System and method for jointly monitoring water flowing fractured zone based on up-down micro-seismic

Through the joint microseismic monitoring system on the well and under the well, combined with the ARAMIS M/E and ARP2000 P/E system, the problem of insufficient positioning accuracy in the vertical direction of the microseismic monitoring technology is solved, high-precision monitoring of the water conduction crack zone is achieved, and water damage is improved by improving coal mines Effects of prevention and control.

CN118962810APending Publication Date: 2024-11-15SHAN XI HUA JIN JI NING MEI YE YOU XIAN ZE REN GONG SI +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411324779.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-23
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing microseismic monitoring technology has poor positioning accuracy in the vertical direction, and it is impossible to effectively analyze and determine the development height of the water-conducting crack zone under the influence of mining, making it difficult to monitor the high-position water-conducting crack zone.

Method used

Adopt the combined microseismic monitoring system on the well, combined with the ARAMIS M/E underground microseismic monitoring system and the ARP2000 P/E ground microseismic monitoring system, data synchronization is achieved through satellite GPS clock, optimize the three-dimensional structure of the microseismic network, and improve the positioning accuracy in the vertical direction. Achieve three-dimensional monitoring.

Benefits of technology

The positioning accuracy of the development height of the water-conducting fracture zone is significantly improved, real-time monitoring of the water-conducting fracture zone under complex hydrogeological conditions is achieved, and the basis for water damage prevention and control of coal mines is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118962810A_ABST
    Figure CN118962810A_ABST
Patent Text Reader

Abstract

The invention belongs to the field of coal mine safety, and particularly relates to a system and a method for jointly monitoring a water flowing fractured zone based on underground micro-seismic. Comprising the steps that an underground micro-seismic monitoring system and a ground micro-seismic monitoring system are adopted to form an underground micro-seismic combined monitoring platform network, the enveloping effect of the micro-seismic platform network on a to-be-monitored area in the vertical direction is improved, the three-dimensional structure of the platform network is optimized, and the whole underground part including the monitored area is in a three-dimensional monitoring state; and under computer dual-system software, underground and underground data conjoint analysis is carried out, and real-time monitoring on the development condition of the flowing water fractured zone under the mining influence is realized. The method solves the problems that the existing monitoring technology is not ideal in positioning precision in the vertical direction and cannot effectively analyze and determine the development height of the water-flowing fractured zone under the influence of mining, and improves the positioning precision of the development vertical height of the water-flowing fractured zone under the influence of mining. High-precision positioning and effective monitoring of the development degree of the working face roof water flowing fractured zone are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of coal mine safety, and in particular to monitoring the development degree of water-conducting fracture zones during mine mining under complex hydrogeological conditions, and specifically to a system and method for jointly monitoring water-conducting fracture zones based on "microseisms" above and below the mine. Background Art

[0002] Water inrush from the coal seam roof is one of the important factors threatening the safety of coal mines, which seriously affects and restricts the construction and safe production of mines. With the increase in the depth of coal mining, the mining of multiple coal seams, the mining of thick and extra-thick coal seams, the differences in the engineering geological characteristics of the overburden rock, and the complex hydrogeological conditions, after the underground coal seams are mined, the original stress state of the overburden rock strata is destroyed, and the stress of the lead rock mass is redistributed. When the secondary stress exceeds the strength limit of the rock mass, it will inevitably cause the destruction and deformation of the overburden rock strata, forming a fracture zone, which is very easy to conduct the overburden aquifer to form a water channel, resulting in roof water inrush accidents.

[0003] The formation and occurrence of mine water hazards have a process of change from gestation, development to occurrence. In this process of change, three conditions must be met (water source, water volume, and water channel). Among these three conditions, the aquifer, which plays a decisive role in the water source and water volume, has the characteristics of regional and planar distribution of its recharge and discharge conditions, which are often easy to identify and predict. However, the water-conducting fracture zone has extremely strong locality, concealment and unpredictability. The fracture zone formed by mining has its corresponding precursors. The destruction and deformation of the overlying rock strata are the microseismic activities of the coal and rock bodies within the mining area. Microseismic monitoring technology is a method to study the location and scale of coal and rock strata fractures through the analysis of vibration waves. It can record the fracture of the rock strata in four-dimensional time and space, and analyze the movement law of the overlying rock and the characteristics of the overlying rock structure damage caused by mining according to the waveform, frequency, spatial position, energy, etc. of the microseismic event.

