A power grid operation monitoring system based on environmental data analysis

Through the power grid operation monitoring system based on environmental data analysis, the connection performance and real-time risk coefficient of the transformer are calculated, which solves the problem of short circuit or fire caused by the loose connection interface of the transformer after the earthquake, realizes stable monitoring and early warning of rural electricity consumption, and ensures Electricity safety after disasters.

CN118554640BActive Publication Date: 2024-10-08GUANGDONG UNIV OF TECH
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202411010586.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-10-08
Estimated Expiration
2044-07-26

AI Technical Summary

Technical Problem

In the existing power grid operation monitoring system, after a small-scale low-level earthquake, the transformer connection interface may become loose, causing a short circuit or fire, which in turn may cause power paralysis in rural areas.

Method used

Design a power grid operation monitoring system based on environmental data analysis. Through the area division module, data acquisition module, data processing module and early warning module, the connection performance risk coefficient and real-life risk coefficient of the transformer are calculated, the operating status of the transformer is judged, and in case of occurrence Issue early warnings in case of malfunctions or hidden dangers.

Benefits of technology

It effectively avoids short circuits or fires caused by long working hours of the transformer when the connection performance is not ideal, ensures the stability of rural electricity, and provides guarantee for post-disaster reconstruction after earthquakes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118554640B_ABST
    Figure CN118554640B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of power grid equipment monitoring, and specifically discloses a power grid operation monitoring system based on environmental data analysis, wherein the system comprises: an area division module, which is used to divide the monitoring position of a transformer, and each divided monitoring area only comprises one connection interface; a data acquisition module, which comprises an environmental information acquisition unit and an equipment information acquisition unit, and can analyze the connection performance between the transformer equipment and the power-consuming equipment by calculating the connection performance risk coefficient of the transformer equipment, and judge whether the connection performance of the transformer is in an ideal state, so as to avoid the situation that the transformer works for too long under the condition of unsatisfactory connection performance and causes a short circuit or a fire, and by analyzing the actual risk coefficient of the transformer equipment, the stability of the current operation of the transformer can be judged and monitored, and a warning can be issued in time when the stability of the operating state is poor, so as to avoid the situation that the power supply in rural areas is paralyzed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid equipment monitoring, and in particular to a power grid operation monitoring system based on environmental data analysis. Background Art

[0002] The power grid operation monitoring system is a system that integrates multiple technologies and functions. It aims to ensure the safe, stable and efficient operation of the power grid. It collects, processes and analyzes power grid operation data in real time. The system can not only remotely monitor and operate power grid equipment, but also conduct in-depth mining and analysis of power grid operation data, providing a scientific basis for power dispatching, energy management and troubleshooting.

[0003] In order to ensure stable electricity consumption in rural areas, the power grid operation monitoring system usually monitors the operating status of the transformer after an earthquake, and judges the stability of the power equipment based on the operating status of the transformer, ensuring that faults and hidden dangers of power grid equipment can be discovered in time, and the causes of the faults can be analyzed and diagnosed to improve the accuracy and efficiency of fault handling;

[0004] After a small-scale, low-level earthquake in a rural area, the existing power grid operation monitoring system will monitor the operating status of the transformer to determine whether there are any faults or hidden dangers in the power grid equipment. Although a small-scale, low-level earthquake will not cause excessive damage to the transformer and the operating status will not change significantly in a short period of time, it may cause the connection interface between the transformer and the electrical equipment to loosen, causing the transformer to work for too long under unsatisfactory connection performance, resulting in a short circuit or fire, which in turn leads to power outages in rural areas after the earthquake. Summary of the invention

[0005] The purpose of the present invention is to provide a power grid operation monitoring system based on environmental data analysis to solve the following technical problems:

[0006] How to avoid short circuit or fire caused by transformer working for too long with unsatisfactory connection performance.

