Comprehensive treatment construction method for tunnel crossing large karst cave

By using hoisting machinery to lower steel pipe piles and reinforcing cages during tunnel construction in karst areas, combined with anchor bolt support and drainage systems, the construction difficulties and safety risks in large karst cave construction were resolved, achieving both tunnel structural stability and drainage effectiveness.

CN119021183APending Publication Date: 2024-11-26GUANGXI ROAD CONSTR ENG GRP CO LTD +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411145018.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

When constructing tunnels in karst areas, especially large karst caves, there are problems such as high construction difficulty and high safety risks. These include the soft and loose filling material inside the cave that is prone to collapse, water inrush from the filling material, bursting of water sacs, and surface subsidence. Moreover, dealing with the complex karst cave structure increases the complexity and risk of construction.

Method used

The steel pipe piles and reinforcing cages are lowered using hoisting machinery and clamps to form a segmental post-grouting steel pipe pile reinforcement system. This system is combined with anchor bolts and adjustable struts to form a support system. Drainage pipes and a collection pool are pre-installed to form a drainage system. The quality of concrete backfilling is controlled by a grouting position monitoring instrument. This system forms an irregular pile cap on the pile top and supports the side walls of the karst cave, ensuring construction safety and quality.

Benefits of technology

It effectively solved the problem of limited construction due to low clearance in tunnels, prevented the collapse of karst sidewalls, ensured reasonable stress on the tunnel structure, achieved smooth drainage and accurate concrete backfilling in the tunnel, and reduced construction risks and difficulties.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119021183A_ABST
    Figure CN119021183A_ABST
Patent Text Reader

Abstract

The invention relates to a comprehensive treatment construction method for a tunnel penetrating through a large karst cave. The method comprises the following steps that existing clay in the karst cave is excavated to the designed elevation of the bottom of a bearing platform; drilling, sequentially lowering the steel pipe pile and the reinforcement cage by a hoisting machine, and backfilling and grouting; laying a reinforcing mesh, and constructing a bearing platform; foam concrete is backfilled to the designed elevation; and a tunnel primary support is constructed, and then an inverted arch and a secondary lining are constructed. The construction method has the beneficial effects that the problem that low-clearance construction in the tunnel is limited is well solved by integrally modifying a hoisting machine and lowering the steel pipe piles and the reinforcement cages in a sectional splicing manner. The non-backfilled part in the karst cave is subjected to the mode of anchor rods and adjustable opposite supporting rods, so that the side wall of the karst cave is effectively prevented from collapsing; a grouting position monitor is mounted at a designed grouting position, so that the concrete backfilling quality and the backfilling position accuracy are ensured; and a plurality of drainage pipes and water collecting tanks are reserved in the karst cave, so that drainage smoothness in the tunnel is realized, and the pressure of the haunch of the tunnel is effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of highway tunnel construction, and in particular relates to a comprehensive treatment construction method for a tunnel passing through a large karst cave. Background Art

[0002] Karst is a general term for various surface or underground dissolution phenomena formed by the chemical and mechanical destruction of soluble rock layers by surface water and groundwater. The distribution area of ​​soluble rocks in my country is about 3.65×106km 2 , accounting for 1 / 3 of the country's land area, is one of the countries with the most developed karst in the world. Under the guidance of the strategy of building a strong transportation country, my country's highway tunnels have made great progress and are striving to move from a large highway tunnel country to a strong highway tunnel country. There is great resistance to the construction of tunnel projects in karst areas. The cave is located at the bottom, and because the filling is soft and loose, it is not conducive to the construction of the tunnel base; it is located at the top, and the filling is prone to collapse during construction, so it is not suitable for excavation; the karst caves in some areas are not solid, and there are many broken materials. If you are not careful during construction, it is easy to collapse; when encountering a filling capsule filled with water, when the tunnel is excavated to its edge, the water-containing filling continues to flow into the tunnel, which is difficult to stop, and even the surface cracks and sinks, and the mountain pressure increases sharply. During construction, it is also possible to encounter large water capsules, causing rocks and soil to rush into the tunnel with water; some karst caves are complex, circuitous, and widely distributed, which are difficult to handle.

[0003] Especially for large caves, it is impossible to backfill them completely. It is necessary to design and formulate treatment methods for tunnel caves in advance to avoid construction accidents. Summary of the invention

[0004] The purpose of the present invention is to overcome the deficiencies in the prior art and provide a comprehensive treatment construction method for a tunnel passing through a large karst cave.