[0004] In recent years, with the rapid development and application of microseismic monitoring technology, the problem of unsatisfactory vertical positioning accuracy is relatively common, and it is impossible to effectively analyze and determine the development height of the water-conducting fracture zone under the influence of mining. Since the sensors are arranged in the underground production space, in the case of a single, nearly horizontal coal seam, the vertical drop between the sensors is small due to the layout of the production space, resulting in a large error in the vertical positioning accuracy of microseismic events, making it difficult to monitor the high-level water-conducting fracture zone. Summary of the invention

[0005] The present invention overcomes the deficiencies of the prior art and, in view of the above-mentioned problems, provides a system and method for jointly monitoring water-conducting fracture zones based on "microseisms" above and below the well. The method of the present invention utilizes the ARAMIS M / E underground microseismic monitoring system and the ARP2000P / E ground microseismic monitoring system to form a joint microseismic monitoring network above and below the well, thereby improving the envelope effect of the microseismic network on the area to be measured in the vertical direction, optimizing the three-dimensional structure of the network, making the entire underground including the monitoring area in a three-dimensional monitoring state, realizing real-time monitoring of the development of the water-conducting fracture zone under the influence of mining, and providing a basis for the prevention and control of water hazards in coal mines.

[0006] The present invention mainly covers two types of microseismic monitoring systems. The first is the ARAMIS M / E underground microseismic monitoring system, which uses the time difference in the process of receiving the vibration wave formed by the rock rupture by the seismic pickup to locate the source position under a specific wave velocity field, perform real-time monitoring of microseismic events in the regional range, and determine the source position of the microseismic event; the second is the ARP2000 P / E ground microseismic monitoring system, which uses an acceleration detector or an electronic seismic detector to record and analyze the speed and acceleration of low-frequency vibrations of rock rupture. Transmitted through a wireless global mobile communication network, the GPS clock on the artificial satellite enables the data substation to ensure very accurate time synchronization. The system monitoring host can be installed with special software as needed, and can realize multi-faceted automatic evaluation of microseismic information through filtering, converting acceleration into velocity and other methods; the two microseismic monitoring systems are combined into a joint microseismic monitoring system above and below the well, which can realize data synchronization through the satellite GPS clock, and conduct joint monitoring and collaborative analysis of above and below the well data based on the dual-system software, thereby optimizing the three-dimensional structure of the roof water-conducting fracture zone monitoring network, greatly improving the positioning accuracy of the vertical height of the water-conducting fracture zone development under the influence of mining, and realizing high-precision positioning and effective monitoring of the development degree of the water-conducting fracture zone on the roof of the working face.

[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is: a system based on the joint monitoring of water-conducting fracture zones by "microseism" above and below the well, wherein the joint monitoring system of "microseism" above and below the well is jointly composed of the ARAMIS M / E downhole microseismic monitoring system and the ARP2000 P / E ground microseismic monitoring system; the ARAMIS M / E downhole microseismic monitoring system includes the SP / DTSS ground central station of the downhole microseismic monitoring system, the downhole substation, the ARAMIS_REJ data recording server and the computer; the downhole substation maintains communication connection with the SP / DTSS ground central station, the SP / DTSS ground central station maintains communication with the ARAMIS_REJ data recording server, and the ARAMIS_REJ data recording server also maintains communication with the computer; the ARP2000P / E ground microseismic monitoring system includes the ground substation of the ground microseismic monitoring system, the wireless transmission system, and the computer equipped with a GSM modem; the ground substation of the ground microseismic monitoring system maintains communication with the computer equipped with a GSM modem through the wireless transmission system.

[0008] As a further limitation of the technical solution of the present invention, the SP / DTSS ground center station is composed of an OCGA digital signal receiving device, an ST / DTSS transmission system control module equipped with a GPS clock, a main channel switching module and an SR 15-150-4 / 11I type distribution device, and is used to monitor microseismic events with a shock energy greater than 100J, a shock frequency of 0~150Hz and a dynamic range less than 100dB.

