Static load test device for connection of large-diameter pipe pile and bearing platform foundation, monitoring method and application

By designing a static load test device on the pile foundation of high-speed rail bridges, using steel cages, sensors and polymer materials, the problems of carrying capacity and vibration response evaluation of large-diameter pipe piles under high-speed rail operating conditions are solved, and the pile foundation is realized Scientific monitoring and early warning have improved the safety and stability of the bridge.

CN119041494APending Publication Date: 2024-11-29NANJING TECH UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411181600.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In the design of pile foundations of high-speed railway bridges, how to accurately evaluate the long-term load-bearing capacity and dynamic response of large-diameter prestressed high-strength concrete pipe piles, especially the impact of horizontal vibrations on pile foundations during high-speed trains, has not been effectively solved.

Method used

A static load test device connecting large diameter pipe piles and base of the bearing is designed, including large diameter pipe piles, load units and bearings, equipped with steel cages, vibration sensors, fiber grating sensors and thermal imaging sensors for monitoring the pipes. The settlement deformation and vibration characteristics of the piles are enhanced by polymer materials.

Benefits of technology

Accurate monitoring of the settlement deformation and vibration characteristics of large-diameter pipe piles is achieved, the seismic performance and stability of the pile foundation is improved, the testing cost is reduced, and long-term monitoring and early warning capabilities are provided.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041494A_ABST
    Figure CN119041494A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building structure monitoring, in particular to a static load test device for connection of a large-diameter tubular pile and a bearing platform foundation, a monitoring method and application of the static load test device for connection of the large-diameter tubular pile and the bearing platform foundation. The load unit or the large-diameter pipe pile is connected with at least one displacement rod vertically penetrating to the position above the bearing platform, a reinforcement cage flush with a pipe opening is arranged on the inner side of the pipe top of the large-diameter pipe pile, the bottom of the reinforcement cage is connected with a first steel plate with the edge wrapped with a rubber sleeve to form upper and lower layer sealing, and a plurality of vibration sensors are installed on the reinforcement cage. The reinforcement cage is grouted to form a filling body, and a plurality of fiber grating sensors are embedded in grooves formed in the outer side wall of the large-diameter pipe pile. According to the invention, settlement deformation of the large-diameter pipe pile and vibration characteristics of the pile head can be monitored stably in a vertical compression resistance static load test, and powerful support is provided for research and practice of the large-diameter pipe pile and bearing platform pile foundation engineering.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building structure monitoring, and in particular to a static load test device for connecting a large-diameter pipe pile with a cap foundation, a monitoring method and an application thereof. Background Art

[0002] In the construction of modern high-speed rail infrastructure, the pile foundation design and construction of high-speed rail bridges are important links to ensure the safety, stability and durability of bridge structures. With the rapid development of high-speed rail technology, high-speed trains have higher and higher requirements on bridge structures, especially the vertical bearing capacity and horizontal vibration of pile foundations. Therefore, the bearing characteristics and long-term monitoring of pile foundations have become the focus of research.

[0003] Large-diameter prestressed high-strength concrete (PHC) piles have superior performance in bearing capacity and seismic resistance, but in actual engineering applications, how to accurately evaluate their long-term bearing capacity and dynamic response is still a challenge. Especially during the operation of high-speed railways, the impact of train vibration loads on pile foundations has gradually attracted widespread attention. When high-speed trains run at high speeds, the horizontal vibrations generated will not only affect the stability of the pile foundation, but may also have a negative impact on the long-term performance of the pile foundation. Therefore, an integrated and efficient test device and a systematic long-term monitoring method are urgently needed to meet the research needs of modern high-speed railway bridge pile foundations.

[0004] In view of the above problems, the present invention proposes a static load test device, a monitoring method and an application of the connection between a large-diameter pipe pile and a cap foundation. Summary of the invention

[0005] In view of the above-mentioned technical problems, the present invention overcomes the shortcomings of the prior art and provides a static load test device, a monitoring method and an application for the connection between large-diameter pipe piles and pedestal foundations, which can stably monitor the settlement deformation of large-diameter pipe piles and the vibration characteristics of the pile heads in vertical compressive static load tests, thereby providing strong support for the research and practice of large-diameter pipe piles and pedestal pile foundation projects.