[0005] The comprehensive treatment construction method for tunnels passing through large karst caves comprises the following steps:

[0006] Step 1: excavate the existing clay in the cave to the designed elevation of the bottom of the cap;

[0007] Step 2: drilling, the mobile gripper and the fixed gripper of the hoisting machine cooperate to lower the steel pipe piles and the steel cage into the clay in sections, and backfill and grout;

[0008] Step 3: Lay the steel mesh and construct the cap at the bottom of the tunnel on one side of the cave;

[0009] Step 4: Anchor rods are driven into the rock walls on both sides of the unfilled part of the cave, and adjustable support rods are installed using the ends of the anchor rods on the rock walls on both sides as support points, and concrete is sprayed on the rock walls;

[0010] Step 5: reserve drainage pipes and water collection tanks to form a drainage system, install a grouting position monitor, and backfill with foam concrete to the designed elevation;

[0011] Step six: construct the initial tunnel support, followed by the invert and secondary lining.

[0012] Preferably, the lifting machinery includes a hydraulic telescopic rod, a sliding plate, a clamping hand, an adjustable counterweight, a rotating shaft, a support rod and a crawler track, wherein the clamping hand is detachably mounted on the outside of the sliding plate, wherein the clamping hand includes a mobile clamping hand and a fixed clamping hand, and the clamping hand is used to clamp and lift steel pipe piles and steel cages; the fixed clamping hand is fixed at the bottom of the sliding plate, and the mobile clamping hand moves up and down along the sliding plate above the fixed clamping hand.

[0013] Preferably, when the clamping hand is used to clamp steel pipe piles, the movable clamping hand and the fixed clamping hand are both provided with a steel pipe pile clamp; the movable clamping hand clamps the upper end of the steel pipe pile, drives the steel pipe pile to slide to the lower end of the sliding plate until the fixed clamping hand clamps the steel pipe pile, the movable clamping hand releases the steel pipe pile and slides to the upper end of the sliding plate, clamps another section of the steel pipe pile and then moves to the upper and lower parts of the two steel pipe piles for welding.

[0014] Preferably, when the clamping hand is a clamping hand for clamping a steel cage, the movable clamping hand and the fixed clamping hand are provided with double-layer forks, and the double-layer fork teeth can move horizontally to adapt to steel cages of different sizes; the movable clamping hand drives the steel cage to slide to the lower end of the sliding plate, the fixed clamping hand clamps the steel cage, the movable clamping hand releases the steel cage and slides to the upper end of the sliding plate, clamps another section of the steel cage and then moves to the upper and lower parts of the two steel cages for welding.

[0015] Preferably, in step 2, the steel pipe piles are drilled in a one-by-one manner, and crushed stone is first filled on the outside of the steel pipe piles and then grouting is performed.

[0016] Preferably, in step three, the foundation is a special-shaped foundation with a steel mesh laid on the bottom and a reserved notch on the top.

[0017] Preferably, in step four, the end of the anchor rod is anchored to the rock wall with a pad and a nut, and the inner recesses at both ends of the support rod can be adjusted to clamp with the end of the anchor rod.

[0018] Preferably, in step five, the upper end of the reserved drainage pipe is open, a plurality of pipe holes are provided at the upper end of the reserved drainage pipe, the portion of the upper end of the drainage pipe with the pipe holes is inserted into a water collecting tank, a filter screen is provided on the water collecting tank, and the top surface height of the water collecting tank corresponds to the design elevation of the foam concrete.

[0019] Preferably, in step five, a grouting position monitor is installed, wherein the grouting position monitor comprises a conductive part, an insulating part, a hollow part and a pressure sensor. The grouting position monitor is tubular, and the tube wall is obtained by splicing the conductive part and the insulating part in pairs. The pressure sensor is arranged on the insulating part of the top surface of the grouting position monitor. The height of the top surface of the grouting position monitor is the same as the height of the top surface of the water collection tank. The grouting position monitor is connected to a receiving instrument through a wire.

[0020] Preferably, in step six, the initial support of the tunnel includes an advance small duct, a double-layer steel mesh and a steel arch frame. The advance small duct and the double-layer steel mesh are both arranged on the side of the steel arch frame close to the cave. The advance small duct is arranged on the outside of the double-layer steel mesh. The upper end of the double-layer steel mesh is connected to a drug coil anchor rod. After the excavation and support of the invert arch is completed, a drainage ditch is constructed and backfilled with concrete. The end of the steel arch frame is fixed in the reserved groove.