[0007] The purpose of the present invention can be achieved through the following technical solutions:

[0008] A power grid operation monitoring system based on environmental data analysis, the system comprising:

[0009] The area division module is used to divide the monitoring location of the transformer, and each divided monitoring area contains only one connection interface;

[0010] A data acquisition module, including an environmental information acquisition unit and an equipment information acquisition unit, wherein the environmental information acquisition unit is used to acquire environmental information around the transformer after an earthquake;

[0011] The equipment information acquisition unit is used to acquire the transformer's body information after the earthquake;

[0012] A data processing module, comprising a data calculation unit and a data analysis unit, wherein the data calculation unit is used to respectively calculate a connection performance risk coefficient of the transformer device and an actual risk coefficient of the transformer device according to information collected by the data collection module;

[0013] The data analysis unit is used to analyze the transformer equipment status and the operating status under the current environment according to the connection performance risk coefficient of the transformer equipment and the actual risk coefficient of the transformer equipment, and judge whether the transformer has faults or hidden dangers according to the analysis results;

[0014] The early warning module is used to decide whether to issue an early warning message based on the analysis results of the data analysis unit.

[0015] Furthermore, the information collected by the environmental information collection unit includes haze concentration, floating matter content in the air and rainfall, and the data collected by the device information collection unit includes the temperature of the interface end in each area, the resistance of the interface end, and the current in the interface end circuit.

[0016] Furthermore, the calculation process of the data calculation unit includes:

[0017] By formula Calculate the transformer equipment The connection performance risk factor of each area ;

[0018] in, For any region, To define a function, if ,but ,like ,but , For transformer equipment The temperature of the interface in each area, For transformer equipment The preset temperature of the interface end in each area, for The standard value of For transformer equipment The resistance of the interface end in each area is For transformer equipment The preset resistance size of the interface end in each area, For transformer equipment The current size at the interface end in each area, For transformer equipment The preset current size of the interface end in each area, for The standard value of is the voltage stability influence function. The above voltage stability influence function can be used to influence the voltage stability coefficient of the interface end. The impact of the connection performance risk factor of each area is obtained based on the test results. For transformer equipment The voltage stability coefficient of the interface end in each area can be set based on empirical fitting.

[0019] Furthermore, the process of analysis by the data analysis unit includes:

[0020] By combining the connection performance risk factors of all areas in the transformer equipment The connection performance risk factor is respectively Make a comparison;

[0021] If any Greater than , the system determines that the connection performance risk coefficient of this area is high, indicating that the connection port in this area of ​​the transformer is loose, and determines that the transformer will fail or even short-circuit and catch fire in subsequent use, and then issues a warning message through the warning module;

[0022] If all All less than The system determines that the connection performance risk coefficients of all areas are at a low level, which means that all the connection ports of the transformer are not loose, and determines that the transformer will not fail in subsequent use. No warning is issued, and the actual risk coefficient of the transformer equipment is calculated.

[0023] Furthermore, the calculation process of the actual risk coefficient of the transformer equipment includes:

[0024] By formula Calculate the actual risk factor of the transformer equipment at the ath time point ;

[0025] in, is the total number of divided areas, a is a data collection at a fixed time interval, and , is the haze concentration around the transformer at the ath time point, is the floating matter content in the air around the transformer at the ath time point, is the preset haze concentration around the transformer at the ath time point, is the preset floating matter content in the air around the transformer at the ath time point, is a rainfall influence function, which can be obtained based on a test according to the influence of rainfall on the actual risk coefficient of the transformer equipment at the ath time point. is the rainfall at the ath time point, is a first error influence function, and the first error influence function can be set according to empirical fitting.

[0026] Furthermore, the analysis process of the data analysis unit also includes:

[0027] By calculating the actual risk factor of the transformer equipment at the ath time point Compared with the preset actual risk factor threshold Make a comparison;

[0028] like Greater than ,The system determines that the actual risk factor of the transformer equipment at this time point is high, the operating load of the transformer equipment in the current environment is large, and the possibility of failure is high, and an early warning is issued through the early warning module;

[0029] like Less than The system determines that the actual risk coefficient of the transformer equipment at this point in time is low, the operating load of the transformer equipment in the current environment is small, and there is no possibility of failure. By calculating the fluctuation value of the operating risk coefficient of the transformer equipment, the system estimates the future operating status of the transformer equipment.