[0006] In the first aspect, the present invention provides a static load test device for connecting a large-diameter pipe pile with a pedestal foundation, specifically comprising a large-diameter pipe pile, a load unit and a pedestal connected in sequence from bottom to top, wherein the load unit or the large-diameter pipe pile is connected with at least one displacement rod vertically penetrating to the top of the pedestal, wherein a steel cage flush with the pipe mouth is arranged on the inner side of the pipe top of the large-diameter pipe pile, a first steel plate with an edge wrapped with a rubber sleeve is connected to the bottom of the steel cage to form an upper and lower layer seal, and a plurality of vibration sensors are installed on the steel cage, the steel cage is cored to form a filling body, and the outer wall of the large-diameter pipe pile is also grooved and embedded with a plurality of fiber optic grating sensors, and the steel cage is installed on the inner side of the pipe top of the large-diameter pipe pile to improve the strength of the pile head, and is suitable for a vertical compressive static load test of the connection between the large-diameter pipe pile and the pedestal foundation.

[0007] Optionally, the load unit includes at least one load box and a large pallet and a small pallet horizontally connected to two ends of the load box respectively.

[0008] Optionally, three load boxes are provided and arranged in an equilateral triangle shape, the small pallet is an octagonal ribbed circular structure, and its bottom surface is matched with the top surface of the large-diameter pipe pile, and the large pallet is an octagonal ribbed square structure, and its bottom surface is connected to the top surfaces of the three load boxes, and the top surface of the large pallet is connected to the bottom surface of the base. This equilateral triangle load box arrangement can effectively and evenly distribute the load, reduce eccentricity and unevenness during load application, thereby improving the bearing capacity and stability of the pipe pile, the octagonal ribbed circular structure of the small pallet enhances its structural strength, can effectively resist deformation caused by external loads, and ensure the accuracy of the test, the octagonal ribbed square structure of the large pallet also has excellent structural strength, and its polygonal design contributes to the uniform distribution of the load, and also plays a role in fixing the protective casing before the base construction.

[0009] Optionally, the small pallet is composed of two parallel circular pallets and eight straight ribs vertically connecting the two, and the large pallet is composed of a parallel upper pallet, a lower pallet and eight inclined ribs vertically connecting the two, wherein the straight ribs in the small pallet ensure uniform transfer of load on the bottom surface of the small pallet by enhancing the load distribution capability, thereby avoiding the phenomenon of local concentrated force on the top of the large-diameter pipe piles, and the inclined ribs in the large pallet enhance the load sharing capability of the large pallet by forming an effective supporting structure, so that the load is evenly distributed from the large pallet to the bottom surface of the pedestal, thereby further improving the stability and accuracy of the test device in the static load test. Through this design, the load is not only well distributed between the pallets, but also ensures uniform force on the entire system, avoiding potential problems caused by uneven force transmission.

[0010] Optionally, a total of four displacement rods are provided and are evenly connected to the small pallet. The four displacement rods are arranged around the outside of the three load boxes, and four protective sleeves are passed through the base and the large pallet to provide space for the displacement rods to move. The setting of the four displacement rods can be used to calculate the uniform settlement of large-diameter pipe piles; if loading cannot be performed or loading is uneven due to improper operation or failure of the load box, the pipe piles will be unevenly stressed and may tilt, so that the displacement data of the displacement rods may be inaccurate. In this case, by analyzing the settlement data of the four displacement rods, abnormal settlement patterns can be discovered in time.

[0011] Optionally, the static load test device also includes a reference beam arranged above the pedestal, the reference beam is provided with a displacement meter matching the number of displacement rods, the bottom surface of the pedestal is also connected to a number of bored piles providing reaction force, the outer wall of the pipe mouth of the large-diameter pipe pile is wrapped with a clamp, and the outer wall of the large-diameter pipe pile is evenly grooved and installed with a fiber optic Bragg grating sensor and a thermal imaging sensor.

[0012] Optionally, the steel cage is composed of a cage structure composed of multiple horizontal annular stirrups and multiple vertical U-shaped steel bars, and the vibration sensors are symmetrically arranged on the horizontal annular stirrups. The arrangement of the vibration sensors close to the inner wall of the large-diameter pipe piles can more accurately capture the vibration and deformation inside the pipe piles, improve the sensitivity and accuracy of the sensor to the vibration signal, and thus more accurately reflect the actual dynamic response of the large-diameter pipe piles during the operation of the high-speed railway.