[0021] The beneficial effects of the present invention are:

[0022] 1) The present invention adopts a hoisting machine as an integrated machine for lowering a segmented post-grouting steel pipe pile reinforcement system and a low-headroom steel pipe pile built-in steel cage. The steel pipe piles and the steel cage are spliced ​​in sections and lowered into the drilled hole. The clamping hand can be detachably installed on the outside of the sliding plate as needed. By modifying the hoisting machine, the clamping hand can be replaced to switch between the clamping and lowering construction of the steel pipe pile and the steel cage, which effectively solves the problem of limited low-headroom construction in the tunnel.

[0023] 2) The present invention casts the pile top cap into a special shape to match the shape of the inverted arch. At the same time, a notch is reserved at the top of the cap to be spliced ​​with the steel arch frame, which is more conducive to the overall stress of the tunnel structure and forms a pile top special-shaped concrete cap system; the unfilled part in the cave is formed by anchor rods and adjustable support rods to form a large hall-type cave side wall anchoring support system, which effectively prevents the cave side wall from collapsing.

[0024] 3) The present invention forms an automatic control system for the grouting elevation of foam concrete backfill by installing a grouting position monitor at the designed grouting position, thereby ensuring the quality of concrete backfill and the accuracy of the backfill position; a number of drainage pipes and water collection pools are reserved in the cave to form a reserved drainage system in the cave, which realizes the smooth drainage in the tunnel and effectively reduces the pressure on the tunnel arch waist. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a top view of the steel pipe pile layout plane;

[0026] Figure 2 It is a cross-sectional view of the cave treatment;

[0027] Figure 3 This is a schematic diagram of the lifting and lowering of steel pipe piles;

[0028] Figure 4 It is a schematic diagram of the steel pipe pile splicing process;

[0029] Figure 5 It is a schematic diagram of the steel pipe pile clamping hand;

[0030] Figure 6 It is a schematic diagram of the steel cage clamping hand;

[0031] Figure 7 It is a schematic diagram of foam concrete backfill;

[0032] Figure 8 It is a schematic diagram of the connection between the steel arch frame and the cap;

[0033] Fig. 9 It is a schematic diagram of the connection between the anchor rod and the adjustable brace rod;

[0034] Fig.10 It is a schematic diagram of the top of the drainage system;

[0035] Fig.11 This is the structural diagram of the grouting position monitor.

[0036] In the figure: 1-clay, 2-cap, 3-lifting machinery, 301-hydraulic telescopic rod, 302-sliding plate, 303-movable clamping hand, 304-fixed clamping hand, 305-adjustable counterweight, 306-rotating shaft, 307-support rod, 308-crawler, 4-steel pipe pile, 5-steel mesh, 6-drilling hole, 7-anchor rod, 8-adjustable support rod, 9-sprayed concrete, 10-reserved drainage pipe, 11-grouting position monitor, 12-grouting pipe, 13-foam concrete, 14-inverted arch, 15-secondary lining, 16-reserved notch, 1 7-steel arch frame, 18-pad, 19-nut, 20-pipe mouth, 21-pipe hole, 22-water collection tank, 23-filter, 24-conductive part, 25-insulating part, 26-hollow part, 27-pressure sensor, 28-cave, 29-tunnel excavation contour, 30-locking steel pipe, 31-candle anchor, 32-advance small guide tube, 33-double-layer steel mesh, 34-initial support of the invert arch, 35-concrete, 36-receiving instrument, 37-drainage ditch, 38-cable trench, 39-steel pipe pile clamp, 40-double-layer fork, 41-conductor. DETAILED DESCRIPTION

[0037] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for ordinary persons in the art, without departing from the principle of the present invention, the present invention can also be modified in some ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0038] Embodiment 1

[0039] As an example, Figures 1 to 11 As shown, the comprehensive treatment construction method for tunnels passing through large karst caves includes the following steps:

[0040] Step 1: excavate the existing clay 1 in the cave 28 to the designed elevation of the bottom of the cap 2;

[0041] Step 2: drilling, hoisting machinery 3 successively lowers steel pipe piles 4 and steel cage, backfills and injects grout; Figure 1 As shown, the drilling is carried out in an alternate drilling method, firstly, gravel is filled on the outside of the steel pipe pile 4 and then grouting is performed, and the construction of all the steel pipe piles 4 in the treatment area of ​​the cave 28 is completed through two "drilling, pipe laying, grouting" circulation operations.

