Construction method for quickly dismantling and reconstructing span bridge on expressway based on Beidou system
Through the multi-stage traffic monitoring and dynamic construction quality correction technology based on Beidou system, the rapid demolition and traffic conversion problems in the demolition and reconstruction of cross-bridges on highways are solved, and an efficient and safe construction process is achieved, reducing the surrounding roads The impact ensures the safety of residents' driving.
Patent Information
- Application Number
- CN202411201035.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-29
- Publication Date
- 2024-11-22
AI Technical Summary
During the renovation and expansion of highways, how to safely, efficiently and quickly remove old bridges and build new upper bridges to reduce the impact on surrounding roads and ensure traffic conversion and residents' driving safety.
Using multi-stage traffic monitoring diversion and guidance based on Beidou system, dynamic construction quality correction and real-time adjustment of old bridge demolition status, the entire process is monitored and analyzed online through Beidou traffic monitoring system, and optimal guidance is carried out in combination with traffic calculation simulation software. The plan is determined to use Beidou positioning and radar scanning systems to carry out precise demolition and new construction to ensure construction safety and quality.
Efficient construction of rapid demolition and reconstruction of cross-bridges on highways has been achieved, reducing the impact on existing highways and local roads, ensuring traffic safety and construction quality, and improving construction efficiency and safety.
Smart Images

Figure CN118997006A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge construction, and in particular relates to a method for quickly dismantling and rebuilding a bridge on a highway based on a Beidou system. Background Art
[0002] Against the background of rapid national economic development, some existing highways no longer meet the requirements of safe and comfortable driving. Therefore, it has become a new trend to renovate, expand and upgrade existing highways. Especially in the process of reconstruction and expansion of highways near urban areas, how to safely, efficiently and quickly dismantle and rebuild existing overpasses has become a problem that needs to be solved urgently. Similarly, how to ensure rapid construction and early traffic conversion of new overpasses and minimize the impact of construction on surrounding existing highways and local roads has also become the key. In response to the above problems, the present invention designs a method for rapid dismantling and reconstruction of highway overpasses based on the Beidou system. Summary of the invention
[0003] In view of the deficiencies in the prior art, the present invention provides a method for rapid dismantling and reconstruction of highway overpasses based on the BeiDou system. The method for rapid dismantling and reconstruction of highway overpasses based on the BeiDou system performs rapid construction in three aspects: multi-stage traffic monitoring and diversion guidance, dynamic correction of new bridge construction quality, and real-time and rapid adjustment of old bridge demolition status. The method achieves full-process, multi-stage, and multi-data real-time online monitoring, and analysis of key points of safety and quality control in the bridge dismantling and reconstruction process, achieves efficient construction, reduces traffic pressure on existing highways and local roads, and ensures residents' driving safety.
[0004] The present invention achieves the above technical objectives through the following technical means.
[0005] A method for rapid dismantling and rebuilding of a highway overpass based on the BeiDou system includes the following steps: Step 1: Traffic diversion preparation: Use the Beidou traffic monitoring system to monitor the traffic volume of surrounding highways and local roads during the entire construction period, and based on the traffic volume statistics of each stage and time period, use traffic calculation simulation software to conduct staged diversion and graded diversion of the road network to determine the optimal diversion plan; Step 2: Temporary closure of traffic; Step 3: Lay the high-speed road surface protective cushion layer; Step 4: Removal of the upper bridge; Step 5: Use a cleaning machine to clean up the waste residue; Step 6: Manually clean the road surface, wash it with a sprinkler truck, and remove temporary facilities; Step 7: Restore traffic; Step 8: Build a new bridge on the collapsed bridge; Step 9: Traffic on the existing highway will be redirected, half of the road will be closed, and the other half will be open to two-way traffic. Temporary steel guardrails will be used to isolate the road, anti-glare panels will be installed, and speed limits will be set; Step 10: Construction of the first and second batches of upper half-bridge middle piers and beam erection. In particular, the Beidou positioning system is strictly used in the construction of the middle piers to ensure accurate beam erection of the pile foundation and structure sections; Step 11: divert the existing high-speed secondary traffic, the method is the same as step 9; Step 12: The other half of the first and second batches of upper spans are constructed, and the other half of the beams are erected, using the automobile hanger beam method to erect the middle span; Step 13: The first batch of overpasses are opened to traffic and diverted. The remaining bridge decks of the first batch of overpasses are under construction. After the construction is completed and opened to traffic, the local road network will be diverted to the first batch of newly opened overpasses; Step 14: The second batch of overpasses will be demolished, newly built and opened to traffic.
