Ballastless track slab construction assembly type storage space frame and using method thereof
By using prefabricated storage space frames in high-speed railway construction and efficient storage of ballastless track plates using the clearance area under high-speed railway beams, the problem of inconvenience is solved, construction efficiency and space utilization are improved, and construction cycle and material waste are reduced. .
Patent Information
- Application Number
- CN202411248872.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-15
AI Technical Summary
During the construction of ball-free track slabs on high-speed railways, due to insufficient clearance area under the high-speed rail beam, it leads to inconvenient storage, resulting in insufficient supply and low construction efficiency.
Adopt a prefabricated storage space frame including active leveling ground beam system, stable support limit system and central partition support system. By leveling the load-bearing strip beam, limit main beam and shock-absorbing partition frame, efficient use of high-speed rail beam under high-speed rail beams is achieved through the leveling of components such as load-bearing strip beams, limit main beams and shock-absorbing partition frames. Storage space in the clearance area.
It improves the continuous paving construction efficiency of ballastless track plates, shortens the transportation distance from storage locations to installation locations, reduces material waste and construction cycles, and facilitates the repair and replacement of parts.
Smart Images

Figure CN118952148A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of high-speed railway construction, and in particular to an assembled storage space frame for ballastless track slab construction and a use method thereof. Background Art
[0002] With the vigorous development of China's economy and China's high-speed railway construction, the high-speed railway network is gradually taking shape, which is of great significance for promoting population and economic exchanges between regions. In recent years, most of the concrete components of high-speed railways have been constructed by prefabrication on site and installation on site to improve the overall construction efficiency of high-speed railways.
[0003] At present, the ballastless track slabs of high-speed railways are fully prefabricated. After prefabrication, they are stored at designated locations on site, and the track slabs are laid as the construction process of the ballastless track slabs progresses. Due to the limited area occupied by high-speed railways, there is no large amount of free space for the storage of ballastless track slabs in sections. At present, the ballastless track slabs are often insufficiently supplied due to untimely scheduling during construction, which seriously reduces the efficiency of continuous paving of ballastless track slabs.
[0004] There is no related invention in the prior art that can effectively utilize the clearance under the high-speed railway beam to realize the efficient storage of ballastless track slabs. Therefore, how to realize the large-scale and efficient storage of ballastless track slabs in the limited clearance area under the high-speed railway beam is a technical problem that needs to be solved urgently in the efficient construction process of high-speed railway ballastless track slabs. Summary of the invention
[0005] In view of the problems in the related art, the present invention proposes an assembled storage space frame for ballastless track slab construction and a method of using the same to overcome the above-mentioned technical problems existing in the existing related art.
[0006] To this end, the specific technical solution adopted by the present invention is as follows:
[0007] A prefabricated storage space frame for ballastless track slab construction comprises an active leveling ground beam system, a stable support limit system and a middle partition support system, wherein the stable support limit system and the middle partition support system are arranged on the upper part of the active leveling ground beam system, the stable support limit system is located at the upper two end positions of the active leveling ground beam system, and the middle partition support system is arranged on the upper part of the active leveling ground beam system and installed in the middle position of the stable support limit system.
[0008] Preferably, the active leveling ground beam system includes a leveling bearing beam, an upper top plate and a bearing beam bottom plate, a spirit level is provided at the center of the side of the leveling bearing beam, the upper top plate and the bearing beam bottom plate are respectively arranged at the top and bottom of the leveling bearing beam, a plurality of limit slots are equally spaced at the center of the top of the upper top plate, a plurality of bolt holes are equally spaced on both sides of the top of the upper top plate, and a plurality of fixing nuts corresponding to the bolt holes are welded and fixed to the bottom of the upper top plate.
[0009] Preferably, positioning holes are provided on both side edges of the upper top plate and located outside the bolt holes, and a group of leveling jacks are respectively provided at the ends of both side edges of the leveling bearing beam, the top ends of the leveling jacks are connected to the positioning holes, and a pressure increasing valve and a pressure reducing valve are provided on the leveling jacks.
[0010] Preferably, the stable support limit system includes a limit main beam and a support sub-beam arranged on the top of the upper top plate, a slot is opened on the side of the limit main beam, one end of the support sub-beam is engaged in the slot, and the other end of the support sub-beam is engaged in the limit slot, and fastening bolts are provided at the bottom of both the limit main beam and the support sub-beam, and the fastening bolts pass through the bolt holes and are connected and fixed to the fixing nuts.
[0011] Preferably, both the position-limiting main beam and the supporting sub-beam are made of H-shaped steel material.