[0042] like Figure 3 As shown, the lifting machinery 3 includes a hydraulic telescopic rod 301, a sliding plate 302, a mobile clamping hand 303, a fixed clamping hand 304, an adjustable counterweight 305, a rotating shaft 306, a support rod 307, and a crawler track 308, wherein the mobile clamping hand 303 and the fixed clamping hand 304 are detachable and replaceable, and can lift steel pipe piles 4 and steel cages as needed.

[0043] Step three, lay the steel mesh 5 and construct the cap 2; the cap 2 is a special-shaped cap, using C30 concrete with a thickness of not less than 50cm, the top of the steel pipe pile 4 is not less than 40cm deep into the cap, and a steel mesh 5 with a spacing of Φ16 and 25cm×25cm is placed at the bottom of the cap 2.

[0044] Step 4: drive anchor rods 7 into the rock walls on both sides of the unfilled part of the cave, install adjustable support rods 8 with the ends of the anchor rods 7 as support points, and spray concrete 9 on the rock walls; Fig. 9 As shown, the end of the anchor rod 7 is anchored by a pad 18 and a nut 19, and the two ends of the support rod 8 can be adjusted to be concave and fixed to the end of the anchor rod 7.

[0045] Step 5: Drainage system: install the grouting position monitor 11 and backfill the foam concrete 13 to the designed elevation through the reserved grouting pipe 12;

[0046] Step 6: construct the initial support of the tunnel, followed by the construction of the invert 14 and the secondary lining 15. Figure 2 , Figure 7 As shown, the initial support on the right side of the tunnel includes an advance small guide tube 32, a double-layer steel mesh 33, and a steel arch frame 17. The upper end of the double-layer steel mesh 33 is connected to the drug coil anchor rod 31. After the excavation and support of the invert arch 14 is completed, a drainage ditch 37 is constructed. The backfill of the invert arch 14 is filled with C15 concrete 35. The top surface elevation needs to be strictly controlled. The invert arch 14 and the backfill concrete 35 cannot be poured at the same time to prevent the backfill low-grade concrete 35 from being mixed into the cross-section of the invert arch 14.

[0047] Embodiment 2

[0048] As another embodiment, this embodiment 2 proposes, based on the embodiment 1, a more specific construction method for comprehensive treatment of tunnels passing through large karst caves, such as Figure 4 , Figure 5 , Figure 6 As shown, when the clamping hand is a steel pipe pile clamping hand, the mobile clamping hand 303 drives the steel pipe pile 4 to slide to the lower end of the sliding plate 302, the fixed clamping hand 304 clamps the steel pipe pile 4, the mobile clamping hand 303 releases the steel pipe pile 4 and slides to the upper end of the sliding plate 302, clamps another section of the steel pipe pile 4 and then moves to a suitable position for welding.

[0049] When the clamping hand is replaced with a steel cage clamping hand, the mobile clamping hand 303 drives the steel cage to slide to the lower end of the sliding plate 302, the fixed clamping hand 304 clamps the steel cage, the mobile clamping hand 303 releases the steel cage and slides to the upper end of the sliding plate 302, clamps another section of the steel cage and moves to a suitable position for welding. The steel cage clamping hand is provided with a double-layer fork 40, and the teeth of the double-layer fork 40 can move horizontally to adapt to steel cages of different sizes.

[0050] The drainage system includes a reserved drainage pipe 10 and a water collection tank 22, such as Fig.10 As shown, the upper end pipe opening 20 of the reserved drainage pipe 10 is open, and a plurality of pipe holes 21 are provided at the upper end of the pipe wall. The drainage pipe 10 is in a water collecting tank 22, and a filter screen 23 is covered on the water collecting tank 22.

[0051] The grouting position monitor 11 includes a conductive part 24, an insulating part 25, a hollow part 26, and a pressure sensor 27. The conductive parts 24 on both sides are opposite to each other but not connected and are separated by the insulating part 25. The pressure sensor 27 is arranged on the top surface of the grouting position monitor 11. The height of the top surface of the grouting position monitor 11 is the same as the height of the top surface of the water collection tank 22. The grouting position monitor 11 is connected to the receiving instrument 36 through a wire 41.

[0052] Furthermore, the original filling of the cave 28 is rich in water. The grouting pressure will cause the water in the original filling to flow out, making the two conductive parts 24 of the sensor connected to each other, which will cause the slurry to reach the designed position and the grouting to be wrongly judged to be completed. Therefore, in this embodiment, a pressure sensor 27 is set on the top of the gradual position monitor 11, which can monitor the change of the pressure value of the pressure sensor 27 within a short time after the conductive part 24 is connected to the obvious turning point to judge whether the grouting has been completed.