[0006] Furthermore, the specific process of step 1 is as follows: In the target diversion area, including adjacent highways and local road networks, Beidou traffic monitoring system is installed to conduct traffic statistics, and to obtain information on two-way traffic volume in different time periods and between different road networks. The statistical information includes: the total traffic volume after the axle load of each type of vehicle is converted to the standard vehicle type, and the proportion of each type; Traffic volume statistics information is imported into traffic calculation simulation software, combined with the time and space requirements of soft foundation treatment, substructure construction, superstructure construction and demolition of old bridges for new bridges, and combined with the six-stage traffic maintenance requirements of "one demolition at a time and in batches" for overpasses to be simulated; the simulation sequence is: local road network traffic diversion → temporary interruption of existing highways → demolition of the first batch of overpasses → construction of the first batch of overpasses (side spans on both sides of existing highways) → primary traffic diversion on existing highways (half-width two-way traffic) → construction of half-width middle piers and beams for the first and second batches of overpasses → secondary traffic diversion on existing highways (half-width two-way traffic) → construction of the other half of the first and second batches of overpasses → opening of the first batch of overpasses → traffic diversion on local road networks → temporary interruption of existing highways → demolition, construction and opening of the second batch of overpasses, the above-mentioned overpass construction stages are combined with traffic volume simulation software to perform corresponding interruption and diversion simulations, and a multi-stage traffic diversion and relief plan is obtained; According to the multi-stage traffic diversion and relief plan, the total traffic volume, the proportion of each type, and the driving speed after the axle load of each type of vehicle is converted into standard vehicle models are animated and simulated. Taking into account the prohibition of trucks with more than three axles in the half-width closed state, the vehicle speed distribution and change pattern are obtained, and the traffic saturation and corresponding service level of adjacent highways and local road networks are obtained to verify the diversion and relief effect, and realize multi-stage optimal dynamic traffic diversion and relief.
[0007] Furthermore, the specific process of step 2 is as follows: The first batch of notices for the demolition of overpasses were issued. Before the temporary closure of the highway, all preparatory work was done, and the closure of the outer roads and other work were implemented by the relevant management departments of the highway, with the cooperation of the project department. After the temporary closure of the highway, the corrugated guardrails within the projection range of the bridge to be demolished and within 10m on both sides were removed, and the columns were directly cut flush with the road surface. Hard fences were used to close the road 250m away from the filling position on the main line of the highway and 50m at both ends of the overpass. Water barriers were placed 3m outside the hard fence with a spacing of 1m. Red and blue warning flashing lights were set above the water barriers. Two ground-mounted reflective signs of construction ahead and no passage were set 50m in front of the water barriers. Special personnel were arranged on duty to prevent vehicles from entering the construction area by mistake.
[0008] Furthermore, in the step 3, the highway pavement protection resources are first pre-placed next to the temporary access roads on both sides leading to the highway main line, and personnel and equipment are immediately arranged to carry out construction from both sides at the same time after the highway is closed; first, colored strips are laid on the highway within a construction range of 10m on both sides of the bridge deck projection line, and double-layer bamboo fences are laid on the colored strips, and then 50cm thick milling materials are laid to prevent broken concrete debris from falling and damaging the asphalt pavement of the highway.
[0009] Furthermore, in step 4, before the upper collapsed bridge is demolished, the Beidou radar scanning and monitoring system is used to scan and analyze the cross-sectional data and defects of the upper span bridge to evaluate its safety status. According to the safety status of the upper collapsed bridge, stress and strain sensors are arranged at the mid-span, 1 / 4 span, and structural damage points for subsequent real-time monitoring of the stress state of the upper collapsed bridge demolition. At the same time, positioning chips are installed in the personnel and machinery involved in the demolition of the upper collapsed bridge. During the demolition process, the Beidou radar scanning and monitoring system and the stress and strain state of the upper collapsed bridge are used to evaluate the safety state of the upper collapsed bridge, adjust the machinery state in real time, and carry out construction symmetrically and synchronously to uniformly adjust the construction progress of each resource.