[0012] Preferably, the middle partition support system includes a plurality of limiting main beams and a plurality of shock-absorbing spacers, and the limiting main beams are connected and fixed to the fixing nuts at the bottom of the upper top plate through the fastening bolts, and a threaded end is provided at the bottom of the fixing nut, and the threaded end is connected and fixed to the fixing nut passing through the bolt hole and the bottom of the upper top plate.
[0013] Preferably, the shock-absorbing spacer is a four-sided long strip rigid body with a rubber outer layer.
[0014] According to another aspect of the present invention, a method for using an assembled storage space frame for ballastless track slab construction is provided, which is used for the assembled storage space frame for ballastless track slab construction, and comprises the following steps:
[0015] S1. Level the ground in the clear area between the piles under the beams according to the on-site construction requirements, and place the required bearing beams end to end in the center of the site, ensuring that the bearing beam bottom plate at the bottom of the bearing beams is close to the leveled ground;
[0016] S2, aligning the positioning holes on the side of each load-bearing beam with the leveling jacks, and connecting the hydraulic device to the four leveling jacks around each load-bearing beam to perform preliminary leveling of the load-bearing beam. When the level gauge on the side of the load-bearing beam shows that the load-bearing beam is level, remove the hydraulic device to perform subsequent beam leveling work;
[0017] S3, respectively install the limit main beams at the appropriate positions at both ends of the two bearing beams, and after fixing them with fastening bolts, push the two ends of the supporting sub-beam into the limit slots and the slots on the side of the limit main beam, and connect them with fastening bolts and fixing nuts;
[0018] S4, placing the track plates in sequence from the inner side of the fixed limit main beam to the middle position, after placing two track plates, a pair of shock-absorbing spacers are installed on the top surface of each bearing beam aligned with the bolt hole where the fixing nut is located, and after placing six track plates, a limit main beam is installed on the top surface of each bearing beam aligned with the bolt hole where the fixing nut is located;
[0019] S5, repeat step S4, placing the track plates from both ends of the bearing beam to the middle position in sequence until all the track plates are placed;
[0020] S6, after all track slabs are placed and left to stand for 1 to 2 days, the on-site management personnel inspect the level gauge on the side of each load-bearing beam to check the horizontality of the load-bearing beam;
[0021] S7. If the load-bearing beam produces a large uneven settlement or tilt, a hydraulic device is used to connect the pressure-increasing valve of the leveling jack at the position with the larger settlement to push out the stroke of the leveling jack. At the same time, the pressure-reducing valve of the leveling jack at the position with the smaller settlement is opened to retract the stroke of the leveling jack to quickly adjust the horizontality of the load-bearing beam.
[0022] The beneficial effects of the present invention are:
[0023] The ballastless track slab construction assembled storage space frame of the present invention fully utilizes the clearance area under the high-speed railway beam to form a storage space, thereby improving the utilization rate of the space, and can supply the ballastless track slab in time during the ballastless track slab paving construction, thereby improving the continuous paving construction efficiency of the ballastless track slab.
[0024] The ballastless track slab construction assembled storage space frame of the present invention is a fully assembled structure, which can be quickly disassembled, transported and assembled in a short time, thus avoiding the material waste and long construction period of the traditional concrete cushion site.
[0025] The ballastless track slab construction assembled storage space frame of the present invention can shorten the transportation distance from the storage position of the track slab to the installation position on the beam, and improve the laying construction efficiency of the ballastless track slab.
[0026] The parts used in the ballastless track slab construction assembled storage space frame of the present invention are all existing mature engineering components, which can be easily repaired or replaced if damaged, and are easily accepted by on-site construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0028] Figure 1 It is a schematic diagram of the overall structure of an assembled storage space frame for ballastless track slab construction according to an embodiment of the present invention;
[0029] Figure 2 The schematic diagram of the local structure of a ballastless track slab construction assembled storage space frame according to an embodiment of the present invention is Figure 1 ;
[0030] Figure 3 The schematic diagram of the local structure of a ballastless track slab construction assembled storage space frame according to an embodiment of the present invention is Figure 2 ;
[0031] Figure 4 The schematic diagram of the local structure of a ballastless track slab construction assembled storage space frame according to an embodiment of the present invention is Figure 3 ;
[0032] Figure 5 The schematic diagram of the local structure of a ballastless track slab construction assembled storage space frame according to an embodiment of the present invention is Figure 4 ;
[0033] Figure 6 It is a structural schematic diagram of an active leveling ground beam system of an assembled storage space frame for ballastless track slab construction according to an embodiment of the present invention;
[0034] Figure 7 The present invention is a flowchart of the steps of constructing an assembled storage space frame for a ballastless track slab and a method for using the frame.