[0030] Furthermore, the process of estimating the future operating state of the transformer equipment includes:

[0031] By formula Calculate the fluctuation value of the total risk factor of the connection performance of the transformer equipment over a period of time ;

[0032] in, is the total number of data collections within a period of time, is the total risk factor of the connection performance of the transformer equipment at the ath time point, which can be expressed as Calculate and obtain, For all The average value of For all The maximum value in For all The minimum value in is an adjustment coefficient comparison table function, and the adjustment coefficient comparison table function can be based on right The influence of the value range of is obtained based on the test. is the second error function, which can be set according to empirical fitting.

[0033] Furthermore, the process of estimating the future operating state of the transformer equipment also includes:

[0034] By calculating the fluctuation value of the total risk factor of the connection performance of the transformer equipment over a period of time With the preset fluctuation value Make a comparison;

[0035] like Greater than , indicating that the dispersion coefficient of the total risk coefficient of the connection performance of the transformer equipment within a period of time is large, which will affect the future operation status of the transformer and cause the transformer to fail in the future. The system will issue an early warning through the early warning module;

[0036] like Less than , indicating that the discrete coefficient of the total risk coefficient of the connection performance of the transformer equipment over a period of time is small, which will not affect the future operation status of the transformer, and the system will not issue an early warning through the early warning module.

[0037] Beneficial effects of the present invention:

[0038] (1) The present invention can analyze the connection performance between the transformer equipment and the electrical equipment by calculating the connection performance risk coefficient of the transformer equipment, and judge whether the connection performance of the transformer is in an ideal state. It can not only avoid the situation where the transformer works for too long under the condition of unsatisfactory connection performance and causes a short circuit or fire, but also judge and monitor the stability of the current operation of the transformer by analyzing the actual risk coefficient of the transformer equipment, and give a timely warning when the operating state stability is poor, so as to avoid the paralysis of rural power supply.

[0039] (2) The present invention combines the connection performance risk coefficients of all areas in the transformer equipment The connection performance risk factor is respectively By comparison, the system can monitor the connection performance of the transformer equipment through the connection performance risk coefficient, and make an accurate judgment on whether its connection performance is in an ideal state. When it is judged that the connection performance of the transformer equipment is in a non-ideal state, the system can promptly issue an early warning through the early warning module to remind the operation and maintenance personnel to carry out repairs, so as to avoid short circuits or fires caused by the transformer working for too long under non-ideal connection performance conditions, thereby avoiding the paralysis of power supply in rural areas after the earthquake, ensuring good power supply in rural areas, and facilitating subsequent post-disaster reconstruction.

[0040] (3) After combining the environmental information data around the transformer after the earthquake, the present invention can calculate the actual risk coefficient of the transformer equipment at the ath time point after the earthquake, and make a preliminary judgment on the operating stability of the transformer equipment after the earthquake through the data, so as to realize real-time monitoring of the operating stability of the transformer equipment, thereby avoiding failures or safety hazards of the transformer equipment when working in the extreme environment after the earthquake, resulting in paralysis of rural electricity supply, thereby ensuring good electricity supply in rural areas and facilitating subsequent post-disaster reconstruction.

[0041] (4) The present invention calculates the fluctuation value of the total risk coefficient of the connection performance of the transformer equipment over a period of time. With the preset fluctuation value By making a comparison, we can make a more accurate prediction of whether the future connection performance of the transformer equipment is in an ideal state, and judge the future operating state of the transformer based on the prediction results. If the dispersion coefficient of the total risk coefficient of the connection performance of the transformer equipment over a period of time is large, it may affect the future operating state of the transformer, resulting in timely warning when the transformer fails in the future, thereby ensuring the good operating state and connection performance of the transformer, and avoiding the connection performance of the transformer from changing from an ideal state to a non-ideal state in subsequent work, resulting in short circuit or fire in the transformer equipment during subsequent long-term work, thereby avoiding the paralysis of power supply in rural areas after the earthquake. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] The present invention will be further described below in conjunction with the accompanying drawings.