[0010] Furthermore, in step 4, when the upper span is demolished, 16 blasting machines are placed on both sides of the bridge to be demolished, and mechanical chiseling construction of the span of the bridge to be demolished is carried out symmetrically at the same time; the chiseling order is: guardrail → box girder flange plate → box girder web plate → box girder top plate → box girder bottom plate → column, and each chiseling operation is carried out from the middle of the span to both sides, and the blasting machines of the same span are constructed synchronously and symmetrically; finally, when only the box girder bottom plate is left, the box girder is disconnected from the middle of the span to allow the beam to droop naturally; after the box girder is dismantled, only 6 rock drills are left on both sides to simultaneously dismantle the column concrete; 2 mechanical hydraulic pliers are cross-equipped to cut the steel bars.
[0011] Furthermore, in step 8, when the upper collapsed bridge is newly built, the soft foundation of the side spans on both sides and the lower structure construction are first carried out, and the pile driver is equipped with a Trimble GNSS monitoring module to obtain the elevation and coordinate positioning information of the pile foundation to realize dynamic monitoring of the pile deviation and pile verticality, to ensure that the position deviation of the pier in the upper span bridge meets the requirements, and the pile position monitoring information is fed back to the platform in real time through the network signal, and an early warning is issued according to the allowable error set in advance; by setting the positioning and settlement sensor monitoring modules at the lower structure contour points and the roadbed settlement points, the settlement information of the structure and the roadbed is collected in real time; when the structure and road construction are staked out, the stakeout position is adjusted in real time according to the monitoring information to achieve the purpose of dynamic and continuous quality correction in the construction of the new bridge; the remaining processes of the new upper span bridge are consistent with the traditional construction method.
[0012] The present invention has the following beneficial effects: The construction method provided by the present invention solves the problem of how to quickly dismantle and rebuild the overpass on the highway and convert traffic as early as possible. In the case of limited time, the overpass on the highway is delivered for use as early as possible, and the impact of the construction on the surrounding existing highways and local roads is reduced as much as possible, ensuring the basic traffic capacity of the road. The present invention adopts intelligent technology to achieve intelligent and efficient construction. Through the deployment of multi-stage traffic monitoring diversion and dredging of the Beidou system, the innovation of dynamic correction of the construction quality of the new bridge construction of the Beidou system, and the optimization of the real-time adjustment of the demolition status of the old bridge of the Beidou system, the whole process, multi-stage, multi-data real-time online monitoring, analysis of the safety and quality control points of the bridge demolition and reconstruction process are achieved, and efficient construction is achieved, which reduces the traffic pressure on existing highways and local roads, ensures the driving safety of residents, and speeds up the process of demolition and reconstruction of the overpass. It has a high promotion value, and can allow more renovation and expansion projects to adopt this intelligent, efficient and safe construction method when using the overpass. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 Flow chart of the new construction process for the demolition of the upper span bridge; Figure 2 A six-stage flow chart for the upper span bridges: "remove one at a time and proceed in batches"; Figure 3 Demolition plan for the upper span bridge; Figure 4 The construction process for dismantling the upper span bridge; Figure 5 Stress and strain section scanning arrangement diagram for upper span bridge removal; Figure 6 Demolition protection layout for the upper span bridge; DETAILED DESCRIPTION
[0014] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited thereto.
[0015] The present invention describes the method for rapid demolition and reconstruction of highway overpasses through three aspects: multi-stage traffic monitoring and diversion guidance by Beidou system, dynamic correction of construction quality of new bridge construction by Beidou system, and real-time rapid adjustment of demolition status of old bridges by Beidou system. This embodiment takes the Lianyungang 3 project of the Lianhuai section of Changshen Expressway as an example to illustrate the scheme. It is located in the main urban area of Guanyun County, Lianyungang City, and is equipped with 1 interchange overpass and 8 separated overpasses. In order to speed up the rapid demolition and reconstruction of highway overpasses within the urban area and ensure the basic traffic capacity of highways and local roads, the Beidou system is combined with the demolition and reconstruction of overpasses to complete the construction tasks efficiently, intelligently and safely.