[0013] Optionally, the large diameter pipe pile, the cap and the load unit are connected in sequence from bottom to top, and one end of the displacement rod is connected to the large diameter pipe pile, and the other end is connected to the load unit, and the displacement data of the cap in the static pull-out load test is measured using a displacement meter.

[0014] Optionally, the material of the filler may be concrete, and specifically may be recycled aggregate, such as green low-carbon concrete made from industrial solid waste materials.

[0015] In the second aspect, the present invention also provides a method for monitoring using the static load test device described in the first aspect, using the static load test device as the pile foundation of the high-speed railway bridge, using a vibration sensor to monitor the dynamic characteristics of the pile head of the large diameter pipe pile during the operation of the high-speed railway, using a fiber grating sensor to monitor the changes in the internal force of the large diameter pipe pile body during the operation of the high-speed railway, and using a thermal imaging sensor to monitor the corrosion state of the large diameter pipe pile in different erosion environments, including but not limited to saline soil, seawater environment, etc., to achieve the purpose of long-term monitoring of the settlement deformation of the large diameter pipe pile and the vibration characteristics of the pile head.

[0016] In the third aspect, the present invention provides a static load test device for use as a pile foundation in a high-speed railway bridge. The static load test device is specifically the static load test device described in the first aspect. The application also includes injecting a polymer material into the pile head of a large-diameter pipe pile through a protective casing, which reacts to expand and solidify, and forming a polymer material reactant layer and a polymer-soil solidified body around the load unit surrounded by the soil layer and the large-diameter pipe pile, respectively, thereby improving the overall strength and seismic resistance of the pile foundation.

[0017] Optionally, the polymer material is made of polyisocyanate and polyether polyol as raw materials, or is made of polyester polyol as raw material.

[0018] The beneficial effects of the present invention are: (1) The static load test device for connecting a large-diameter pipe pile with a cap foundation proposed in the present invention can stably monitor the settlement deformation of the large-diameter pipe pile and the vibration characteristics of the pile head in a vertical compressive static load test by sequentially connecting a large-diameter pipe pile, a load unit and a cap, and installing a steel cage and a sensor in the pipe pile, thereby providing strong support for the research and practice of large-diameter pipe pile and cap pile foundation engineering; (2) The load unit of the present invention can be reserved in the foundation as a support after the static load test. The load box can compensate for the settlement difference when uneven settlement occurs during the operation of the high-speed train. Therefore, the static load test device for connecting the large-diameter pipe pile with the cap foundation proposed in the present invention can be used as a pile foundation in high-speed railway bridges. At the same time, a polymer material is injected into the pile head through a protective sleeve. The polymer material has the characteristics of high toughness and can achieve a shock-absorbing effect during the operation of the high-speed train to protect the pile head. (3) In addition to the vertical compressive static load test of large-diameter pipe piles, the static load test device proposed in the present invention can also carry out the vertical pullout static load test of large-diameter pipe piles after adjusting the construction sequence of the load unit. The pullout bearing characteristics of large-diameter pipe piles can be studied through the static pullout test of the reaction force of the cast-in-place pile anchor cap-pile. (4) The static load test device of the present invention provides a complete monitoring system. The fiber grating sensor can reflect the changes in the internal force of the pile body during the static load test. The vibration sensor is used to monitor the dynamic characteristics of the pile head under the horizontal vibration load generated during the operation of the high-speed rail. When the critical value of the horizontal vibration load is reached, a vibration warning is issued to the remote control PC. The thermal imaging sensor is used to collect images in real time and transmit the collected images to the remote control PC, which intuitively reflects the corrosion state of the large-diameter pile in different erosion environments. (5) There is a waste of test piles in the traditional anchor pile method static load test. The large-diameter pipe piles, load units and caps in the static load test device of the present invention can ultimately be used in actual engineering (applied to high-speed railway bridge foundations), which greatly saves test costs and has extremely high economic benefits. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a structural schematic diagram of a static load test device (vertical compression resistance) in a specific embodiment of the present invention; Figure 2 It is a structural schematic diagram of a load unit in a static load test device in a specific embodiment of the present invention; Figure 3 For the present invention Figure 2 Enlarged view of point A in the middle; Figure 4 It is a structural cross-sectional view of the upper part of a large-diameter pipe pile in a specific embodiment of the present invention; Figure 5 It is a structural schematic diagram of a clamp in a specific embodiment of the present invention (before and after assembly); Figure 6 This is a schematic structural diagram of a small pallet in a specific embodiment of the present invention; Figure 7 It is a structural schematic diagram of a load box in a specific embodiment of the present invention; Figure 8 It is a structural schematic diagram of a casing in a specific embodiment of the present invention; Fig. 9 It is a structural schematic diagram of a large support plate in a specific embodiment of the present invention; Fig.10 It is a schematic diagram of the outer side wall of a large diameter pipe pile in a specific embodiment of the present invention; Fig.11 It is a structural schematic diagram of a static load test device (vertical pull-out resistance) in a specific embodiment of the present invention; Fig.12 It is a structural cross-sectional view of a static load test device in a specific embodiment of the present invention when it is used as a pile foundation of a high-speed railway bridge (with polymer material injected); In the figure: 1. Large diameter pipe pile; 2. Bored pile; 3. Cap; 4. Remote control PC terminal; 5. Steel cage; 11. Displacement meter; 12. Reference beam; 13. Displacement rod; 14. Protective casing; 21. Large support plate; 22. Casing; 23. Hoop; 24. Sensor system; 25. Load box; 26. Small support plate; 31. polymer material reaction product layer; 32. polymer-soil solidified body; 33. soil layer; 41. Fiber Bragg grating sensor; 42. Thermal imaging sensor; 51. Filling body; 52. Vibration sensor; 53. Rubber sleeve; 54. Horizontal hoop reinforcement; 55. First steel plate; 56. Vertical U-shaped reinforcement; 231. Second steel plate; 232. Bolt. DETAILED DESCRIPTION

