An Optimization Design Method for a Wastewater Source Heat Pump System

By establishing a mixed-integer nonlinear programming model to optimize the equipment scale and operating parameters of the sewage source heat pump system, the problem of efficient operation of the sewage source heat pump system under different ambient temperatures was solved, and the overall cost was reduced.

CN116050164BActive Publication Date: 2026-11-17SHANGHAI UNIV OF ENG SCI +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310097532.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-02-08
Publication Date
2026-11-17
Estimated Expiration
2043-02-08

AI Technical Summary

Technical Problem

Existing wastewater source heat pump systems are difficult to operate efficiently under different ambient temperatures and fail to fully consider system performance factors, resulting in high investment and operating costs.

Method used

By establishing a mixed integer nonlinear programming model, the equipment scale and operating parameters of the sewage source heat pump system are optimized. Combined with the heating demand under different ambient temperature conditions, the optimal design scheme is generated, including the optimization design of variables such as heat exchange medium, evaporation temperature, condensation temperature, superheat, subcooling and compression ratio.

Benefits of technology

The goal of reducing total costs under multiple operating conditions has been achieved, ensuring efficient operation of the wastewater source heat pump system under different ambient temperatures, optimizing equipment size and operating parameters, and reducing investment and operating costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116050164B_ABST
    Figure CN116050164B_ABST
Patent Text Reader

Abstract

This invention relates to an optimization design method for a wastewater source heat pump system. The method includes: determining the efficiency parameters of each device included in the wastewater source heat pump system, the operating parameters of the wastewater source heat pump system, and the design variables to be optimized in the wastewater source heat pump system; setting alternative heat exchanger schemes for the wastewater source heat pump system; performing process simulation on the wastewater source heat pump system, establishing a thermodynamic cycle process calculation model for the heat exchanger in each alternative scheme, and determining the physical property parameters of each heat exchanger under operating conditions; establishing an objective function, and generating a mixed-integer nonlinear programming model based on the energy balance equations of each device in the wastewater source heat pump system and the constraints of the design variables to be optimized; solving the mixed-integer nonlinear programming model, and finally determining the optimal scale of each device in the wastewater source heat pump system, the optimal heat exchanger of the wastewater source heat pump system under multiple operating conditions at ambient temperature, and the operating parameters under each operating condition.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of wastewater waste heat recovery technology, and in particular to an optimized design method for a wastewater source heat pump system. Background Technology

[0002] With rapid economic development and urbanization, wastewater treatment plant emission standards are constantly increasing. Meeting these high standards often comes at the cost of high energy consumption, forcing wastewater treatment plants to prioritize energy recovery and improve energy efficiency. Wastewater source heat pump technology can recover waste heat from wastewater, improving its utilization efficiency and reducing greenhouse gas emissions. It is a crucial means for urban wastewater treatment plants to achieve synergistic efficiency gains in pollution reduction and carbon reduction.

[0003] Optimizing the design of wastewater source heat pump systems to achieve efficient operation under various conditions helps improve their economic efficiency. Existing wastewater source heat pump systems exhibit varying optimal design and operating parameters depending on the region and the specific heating demands. Current system designs are typically based on a fixed heating load and outdoor ambient temperature, making it difficult to guarantee efficient operation under diverse conditions caused by temperature variations. Furthermore, existing methods for optimizing wastewater source heat pump system design have limitations, such as insufficient consideration of factors affecting system performance, failure to simultaneously optimize system configuration and operating parameters, and neglect of system investment and operating costs.

[0004] Therefore, further improvements to existing technologies are needed. Summary of the Invention

[0005] The technical problem to be solved by the present invention is to provide an optimization design method for a wastewater source heat pump system that, while ensuring that the wastewater source heat pump system meets certain heating requirements, aims to reduce the total cost and obtain the optimal equipment size and operating parameters under multiple operating conditions, in light of the above-mentioned prior art.

[0006] The technical solution adopted by the present invention to solve the above-mentioned technical problems is: an optimized design method for a wastewater source heat pump system, characterized by comprising the following steps:

[0007] Step 1: Determine the efficiency parameters of each device included in the wastewater source heat pump system, the operating parameters of the wastewater source heat pump system, and the design variables to be optimized in the wastewater source heat pump system.

[0008] Step 2: Based on the heating demand of the wastewater source heat pump system under different ambient temperature conditions, set up alternative heat exchange working fluid schemes for the wastewater source heat pump system.

[0009] Step 3: Perform process simulation on the wastewater source heat pump system, establish a thermodynamic cycle process calculation model for the heat exchange medium in each alternative scheme in Step 2, and use the established thermodynamic cycle process calculation model to calculate the thermodynamic properties of the heat exchange medium in each alternative scheme under different temperature and pressure conditions, and determine the physical property parameters of the heat exchange medium in each alternative scheme under the operating conditions of the wastewater source heat pump system.

[0010] Step 4: Establish the objective function and generate a mixed integer nonlinear programming model based on the energy balance equations of each device in the wastewater source heat pump system and the constraints of the design variables to be optimized in Step 1.

[0011] Step 5: Solve the mixed integer nonlinear programming model to minimize the objective function while satisfying the constraints in Step 4. Finally, determine the optimal scale of each device in the wastewater source heat pump system, the optimal heat exchange medium of the wastewater source heat pump system under multiple ambient temperature conditions, and the operating parameters under each condition.

[0012] Specifically, the equipment in the wastewater source heat pump system in step 1 includes at least a compressor, an evaporator, and a condenser.