[0053] It should be noted that the parts in this embodiment that are the same or similar to those in the first embodiment can be referenced to each other and will not be described in detail in this application.

[0054] Embodiment 3

[0055] As another embodiment, this embodiment 3 proposes, on the basis of embodiments 1 and 2, a tunnel crossing a large karst cave comprehensive treatment construction method, and a tunnel crossing a large karst cave comprehensive treatment structure obtained: including: a cap 2, a drainage system, a grouting position monitor 11, foam concrete 13, an invert 14, a secondary lining 15 and an initial tunnel support;

[0056] The clay 1 in the cave 28 is dug to the bottom of the tunnel. A cap 2 is provided below the tunnel in the cave 28. Steel pipe piles 4 are driven into the clay 1 from the bottom of the cap 2. The drainage system includes a reserved drainage pipe 10 and a water collection tank 22. Foam concrete 13 is poured above the clay 1. A grouting position monitor 11 and a water collection tank 22 are provided at the pouring elevation of the foam concrete 13. An automatic control system for the grouting elevation of the foam concrete backfill is formed to ensure the quality of the concrete backfill and the accuracy of the backfill position.

[0057] One end of the reserved drainage pipe 10 is inserted into the water collection pool 22, and the other end extends into the drainage ditch 37 in the tunnel, forming a reserved drainage system in the cave to achieve smooth drainage in the tunnel and effectively reduce the pressure on the tunnel waist.

[0058] The initial support of the tunnel includes an advance small duct 32, a double-layer steel mesh 33 and a steel arch frame 17. The steel arch frame 17 is arranged outside the tunnel. The advance small duct 32 and the double-layer steel mesh 33 are both arranged on the side of the steel arch frame 17 close to the cave 28. The advance small duct 32 is arranged outside the double-layer steel mesh 33. The upper end of the double-layer steel mesh 33 is connected to a drug-coiled anchor rod 31. A drainage ditch 37 is constructed on the invert 14, and the invert 14 below the top surface of the drainage ditch 37 is backfilled with concrete 35; the pedestal 2 is a special-shaped pedestal, with a steel mesh 5 laid on the bottom and a reserved notch 16 on the top, and the end of the steel arch frame 17 is fixed in the reserved notch 16.

[0059] Embodiment 4

[0060] As another embodiment, this embodiment 4 proposes, based on the embodiment 3, another more specific comprehensive treatment structure for tunnels crossing large karst caves:

[0061] Anchor rods 7 are driven into the rock walls on both sides of the unfilled part of the cave 28, and adjustable support rods 8 are installed between the ends of the anchor rods 7 on the rock walls on both sides, forming a large hall-type cave side wall anchoring support system, which effectively prevents the collapse of the cave side walls; the ends of the anchor rods 7 are anchored to the rock walls with pads 18 and nuts 19, and the two ends of the adjustable support rods 8 are concave and fixed to the ends of the anchor rods 7; concrete 9 is sprayed on the rock walls.

[0062] The grouting position monitor 11 includes a conductive part 24, an insulating part 25, a hollow part 26 and a pressure sensor 27. The grouting position monitor 11 is tubular, and the tube wall is obtained by splicing the conductive part 24 and the insulating part 25 in pairs. The pressure sensor 27 is arranged on the insulating part 25 on the top surface of the grouting position monitor 11. The height of the top surface of the grouting position monitor 11 is the same as the height of the top surface of the water collection tank 22. The grouting position monitor 11 is connected to a receiving instrument 36 through a wire 41.

[0063] The pipe opening 20 at the upper end of the reserved drainage pipe 10 is open, and a plurality of pipe holes 21 are provided at the upper end of the reserved drainage pipe 10. The portion of the upper end of the drainage pipe 10 where the pipe holes 21 are provided is inserted into a water collecting tank 22. The water collecting tank 22 is covered with a filter screen 23. The top surface height of the water collecting tank 22 corresponds to the design elevation of the foam concrete 13.

[0064] It should be noted that the parts in this embodiment that are the same or similar to those in Embodiment 3 can be referenced to each other and will not be described in detail in this application.