[0020] To make the present invention more clear, the static load test device, monitoring method and application of the large-diameter pipe pile connected to the cap foundation of the present invention are further described below in conjunction with the accompanying drawings. The specific embodiments described here are only used to explain the present invention and are not used to limit the present invention.

[0021] As one of the optional specific embodiments of the present invention, see Figure 1-Figure 3 The static load test device for connecting the large-diameter pipe pile with the cap foundation specifically includes a large-diameter pipe pile 1, a bored pile 2, a cap 3, a remote control PC terminal 4, a steel cage 5, a displacement meter 11, a reference beam 12, a displacement rod 13, a protective casing 14, a large support plate 21, a casing 22, a hoop 23, a sensor system 24, a load box 25 and a small support plate 26.

[0022] See also Fig.10 The fiber grating sensors 41 and thermal imaging sensors 42 are embedded in grooves symmetrically cut in the pipe pile 1. The number and arrangement of the fiber grating sensors 41 are designed according to the length of the large-diameter pipe pile 1, and two thermal imaging sensors 42 are arranged in each section of the pipe pile.

[0023] In this embodiment, the large diameter pipe pile 1 is composed of three pipe pile sections welded together. The fiber grating sensor 41 is used to reflect the change of the internal force of the large diameter pipe pile 1 during the static load test. The fiber grating sensor 41 is symmetrically arranged in the groove on the surface of the pile body, and a total of 11 sections are arranged along the pile body. The thermal imaging sensor 42 is used to collect images in real time and transmit the collected images to the remote control PC end 4, which can intuitively reflect the corrosion state of the large diameter pipe pile 1 in different erosion environments. The thermal imaging sensor 42 is symmetrically arranged in the groove on the surface of the pile body, and a total of 3 sections are arranged along the pile body. It is arranged 5 m below the top of each pipe pile section to avoid damage to the thermal imaging sensor 42 during the pipe pile construction process. The fiber grating sensor 41 and the thermal imaging sensor 42 are sealed and fixed with epoxy resin.

[0024] See also Figure 1 After the large diameter pipe pile 1 is hammered to the designed elevation, the bored pile 2 is constructed, and the soil layer is excavated to expose the pile head of the large diameter pipe pile 1.