[0013] Preferably, the design variables to be optimized in step 1 include the evaporation temperature T of the heat exchange medium. evap Condensation temperature T cond Superheat T sh Supercooling T sc Compression ratio ε, wastewater outlet temperature Wastewater mass flow rate m sewage and the mass flow rate of the heat exchange medium (m) wf .

[0014] In this invention, the objective function in step 4 is the annualized total cost (TAC) of the wastewater source heat pump system, and the formula for calculating TAC is:

[0015] TAC = AF * ICC + AOC

[0016] Where AF is the annualized coefficient, ICC is the initial investment cost of the wastewater source heat pump system, and AOC is the annual operating cost of the wastewater source heat pump system.

[0017] The formula for calculating the initial investment cost (ICC) of a wastewater source heat pump system is as follows:

[0018]

[0019] Among them, cost comp (s,i) represents the cost of the compressor for the i-th heat exchange medium under the s-th ambient temperature condition, ∑ ia(i) = 1, where a(i) is a binary variable representing the selection of the i-th heat exchange medium in the wastewater source heat pump system; it is 1 if selected and 0 if not selected; cost evap (s,i) represents the cost of the evaporator for the i-th heat exchange medium under the s-th ambient temperature condition. cond (s,i) represents the cost of the condenser for the i-th heat exchange medium under the s-th ambient temperature condition. add (s,i) represents the cost of additional equipment for the i-th heat exchange medium under the s-th ambient temperature condition.

[0020] The formula for calculating the annual operating cost (AOC) of the above-mentioned wastewater source heat pump system is as follows:

[0021]

[0022]

[0023] Where MC represents the annual maintenance cost of the wastewater source heat pump system; AOC s (s,i) represents the operating cost of the i-th heat exchange medium selected in the wastewater source heat pump system under the s-th ambient temperature condition; f(s) represents the weighting coefficient of the s-th ambient temperature condition.

[0024] In this scheme, the energy balance equation in step 4 includes:

[0025] Energy balance equations corresponding to the actual heating load of a wastewater source heat pump system under different ambient temperature conditions:

[0026] Q bin (s)=Q des ×((HLET-T amb (s)) / (HLET-T des ))

[0027] Among them, Q bin (s) represents the actual heating load of the wastewater source heat pump system under the s-th ambient temperature condition, in W / m². 2 Q des This represents the design heating load, in W / m². 2 HLET represents the design indoor heating temperature, in °C; T amb (s) represents the outdoor ambient temperature under the s-th ambient temperature condition, in °C; T des The unit for indicating the outdoor temperature for heating is °C.

[0028] In this scheme, the energy balance equation in step 4 also includes:

[0029] Energy balance equations for wastewater source heat pump systems under different ambient temperature conditions:

[0030]

[0031] Among them, Q cond (s) represents the condensation heat release of the wastewater source heat pump system under the s-th ambient temperature condition, in kJ / h; Q evap (s,i) represents the heat absorption by the evaporation of the i-th working fluid in the wastewater source heat pump system under the s-th ambient temperature condition, in kJ / h; W comp (s,i) represents the compression work of the wastewater source heat pump system under the i-th working fluid and the s-th ambient temperature condition, in kJ / h.

[0032] Furthermore, the energy balance equation in step 4 also includes:

[0033] The energy balance equation corresponding to the heat absorbed by the working fluid during the heat exchange process in the evaporator:

[0034]

[0035] Where h3(s,i), h1(s,i) and m wf (s,i) represent the enthalpy of the heat exchange medium at the evaporator outlet, the enthalpy of the heat exchange medium at the evaporator inlet, and the mass flow rate of the heat exchange medium, respectively, under the ambient temperature condition of the s-th heat exchange medium. and m sewage (s,i) represent the enthalpy of wastewater at the evaporator inlet, the enthalpy of wastewater at the evaporator outlet, and the mass flow rate of wastewater, respectively, when the i-th heat exchange medium is selected for heat exchange under the s-th ambient temperature condition.

[0036] Furthermore, h3(s,i)≥h1(s,i) This represents the maximum mass flow rate of the wastewater.

[0037] Furthermore, the energy balance equation in step 4 also includes:

[0038] The energy balance equation corresponding to the heat released by the working fluid during the heat exchange process in the condenser:

[0039]

[0040] Where h4(s,i) and h6(s,i) represent the enthalpy of the heat exchange medium at the condenser inlet and the enthalpy of the heat exchange medium at the s-th ambient temperature, respectively, and h4(s,i)≥h6(s,i). and m hotwater(s,i) represent the specific enthalpy of the circulating hot water at the condenser outlet, the specific enthalpy of the circulating hot water at the condenser inlet, and the mass flow rate of the circulating hot water under the s-th ambient temperature condition when the ith heat exchange medium is selected.

[0041] In this scheme, the constraints of the design variables to be optimized in step 4 are as follows:

[0042]

[0043]

[0044] 0≤T sh

[0045] 0≤T sc

[0046] ε min ≤ε≤ε max

[0047]

[0048] in, and These are the minimum and maximum evaporation temperatures, respectively. Let ΔT be the temperature of the wastewater heat source. min This is the minimum heat transfer temperature of the heat exchanger. and These are the minimum and maximum values ​​of the condensation temperature, respectively. ε is the return water temperature of the circulating hot water; min and ε max These represent the minimum and maximum compression ratios, respectively.