[0016] Reference Figure 1 , 4 The method for rapid dismantling and reconstruction of a highway bridge based on the Beidou system of the present invention comprises the following steps: Step 1: Traffic diversion preparation; In the target diversion area, including adjacent highways and local road networks, Beidou traffic monitoring system is installed to conduct traffic statistics, and grasp the two-way traffic information between different time periods and road networks. The statistical information mainly includes: the total traffic volume of each type of vehicle after the axle load is converted to the standard vehicle type, and the proportion of each type; Import traffic volume statistics into traffic calculation simulation software, combine the time and space requirements of soft foundation treatment, substructure construction, superstructure construction and demolition of old bridges, and combine Figure 2 The six-stage traffic maintenance demand of "removing one at a time and in batches" of the overpass shown in the figure is simulated; the simulation order is: local road network traffic diversion → temporary interruption of existing highways → removal of the first batch of overpasses → construction of the first batch of overpasses (side spans on both sides of existing highways) → primary traffic diversion of existing highways (half-width two-way traffic) → construction of half-width middle piers and beam erection of the first and second batches of overpasses → secondary traffic diversion of existing highways (half-width two-way traffic) → construction of the other half of the first and second batches of overpasses → opening to traffic of the first batch of overpasses → local road network traffic diversion → temporary interruption of existing highways → removal, construction and opening to traffic of the second batch of overpasses. The above-mentioned overpass construction stages are combined with traffic volume simulation software to carry out corresponding interruption and diversion simulations, and a multi-stage traffic diversion and relief plan is obtained; According to the multi-stage traffic diversion and relief plan, the total traffic volume, the proportion of each type, and the driving speed after the axle load of each type of vehicle is converted into standard vehicle models are animated and simulated. Taking into account the prohibition of trucks with more than three axles in the half-width closed state, the vehicle speed distribution and change pattern are obtained, and the traffic saturation and corresponding service level of adjacent highways and local road networks are obtained to verify the diversion and relief effect, and realize multi-stage optimal dynamic traffic diversion and relief.
[0017] Step 2: Temporarily close traffic; The first batch of notices on the demolition of overpasses were issued. Before the temporary closure of the highway, all preparations were done. The relevant management departments of the highway were asked to implement the peripheral road closures and other work, and the project department fully cooperated. After the temporary closure of the highway, the corrugated guardrails within the projection range of the bridge to be demolished and within 10m on both sides were removed, and the columns were directly cut flush with the road surface. Hard fences were used to close the road 250m outside the filling position on the main line of the highway and 50m at both ends of the overpass. Water barriers were placed 3m outside the hard fences with a spacing of 1m. Red and blue warning flashing lights were set above the water barriers. Two reflective signs of construction ahead and no passage were set 50m in front of the water barriers, and special personnel were arranged on duty to prevent vehicles from entering the construction area by mistake.
[0018] Step 3: Laying the high-speed road surface protective cushion; Before the overpass is removed, the highway road protection resources are placed on both sides of the temporary access roads leading to the highway main line. After the highway is closed, personnel and equipment are immediately arranged to carry out construction from both sides at the same time. Figure 6 As shown, the road surface protection adopts colored strip cloth + double-layer bamboo fence + 50cm thick milling material, and the paving range is 2m on both sides of the bridge deck projection line + 8m width of the mechanical station on both sides. That is, the colored strip cloth is first laid on the highway within the construction range of 10m on both sides of the bridge deck projection line, and the colored strip cloth is fully covered with double-layer bamboo fence, and then 50cm thick milling material is laid to prevent broken concrete debris from falling and damaging the asphalt pavement of the highway.
[0019] Step 4: Removal of the upper bridge; like Figure 5 As shown in the figure, before the upper collapsed bridge (old bridge) is demolished, the Beidou radar scanning monitoring system is used to scan and analyze the cross-section data and defects of the old bridge to evaluate its safety status. According to the safety status of the old bridge, stress and strain sensors are arranged in the mid-span, 1 / 4 span, and structural damage to monitor the stress status of the old bridge in real time. Positioning chips are installed in the personnel and machinery involved in the demolition of the old bridge. During the demolition process, the Beidou radar scanning monitoring system and the stress and strain status of the old bridge are used to evaluate the safety status of the old bridge, adjust the machinery status in real time, and carry out symmetrical and synchronous construction. The construction progress of each resource is uniformly adjusted, the scheduling of construction resources is strengthened, and the demolition is fast, safe and efficient. like Figure 3 As shown, during the specific demolition, 16 rock drills are placed on both sides of the bridge to be demolished, and the mechanical chiseling construction of the bridge span to be demolished is carried out symmetrically at the same time; the chiseling order is: guardrail → box girder flange plate → box girder web plate → box girder top plate → box girder bottom plate → column, each chiseling operation must be carried out from the middle of the span to both sides, and the rock drills on the same span must be carried out synchronously and symmetrically; finally, when only the box girder bottom plate is left, the box girder can be disconnected from the middle of the span to allow the beam to droop naturally; after the box girder is demolished, only 6 rock drills are left on both sides to simultaneously remove the column concrete; 2 mechanical hydraulic pliers are cross-equipped to cut the steel bars.