[0009] As a further limitation of the technical solution of the present invention, the underground substation includes a seismic pickup and a probe sensor, wherein the seismic pickup is an SPI-70 seismic pickup, and the probe sensor is an NSGA vibration signal transmitter. The advantages of the seismic pickup are high monitoring sensitivity and long monitoring distance, but the disadvantage is that a cement foundation needs to be laid, which makes it inconvenient to move; the advantage of the probe sensor is that it is directly installed on the anchor rod, which is convenient to move and install, but the disadvantage is low sensitivity and short monitoring distance. The optimal solution is to use a seismic pickup and a probe for combined monitoring, using a seismic pickup for monitoring in fixed areas, and using a probe sensor for areas such as mining working faces where the detectors need to be moved frequently, which can achieve better results. It is locally connected to the ground through a communication cable. Vibration events are obtained and processed into digital signals.

[0010] As a further limitation of the technical solution of the present invention, the ARAMIS_REJ data recording server is a system data recording server installed with ARAMIS_REJ software (DTSS transmission system monitoring software); it is used for data filtering and recording continuous real-time vibration monitoring.

[0011] As a further limitation of the technical solution of the present invention, the computer is a data processing part composed of ARAMISWIN software (microseismic event positioning, vibration energy calculation) and MAPCREATOR software (positioning result display) installed on the computer; three positioning methods and two energy calculation methods are used to process and analyze the microseismic event data, realize the positioning and energy calculation of the microseismic event, analyze the development height of the water-conducting fracture zone, and display the positioning results on the planar schematic diagram of the mining area. As a further limitation of the technical solution of the present invention, the ground substation of the ground microseismic monitoring system includes a seismic pickup and a monitoring concentrator; the seismic pickup is an SPI-70 seismic pickup, and the monitoring concentrator is an LKP-ARP monitoring concentrator equipped with GPS; the ground substation converts the vibration event into a digital signal, monitors and records the signal through the monitoring concentrator, and enables the data substation to ensure very precise time synchronization through the GPS clock on the artificial satellite.

[0012] As a further limitation of the technical solution of the present invention, the wireless transmission system transmits the monitoring data to the microseismic extension computer in real time through 4G wireless signals, reducing the workload of laying communication cables, etc.; the computer equipped with a GSM modem is a modem that realizes two-way digital wireless communication through a detection data concentrator, and is software for data archiving, visualization and preprocessing, and the software is installed in the host computer.

[0013] A method for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well, using the above-mentioned system, including forming a microseismic monitoring network above and below the well and performing joint microseismic monitoring positioning calculation above and below the well; The above-and-below microseismic monitoring network is a network where the monitoring data of the ARAMIS M / E underground microseismic monitoring system and the ARP2000 P / E ground microseismic monitoring system are synchronized through the satellite GPS clock, and the above-and-below data are jointly monitored on a computer with dual-system software installed to build an above-and-below joint monitoring microseismic network; The steps of the above-and-below well microseismic joint monitoring and positioning calculation are as follows: A. Divide the underground space to be monitored into layers according to the logging data, establish an initial horizontal layered velocity model, and modify the initial horizontal layered velocity model according to the travel time difference of the measuring medium in the perforation and the position of the perforation to obtain an optimized velocity model; B. Through the microseismic monitoring network above and below the well, data analysis is carried out on microseismic events affected by mining, and the travel time and travel time difference of the seismic phase of the microseismic event are obtained; C. Calculating the location and energy of the microseismic event based on the velocity model, the travel time and travel time difference of the seismic phase and the first arrival time of the P wave to obtain the three-dimensional coordinates and energy of the microseismic event; D. Determine the layer and height range of microseismic events caused by rock strata fragmentation under the influence of mining. Based on the layer where high-energy microseismic events occur, further analyze and reveal the development height of water-conducting fracture zones, and realize real-time monitoring of the development of water-conducting fracture zones in mining-affected overburden rocks.

[0014] The present invention also provides the application of the above-mentioned method of jointly monitoring water-conducting fracture zones based on "microseisms" above and below the well in monitoring the development degree of water-conducting fracture zones under the influence of mine tunnel excavation and mine resource mining.