[0035] In the figure:
[0036] 1-1. Limiting main beam; 1-2. Leveling jack; 1-3. Shock-absorbing spacer; 1-4. Supporting sub-beam; 1-5. Load-bearing beam; 2-1. Fastening bolts; 2-2. Level; 2-3. Positioning holes; 2-4. Limiting slots; 3-1. Fixing nuts; 3-2. Load-bearing beam bottom plate; 6-1. Pressurizing valve; 6-2. Pressure reducing valve. DETAILED DESCRIPTION
[0037] To further illustrate each embodiment, the present invention provides drawings, which are part of the disclosure of the present invention and are mainly used to illustrate the embodiments and can be used in conjunction with the relevant descriptions in the specification to explain the operating principles of the embodiments. With reference to these contents, ordinary technicians in the field should be able to understand other possible implementations and advantages of the present invention. The components in the figures are not drawn to scale, and similar component symbols are generally used to represent similar components.
[0038] According to an embodiment of the present invention, a prefabricated storage space frame for ballastless track slab construction is provided.
[0039] Embodiment 1;
[0040] like Figure 1-6 As shown, the assembled storage space frame for ballastless track slab construction according to an embodiment of the present invention includes an active leveling ground beam system, a stable support limit system and a middle partition support system, wherein the stable support limit system and the middle partition support system are arranged on the upper part of the active leveling ground beam system, the stable support limit system is located at the upper two end positions of the active leveling ground beam system, and the middle partition support system is arranged on the upper part of the active leveling ground beam system and installed in the middle position of the stable support limit system;
[0041] The active leveling ground beam system includes a leveling jack 1-2, a bearing bar beam 1-5, a spirit level 2-2, a positioning hole 2-3, a limit slot 2-4, a fixing nut 3-1 and a bearing bar beam bottom plate 3-2. The bearing bar beam 1-5 can be provided with multiple pieces in the whole device, and the head and tail assembly realizes the overall extension. The spirit level 2-2 is located at the center position of one side of each bearing bar beam bottom plate 3-2. Four leveling jacks 1-2 are arranged on each bearing bar beam. The top end of the leveling jack 1-2 is installed in the positioning hole 2-3. The leveling jack 1-2 is provided with a pressure valve 6-1 and a pressure reducing valve 6-2. The fixing nuts 3-1 are evenly distributed and welded to the bottom surface of the upper top plate of the bearing bar beam 1-5.
[0042] The stable support limiting system includes a limiting main beam 1-1, a supporting sub-beam 1-4 and a fastening bolt 2-1. The limiting main beam 1-1 and the supporting sub-beam 1-4 are both made of H-shaped steel materials. The limiting main beam 1-1 and the supporting sub-beam 1-4 are assembled with the bearing beam 1-5 by inserting the fastening bolt 2-1 into the fixing nut 3-1. One end of the supporting sub-beam 1-4 engages with the limiting slot 2-4 on the bearing beam 1-5, and the other end engages with the slot on the limiting main beam 1-1.
[0043] The intermediate partition support system includes a limiting main beam 1-1 and a shock-absorbing spacer 1-3. The intermediate partition support system includes multiple limiting main beams 1-1 and multiple shock-absorbing spacers 1-3, which can be increased or decreased according to the number of track plates. The limiting main beam 1-1 is fixed by inserting the fastening bolts 2-1 into the fixing nuts 3-1. The shock-absorbing spacers 1-3 are four-sided long strip rigid bodies with a rubber outer layer, one end of which has a thread that can be directly screwed into the fixing nut 3-1. It is most appropriate to control the quantity ratio of the shock-absorbing spacers 1-3 to the limiting main beam 1-1 to be about 3:1.