[0043] Figure 1 It is a schematic block diagram of a power grid operation monitoring system based on environmental data analysis in the present invention; DETAILED DESCRIPTION

[0044] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0045] See also Figure 1 As shown, in one embodiment, the present application provides a power grid operation monitoring system based on environmental data analysis, the system comprising:

[0046] The area division module is used to divide the monitoring location of the transformer, and each divided monitoring area contains only one connection interface;

[0047] A data acquisition module, including an environmental information acquisition unit and an equipment information acquisition unit, wherein the environmental information acquisition unit is used to acquire environmental information around the transformer after an earthquake;

[0048] The equipment information acquisition unit is used to acquire the transformer's body information after the earthquake;

[0049] A data processing module, comprising a data calculation unit and a data analysis unit, wherein the data calculation unit is used to respectively calculate a connection performance risk coefficient of the transformer device and an actual risk coefficient of the transformer device according to information collected by the data collection module;

[0050] The data analysis unit is used to analyze the transformer equipment status and the operating status under the current environment according to the connection performance risk coefficient of the transformer equipment and the actual risk coefficient of the transformer equipment, and judge whether the transformer has faults or hidden dangers according to the analysis results;

[0051] The early warning module is used to decide whether to issue an early warning message based on the analysis results of the data analysis unit;

[0052] Through the above technical solution, this embodiment provides a data acquisition module, through the environmental information acquisition unit and the equipment information acquisition unit in the data acquisition module, the environmental information around the transformer after the earthquake and its body information can be collected, and then the connection performance risk coefficient of the transformer equipment and the actual risk coefficient of the transformer equipment are calculated according to the collected information through the data module, and the connection performance risk coefficient of the transformer equipment and the actual risk coefficient of the transformer equipment are analyzed according to the data analysis unit. The transformer equipment state and the operating state under the current environment are analyzed respectively, so as to judge whether the transformer has a fault or hidden danger;

[0053] Through such settings, the system can analyze the connection performance between the transformer equipment and the electrical equipment by calculating the connection performance risk coefficient of the transformer equipment, and judge whether the connection performance of the transformer is in an ideal state. It can not only avoid short circuits or fires caused by the transformer working for too long under unsatisfactory connection performance, but also judge and monitor the stability of the current operation of the transformer by analyzing the actual risk coefficient of the transformer equipment, and issue timely warnings when the operating status stability is poor, thereby avoiding paralysis of rural power supply.

[0054] The information collected by the environmental information collection unit includes haze concentration, floating matter content in the air and rainfall, and the data collected by the device information collection unit includes the temperature of the interface end in each area, the resistance of the interface end, and the current in the circuit of the interface end;

[0055] Through the above technical solution, this embodiment provides information collected by the environment information collection unit and the equipment information collection unit. The temperature of the interface end in each area of ​​the transformer, the resistance of the interface end, and the current in the circuit of the interface end collected by the equipment information collection unit can provide accurate data for the subsequent calculation of the connection performance risk factor of the transformer equipment, thereby improving the accuracy of the subsequent judgment of whether the connection performance of the transformer is in an ideal state, thereby ensuring that an early warning is given in time when it is found that the connection performance of the transformer is in a non-ideal state, thereby avoiding the transformer from working for too long in a non-ideal connection performance state and causing a short circuit or fire;

[0056] In addition, the haze concentration, floating matter content in the air and rainfall information collected by the environmental information collection unit can provide accurate data for the subsequent calculation of the actual risk coefficient of the transformer equipment. The actual risk coefficient of the transformer equipment can reflect the operating status of the transformer in the extreme environment after the earthquake, thereby making an accurate judgment on whether the current operating status of the transformer equipment is stable, and issuing an early warning in time when it is judged that the current operating status of the transformer equipment is unstable, and reminding the staff to carry out maintenance to avoid the paralysis of power supply in rural areas after the earthquake.

[0057] The calculation process of the data calculation unit includes:

[0058] By formula Calculate the transformer equipment The connection performance risk factor of each area ;