[0049] Compared with existing technologies, the advantages of this invention are as follows: By using the reduction of total cost as the objective function and based on the heating demand of the wastewater source heat pump system under different ambient temperature conditions, alternative scale parameters for each device in the wastewater source heat pump system are generated. Corresponding operating parameters are set for each alternative scheme. Finally, the optimal scale of each device in the wastewater source heat pump system, the optimal heat exchange medium for the wastewater source heat pump system under multiple ambient temperature conditions, and the operating parameters under each condition are calculated using the energy balance equation and constraints. Therefore, this optimization design method simultaneously optimizes the equipment scale and operating parameters of the wastewater source heat pump system, achieving the lowest investment and operating costs (total cost) while ensuring heating demand. Attached Figure Description

[0050] Figure 1 This is a flowchart of the wastewater source heat pump system optimization design method in an embodiment of the present invention;

[0051] Figure 2 This is a schematic diagram of the working process of the wastewater source heat pump system in an embodiment of the present invention;

[0052] Figure 3 This is a temperature entropy diagram of the sewage source heat pump system at various operating states in an embodiment of the present invention;

[0053] Figure 4 This is a schematic diagram of hourly outdoor environmental temperature in an embodiment of the present invention;

[0054] Figure 5 This is a schematic diagram of the heating load under changes in outdoor ambient temperature in an embodiment of the present invention. Detailed Implementation

[0055] The present invention will be further described in detail below with reference to the accompanying drawings and embodiments.

[0056] like Figure 1 As shown, the optimized design method for the wastewater source heat pump system in this embodiment includes the following steps:

[0057] Step 1: Determine the efficiency parameters of each device included in the wastewater source heat pump system, the operating parameters of the wastewater source heat pump system, and the design variables to be optimized in the wastewater source heat pump system.

[0058] In this embodiment, the equipment of the wastewater source heat pump system includes a compressor, an evaporator, a condenser, etc.; the efficiency parameters of the above equipment include the isentropic efficiency of the compressor, the mechanical efficiency of the compressor, the mechanical efficiency of each water pump, and the total heat transfer efficiency of the evaporator and condenser; the operating parameters of the wastewater source heat pump system include the heating load, wastewater temperature, maximum wastewater mass flow rate, circulating hot water outlet temperature, and circulating hot water return temperature; both the efficiency parameters and the operating parameters are fixed values.

[0059] In this embodiment, the design variables to be optimized include the evaporation temperature T of the heat exchange medium. evap Condensation temperature T cond Superheat T sh Supercooling T sc Compression ratio ε, wastewater outlet temperature Wastewater mass flow rate m sewage and the mass flow rate of the heat exchange medium (m) wf ;

[0060] Step 2: Based on the heating demand of the wastewater source heat pump system under different ambient temperature conditions, set up alternative heat exchange working fluid schemes for the wastewater source heat pump system.

[0061] Step 3: Perform process simulation on the wastewater source heat pump system, establish a thermodynamic cycle process calculation model for the heat exchange medium in each alternative scheme in Step 2, and use the established thermodynamic cycle process calculation model to calculate the thermodynamic properties of the heat exchange medium in each alternative scheme under different temperature and pressure conditions, and determine the physical property parameters of the heat exchange medium in each alternative scheme under the operating conditions of the wastewater source heat pump system.

[0062] In this embodiment, the following assumptions need to be made when establishing the thermodynamic cycle flow calculation model of the heat exchange working fluid in the wastewater source heat pump system:

[0063] Ignore heat exchange losses between the system and the environment;

[0064] Both the evaporation and condensation processes of the working fluid are considered isobaric processes;

[0065] The expansion process of the working fluid through the throttling valve is considered an isenthalpic process;

[0066] Specifically, in the thermodynamic cycle calculation model of the heat exchange working fluid in a wastewater source heat pump system, the processes experienced by the system are determined by each state point. Therefore, each process of the thermodynamic cycle in a wastewater source heat pump system can be expressed as a relationship between the thermodynamic properties of the initial and final state points of each process. Figure 3 In the diagram, points 1, 3, 4, and 6 correspond to the evaporator inlet, evaporator outlet, condenser inlet, and condenser outlet in the wastewater source heat pump system, respectively. Figure 3 In the diagram, points 1 to 3 represent the isobaric evaporation process of the working fluid, corresponding to... Figure 2 The process is carried out in evaporator 1. Figure 2 Wastewater from the wastewater treatment plant is pumped to evaporator 1 via the first pump 2. Evaporator 1 has an inlet wastewater 11 and an outlet wastewater 12. Points 3 to 4' represent isentropic compression of the working fluid; points 3 to 4' represent non-isentropic compression of the working fluid. Figure 2 The process takes place in compressor 3; points 4 to 6 represent the isobaric condensation process of the working fluid, corresponding to... Figure 2 The process takes place in condenser 4. Figure 2 Water is pumped to condenser 4 via the second pump 5. Condenser 4 has an inlet circulating hot water 41 and an outlet circulating hot water 42. Points 6 to 1 indicate... Figure 2 The working fluid expands through throttling valve 6. The temperature and pressure of the working fluid are variables during both evaporation and condensation.