[0025] See also Figure 4 According to the size of the large-diameter pipe pile 1, a steel cage 5 with a diameter of three times the pile diameter, i.e., 3 m, is manufactured. The steel cage 5 is fixedly composed of 7 horizontal hoop bars 54 and 8 vertical U-shaped steel bars 56. The diameter of the steel bar is 10 mm. The vibration sensor 52 is symmetrically fixed on the horizontal hoop bars 54. A 5 mm thick first steel plate 55 is welded at the bottom end of the steel cage 5 to seal the bottom to prevent leakage from the bottom. A rubber sleeve 53 is wrapped around the edge of the first steel plate 55. After the steel cage 5 is installed, a C40 concrete core is poured to form a filling body 51. Of course, in some other implementations, the C40 concrete can also be replaced with recycled aggregates of industrial solid waste materials to meet green and low-carbon requirements.

[0026] In this embodiment, the vibration sensor 52 is used to monitor the dynamic characteristics of the pile head of the large-diameter pipe pile 1 under the horizontal vibration load generated during the operation of the high-speed railway, and sends a vibration warning to the remote control PC terminal 4 when the critical value of the horizontal vibration load is reached. The vibration sensor 52 is symmetrically fixed on the second, fourth and sixth horizontal annular stirrups 54 (from the bottom to the top), and a total of 6 are symmetrically arranged.

[0027] See also Figure 1, check the survival rates of the vibration sensor 52, the fiber grating sensor 41 and the thermal imaging sensor 42, and use rubber pipes to wrap each sensor for protection to form a sensor system 24. The remote control PC terminal 4 can respectively record the data transmitted by the vibration sensor 52, the fiber grating sensor 41 and the thermal imaging sensor 42 and upload them to the cloud.

[0028] See also Figure 5-Figure 9 The hoop 23 is welded and manufactured by the second steel plate 231, with a height of 50 cm. The second steel plate 231 is 1 cm thick, and the ears and ribs are 2 cm thick. They are connected by 8 M20 bolts 232. After the hoop 23 is installed on the head of the large-diameter pipe pile 1, the small support plate 26 and the load box 25 are installed in sequence. According to the distance of the reserved holes and grooves of the large support plate 21, the displacement rod 13 is welded to the side of the small support plate 26, and the protective sleeve 14 is welded to the bottom of the large support plate 21 through the reserved holes and grooves of the large support plate 21. The casing 22 is installed between the head of the large-diameter pipe pile 1 and the large support plate 21. After the casing 22 is installed, the large support plate 21 is lifted by the vehicle-mounted crane to allow the displacement rod 13 to pass through the protective sleeve 14, and the sensor system 24 to pass through the reserved holes and grooves of the casing 22.

[0029] See also Figure 1 , the displacement rod 13 adopts a steel pipe with a diameter of 25 mm, the protective sleeve 14 adopts a sonic detection tube with a diameter of 50 mm, a wall thickness of 3 mm, and is 10 cm-20 cm higher than the cap. The displacement observation is carried out on the upper part of the cap 3. The bored pile 2 is connected to the cap 3 through 16 pile body steel bars as an anchor pile. The entire static load test device contains 8 bored piles 2. The diameter of the bored pile 2 is the same as that of the large-diameter pipe pile 1 to prevent the damage of the cap 3 during loading and provide sufficient reaction force; the cap 3 adopts an octagonal cap with a centrally symmetrical structure as a whole and is reinforced with a secondary cap; the displacement rod 13 passes through the cap 3 through the protective sleeve 14, which adopts a steel bar with a diameter of 25 mm and is welded to the small support plate 26 at the bottom; the protective sleeve 14 passes through the hole groove reserved between the cap 3 and the large support plate 21, and the bottom of the protective sleeve 14 is flush with the bottom of the large support plate 21.

[0030] See also Figure 6 ,In the load unit, the small pallet 26 adopts an octagonal ribbed circular structure with a diameter of 100 cm and a height of 200 mm, both of which are made of 40 mm thick steel plates.

[0031] See also Figure 7 The load box 25 is composed of a 500 t hydraulic jack, which is placed on a small pallet 26 in a triangular position.

[0032] See also Figure 8 The casing 22 is a thin-walled cylinder with a height of 1 m-1.5 m and a wall thickness of 1 cm, and a hole groove with a diameter of 3 cm-5 cm is reserved on the side wall.

[0033] See also Fig. 9 The large pallet 21 has eight sides with ribs. The top and bottom plates are both square with side lengths of 2 m and 1 m respectively. Four holes are reserved in the top and bottom plates with a diameter of 60 mm and a hole center spacing of 1060 mm. They are all made of 40 mm thick steel plates.