[0059] in, For any region, To define a function, if ,but ,like ,but , For transformer equipment The temperature of the interface in each area, For transformer equipment The preset temperature of the interface end in each area, for The standard value of the above standard value is set according to the allowable error fitting in the empirical data. For transformer equipment The resistance of the interface end in each area is For transformer equipment The preset resistance size of the interface end in each area, For transformer equipment The current size at the interface end in each area, For transformer equipment The preset current size of the interface end in each area, for The standard value of the above standard value is set according to the allowable error fitting in the empirical data. is the voltage stability influence function. The above voltage stability influence function can be used to influence the voltage stability coefficient of the interface end. The impact of the connection performance risk factor of each area is obtained based on the test results. For transformer equipment The voltage stability coefficient of the interface end in each region can be set according to empirical fitting; through the above technical solution, this embodiment provides a transformer device The connection performance risk factor of each area , can be obtained by formula It is obvious that after an earthquake, the transformer equipment The higher the temperature and resistance of the interface end in a region and the lower the current, the greater the risk factor of the connection performance in this region, indicating that the connection performance of the transformer is in a non-ideal state. Vibration may cause the connection interface between the transformer and the electrical equipment to loosen. Conversely, when the transformer equipment is The lower the temperature and resistance of the interface end in each area and the closer the current is to the preset current, the lower the risk factor of the connection performance in this area, indicating that the connection performance of the transformer is in an ideal state at this time, and the earthquake has not caused the connection interface between the transformer and the electrical equipment to become loose;

[0060] By setting up in this way, the transformer equipment After calculating the connection performance risk coefficient of each area, since the connection performance risk coefficient can reflect whether the connection interface between the transformer and the electrical equipment is loose, the connection performance of the transformer equipment can be monitored according to the size of the connection performance risk coefficient, and when it is judged that the connection performance of the transformer equipment is not in an ideal state, an early warning can be issued in time to avoid the transformer from working for too long under an unsatisfactory connection performance state, causing a short circuit or fire, thereby protecting the rural power environment.

[0061] The process of analysis by the data analysis unit includes:

[0062] By combining the connection performance risk factors of all areas in the transformer equipment The connection performance risk factor is respectively Make a comparison;

[0063] If any Greater than , the system determines that the connection performance risk coefficient of this area is high, indicating that the connection port in this area of ​​the transformer is loose, and determines that the transformer will fail or even short-circuit and catch fire in subsequent use, and then issues a warning message through the warning module;

[0064] If all All less than The system determines that the connection performance risk coefficients of all areas are at a low level, which means that all the connection ports of the transformer are not loose, and determines that the transformer will not fail in subsequent use, does not issue an early warning, and calculates the actual risk coefficient of the transformer equipment;

[0065] Through the above technical solution, this implementation calculates the connection performance risk coefficient of all areas in the transformer equipment The connection performance risk factor is respectively Compare, if any Greater than The system determines that the risk factor of the connection performance in this area is high, indicating that the connection port in this area of ​​the transformer is loose, which will cause the connection performance of the transformer to be in a non-ideal state, and determines that the transformer will fail or even short-circuit and catch fire in subsequent use. Then, the early warning module issues an early warning message. If all All less than The system determines that the connection performance risk coefficients of all areas are at a low level, which means that all the connection ports of the transformer are not loose, and the connection performance of the transformer is in an ideal state. It also determines that the transformer will not fail in subsequent use and does not issue a warning;

[0066] Through this judgment method, the system can monitor the connection performance of the transformer equipment through the connection performance risk coefficient, and make an accurate judgment on whether its connection performance is in an ideal state. When it is judged that the connection performance of the transformer equipment is in a non-ideal state, an early warning module is used to promptly issue an early warning to remind the operation and maintenance personnel to carry out repairs, so as to avoid short circuits or fires caused by the transformer working for too long under non-ideal connection performance conditions, thereby avoiding the paralysis of power supply in rural areas after the earthquake, ensuring good power supply in rural areas, and facilitating subsequent post-disaster reconstruction.

[0067] The calculation process of the actual risk factor of the transformer equipment includes:

[0068] By formula Calculate the actual risk factor of the transformer equipment at the ath time point ;

[0069] in, is the total number of divided areas, a is a data collection at a fixed time interval, and , is the haze concentration around the transformer at the ath time point, is the floating matter content in the air around the transformer at the ath time point, is the preset haze concentration around the transformer at the ath time point, is the preset floating matter content in the air around the transformer at the ath time point, is a rainfall influence function, which can be obtained based on a test according to the influence of rainfall on the actual risk coefficient of the transformer equipment at the ath time point. is the rainfall at the ath time point, is a first error influence function, which may be set based on empirical fitting;

[0070] Through the above technical solution, this embodiment provides the actual risk coefficient of the transformer equipment at the ath time point: , can be obtained by formula It is obvious that when the haze concentration around the transformer and the floating matter content in the air at the a-th time point are higher, the impact on the actual risk coefficient of the transformer equipment at the a-th time point is greater, which may affect the stability of the current operation of the transformer equipment. On the contrary, when the haze concentration around the transformer and the floating matter content in the air at the a-th time point are lower, the impact on the actual risk coefficient of the transformer equipment at the a-th time point is smaller, and the possibility of affecting the stability of the current operation of the transformer equipment is lower.