[0067] The main relationships involved in the thermodynamic cycle of a wastewater source heat pump system are:

[0068] Heat absorption per unit mass of working fluid during the evaporator heat absorption process (unit: kJ / kg): h3-h1

[0069] Heat release per unit mass of working fluid during the condenser heat release process (unit: kJ / kg): h4-h6

[0070] Specific enthalpy of the working fluid after a non-isentropic compression process (unit: kJ / kg): h4=h3+(h`4-h3) / η ie

[0071] Work done by the compressor on a unit mass of working fluid (unit: kJ / kg): h4-h3

[0072] Compression ratio: ε = p cond / p evap

[0073] Specific enthalpy of the working fluid during the throttling expansion process: h6 = h1

[0074] In the formula, h1, h3, h4, h`4, and h6 respectively represent Figure 3 The enthalpy values ​​at points 1, 3, 4, 4' and 6, that is... Figure 2 Specific enthalpy at evaporator inlet, evaporator outlet, condenser inlet, and condenser outlet, in kJ / kg; η ie p represents the isentropic efficiency of the compressor. cond and p evap These represent the condensation pressure and evaporation pressure, respectively, in kPa.

[0075] Step 4: Establish the objective function and generate a mixed integer nonlinear programming model based on the energy balance equations of each device in the wastewater source heat pump system and the constraints of the design variables to be optimized in Step 1.

[0076] In this embodiment, the objective function is the annualized total cost (TAC) of the wastewater source heat pump system, and the formula for calculating TAC is:

[0077] TAC = AF * ICC + AOC

[0078] Where AF is the annualized coefficient, ICC is the initial investment cost of the wastewater source heat pump system, and AOC is the annual operating cost of the wastewater source heat pump system.

[0079] The annualized coefficient AF mentioned above can be calculated using the formula. ICC and AOC are both variables. The purpose of the optimization design in this embodiment is to find the minimum annualized total cost TAC. If the area of ​​the heat exchanger in the wastewater source heat pump system is relatively large, the initial investment cost ICC will be high. When the required flow rate is small, the annual operating cost AOC will be low. However, if the area of ​​the heat exchanger in the wastewater source heat pump system is small, the initial investment cost ICC will be low. When the required flow rate is large, the annual operating cost AOC will be high. Therefore, the optimization idea in this embodiment is to balance ICC and AOC.

[0080] The formula for calculating the initial investment cost (ICC) of a wastewater source heat pump system is as follows:

[0081]

[0082] Among them, cost comp (s,i) represents the cost of the compressor for the i-th heat exchange medium under the s-th ambient temperature condition, ∑ i a(i) = 1, where a(i) is a binary variable representing the selection of the i-th heat exchange medium in the wastewater source heat pump system. It is 1 if selected and 0 if not, ensuring that the wastewater source heat pump system selects an optimal heat exchange medium; cost evap (s,i) represents the cost of the evaporator for the i-th heat exchange medium under the s-th ambient temperature condition. cond (s,i) represents the cost of the condenser for the i-th heat exchange medium under the s-th ambient temperature condition. add (s,i) represents the cost of additional equipment for the i-th heat exchange medium under the s-th ambient temperature condition; the scale of each piece of equipment is determined by the thermodynamic cycle parameters of the wastewater source heat pump system, and then the investment cost of each piece of equipment is calculated.

[0083] The cost of the heat exchangers (evaporator and condenser) is related to the heat exchange area A. In this embodiment, a tube-and-shell heat exchanger is used. Assuming the overall heat transfer coefficient U is a fixed parameter, the heat exchange area is determined using the logarithmic mean temperature difference (LMTD). The heat exchange area A can be determined by the following formula:

[0084]

[0085] The above costs evap The formula for calculating (s,i) is:

[0086] log 10 cost evap (s,i)=K1+K2×log 10 A evap (s,i)+K3×A evap (s,i) 2

[0087] Where K1, K2, and K3 are all calculation constants; A evap (s,i) represents the heat exchange area of ​​the evaporator for the i-th heat exchange medium under the s-th ambient temperature condition. Q evap (s,i) represents the heat transfer capacity of the evaporator for the i-th heat transfer medium under the s-th ambient temperature condition, in kJ / h; U is the overall heat transfer coefficient, LMTD. evap (s,i) represents the logarithmic mean temperature difference of the evaporator for the i-th heat exchange medium under the s-th ambient temperature condition, LMTD evapThe formula for (s,i) is T3(s,i) represents the inlet temperature of the i-th heat exchange medium under the s-th ambient temperature condition; T3(s,i) represents the outlet temperature of the i-th heat exchange medium at the evaporator under the s-th ambient temperature condition. T1(s,i) represents the wastewater effluent temperature of the i-th heat exchange medium under the s-th ambient temperature condition; T1(s,i) represents the temperature of the i-th heat exchange medium at the evaporator inlet under the s-th ambient temperature condition; A above evap (s,i), Q evap (s,i), LMTD evap (s,i) T3(s,i) Both T1(s,i) and T1(s,i) are variables; The parameters are known.

[0088] Similarly, the above costs cond The formula for calculating (s,i) is:

[0089] log 10 cost cond (s,i)=K1+K2×log 10 A cond (s,i)+K2×A cond (s,i) 2

[0090] Among them, A cond (s,i) represents the heat exchange area of ​​the condenser for the i-th heat exchange medium under the s-th ambient temperature condition. Q cond (s) represents the heat transfer rate of the condenser under the s-th ambient temperature condition, LMTD cond (s,i) represents the logarithmic mean temperature difference of the condenser under the s-th ambient temperature condition for the ith heat exchange medium. cond The formula for (s,i) is

[0091]

[0092] T4(s,i) is the temperature of the i-th heat exchange medium at the condenser inlet under the s-th ambient temperature condition. T6(s,i) represents the circulating hot water outlet temperature of the i-th heat exchange medium under the s-th ambient temperature condition; T6(s,i) represents the temperature of the i-th heat exchange medium at the condenser outlet under the s-th ambient temperature condition. Let A be the return water temperature of the circulating hot water for the i-th heat exchange medium under the s-th ambient temperature condition; cond (s,i), LMTD cond (s,i), T4(s,i), and T6(s,i) are all variables; Qcond (s), and The parameters are known.