[0020] Step 5: waste residue cleaning; After the blasting machines completed the crushing, they all withdrew to the outside of the highway, and two excavators and two loaders quickly cleaned the concrete fragments on the highway to the outside of the highway. Specifically, the loaders were used to transport large piles of waste to the outside of the road, and then the excavators were used to clean small piles of waste to the outside of the guardrail.
[0021] Step 6: Road cleaning; For the waste residue on the road surface, after the mechanical cleaning is completed, manual work (about 10 people on each side) will go on the road to clean it up, sweep the road surface with a broom, then use a sprinkler truck to wash it, and finally remove the temporary signs, lighting facilities, etc.
[0022] Step 7: Restore traffic; After the road surface is cleared, temporary steel guardrails are used to restore the guardrails on both sides of the center dividing strip. Anti-glare panels are installed above the temporary steel guardrails. Corrugated guardrails of the same specifications and models are used to restore both sides of the main line to ensure driving safety on the main line.
[0023] Step 8: Construction of upper span bridge; First, the soft foundation of the side spans on both sides and the substructure construction are carried out. The pile driver is equipped with a Trimble GNSS monitoring module to obtain the elevation and coordinate positioning information of the pile foundation so as to realize dynamic monitoring of the pile deviation and verticality of the pile. In particular, it can ensure the position deviation of the middle pier of the upper span bridge. The pile position monitoring information is fed back to the platform in real time through network signals, and an early warning is issued according to the pre-set allowable error; positioning and settlement sensor monitoring modules are set at the contour points of the substructure and the subgrade settlement points to collect the settlement information of the structure and subgrade in real time; when laying out the structure and road construction, the laying out position can be adjusted in real time according to the monitoring information to achieve the purpose of dynamic and continuous quality correction in the construction of the new bridge; the remaining processes of the new upper span bridge are consistent with the traditional construction methods.
[0024] Step 9: Traffic diversion on existing highways; Half of the road is closed, and the other half is open to two-way traffic. It is separated by temporary steel guardrails and anti-glare panels are installed, with a speed limit of 60km / h.
[0025] Step 10: Construction of the middle piers and beams for the first and second batches of upper span bridges. In particular, the Beidou positioning system is strictly used in the construction of the middle piers to ensure accurate beam erection of pile foundations and structural sections.
[0026] Step 11: divert secondary traffic on existing highways; The method is the same as step nine. Close half of the road and allow two-way traffic on the other half. Use temporary steel guardrails to isolate the road and install anti-glare panels. The speed limit is 60km / h.
[0027] Step 12: The other half of the first and second batches of upper spans are constructed, and the other half of the beams are erected using the automobile hanger beam method to erect the middle span.
[0028] Step 13: The first batch of overpasses are open to traffic diversion; The remaining bridge decks of the first batch of overpasses are under construction and will be opened to traffic as soon as the construction is completed. The local road network will then be diverted to allow traffic to pass through the first batch of newly opened overpasses.
[0029] Step 14: The second batch of overpasses will be demolished, newly built and opened to traffic.
[0030] The method for rapid demolition and reconstruction of highway overpasses based on the BeiDou system described in the present invention uses the BeiDou system for intelligent and standardized control during the entire process of new construction and demolition of overpasses. The BeiDou system monitors the traffic volume of surrounding highways and local roads during the entire construction period, and uses traffic simulation software to conduct phased diversion and graded diversion of the road network using traffic volume statistics at each stage and time period, and quickly determines the optimal diversion and modification plan; in the construction of new bridges, the BeiDou system is used to monitor the entire process of soft foundation treatment and structure construction, and dynamically correct its construction quality for efficient construction; when dismantling old bridges, the BeiDou system is used to scan the safety status of old bridges, monitor the dismantling of old bridges and the connection status of each process in real time, and adjust its personnel and machinery configuration according to the system feedback status to protect the existing highway pavement and quickly dismantle it. During the demolition and reconstruction of overpasses, construction is carried out in a refined control and real-time dynamic correction manner, and quality is driven by data, which is both efficient and safe.