[0071] Through such a setting, after combining the environmental information data around the transformer after the earthquake, the actual risk coefficient of the transformer equipment at the ath time point after the earthquake can be calculated, and the data can be used to make a preliminary judgment on the operating stability of the transformer equipment after the earthquake, thereby realizing real-time monitoring of the operating stability of the transformer equipment, thereby avoiding failures or safety hazards when the transformer equipment is working in the extreme environment after the earthquake, resulting in paralysis of rural electricity supply, thereby ensuring good electricity supply in rural areas and facilitating subsequent post-disaster reconstruction.

[0072] The analysis process of the data analysis unit also includes:

[0073] By calculating the actual risk factor of the transformer equipment at the ath time point Compared with the preset actual risk factor threshold Make a comparison;

[0074] like Greater than ,The system determines that the actual risk factor of the transformer equipment at this time point is high, the operating load of the transformer equipment in the current environment is large, and the possibility of failure is high, and an early warning is issued through the early warning module;

[0075] like Less than , the system determines that the actual risk coefficient of the transformer equipment at this time point is low, the operating load of the transformer equipment in the current environment is small, and there is no possibility of failure. By calculating the fluctuation value of the operating risk coefficient of the transformer equipment, the system estimates the future operating status of the transformer equipment;

[0076] Through the above technical solution, this embodiment calculates the actual risk coefficient of the transformer equipment at the ath time point Compared with the preset actual risk factor threshold For comparison, if Greater than The system determines that the actual risk factor of the transformer equipment at this time point is high, the operating load of the transformer equipment in the current environment is large, and the possibility of failure is high, and an early warning is issued through the early warning module. Otherwise, if Less than , the system determines that the actual risk coefficient of the transformer equipment at this time point is low, the operating load of the transformer equipment in the current environment is small, and there is no possibility of failure. By calculating the fluctuation value of the operating risk coefficient of the transformer equipment, the system estimates the future operating status of the transformer equipment;

[0077] Through this judgment method, an accurate judgment can be made on the operating load of the transformer equipment in the current environment, so as to further judge whether the transformer equipment will have failures or safety hazards. When it is judged that the operating load of the transformer equipment in the current environment is large and the possibility of failure is high, an early warning can be issued in time through the early warning module, so as to avoid the transformer working under heavy operating load for a long time, resulting in subsequent short circuit or fire, and thus avoiding the paralysis of power supply in rural areas after the earthquake.

[0078] The process of estimating the future operating state of the transformer equipment includes:

[0079] By formula Calculate the fluctuation value of the total risk factor of the connection performance of the transformer equipment over a period of time ;

[0080] in, is the total number of data collections within a period of time, is the total risk factor of the connection performance of the transformer equipment at the ath time point, which can be expressed as Calculate and obtain, For all The average value of For all The maximum value in For all The minimum value in is an adjustment coefficient comparison table function, and the adjustment coefficient comparison table function can be based on right The influence of the value range of is obtained based on the test. is the second error function, which can be set according to empirical fitting;

[0081] Through the above technical solution, this implementation provides the fluctuation value of the total risk coefficient of the connection performance of the transformer equipment over a period of time. , can be obtained by formula It is calculated that, through such a setting, after calculating the fluctuation value of the total risk coefficient of the connection performance of the transformer equipment over a period of time, the discrete degree of the connection state of the transformer equipment over a period of time can be understood, and the risk coefficient of the future connection performance of the transformer equipment can be estimated through this data, so as to realize the monitoring of whether the future connection performance of the transformer equipment is in an ideal state, thereby avoiding the connection performance of the transformer from changing from an ideal state to a non-ideal state in subsequent work, causing the transformer equipment to short-circuit or catch fire in the subsequent long-term work, thereby avoiding the paralysis of power supply in rural areas after the earthquake.