[0015] Compared with the prior art, the present invention has the following beneficial effects: The present invention relates to a technical method for jointly monitoring water-conducting fracture zones based on "microseisms" above and below the well. The technical method for jointly monitoring "microseisms" above and below the well is used to effectively improve the vertical positioning accuracy of microseisms, optimize the three-dimensional structure of the microseismic network, and put the monitoring area in a three-dimensional monitoring state, thereby realizing real-time monitoring of the development of water-conducting fracture zones affected by mining under complex hydrogeological conditions.

[0016] The present invention solves the problem in the prior art of microseismic monitoring technology that the vertical positioning accuracy error of microseismic events is relatively large because the sensors are all arranged in the underground production space and the vertical drop between the sensors is relatively small.

[0017] The present invention can be applied to monitor the development of water-conducting fracture zones in roofs of deep resource exploitation under complex hydrogeological conditions, thereby improving the safety and efficiency of resource exploitation. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a diagram of the underground microseismic monitoring system.

[0019] Figure 2 This is a diagram of the ground microseismic monitoring system.

[0020] Figure 3 This is the layout diagram of the combined microseismic monitoring equipment above and below the well.

[0021] Figure 4 This is a schematic diagram of the layout of the combined microseismic monitoring network above and below the well.

[0022] Figure 5 This is a schematic diagram of the positioning calculation of microseismic joint monitoring above and below the well.

[0023] Figure 6 This is the flow chart of the joint microseismic monitoring above and below the well.

[0024] The following are marked in the figure: 1-seismic pickup, 2-probe sensor, 3-SP / DTSS ground center station, 4-ARAMIS_REJ data recording server, 5-data processing computer, 6-ARP concentrator, 7-modulator, 8-ground substation, 9-industrial square, 10-monitoring host, 11-seismic source. DETAILED DESCRIPTION

[0025] The present invention is further described below in conjunction with specific embodiments. Example

[0026] The present invention proposes a technical method for jointly monitoring water-conducting fracture zones based on "microseisms" above and below the well, which is applied in the field of coal mine safety monitoring such as water hazard prevention and control under mine resource exploitation. It is a technical method for jointly monitoring the development of water-conducting fracture zones by integrating geology, well logging, ground microseismicity and underground microseismicity.

[0027] Specifically, Figure 1 As shown in the figure, the underground microseismic monitoring system diagram is ARAMIS M / E underground microseismic monitoring capable of dynamic load source identification, including ground and underground parts. The system integrates a digital communication system (DTSS) to realize the positioning and energy calculation of microseismic events under the influence of mining in the mine. The seismic pickup obtains microseismic events and processes them into digital signals, which are then transmitted to the ground by the digital communication system. It can monitor microseismic events with a shock energy greater than 100J, a shock frequency of 0~150Hz and a dynamic range less than 100dB. Among them, 1 is a seismic pickup, 2 is a probe sensor, 3 is a SP / DTSS ground center station, 4 is an ARAMIS_REJ data recording server, and 5 is a data processing computer.

[0028] Specifically, Figure 2 As shown in the figure, the ground microseismic monitoring system is the ARP2000 P / E ground microseismic monitoring system, which is a digital remote control system that can record and analyze the velocity and acceleration of low-frequency vibrations of the earth's crust; the GPS clock on the artificial satellite, which is transmitted through the wireless global mobile communication network, enables the data substation to ensure very accurate time synchronization, reducing the workload of laying communication cables, etc. Based on the computer equipped with a modulator to filter the signal and convert the acceleration into velocity, the automatic evaluation of microseismic events is realized. Among them, 1 is a seismic pickup, 5 is a data processing computer, 6 is an ARP concentrator, and 7 is a modulator.

[0029] Specifically, Figure 3As shown, the layout diagram of the microseismic joint monitoring equipment includes the ARAMIS M / E underground microseismic monitoring system and the ARP2000 P / E ground microseismic monitoring system. First, the ARAMIS M / E underground microseismic monitoring system consists of ARAMIS underground equipment and ARAMIS ground equipment. The ARAMIS underground equipment consists of a seismic pickup and a probe sensor, and the ARAMIS ground equipment consists of an SP / DTSS ground central station, an ARAMIS_REJ data recording server, and a data processing computer; second, the ARP2000 P / E ground microseismic monitoring system consists of a ground substation, a modulation regulator, and a data processing computer, and the ground substation consists of a seismic pickup and an ARP concentrator; the layout of the microseismic joint monitoring equipment can effectively improve the positioning accuracy of the vertical height of the microseismic event source, and realize the high-precision positioning and effective monitoring of the water-conducting fracture zone formed by the roof activity and fracture of the working face under the influence of mining in the mine. Among them, 1 is the vibration pickup, 2 is the probe sensor, 3 is the SP / DTSS ground center station, 4 is the ARAMIS_REJ data recording server, 5 is the data processing computer, 6 is the ARP concentrator, and 7 is the modem.