[0093] In addition, the investment cost of the compressor is expressed as follows:

[0094] log 10 cost comp (s,i)=K4+K5×log 10 W comp (s,i)+K6×W comp (s,i) 2

[0095] Among them, W comp (s,i) are variables, representing the compression work of the compressor for the i-th heat exchange medium under the s-th ambient temperature condition, in kW; K4, K5, and K6 are calculation constants;

[0096] The formula for calculating the annual operating cost (AOC) of the above-mentioned wastewater source heat pump system is as follows:

[0097]

[0098]

[0099] Where MC represents the annual maintenance cost of the wastewater source heat pump system; AOC s (s,i) represents the operating cost of the i-th heat exchange medium selected in the wastewater source heat pump system under the s-th ambient temperature condition; f(s) represents the weighting coefficient of the s-th ambient temperature condition.

[0100] The energy balance equation in the mixed-integer nonlinear programming model is as follows:

[0101] 1. Energy balance equations corresponding to the actual heating load of a wastewater source heat pump system under different ambient temperature conditions:

[0102] Q bin (s)=Q des ×((HLFT-T amb (s)) / (HLET-T des ))

[0103] Among them, Q bin (s) represents a known parameter, indicating the actual heating load of the wastewater source heat pump system under the s-th ambient temperature condition, in W / m². 2 Q des Given parameters, representing the design heating load, in W / m². 2 HLET represents the known parameter, indicating the design indoor heating temperature in °C; T amb(s) is a known parameter, representing the outdoor ambient temperature under the s-th ambient temperature condition, in °C; T des Given parameters, representing the design outdoor temperature for heating, in °C;

[0104] 2. Energy balance equations for wastewater source heat pump systems under different ambient temperature conditions:

[0105]

[0106] Among them, Q cond (s) is a known parameter, representing the condensation heat release of the wastewater source heat pump system under the s-th ambient temperature condition, in kJ / h; Q evap (s,i) are positive variables, representing the heat absorbed by the evaporation of the i-th working fluid under the s-th ambient temperature condition in the wastewater source heat pump system, in kJ / h; w comp (s,i) is a positive variable, representing the compression work of the wastewater source heat pump system under the s-th ambient temperature condition for the i-th working fluid, in kJ / h.

[0107] 3. The energy balance equation corresponding to the heat absorbed by the working fluid during the heat exchange process in the evaporator:

[0108]

[0109] Where h3(s,i), h1(s,i) and m wf (s,i) are variables, representing the evaporator outlet specific enthalpy (kJ / kg), evaporator inlet specific enthalpy (kJ / kg), and mass flow rate (kg / h) of the heat exchange medium for the i-th heat exchange medium under the s-th ambient temperature condition, respectively. and m sewage (s,i) represent the enthalpy of the wastewater at the evaporator inlet (kJ / kg), the enthalpy of the wastewater at the evaporator outlet (kJ / kg), and the mass flow rate of the wastewater (kg / h) under the ambient temperature condition of the s-th ambient temperature when the i-th heat exchange medium is selected. Given parameters, and m sewage (s,i) are variables;

[0110] Furthermore, to ensure normal heat exchange in the evaporator, the outlet temperature of the working fluid evaporator must be higher than the inlet temperature; however, for wastewater, the inlet temperature of the evaporator must be higher than the outlet temperature, expressed in terms of enthalpy as follows:

[0111] h3(s,i)≥h1(s,i)

[0112] In addition, the mass flow rate of the wastewater must be less than the maximum wastewater mass flow rate specified by the wastewater treatment plant:

[0113] This represents the maximum mass flow rate of the wastewater.

[0114] 4. The energy balance equation corresponding to the heat released by the working fluid during the heat exchange process in the condenser:

[0115]

[0116] Where h4(s,i) and h6(s,i) are variables, representing the enthalpy of the condenser inlet working fluid (unit kJ / kg) and the enthalpy of the condenser outlet working fluid (unit kJ / kg) of the ith heat exchange working fluid under the s-th ambient temperature condition, respectively, and h4(s,i)≥h6(s,i); and m hotwater (s,i) are known parameters, representing the specific enthalpy of the circulating hot water at the condenser outlet (kJ / kg), the specific enthalpy of the circulating hot water at the condenser inlet (kJ / kg), and the mass flow rate of the circulating hot water (kg / h) under the ambient temperature condition of the s-th ambient temperature when the i-th heat exchange medium is selected.

[0117] To ensure proper heat exchange in the condenser, the inlet temperature of the working fluid condenser must be higher than the outlet temperature, expressed as enthalpy as follows:

[0118] h4(s,i)≥h6(s,i).