[0082] The process of estimating the future operating state of the transformer equipment also includes:

[0083] By calculating the fluctuation value of the total risk factor of the connection performance of the transformer equipment over a period of time With the preset fluctuation value Make a comparison;

[0084] like Greater than , indicating that the dispersion coefficient of the total risk coefficient of the connection performance of the transformer equipment within a period of time is large, which will affect the future operation status of the transformer and cause the transformer to fail in the future. The system will issue an early warning through the early warning module;

[0085] like Less than , indicating that the discrete coefficient of the total risk coefficient of the connection performance of the transformer equipment within a period of time is small, which will not affect the future operation status of the transformer, and the system will not issue an early warning through the early warning module;

[0086] Through the above technical solution, this embodiment calculates the fluctuation value of the total risk coefficient of the connection performance of the transformer equipment over a period of time. With the preset fluctuation value For comparison, if Greater than , indicating that the dispersion coefficient of the total risk coefficient of the connection performance of the transformer equipment over a period of time is large, indicating that over a period of time, the volatility of the risk coefficient of the connection performance of the transformer equipment is large. There may be repeated loosening of the interface of the transformer equipment due to the influence of the external environment, which may affect the future operation of the transformer and cause the transformer to fail in the future. The system will issue an early warning through the early warning module. If Less than , indicating that the discrete coefficient of the total risk coefficient of the connection performance of the transformer equipment within a period of time is small, which will not affect the future operation status of the transformer, and the system will not issue an early warning through the early warning module;

[0087] Through this judgment method, a relatively accurate prediction can be made on whether the future connection performance of the transformer equipment is in an ideal state, and the future operating state of the transformer can be judged based on the prediction results. If the dispersion coefficient of the total risk coefficient of the connection performance of the transformer equipment over a period of time is large, it means that over a period of time, it may affect the future operating state of the transformer, resulting in a timely warning when the transformer fails in the future, thereby ensuring the good operating state and connection performance of the transformer, and avoiding the connection performance of the transformer from changing from an ideal state to a non-ideal state in subsequent work, resulting in short circuit or fire in the transformer equipment during subsequent long-term work, thereby avoiding the paralysis of power supply in rural areas after the earthquake.

[0088] An embodiment of the present invention has been described in detail above, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention.

[0089] All equivalent changes and improvements made within the scope of the present invention should still fall within the patent scope of the present invention.

Claims

1. A power grid operation monitoring system based on environmental data analysis, characterized in that: The system comprises: The area division module is used to divide the monitoring location of the transformer, and each divided monitoring area contains only one connection interface; A data acquisition module, including an environmental information acquisition unit and an equipment information acquisition unit, wherein the environmental information acquisition unit is used to acquire environmental information around the transformer after an earthquake; The equipment information acquisition unit is used to acquire the transformer's body information after the earthquake; A data processing module, comprising a data calculation unit and a data analysis unit, wherein the data calculation unit is used to respectively calculate a connection performance risk coefficient of the transformer device and an actual risk coefficient of the transformer device according to information collected by the data collection module; The data analysis unit is used to analyze the transformer equipment status and the operating status under the current environment according to the connection performance risk coefficient of the transformer equipment and the actual risk coefficient of the transformer equipment, and judge whether the transformer has faults or hidden dangers according to the analysis results; The early warning module is used to decide whether to issue an early warning message based on the analysis results of the data analysis unit; The information collected by the environmental information collection unit includes haze concentration, floating matter content in the air and rainfall, and the data collected by the device information collection unit includes the temperature of the interface end in each area, the resistance of the interface end, and the current in the circuit of the interface end; The calculation process of the data calculation unit includes: By formula Calculate the transformer equipment The connection performance risk factor of each area ; in, For any region, To define a function, if ,but ,like ,but , For transformer equipment The temperature of the interface in each area, For transformer equipment The preset temperature of the interface end in each area, for The standard value of For transformer equipment The resistance of the interface end in each area is For transformer equipment The preset resistance size of the interface end in each area, For transformer equipment The current size at the interface end in each area, For transformer equipment The preset current size of the interface end in each area, for The standard value of is the voltage stability influence function. The above voltage stability influence function can be used to influence the voltage stability coefficient of the interface end. The impact of the connection performance risk factor of each area is obtained based on the test results. For transformer equipment The voltage stability coefficient of the interface end in each area can be set based on empirical fitting.

