative pressure environment; when the pressure detector detects that the pressure in the closed inner cavity of the return slurry container is greater than the set value, the slurry discharge valve is opened and the cement soil slurry in the closed inner cavity of the return slurry container can be quickly sucked into the negative pressure suction tank through the slurry discharge pipe.

[0068] When the slurry discharge valve is closed, the switch valve on the air inlet can be opened to balance the air pressure in the negative pressure suction tank with the outside world; then the second slurry discharge valve can be opened, and the slurry in the negative pressure suction tank can be pumped into the mixing tank through the second slurry pipe by the slurry pump. The cement soil slurry in the mixing tank is pumped into the filter press through the feed pipe and feed pump, and the filter press is used to separate the cement soil slurry from mud and water.

[0069] A slurry agitator is provided in the mixing tank. The slurry agitator includes a stirring shaft rotatably arranged on the mixing tank, a stirring paddle arranged on the stirring shaft, and a driving motor for driving the stirring shaft to rotate. In this way, the cement soil slurry in the mixing tank can be stirred by the slurry agitator to avoid the sedimentation of the cement soil slurry in the mixing tank, which is beneficial to the subsequent separation of mud and water.

[0070] Specific embodiment 4 is a subway tunnel reinforcement method using a self-balancing grouting system for subway tunnel reinforcement construction. The specific structure of the self-balancing grouting system for subway tunnel reinforcement construction in this embodiment refers to specific embodiment 1 or specific embodiment 2.

[0071] A subway tunnel reinforcement method using a self-balancing grouting system for subway tunnel reinforcement construction comprises the following steps in sequence:

[0072] First, a hole is drilled on the shield segment of the subway tunnel by a drilling machine to form a segment through hole on the shield segment. The segment through hole penetrates the shield segment. The inner diameter of the segment through hole is larger than the outer diameter of the rotary jet pipe.

[0073] Second, install the underground pressure balancer, and use expansion screws to fix the slurry return container mounting base to the inner wall of the shield segment where the segment through-hole is located. The lower through-hole of the rotary jet pipe is opposite to the segment through-hole, and a sealing gasket is arranged between the slurry return container mounting base and the shield segment to ensure a sealed connection between the lower through-hole of the rotary jet pipe and the segment through-hole.

[0074] Third, adjust the jetting pipe of the high-pressure jetting pile machine to make the jetting pipe coaxial with the through hole on the jetting pipe;

[0075] Next, the jet pipe passes through the upper through hole of the jet pipe, the closed inner cavity, the lower through hole of the jet pipe and the through hole of the pipe segment in sequence, and extends to the specified depth underground. At this time, the upper through hole of the jet pipe and the jet pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole of the jet pipe and the jet pipe.

[0076] Next, the high-pressure jet grouting machine sprays grout through the jet grouting pipe to construct high-pressure jet grouting piles on the outside of the shield segment of the subway tunnel, thereby forming high-pressure jet grouting piles for reinforcing the subway tunnel on the outside of the shield segment of the subway tunnel. In this process, the cement soil slurry that emerges through the through-holes of the segment will enter the closed inner cavity of the slurry container through the slurry gap; when the pressure detector detects that the pressure in the closed inner cavity of the slurry container is less than the set value, the slurry discharge valve is closed to ensure the pressure of the underground cement soil and avoid the problem of affecting the construction quality of the high-pressure jet grouting piles due to low pressure. When the pressure detector detects that the pressure in the closed inner cavity of the slurry container is greater than the set value, the slurry discharge valve is opened to discharge the cement soil slurry into the slurry storage tank through the slurry discharge pipe.

[0077] The cement-soil slurry in the slurry storage tank is pumped into the filter press through the feed pipe and feed pump, and the filter press is used to separate the cement-soil slurry from mud and water. The water separated by the filter press is recovered into the recovery tank for recycling; of course, it is also discharged to a designated location outside the subway tunnel. The mud separated by the filter press is packaged and transported away, thereby avoiding the problem of cement-soil slurry bubbling into the tunnel and polluting the tunnel.

[0078] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any way. Any simple modification, change and equivalent transformation made to the above embodiment based on the technical essence of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A self-balancing grouting system for subway tunnel reinforcement construction, which is used in subway tunnel reinforcement construction using high-pressure jet grouting piles, and is characterized by: include: An underground pressure balancer is used to cooperate with the jet pipe of the high-pressure jet pile machine during the high-pressure jet pile construction process. The underground pressure balancer includes a slurry return container and a pressure detector. The slurry return container has a closed inner cavity. The top of the slurry return container is provided with a jet pipe upper through hole. The inner wall of the jet pipe upper through hole is provided with a sealing ring for cooperating with the jet pipe. The bottom of the slurry return container is provided with a slurry return container mounting seat. The slurry return container mounting seat is provided with a jet pipe lower through hole. The pressure detector is used to detect the pressure in the closed inner cavity of the slurry return container. A slurry storage tank, the inner cavity of which is connected to the sealed inner cavity of the slurry return container via a slurry discharge pipe; The slurry discharge valve is used to control the on and off of the slurry discharge pipe; The filter press comprises a feed pump, the inlet of the feed pump is connected to the inner cavity of the slurry storage tank through a feed pipeline; During the construction of high-pressure rotary jet piles, the rotary jet pipe is inserted into the upper through hole and the lower through hole of the rotary jet pipe. At this time, the upper through hole and the rotary jet pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole and the rotary jet pipe; when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the slurry discharge valve opens; when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the slurry discharge valve closes.

2. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 1 is characterized in that: The re-slurry container mounting seat includes a mounting base and a compensator connecting the mounting base and the bottom of the re-slurry container, and the lower through hole of the rotary spray pipe includes a compensator inner hole arranged in the compensator and a base through hole arranged in the mounting base.

3. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 1 is characterized in that: It also includes a negative pressure pump and a slurry pump. The slurry storage tank includes a negative pressure suction tank and a mixing tank. The negative pressure pump vacuums the top of the inner cavity of the negative pressure suction tank. The slurry discharge pipe includes a first slurry discharge pipe connecting the closed inner cavity of the return slurry container and the negative pressure suction tank, and a second slurry discharge pipe connecting the bottom of the negative pressure suction tank and the mixing tank. The slurry discharge pump is used to pump the slurry in the negative pressure suction tank into the mixing tank through the second slurry discharge pipe. The slurry discharge valve includes a first slurry discharge valve for controlling the on and off of the first slurry discharge pipe and a second slurry discharge valve for controlling the on and off of the second slurry discharge pipe; the feed pipe connects the inlet of the feed pump and the inner cavity of the mixing tank.

4. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 3 is characterized in that: An air inlet is arranged on the top of the negative pressure suction tank, and a switch valve is arranged on the air inlet.

5. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 3 is characterized in that: A slurry agitator is arranged in the stirring tank, and the slurry agitator comprises a stirring shaft rotatably arranged on the stirring tank, a stirring paddle arranged on the stirring shaft, and a driving motor for driving the stirring shaft to rotate.

6. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 1 is characterized in that: It also includes a traveling vehicle capable of traveling in a subway tunnel, wherein a mounting platform is arranged on the traveling vehicle, and the slurry storage tank, the filter press and the high-pressure rotary jet pile machine are all mounted on the mounting platform.

7. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 1 is characterized in that: A feeding valve is provided on the feeding pipeline to control the on-off of the feeding pipeline.

8. The self-balancing grouting system for subway tunnel reinforcement construction according to claim 7 is characterized in that: The feeding valve is a solenoid valve or a manual valve.

9. A subway tunnel reinforcement method using the self-balancing grouting system for subway tunnel reinforcement construction according to any one of claims 1 to 8, characterized in that: The following steps are included in sequence: First, use a drilling machine to drill holes on the shield segments of the subway tunnel to form segment holes on the shield segments; Second, install the underground pressure balancer, and use expansion screws to fix the slurry return container mounting base to the shield segment where the segment through hole is located. The through hole under the rotary jet pipe is directly opposite to the through hole of the segment. A sealing gasket is arranged between the slurry return container mounting base and the shield segment to ensure that the through hole under the rotary jet pipe is sealed and connected with the through hole of the segment. Third, adjust the jetting pipe of the high-pressure jetting pile machine to make the jetting pipe coaxial with the through hole on the jetting pipe; Next, the jet pipe passes through the upper through hole of the jet pipe, the closed inner cavity, the lower through hole of the jet pipe and the through hole of the pipe segment in sequence, and extends to the specified depth underground. At this time, the upper through hole of the jet pipe and the jet pipe are sealed and connected by a sealing ring, and there is a slurry return gap between the inner wall of the lower through hole of the jet pipe and the jet pipe. Next, the high-pressure rotary jet pile machine constructs on the outside of the shield segment of the subway tunnel through the rotary jet pipe to form high-pressure rotary jet piles for reinforcing the subway tunnel on the outside of the shield segment of the subway tunnel. In this process, the cement soil slurry emerging from the through holes of the segment will enter the closed inner cavity of the slurry return container through the slurry return gap. When the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is less than the set value, the slurry discharge valve is closed; when the pressure detector detects that the pressure in the closed inner cavity of the slurry return container is greater than the set value, the slurry discharge valve is opened to discharge the cement soil slurry into the slurry storage tank through the slurry discharge pipe.

10. A subway tunnel reinforcement method using a self-balancing grouting system for subway tunnel reinforcement construction according to claim 9, characterized in that: The following steps are also included: The cement-soil slurry in the slurry storage tank is pumped into the filter press through the feed pipe and the feed pump, and the filter press is used to separate the mud and water in the cement-soil slurry.

Citation Information

Patent Citations

  • Porous pipe horizontal rotary spraying drill bit

    CN103541658A

  • Pipe replacing and slurry discharging device for slurry shield and slurry discharging mode

    CN105298510A

  • In-hole multi-angle cement-soil pile construction equipment and tunnel reinforcement construction method

    CN111550182A

  • Shield machine spreader and the shield machine making use thereof

    JP2005155197A

  • Subterranean hollow element for Anti-soil pressure wall

    JP2007191944A