[0119] The constraints for the design variables to be optimized in step 5 are:

[0120]

[0121]

[0122] 0≤T sh

[0123] 0≤T sc

[0124] ε min ≤ε≤ε max

[0125]

[0126] in, and These are the minimum and maximum evaporation temperatures, respectively. Let ΔT be the temperature of the wastewater heat source. min This is the minimum heat transfer temperature of the heat exchanger. and These are the minimum and maximum values ​​of the condensation temperature, respectively. The return water temperature is the temperature of the circulating hot water. To ensure the normal operation of the compressor, the working fluid must not be in a gas-liquid two-phase state during the compression process, so the superheat T of the heat exchanger is introduced. sh and supercooling T sc The lower limit; meanwhile, the system does not yet consider multi-level compression ε. mi and ε max These are the minimum and maximum values ​​of the compression ratio, respectively, therefore ε min and ε max The pressure ratio is determined based on the minimum and maximum pressure ratio of the first-stage compression; to avoid cross-heat transfer in the heat exchanger, the outlet temperature of the wastewater heat source is... The lower limit depends on the evaporation temperature T. evap Sure;

[0127] Step 5: Solve the mixed integer nonlinear programming model to minimize the objective function while satisfying the constraints in Step 4. Finally, determine the optimal scale of each device in the wastewater source heat pump system, the optimal heat exchange medium of the wastewater source heat pump system under multiple ambient temperature conditions, and the operating parameters under each condition.

[0128] The following example illustrates the optimized design method of the wastewater source heat pump system in this invention:

[0129] A wastewater treatment plant with a treatment capacity of 3000 t / h was selected as the heat source, and a wastewater source heat pump system was used to heat 100,000 m³ of wastewater. 2 The building is heated; the wastewater source heat pump system includes main equipment such as evaporators, compressors, and condensers, as well as other equipment such as expansion valves and pumps. The local hourly outdoor ambient temperature is as follows: Figure 4 As shown, wastewater source heat pump systems must meet the actual heating needs of buildings when providing heating. The relevant conditions for local wastewater source heat pump systems are shown in Table 1.

[0130] Table 1 Heating-related conditions for local wastewater source heat pump systems

[0131] Building heating area <![CDATA[[m 2 ]]]> 100000 Design indoor heating temperature [℃] 18 Design heating outdoor temperature [℃] -9 Building heating and heat supply indicators <![CDATA[[W / m 2 ]]]> 61.8 Building heating time [h] 3618.5 Maximum mass flow rate of wastewater [t / h] 3000 wastewater temperature [℃] 13 Circulating hot water outlet temperature [℃] 45 Circulating hot water return temperature [℃] 40 Electricity price [¥ / kWh] 0.4883 Basic heat price <![CDATA[[¥ / m 2 ]]]> 12 Metered heat price [¥ / kWh] 0.16

[0132] Based on the local outdoor ambient temperature and heating conditions, the heating demand of the wastewater source heat pump system under different ambient temperature conditions can be calculated using the following formula: The heating load under hourly changes in local outdoor ambient temperature is as follows: Figure 5 As shown:

[0133] Q bin (s)=61.8×((18-T amb (s)) / (18+9))

[0134] Based on the heating demand under different local ambient temperature conditions, candidate working fluids were selected. In this case, R134a and R152a were chosen as the two heat exchange working fluids, and their basic physical properties are shown in Table 2.

[0135] Table 2 Basic physical properties of two heat exchange working fluids, R134a and R152a.

[0136] heat exchange medium R134a R152a Standard boiling point (°C) -26.1 -24.7 Critical temperature (°C) 101.1 113.5 Critical pressure (kPa) 4060 4520 Ozone depletion potential 0 0 Global warming potential 1430 124

[0137] In this embodiment, the thermodynamic property calculation equations of the wastewater source heat pump system at various state points are obtained by using the fitting function of the process simulation software Aspen. Based on this, a thermodynamic cycle process calculation model of the selected working fluid is established. This model can be used to calculate the thermodynamic properties of the working fluid under different temperature and pressure process states.

[0138] This embodiment Figure 3 Midpoints 1-3 represent the isobaric evaporation process of the working fluid, and points 4-6 represent the isobaric condensation process. The temperature and pressure of the working fluid are variables during both evaporation and condensation. To more accurately describe the evaporation and condensation states of the working fluid, a nonlinear mathematical model of temperature and pressure during the evaporation and condensation processes is obtained using Aspen fitting. The calculation equations are as follows:

[0139] T evap =a T,evap ·p evap 2 +b T,evap ·p evap +c T,evap

[0140] T cond =a T,cond ·p cond 2 +b T,cond ·p cond +c T,cond

[0141] In the formula, T evap This indicates the evaporation temperature, in °C (°C) and p (temperature). evap Indicates evaporation pressure, a T,evap b T,evap and c T,eva The coefficients obtained by fitting the evaporation temperature and evaporation pressure are all constant values; T cond This indicates the condensation temperature, in °C (°C) and p (p). cond Indicates condensation pressure; a T,cond b T,cond and c T,cond The coefficients obtained by fitting the condensation temperature and condensation pressure are all constant values.