[0034] See also Figure 1 , pour the cushion layer to the height of the top surface of the large support plate 21, install the steel bars of the pedestal 3 and arrange the steel bars of the bored pile 2 after the cushion layer reaches the design strength, build the reference beam 12 and the displacement meter 11 after the construction of the pedestal 3 is completed and maintained to reach the design strength, and start the static load test of the large-diameter pipe pile 1. Through the static load test of the engineering pile anchor pile method: the static load test method of the bored pile anchoring pedestal-large-diameter pipe pile reaction force, the pile top load-pile top settlement curve of the test pile is obtained, and according to the data obtained by the fiber grating sensor 41, the variation curves of the pile body axial force and the lateral friction resistance with the depth and time are analyzed, and the long-term bearing characteristics of the large-diameter pipe pile 1 are analyzed.

[0035] The construction steps of the static load test device for connecting the large-diameter pipe pile and the foundation of the pedestal include: step 1, symmetrically cutting grooves on the outer wall of the large-diameter pipe pile 1 to pre-embed the fiber optic Bragg grating sensor 41 and the thermal imaging sensor 42, hammering the large-diameter pipe pile 1 to the designed elevation and then constructing the bored pile 2, excavating the soil layer to expose the pile head of the large-diameter pipe pile 1, and making a steel cage 5 with a height of 3 times the pile diameter according to the size, the steel cage 5 is fixed by 7 horizontal annular stirrups 54 and 8 vertical U-shaped steel bars 56, and the vibration sensor 52 is respectively fixed on the second, fourth and sixth horizontal annular stirrups 54 (from the bottom to the top), and the first steel plate 55 is welded to the bottom of the steel cage 5 to seal the bottom to prevent leakage of the bottom, and the rubber sleeve 53 is wrapped around the edge, and after the steel cage 5 is installed, concrete is poured to form a filling. Filling 51; Step 2: Check the survival rates of the vibration sensor 52, the fiber grating sensor 41 and the thermal imaging sensor 42, and use rubber pipes to wrap each sensor for protection to form a sensor system 24; Install the clamp 23 on the large diameter pipe pile 1, and install the small support plate 26, the load box 25, the displacement rod 13, the casing 22, the protective sleeve 14 and the large support plate 21 in sequence, and the sensor system 24 passes through the hole groove reserved in the casing 22; Step 3, pour the cushion layer to the height of the top surface of the large support plate 21, install the steel bars of the pedestal 3 and arrange the steel bars of the bored pile 2. After the construction of the pedestal 3 is completed and the maintenance reaches the design strength, build the reference beam 12 and the displacement meter 11, and start the vertical compressive static load test. After the test is completed, the polymer is injected into the pile head of the large diameter pipe pile 1 through the protective sleeve 14.

[0036] It should be noted that the present invention can apply the static load test device as the pile foundation of the high-speed railway bridge, use the vibration sensor 52 to monitor the dynamic characteristics of the pile head of the large diameter pipe pile 1 during the operation of the high-speed railway, and use the fiber optic Bragg grating sensor 41 to monitor the changes in the internal force of the pile body of the large diameter pipe pile 1 during the operation of the high-speed railway. The thermal imaging sensor 42 can be used to collect images in real time and transmit the collected images to the remote control PC end 4, which can intuitively reflect the corrosion state of the large diameter pipe pile 1 in the seawater or saline soil environment, thereby achieving a long-term monitoring effect on the pile foundation of the high-speed railway bridge.

[0037] In some specific embodiments, loading devices such as the small pallet 26, the load box 25, the casing 22 and the large pallet 21 are reserved in the foundation as supports. The load box 25 is a movable device that can supplement the settlement difference when uneven settlement occurs during the operation of the high-speed train. After the static load test is completed, the polymer material is injected into the pile head of the large-diameter pipe pile 1 through the protective sleeve 14. The polymer material is made of raw materials such as polyisocyanate and polyether polyol or polyester polyol. The material expands and solidifies after reaction. The polymer material has the characteristics of high toughness and can achieve a shock-absorbing effect during the operation of the high-speed train. It can be seen that the protective sleeve 14 can not only serve as a moving channel for the displacement rod 13 during the static load test to play a protective role, but also serve as a channel for injecting polymer materials into the load unit at a fixed point after the static load test is completed. The polymer material can be evenly injected around the load unit through the four displacement rods 13. Fig.12 As shown, after the polymer material is injected, the load unit surrounded by the soil layer 33 and the periphery of the large-diameter pipe pile 1 form a polymer material reaction layer 31 and a polymer-soil solidified body 32 respectively, thereby improving the overall strength and earthquake resistance.