[0031] The embodiments are preferred implementations of the present invention, but the present invention is not limited to the above-mentioned implementations. Any obvious improvements, substitutions or modifications that can be made by those skilled in the art without departing from the essential content of the present invention belong to the protection scope of the present invention.
Claims
1. A method for rapid demolition and reconstruction of a highway bridge based on the Beidou system, characterized in that: The process includes the following: Step 1: Traffic diversion preparation: Use the Beidou traffic monitoring system to monitor the traffic volume of surrounding highways and local roads during the entire construction period, and based on the traffic volume statistics of each stage and time period, use traffic calculation simulation software to conduct staged diversion and graded diversion of the road network to determine the optimal diversion plan; Step 2: Temporary closure of traffic; Step 3: Lay the high-speed road surface protective cushion layer; Step 4: Removal of the upper bridge; Step 5: Use a cleaning machine to clean up the waste residue; Step 6: Manually clean the road surface, wash it with a sprinkler truck, and remove temporary facilities; Step 7: Restore traffic; Step 8: Build a new bridge on the collapsed bridge; Step 9: Traffic on the existing highway will be redirected, half of the road will be closed, and the other half will be open to two-way traffic. Temporary steel guardrails will be used to isolate it, anti-glare panels will be installed, and speed limits will be set; Step 10: Construction of the first and second batches of upper half-bridge middle piers and beam erection. In particular, the Beidou positioning system is strictly used in the construction of the middle piers to ensure accurate beam erection of the pile foundation and structure sections; Step 11: divert the existing high-speed secondary traffic, the method is the same as step 9; Step 12: The other half of the first and second batches of upper spans are constructed, and the other half of the beams are erected, using the automobile hanger beam method to erect the middle span; Step 13: The first batch of overpasses are opened to traffic and diverted. The remaining bridge decks of the first batch of overpasses are under construction. After the construction is completed and opened to traffic, the local road network will be diverted to the first batch of newly opened overpasses; Step 14: The second batch of overpasses will be demolished, newly built and opened to traffic.
2. The method for rapid dismantling and reconstruction of a highway bridge based on the Beidou system according to claim 1 is characterized in that: The specific process of step 1 is as follows: In the target diversion area, including adjacent highways and local road networks, Beidou traffic monitoring system is installed to conduct traffic statistics, and to obtain information on two-way traffic volume in different time periods and between different road networks. The statistical information includes: the total traffic volume after the axle load of each type of vehicle is converted to the standard vehicle type, and the proportion of each type; Traffic volume statistics information is imported into traffic calculation simulation software, combined with the time and space requirements of soft foundation treatment, substructure construction, superstructure construction and demolition of old bridges for new bridges, and combined with the six-stage traffic maintenance requirements of "one demolition at a time and in batches" for overpasses, simulation is carried out; the simulation sequence is: local road network traffic diversion → temporary interruption of existing highways → demolition of the first batch of overpasses → construction of the first batch of overpasses (side spans on both sides of existing highways) → primary traffic diversion of existing highways (half-width two-way traffic) → construction of half-width middle piers and beams of the first and second batches of overpasses → secondary traffic diversion of existing highways (half-width two-way traffic) → construction of the other half of the first and second batches of overpasses → opening of the first batch of overpasses → traffic diversion of local road network → temporary interruption of existing highways → demolition, construction and opening of the second batch of overpasses, the above overpass construction stages are combined with traffic volume simulation software for corresponding interruption and diversion simulation, and a multi-stage traffic diversion and relief plan is obtained; According to the multi-stage traffic diversion and relief plan, the total traffic volume, the proportion of each type, and the driving speed after the axle load of each type of vehicle is converted into standard vehicle models are animated and simulated. Taking into account the prohibition of trucks with more than three axles in the half-width closed state, the vehicle speed distribution and change pattern are obtained, and the traffic saturation and corresponding service level of adjacent highways and local road networks are obtained to verify the diversion and relief effect, and realize multi-stage optimal dynamic traffic diversion and relief.
