Optimized scheduling and resource allocation construction method and system relating to water conservancy flood prevention
Through detailed processing and analysis of regional remote sensing image data, a detailed flood model is generated, risk areas are identified and resource allocation is optimized, and the shortcomings in risk identification and resource allocation of the existing flood control system are solved, and the comprehensiveness of the flood control system is improved. accuracy.
Patent Information
- Application Number
- CN202411495667.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-25
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-10-25
AI Technical Summary
The existing flood control system lacks precise simulation and optimization in the identification of risk areas and resource allocation, resulting in low comprehensiveness and accuracy of system construction.
By obtaining regional remote sensing image data, pre-processing and screening, a standard data set is generated, rainfall trend analysis, flood mechanism research, urban flood model construction and coupling, simulate flood conditions, label risk areas, and perform resource allocation simulation optimization. Finally converted to 3D heatmap and real-time updates.
It has improved the ability to predict extreme rainfall events, the understanding of the causes of floods, the efficiency and accuracy of resource allocation, and enhanced the comprehensive flood control capabilities and decision-making support level of the flood control system.