[0142] superheat T of the working fluid shAs a variable, in °C, the temperature T3 of the working fluid at the evaporator outlet can be obtained using the following equation. The specific enthalpy h3 and specific entropy s3 of the working fluid at the evaporator outlet, as functions of temperature and pressure, are calculated using the Aspen fit equation as follows:

[0143] T3 = T evap +T sh

[0144] h3 = z h3 +a h3 ·T3+b h3 ·p evap +c h3 ·T3 2 +d h3 ·p evap 2 +f h3 ·T3·p evap

[0145] s3=z s3 +a s3 ·T3+b s3 ·p evap +c s3 ·T3 2 +d s3 ·p evap 2 +f s3 ·T3·p evap

[0146] Among them, z h3 a h3 b h3 c h3 d h3 f h3 z s3 a s3 b s3 c s3 d s3 and f s3 All are calculated constants obtained through fitting;

[0147] Figure 3 Midpoints 3-4' represent the isentropic compression process of the compressor. The specific entropy s of isentropic compression... 4′ =s3, using the Aspen fitting process to consider the compressor mechanical efficiency η me The temperature T of the isentropically compressed gaseous working fluid was obtained by fitting. 4′ and enthalpy h 4′ The calculation equation is as follows:

[0148] T 4′ =z T4′ +a T4′ ·pcond +b T4′ ·s 4′ +c T4′ ·p cond 2 +d T4′ ·s 4′ 2 +f T4′ ·p cond ·s 4′

[0149] h 4′ =z h4′ +a h4′ ·T 4′ +b h4′ ·p cond +c h4′ ·T 4′ 2 +d h4′ ·p cond 2 +f h4′ ·T 4′ ·p cond

[0150] Among them, z T4′ a T4′ b T4′ c T4′ d T4′ f T4′ z h4′ a h4′ b h4′ c h4′ d h4′ and f h4′ All are calculated constants obtained through fitting;

[0151] In the actual operation of a wastewater source heat pump, the compressor operates as a non-isentropic compression process. Isentropic efficiency is denoted by η. is Therefore, the non-isentropic enthalpy h4 at the compressor outlet can be obtained from the equation. The fitting equation for the outlet temperature T4 of non-isentropic compression is as follows.

[0152] h4=h3+(h 4′ -h3) / η is

[0153]

[0154] Among them, z T4 a T4 b T4 , and f T4 All are calculated constants obtained through fitting;

[0155] To lower the temperature of the working fluid entering the expansion valve, reduce flash gas generation during or after throttling expansion, and appropriately improve efficiency, a subcooling process is also added to the working fluid during the condensation stage. The subcooling degree T of the working fluid... sc As a variable, its temperature T6 at the evaporator outlet can be obtained using an equation. Similar to the evaporation process, the specific enthalpy h6 of the working fluid at the condenser outlet is calculated using the following equation. Due to the isenthalpic throttling expansion of the working fluid, the specific enthalpy h1 of the working fluid at the evaporator inlet is equal to the specific enthalpy h6 of the working fluid at the condenser outlet, as shown in the following equation.

[0156] T6 = T cond -T sc

[0157] h6 = z h6 +a h6 ·T6+b h6 ·p cond +c h6 ·T6 2 +d h6 ·p cond 2 +f h6 ·T6·p cond

[0158] h1 = h6

[0159] Among them, z h6 a h6 b h6 c h6 d h6 and f h6 All are calculated constants obtained through fitting;

[0160] In this embodiment, taking the calculation of the specific enthalpy of the working fluid at the evaporator outlet as an example, the calculation model of the thermodynamic properties of the wastewater source heat pump system is as follows:

[0161] h3 = z h3 +a h3 ·T3+b h3 ·p evap +c h3 ·T3 2 +d h3 ·p evap 2 +f h3 ·T3·p evap

[0162] Where h3 represents the specific enthalpy of the working fluid at the evaporator outlet, in kJ / kg; T3 represents the temperature of the working fluid at the evaporator outlet, in °C; p evap This indicates the evaporation pressure of the working fluid at the evaporator outlet, in kPa.

[0163] Taking the calculation of the specific enthalpy of the working fluid at the evaporator outlet as an example, the model calculation constants for this case, which select two heat exchange working fluids, R134a and R152a, are shown in Table 3:

[0164] Table 3 Model calculation constants for two heat exchange working fluids, R134a and R152a.

[0165]

[0166] The design variables to be optimized need to meet the following constraints:

[0167] 0≤T evap ≤14

[0168] 41≤T cond ≤75

[0169] 0≤T sh

[0170] 0≤T sc

[0171] 3≤ε≤5

[0172] Write out the energy balance equations for each device, establish the objective function and constraint condition function relationships, generate a mixed integer nonlinear programming model, solve the mixed integer nonlinear programming model using GAMS software, and obtain the design scheme of the sewage source heat pump system that meets multiple operating conditions, as shown in Table 4, and the operating parameters under each operating condition, as shown in Table 5.

[0173] Table 4 Design Scheme of Wastewater Source Heat Pump System under Multiple Operating Conditions

[0174] Preferred heat exchange medium / R152a Evaporator heat exchange area <![CDATA[[m 2 ]]]> 1191.716 Condenser heat exchange area <![CDATA[[m 2 ]]]> 915.796 compressor rated power [kW] 1372.916 Annual operating costs [¥] 1468393.434 Annualized total cost [¥] 4813202.749 Investment recovery period [year] 10.159

[0175] Table 5 Operating parameters under various working conditions

[0176]