[0044] Embodiment 2:
[0045] like Figure 1-7 As shown, according to an embodiment of the present invention, a method for using a prefabricated storage space frame for ballastless track slab construction is also provided, which is used for the prefabricated storage space frame for ballastless track slab construction, and includes the following steps:
[0046] S1, level the ground in the clear area between the piles under the beams according to the on-site construction requirements, and place the required bearing beams 1-5 end to end in the center of the site, ensuring that the bearing beam bottom plate 3-2 at the bottom of the bearing beams 1-5 is in close contact with the leveled ground;
[0047] S2, aligning the positioning hole 2-3 with the side position of each bearing beam 1-5, installing the leveling jack 1-2, and connecting the hydraulic device to the four leveling jacks 1-2 around each bearing beam 1-5 to perform preliminary leveling of the bearing beam 1-5. When the level meter 2-2 on the side of the bearing beam 1-5 shows that the bearing beam 1-5 is level, remove the hydraulic device to perform subsequent beam leveling work;
[0048] S3, install the limiting main beam 1-1 at the appropriate positions at both ends of the two bearing beams 1-5, and after fixing them with the fastening bolts 2-1, push the two ends of the supporting sub-beam 1-4 into the limiting card slot 2-4 and the card slot on the side of the limiting main beam 1-1, and connect them with the fastening bolts 2-1 and the fixing nuts 3-1;
[0049] S4, placing the track plates in sequence from the inner side of the fixed limit main beam 1-1 to the middle position, after placing two track plates, a pair of shock-absorbing spacers 1-3 are installed on the top surface of each bearing beam 1-5 aligned with the bolt hole where the fixing nut 3-1 is located, and after placing six track plates, a limit main beam 1-1 is installed on the top surface of each bearing beam 1-5 aligned with the bolt hole where the fixing nut 3-1 is located;
[0050] S5, repeat step S4, placing the track plates from both ends of the bearing beams 1-5 to the middle position in sequence until all the track plates are placed;
[0051] S6, after all track plates are placed and left to stand for 1 to 2 days, the on-site management personnel inspect the level gauge 2-2 on the side of each load-bearing beam 1-5 to check the levelness of the load-bearing beam 1-5;
[0052] S7, if the bearing bar beam 1-5 produces a large uneven settlement or tilt, a hydraulic device is used to connect the pressure-increasing valve 6-1 of the leveling jack 1-2 at the position with a larger settlement, and the stroke of the leveling jack 1-2 is pushed out. At the same time, the pressure-reducing valve 6-2 of the leveling jack 1-2 at the position with a smaller settlement is opened to retract the stroke of the leveling jack 1-2, so as to quickly adjust the horizontality of the bearing bar beam 1-5.
[0053] In summary, the assembled storage space frame for ballastless track slab construction of the present invention makes full use of the clearance area under the high-speed railway beam to form a storage space, thereby improving the utilization rate of the space, and can supply ballastless track slabs in time during the ballastless track slab paving construction, thereby improving the continuous paving construction efficiency of the ballastless track slab.
[0054] The ballastless track slab construction assembled storage space frame of the present invention is a fully assembled structure, which can be quickly disassembled, transported and assembled in a short time, thus avoiding the material waste and long construction period of the traditional concrete cushion site.
[0055] The ballastless track slab construction assembled storage space frame of the present invention can shorten the transportation distance from the storage position of the track slab to the installation position on the beam, and improve the laying construction efficiency of the ballastless track slab.
[0056] The parts used in the ballastless track slab construction assembled storage space frame of the present invention are all existing mature engineering components, which can be easily repaired or replaced if damaged, and are easily accepted by on-site construction personnel.
[0057] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A ballastless track slab construction assembled storage space frame, It is characterized in that It includes an active leveling ground beam system, a stable support limit system and a middle partition support system. The stable support limit system and the middle partition support system are arranged on the upper part of the active leveling ground beam system. The stable support limit system is located at the upper two end positions of the active leveling ground beam system. The middle partition support system is arranged on the upper part of the active leveling ground beam system and installed in the middle position of the stable support limit system.
2. The assembled storage space frame for ballastless track slab construction according to claim 1, It is characterized in that The active leveling ground beam system comprises a leveling bearing bar beam (1-5), an upper top plate and a bearing bar beam bottom plate (3-2); a level gauge (2-2) is provided at the center of the side of the leveling bearing bar beam (1-5); the upper top plate and the bearing bar beam bottom plate (3-2) are respectively arranged at the top and bottom of the leveling bearing bar beam (1-5); a plurality of limit slots (2-4) are evenly spaced at the center of the top of the upper top plate; a plurality of bolt holes are evenly spaced on both sides of the top of the upper top plate; and a plurality of fixing nuts (3-1) corresponding to the bolt holes are welded and fixed to the bottom of the upper top plate.
3. The assembled storage space frame for ballastless track slab construction according to claim 2, It is characterized in that Positioning holes (2-3) are provided on both side edges of the upper top plate and outside the bolt holes, and a group of leveling jacks (1-2) are provided at the ends of both side edges of the leveling bearing beam (1-5), the top ends of the leveling jacks (1-2) are connected to the positioning holes (2-3), and the leveling jacks (1-2) are provided with a pressure valve (6-1) and a pressure reducing valve (6-2).