[0030] Specifically, Figure 4 As shown in the figure, the above-and-below microseismic joint monitoring network layout diagram is based on the actual situation of the mine. On the basis of the underground microseismic monitoring system, ground monitoring stations are added to form the above-and-below microseismic joint monitoring network. The seismic pickup and probe sensor are laid out in the excavated tunnel, and transmitted to the monitoring host of the ground industrial square through cables; at the same time, the ground substation is laid out on the ground corresponding to the mine, and the monitoring host of the ground industrial square is transmitted through the wireless transmission system; the synchronization of underground microseismic monitoring and ground microseismic monitoring data is realized under the underground satellite GPS clock, and finally the above-and-below data are jointly analyzed based on the computer dual system software, so as to improve the envelope effect of the microseismic network on the measured area in the vertical direction, optimize the three-dimensional structure of the network, so that the entire underground including the monitoring area is in a three-dimensional monitoring state, and the problem of large positioning accuracy error in the vertical direction is solved. Among them, 1 is a seismic pickup, 2 is a probe sensor, 8 is a ground substation, 9 is an industrial square, 10 is a monitoring host, and 11 is a seismic source. The ground substation 8 is composed of 1 seismic pickup and 6 ARP concentrators, and the monitoring host 10 is composed of 3 SP / DTSS ground central stations, 4 ARAMIS_REJ data recording servers, 5 data processing computers, and 7 modems.

[0031] Specifically, Figure 5As shown in the figure, the schematic diagram of the above-and-below microseismic joint monitoring and positioning calculation is that the ARAMIS M / E downhole microseismic monitoring system and the ARP2000 P / E ground microseismic monitoring system obtain the vibration signal of the microseismic event of the same rock formation fracture to form a water-conducting fracture zone, and obtain the above-and-below microseismic waveforms; the above-and-below microseismic waveforms are processed by seismic phase to obtain the travel time and travel time difference of the microseismic event phase, and the location and energy of the microseismic event are calculated according to the first arrival time of the P wave, and the three-dimensional coordinates and energy of the microseismic event are obtained. Among them, 1 is a seismic pickup, 2 is a probe sensor, 8 is a ground substation, and 11 is a seismic source. 8 ground substations are composed of 1 seismic pickup and 6 ARP concentrators.

[0032] Specifically, Figure 6 As shown in the figure, the microseismic joint monitoring flow chart is based on the ARAMISM / E system for the joint monitoring system above and below the well. The ARP system monitoring station monitors the seismic wave data → wirelessly transmits it to the ARP software → the ARP software pre-processes and saves the data; the ARAMISM / E system retrieves the ARP software seismic wave data to participate in the microseismic event positioning calculation. It can realize the analysis of the height of the water-conducting fracture zone in the mining overburden, and provide a basis for the prevention and control of coal mine water hazards.

[0033] The above is a specific embodiment of the present invention, and the purpose, technical scheme and beneficial effects of the present invention are further described in detail. Those skilled in the art can understand that the above is only a specific embodiment of the present invention and is not intended to limit the scope of protection of the present invention. Any equivalent or modification or improvement that is completed without departing from the spirit disclosed in the present invention should be included in the scope of protection of the present invention.

Claims

1. A system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well, characterized in that: The above-and-below "microseismic" joint monitoring system is jointly composed of the ARAMIS M / E downhole microseismic monitoring system and the ARP2000 P / E ground microseismic monitoring system; the ARAMIS M / E downhole microseismic monitoring system includes the SP / DTSS ground central station, downhole substation, ARAMIS_REJ data recording server and computer of the downhole microseismic monitoring system; the downhole substation maintains communication connection with the SP / DTSS ground central station, the SP / DTSS ground central station maintains communication with the ARAMIS_REJ data recording server, and the ARAMIS_REJ data recording server also maintains communication with the computer; the ARP2000 P / E ground microseismic monitoring system includes the ground substation of the ground microseismic monitoring system, a wireless transmission system, and a computer equipped with a GSM modem; the ground substation of the ground microseismic monitoring system maintains communication with the computer equipped with a GSM modem through the wireless transmission system.