2. A power grid operation monitoring system based on environmental data analysis according to claim 1, characterized in that: The process of analysis by the data analysis unit includes: By combining the connection performance risk factors of all areas in the transformer equipment The connection performance risk factor is respectively Make a comparison; If any Greater than , the system determines that the connection performance risk coefficient of this area is high, indicating that the connection port in this area of ​​the transformer is loose, and determines that the transformer will fail or even short-circuit and catch fire in subsequent use, and then issues a warning message through the warning module; If all All less than The system determines that the connection performance risk coefficients of all areas are at a low level, which means that all the connection ports of the transformer are not loose, and determines that the transformer will not fail in subsequent use. No warning is issued, and the actual risk coefficient of the transformer equipment is calculated.

3. A power grid operation monitoring system based on environmental data analysis according to claim 2, characterized in that: The calculation process of the actual risk factor of the transformer equipment includes: By formula Calculate the actual risk factor of the transformer equipment at the ath time point ; in, is the total number of divided areas, a is a data collection at a fixed time interval, and , is the haze concentration around the transformer at the ath time point, is the floating matter content in the air around the transformer at the ath time point, is the preset haze concentration around the transformer at the ath time point, is the preset floating matter content in the air around the transformer at the ath time point, is a rainfall influence function, which can be obtained based on a test according to the influence of rainfall on the actual risk coefficient of the transformer equipment at the ath time point. is the rainfall at the ath time point, is a first error influence function, and the first error influence function can be set according to empirical fitting.

4. A power grid operation monitoring system based on environmental data analysis according to claim 3, characterized in that: The analysis process of the data analysis unit also includes: By calculating the actual risk factor of the transformer equipment at the ath time point Compared with the preset actual risk factor threshold Make a comparison; like Greater than ,The system determines that the actual risk factor of the transformer equipment at this time point is high, the operating load of the transformer equipment in the current environment is large, and the possibility of failure is high, and an early warning is issued through the early warning module; like Less than The system determines that the actual risk coefficient of the transformer equipment at this point in time is low, the operating load of the transformer equipment in the current environment is small, and there is no possibility of failure. By calculating the fluctuation value of the operating risk coefficient of the transformer equipment, the system estimates the future operating status of the transformer equipment.

5. A power grid operation monitoring system based on environmental data analysis according to claim 4, characterized in that: The process of estimating the future operating state of the transformer equipment includes: By formula Calculate the fluctuation value of the total risk factor of the connection performance of the transformer equipment over a period of time ; in, is the total number of data collections within a period of time, is the total risk factor of the connection performance of the transformer equipment at the ath time point, which can be expressed as Calculate and obtain, For all The average value of For all The maximum value in For all The minimum value in is an adjustment coefficient comparison table function, and the adjustment coefficient comparison table function can be based on right The influence of the value range of is obtained based on the test. is the second error function, which can be set according to empirical fitting.

6. A power grid operation monitoring system based on environmental data analysis according to claim 5, characterized in that: The process of estimating the future operating state of the transformer equipment also includes: By calculating the fluctuation value of the total risk factor of the connection performance of the transformer equipment over a period of time With the preset fluctuation value Make a comparison; like Greater than , indicating that the dispersion coefficient of the total risk coefficient of the connection performance of the transformer equipment within a period of time is large, which will affect the future operation status of the transformer and cause the transformer to fail in the future. The system will issue an early warning through the early warning module; like Less than , indicating that the discrete coefficient of the total risk coefficient of the connection performance of the transformer equipment over a period of time is small, which will not affect the future operation status of the transformer, and the system will not issue an early warning through the early warning module.

Citation Information

Patent Citations

  • Method for analyzing power stability based on random partial differential equation

    CN115544739A

  • Fire early warning and supervising system for agriculture and forestry areas based on artificial intelligence

    CN116246407A

  • Equipment state evaluation method and system based on digital twinning

    CN118312746A

  • Intelligent water conservancy intelligent monitoring system based on multi-source data fusion

    CN118313672A