3. The method for rapid dismantling and reconstruction of a highway bridge based on the Beidou system according to claim 1 is characterized in that: The specific process of step 2 is as follows: The first batch of overpass demolition notices were issued, and the relevant highway management departments were asked to be responsible for the implementation of the peripheral road closure work, with the cooperation of the project department; after the temporary closure of the highway, the corrugated guardrails within the projection range of the bridge to be demolished and within 10m on both sides were removed, and the columns were directly cut flush with the road surface; hard fences were used to close the road 250m away from the filling position on the main line of the highway and 50m at both ends of the overpass head, and water barriers were placed 3m outside the outside of the hard fence with a spacing of 1m. Red and blue warning flashing lights were set above the water barriers, and two ground-mounted reflective signs of construction ahead and no passage were set 50m in front of the water barriers. Special personnel were arranged on duty to prevent vehicles from entering the construction area by mistake.
4. The method for rapid dismantling and rebuilding of a highway bridge based on the Beidou system according to claim 1 is characterized in that: In the step 3, firstly, the highway pavement protection resources are pre-placed next to the temporary access roads on both sides leading to the highway main line, and personnel and equipment are immediately arranged to carry out construction from both sides at the same time after the highway is closed; firstly, colored strips are laid on the highway within the construction range of 10m on both sides of the bridge deck projection line, and double-layer bamboo fences are laid on the colored strips, and then 50cm thick milling materials are laid to prevent broken concrete debris from falling and damaging the asphalt pavement of the highway.
5. The method for rapid dismantling and rebuilding of a highway bridge based on the Beidou system according to claim 1 is characterized in that: In the step 4, before the upper collapsed bridge is demolished, the Beidou radar scanning and monitoring system is used to scan and analyze the cross-sectional data and defects of the upper span bridge to evaluate its safety status. According to the safety status of the upper collapsed bridge, stress and strain sensors are arranged at the mid-span, 1 / 4 span, and structural damage points for subsequent real-time monitoring of the stress state of the upper collapsed bridge demolition. At the same time, positioning chips are installed in the personnel and machinery involved in the demolition of the upper collapsed bridge. During the demolition process, the Beidou radar scanning and monitoring system and the stress and strain state of the upper collapsed bridge are used to evaluate the safety state of the upper collapsed bridge, adjust the machinery state in real time, and carry out construction symmetrically and synchronously, and uniformly adjust the construction progress of each resource.
6. The method for rapid dismantling and rebuilding of a highway bridge based on the BeiDou system according to claim 1 is characterized in that: In step 4, when the upper span is demolished, 16 blasting machines are placed on both sides of the bridge to be demolished, and mechanical chiseling construction of the span of the bridge to be demolished is carried out symmetrically at the same time; the chiseling order is: guardrail → box girder flange plate → box girder web plate → box girder top plate → box girder bottom plate → column, and each chiseling operation is carried out from the middle of the span to both sides, and the construction is carried out synchronously and symmetrically by the blasting machines of the same span; finally, when only the box girder bottom plate is left, the box girder is disconnected from the middle of the span to allow the beam to droop naturally; after the box girder is dismantled, only 6 rock drills are left on both sides to simultaneously dismantle the column concrete; 2 mechanical hydraulic pliers are cross-equipped to cut the steel bars.
7. The method for rapid dismantling and rebuilding of a highway bridge based on the Beidou system according to claim 1 is characterized in that: In step 8, when the upper collapsed bridge is newly built, the soft foundation of the side spans on both sides and the lower structure construction are carried out first. The pile driver is equipped with a Trimble GNSS monitoring module to obtain the elevation and coordinate positioning information of the pile foundation to realize dynamic monitoring of the pile deviation and pile verticality, ensure that the position deviation of the pier in the upper span bridge meets the requirements, and feed back the pile position monitoring information to the platform in real time through network signals, and issue an early warning based on the pre-set allowable error; by setting positioning and settlement sensor monitoring modules at the lower structure contour points and roadbed settlement points, the settlement information of the structure and roadbed is collected in real time; when the structure and road construction are staked out, the stakeout position is adjusted in real time according to the monitoring information to achieve the purpose of dynamic and continuous quality correction in the construction of the new bridge; the remaining processes of the new upper span bridge are consistent with the traditional construction method.