2. A system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well according to claim 1, characterized in that: The SP / DTSS ground center station consists of an OCGA digital signal receiving device, an ST / DTSS transmission system control module equipped with a GPS clock, a main channel switching module and an SR 15-150-4 / 11 I type distribution device, and is used to monitor microseismic events with a shock energy greater than 100J, a shock frequency of 0~150Hz and a dynamic range less than 100dB.

3. A system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well according to claim 1, characterized in that: The underground substation includes a vibration pickup and a probe sensor, wherein the vibration pickup is an SPI-70 vibration pickup and the probe sensor is an NSGA vibration signal transmitting device.

4. A system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well according to claim 1, characterized in that: The ARAMIS_REJ data recording server is a system data recording server installed with the ARAMIS_REJ software; it is used for data filtering and recording continuous real-time vibration monitoring.

5. The system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well according to claim 1 is characterized in that: The computer is a data processing part composed of ARAMISWIN software and MAPCREATOR software installed on the computer; it realizes the positioning and energy calculation of microseismic events, analyzes the development height of water-conducting fracture zones, and displays the positioning results on the plan diagram of the mining area.

6. A system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well according to claim 1, characterized in that: The ground substation of the ground microseismic monitoring system includes a seismic pickup and a monitoring concentrator; the seismic pickup is an SPI-70 seismic pickup, and the monitoring concentrator is an LKP-ARP monitoring concentrator equipped with GPS; the ground substation converts the vibration event into a digital signal, monitors and records the signal through the monitoring concentrator, and uses the GPS clock on the artificial satellite to ensure very accurate time synchronization for the data substation.

7. The system for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well according to claim 1 is characterized in that: The wireless transmission system transmits the monitoring data to the microseismic extension computer in real time through 4G wireless signals; the computer equipped with a GSM modem is a software for data archiving, visualization and preprocessing, which is installed in the host computer and realizes two-way digital wireless communication through the detection data concentrator.

8. A method for jointly monitoring water-conducting fracture zones based on "microseismic" above and below the well, using the system according to any one of claims 1 to 7, characterized in that: It includes forming a microseismic monitoring network above and below the well and performing joint microseismic monitoring and positioning calculation above and below the well; The above-and-below microseismic monitoring network is a network where the monitoring data of the ARAMIS M / E underground microseismic monitoring system and the ARP2000 P / E ground microseismic monitoring system are synchronized through the satellite GPS clock, and the above-and-below data are jointly monitored on a computer with dual-system software installed to build an above-and-below joint monitoring microseismic network; The steps of the above-and-below well microseismic joint monitoring and positioning calculation are as follows: A. Divide the underground space to be monitored into layers according to the logging data, establish an initial horizontal layered velocity model, and modify the initial horizontal layered velocity model according to the travel time difference of the measuring medium in the perforation and the position of the perforation to obtain an optimized velocity model; B. Through the microseismic monitoring network above and below the well, data analysis is carried out on microseismic events affected by mining, and the travel time and travel time difference of the seismic phase of the microseismic event are obtained; C. Calculating the location and energy of the microseismic event based on the velocity model, the travel time and travel time difference of the seismic phase and the first arrival time of the P wave to obtain the three-dimensional coordinates and energy of the microseismic event; D. Determine the layer and height range of microseismic events caused by rock strata fragmentation under the influence of mining. Based on the layer where high-energy microseismic events occur, further analyze and reveal the development height of water-conducting fracture zones, and realize real-time monitoring of the development of water-conducting fracture zones in mining-affected overburden rocks.

9. An application of a method for jointly monitoring water-conducting fracture zones based on "microseisms" above and below the well as claimed in claim 8 in monitoring the development degree of water-conducting fracture zones under the influence of mine tunnel excavation and mine resource mining.

Citation Information

Cited By

  • Self-adaptive grouting control plugging method based on mining-induced fracture real-time monitoring

    CN120508175A