4. The assembled storage space frame for ballastless track slab construction according to claim 1, It is characterized in that The stable support and limiting system comprises a limiting main beam (1-1) and a supporting sub-beam (1-4) arranged on the top of the upper top plate; a slot is provided on the side of the limiting main beam (1-1); one end of the supporting sub-beam (1-4) is engaged in the slot; the other end of the supporting sub-beam (1-4) is engaged in the limiting slot (2-4); the bottoms of both the limiting main beam (1-1) and the supporting sub-beam (1-4) are provided with fastening bolts (2-1); the fastening bolts (2-1) pass through the bolt holes and are connected and fixed to the fixing nuts (3-1).
5. The assembled storage space frame for ballastless track slab construction according to claim 4, It is characterized in that Both the position-limiting main beam (1-1) and the supporting secondary beam (1-4) are made of H-shaped steel material.
6. The assembled storage space frame for ballastless track slab construction according to claim 1, It is characterized in that The intermediate partition support system comprises a plurality of limiting main beams (1-1) and a plurality of shock-absorbing spacers (1-3); the limiting main beams (1-1) are connected and fixed to the fixing nuts (3-1) at the bottom of the upper top plate via the fastening bolts (2-1); a threaded end is provided at the bottom of the fixing nut (3-1); the threaded end is connected and fixed to the fixing nut (3-1) passing through the bolt hole and at the bottom of the upper top plate.
7. The assembled storage space frame for ballastless track slab construction according to claim 6, It is characterized in that The shock-absorbing spacer (1-3) is a four-sided long strip-shaped rigid body with a rubber outer layer.
8. A method for using an assembled storage space frame for ballastless track slab construction, It is characterized in that The assembled storage space frame for ballastless track slab construction as claimed in claim 7 comprises the following steps: S1, leveling the ground in the clear area between the piles under the beams according to the on-site construction requirements, placing the required bearing beams (1-5) end to end in the center of the site, and ensuring that the bearing beam bottom plate (3-2) at the bottom of the bearing beams (1-5) is in close contact with the leveled ground; S2, installing a leveling jack (1-2) on the side of each load-bearing beam (1-5) so as to align with the positioning hole (2-3), and connecting a hydraulic device to four leveling jacks (1-2) around each load-bearing beam (1-5) to perform preliminary leveling on the load-bearing beam (1-5); when the level gauge (2-2) on the side of the load-bearing beam (1-5) shows that the load-bearing beam (1-5) is level, removing the hydraulic device to perform subsequent beam body leveling work; S3, respectively installing the limiting main beam (1-1) at appropriate positions at both ends of the two bearing beams (1-5), and after fixing them with fastening bolts (2-1), respectively pushing the two ends of the supporting sub-beam (1-4) into the limiting clamping groove (2-4) and the clamping groove on the side of the limiting main beam (1-1), and connecting them with the fastening bolts (2-1) and the fixing nuts (3-1); S4, placing track plates in sequence from the inner side of the fixed limit main beam (1-1) to the middle position, after placing two track plates, installing a pair of shock-absorbing spacers (1-3) on the top surface of each bearing bar beam (1-5) aligned with the bolt hole where the fixing nut (3-1) is located, and after placing six track plates, installing a limit main beam (1-1) on the top surface of each bearing bar beam (1-5) aligned with the bolt hole where the fixing nut (3-1) is located; S5, repeating step S4, placing the track plates from both ends of the bearing beams (1-5) to the middle position in sequence until all the track plates are placed; S6, after all the track plates are placed and left to stand for 1 to 2 days, the on-site management personnel inspect the level gauge (2-2) on the side of each load-bearing beam (1-5) to check the levelness of the load-bearing beam (1-5); S7, if the bearing bar beam (1-5) has a large uneven settlement or tilt, a hydraulic device is used to connect the pressure valve (6-1) of the leveling jack (1-2) at the position with a larger settlement, and the stroke of the leveling jack (1-2) is pushed out. At the same time, the pressure reducing valve (6-2) of the leveling jack (1-2) at the position with a smaller settlement is opened to retract the stroke of the leveling jack (1-2), so as to quickly adjust the horizontality of the bearing bar beam (1-5).
Citation Information
Patent Citations
Cross beam soil anchor type traction assembly type open caisson device and method
CN115162391A
CRTS III type ballastless track plate storage and intelligent maintenance system
CN212421704U
Track plate storing and positioning device
CN219190184U
Ballast-free railway track for cargo and passenger high-speed traffic and method for construction thereof
RU2755804C1