[0065] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

Claims

1. A comprehensive treatment construction method for a tunnel passing through a large karst cave, characterized in that: The following steps are involved: Step 1: excavate the existing clay in the cave to the designed elevation of the bottom of the cap; Step 2: drilling, the mobile gripper and the fixed gripper of the hoisting machine cooperate to lower the steel pipe piles and the steel cage into the clay in sections, and backfill and grout; Step 3: Lay the steel mesh and construct the cap at the bottom of the tunnel on one side of the cave; Step 4: Anchor rods are driven into the rock walls on both sides of the unfilled part of the cave, and adjustable support rods are installed using the ends of the anchor rods on the rock walls on both sides as support points, and concrete is sprayed on the rock walls; Step 5: reserve drainage pipes and water collection tanks to form a drainage system, install a grouting position monitor, and backfill with foam concrete to the designed elevation; Step six: construct the initial tunnel support, followed by the invert and secondary lining.

2. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 1 is characterized by: The lifting machinery includes a hydraulic telescopic rod, a sliding plate, a clamping hand, an adjustable counterweight, a rotating shaft, a support rod and a crawler track. The clamping hand is detachably installed on the outside of the sliding plate, wherein the clamping hand includes a mobile clamping hand and a fixed clamping hand. The clamping hand is used to clamp and lift steel pipe piles and steel cages; the fixed clamping hand is fixed at the bottom of the sliding plate, and the mobile clamping hand moves up and down along the sliding plate above the fixed clamping hand.

3. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 2 is characterized by: When the clamping hand is used to clamp a steel pipe pile, the movable clamping hand and the fixed clamping hand are both provided with a steel pipe pile clamp; the movable clamping hand clamps the upper end of the steel pipe pile, drives the steel pipe pile to slide to the lower end of the sliding plate until the fixed clamping hand clamps the steel pipe pile, the movable clamping hand releases the steel pipe pile and slides to the upper end of the sliding plate, clamps another section of the steel pipe pile and then moves to the upper and lower butt joint of the two sections of the steel pipe pile for welding.

4. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 2 is characterized by: When the clamping hand is used to clamp a steel cage, the mobile clamping hand and the fixed clamping hand are provided with double-layer forks, and the double-layer fork teeth can move horizontally to adapt to steel cages of different sizes; the mobile clamping hand drives the steel cage to slide to the lower end of the sliding plate, the fixed clamping hand clamps the steel cage, the mobile clamping hand releases the steel cage and slides to the upper end of the sliding plate, clamps another section of the steel cage and then moves to the upper and lower parts of the two steel cages for welding.

5. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 1 is characterized by: In step 2, the steel pipe piles are drilled in alternate holes, and crushed stone is first filled on the outside of the steel pipe piles and then grouting is performed.

6. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 1 is characterized by: In step three, the foundation is a special-shaped foundation with a steel mesh laid on the bottom and a reserved notch on the top.

7. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 1 is characterized by: In step 4, the end of the anchor rod is anchored to the rock wall with a pad and a nut, and the inner recesses at both ends of the support rod can be adjusted to be clamped with the end of the anchor rod.

8. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 1 is characterized by: In step five, the upper end of the reserved drainage pipe is opened, and a plurality of pipe holes are arranged on the upper end of the reserved drainage pipe. The portion of the upper end of the drainage pipe with the pipe holes is inserted into the water collecting tank, and the water collecting tank is covered with a filter screen. The top surface height of the water collecting tank corresponds to the design elevation of the foam concrete.

9. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 1 is characterized by: In step five, a grouting position monitor is installed. The grouting position monitor includes a conductive part, an insulating part, a hollow part and a pressure sensor. The grouting position monitor is tubular, and the tube wall is obtained by splicing the conductive part and the insulating part in pairs. The pressure sensor is arranged on the insulating part of the top surface of the grouting position monitor. The height of the top surface of the grouting position monitor is the same as the height of the top surface of the water collection tank. The grouting position monitor is connected to a receiving instrument through a wire.

10. The comprehensive treatment construction method for tunnels passing through large karst caves according to claim 6 is characterized by: In step six, the initial support of the tunnel includes an advance small duct, a double-layer steel mesh and a steel arch frame. The advance small duct and the double-layer steel mesh are both located on the side of the steel arch frame close to the cave. The advance small duct is located on the outside of the double-layer steel mesh. The upper end of the double-layer steel mesh is connected to a drug coil anchor rod. After the excavation and support of the invert arch is completed, a drainage ditch is constructed and backfilled with concrete. The end of the steel arch frame is fixed in the reserved groove.