Claims

1. An optimized design method for a wastewater source heat pump system, characterized in that... Includes the following steps: Step 1: Determine the efficiency parameters of each device in the wastewater source heat pump system, the operating parameters of the wastewater source heat pump system, and the design variables to be optimized in the wastewater source heat pump system; the devices in the wastewater source heat pump system include at least a compressor, an evaporator, and a condenser; the design variables to be optimized include the evaporation temperature of the heat exchange medium. Condensation temperature overheating supercooling Compression ratio Wastewater outlet temperature Wastewater mass flow rate and the mass flow rate of the heat exchange medium ; Step 2: Based on the heating demand of the wastewater source heat pump system under different ambient temperature conditions, set up alternative heat exchange working fluid schemes for the wastewater source heat pump system. Step 3: Perform process simulation on the wastewater source heat pump system, establish a thermodynamic cycle process calculation model for the heat exchange medium in each alternative scheme in Step 2, and use the established thermodynamic cycle process calculation model to calculate the thermodynamic properties of the heat exchange medium in each alternative scheme under different temperature and pressure conditions, and determine the physical property parameters of the heat exchange medium in each alternative scheme under the operating conditions of the wastewater source heat pump system. Step 4: Establish the objective function and generate a mixed integer nonlinear programming model based on the energy balance equations of each device in the wastewater source heat pump system and the constraints of the design variables to be optimized in Step 1. The objective function is the annualized total cost (TAC) of the wastewater source heat pump system. The formula for calculating TAC is: TAC = AF * ICC + AOC Where AF is the annualized coefficient, ICC is the initial investment cost of the wastewater source heat pump system, and AOC is the annual operating cost of the wastewater source heat pump system. The formula for calculating the initial investment cost (ICC) of a wastewater source heat pump system is as follows: in, The cost of the compressor for the i-th heat exchange medium under the s-th ambient temperature condition is... , This is a binary variable representing the selection of the i-th heat exchange medium in the wastewater source heat pump system. It is 1 if selected and 0 if not selected. The cost of the evaporator for the i-th heat exchange medium under the s-th ambient temperature condition is... The cost of the condenser for the i-th heat exchange medium under the s-th ambient temperature condition is... The cost of additional equipment for the i-th heat exchange medium under the s-th ambient temperature condition; The formula for calculating the annual operating cost (AOC) of the above-mentioned wastewater source heat pump system is as follows: in, Annual maintenance cost of wastewater source heat pump system; The operating cost of the i-th heat exchange medium selected for the wastewater source heat pump system under the s-th ambient temperature condition. is the weighting coefficient for the s-th ambient temperature condition; Step 5: Solve the mixed integer nonlinear programming model to minimize the objective function while satisfying the constraints in Step 4. Finally, determine the optimal scale of each device in the wastewater source heat pump system, the optimal heat exchange medium of the wastewater source heat pump system under multiple ambient temperature conditions, and the operating parameters under each condition.

2. The optimized design method for a wastewater source heat pump system according to claim 1, characterized in that: The energy balance equation in step 4 includes: Energy balance equations corresponding to the actual heating load of a wastewater source heat pump system under different ambient temperature conditions: in, This represents the actual heating load of the wastewater source heat pump system under the s-th ambient temperature condition, in W / m². 2 ; This represents the design heating load, in W / m². 2 ; This indicates the designed indoor heating temperature, in °C. The outdoor ambient temperature is represented under the s-th ambient temperature condition, in °C. The unit for indicating the outdoor temperature for heating is °C.

3. The optimized design method for a wastewater source heat pump system according to claim 2, characterized in that: The energy balance equation in step 4 also includes: Energy balance equations for wastewater source heat pump systems under different ambient temperature conditions: in, The unit is kJ / h, which represents the condensation heat release of the wastewater source heat pump system under the s-th ambient temperature condition. This represents the heat absorbed by the evaporation of the i-th working fluid under the s-th ambient temperature condition in the wastewater source heat pump system, in kJ / h. This represents the compression work done by the wastewater source heat pump system under the i-th working fluid and the s-th ambient temperature condition, in kJ / h.

4. The optimized design method for a wastewater source heat pump system according to claim 3, characterized in that: The energy balance equation in step 4 also includes: The energy balance equation corresponding to the heat absorbed by the working fluid during the heat exchange process in the evaporator: in, , and Let represent the specific enthalpy of the heat exchange medium at the evaporator outlet, the specific enthalpy of the heat exchange medium at the evaporator inlet, and the mass flow rate of the heat exchange medium, respectively, under the operating condition of the s-th ambient temperature. , and These represent the enthalpy of the wastewater at the evaporator inlet, the enthalpy of the wastewater at the evaporator outlet, and the mass flow rate of the wastewater, respectively, when the i-th heat exchange medium is selected for heat exchange under the s-th ambient temperature condition. and, , , , This represents the maximum mass flow rate of the wastewater.

5. The optimized design method for a wastewater source heat pump system according to claim 4, characterized in that: The energy balance equation in step 4 also includes: The energy balance equation corresponding to the heat released by the working fluid during the heat exchange process in the condenser: in, and Let represent the enthalpy of the heat exchange medium at the condenser inlet and the enthalpy of the heat exchange medium at the s-th ambient temperature condition, respectively. ; , and These represent the specific enthalpy of the circulating hot water at the condenser outlet, the specific enthalpy of the circulating hot water at the condenser inlet, and the mass flow rate of the circulating hot water, respectively, when the i-th heat exchange medium is selected for heat exchange under the s-th ambient temperature condition.

6. The optimized design method for a wastewater source heat pump system according to claim 1, characterized in that: The constraints on the design variables to be optimized in step 4 are as follows: in, and These are the minimum and maximum evaporation temperatures, respectively. , The temperature of the wastewater heat source, This is the minimum heat transfer temperature of the heat exchanger. and These are the minimum and maximum values ​​of the condensation temperature, respectively. , The return water temperature of the circulating hot water; and These represent the minimum and maximum compression ratios, respectively.