[0038] The static load test device for connecting large diameter pipe piles with a cap foundation proposed in the present invention can perform vertical compression static load test on large diameter pipe piles and vertical tensile static load test on large diameter pipe piles after adjusting the construction sequence of the loading device.

[0039] See also Fig.11 After the large-diameter pipe pile 1 is reinforced, the displacement rod 13 and the protective sleeve 14 are respectively welded to the large-diameter pipe pile 1 head according to the reserved hole groove distance of the large support plate 21. The displacement rod 13 passes through the protective sleeve 14 and is fixed by tying the steel bars of the pedestal 3 to strictly control the verticality of the protective sleeve 14. After the construction of the pedestal 3 is completed and maintained to reach the design strength, the large support plate 21, the load box 25, and the small support plate 26 are sequentially built. The other end of the displacement rod 13 away from the large-diameter pipe pile 1 head is welded to the small support plate 26. The displacement data of the four displacement rods 13 are used to intuitively reflect the static pull-out load capacity.

[0040] In this embodiment, the spacing between the protective sleeves 14 is consistent with the distance between the reserved holes and grooves of the large support plate 21, which is convenient for installing the large support plate 21. The top of the protective sleeve 14 is flush with the top of the large support plate 21. The displacement rod 13 is welded to the side of the small support plate 26. The displacement meter 11 records the displacement change of the small support plate 26. The test uses 8 bored cast-in-place piles 2 as anchor piles, and the pull-out bearing characteristics of the large diameter pipe pile 1 are studied through the static load pull-out test of the reaction force of the bored pile anchoring foundation-pipe pile. The test is carried out using the slow maintained load method. After the pull-out static load test is completed, the polymer material is injected into the pile head of the large diameter pipe pile 1 through the protective sleeve 14 to achieve the shock absorption effect.

[0041] The static load test device, monitoring method and application of the connection between the large-diameter pipe pile and the pedestal foundation of the present invention are helpful to improve the scientificity and practicality of the pile foundation design, which can not only optimize the design and construction plan of the high-speed railway bridge, but also track the health status of the pile foundation in real time during operation, and warn of potential risks in advance, thereby ensuring the safety and stability of the high-speed railway bridge. This innovative research will fill the gap in current technology and provide strong support for the research and practice of future high-speed railway bridge pile foundation projects.

[0042] In addition to the above embodiments, the present invention may also have other implementation modes. Any technical solution formed by equivalent replacement or equivalent transformation falls within the protection scope required by the present invention.

Claims

1. A static load test device for connecting a large diameter pipe pile with a cap foundation, comprising a large diameter pipe pile (1), a load unit and a cap foundation (3) connected in sequence from bottom to top, characterized in that: The load unit or large-diameter pipe pile (1) is connected to at least one displacement rod (13) vertically penetrating to the top of the pedestal (3), wherein a steel cage (5) flush with the pipe mouth is arranged on the inner side of the pipe top of the large-diameter pipe pile (1), a first steel plate (55) with an edge wrapped with a rubber sleeve (53) is connected to the bottom of the steel cage (5) to form an upper and lower layer seal, and a plurality of vibration sensors (52) are installed on the steel cage (5), the steel cage (5) is cored to form a filling body (51), and the outer wall of the large-diameter pipe pile (1) is also grooved and embedded with a plurality of fiber optic Bragg grating sensors (41).

2. The static load test device according to claim 1, characterized in that: The load unit comprises at least one load box (25) and a large support plate (21) and a small support plate (26) respectively connected horizontally to two ends of the load box (25).

3. The static load test device according to claim 2, characterized in that: The load boxes (25) are provided in three numbers and arranged in a regular triangle shape. The small support plate (26) is in an octagonal ribbed circular structure, and its bottom surface is adapted to the top surface of the large-diameter pipe pile (1). The large support plate (21) is in an octagonal ribbed square structure, and its bottom surface is connected to the top surfaces of the three load boxes (25), and the top surface of the large support plate (21) is connected to the bottom surface of the base (3).

4. The static load test device according to claim 3, characterized in that: The small support plate (26) is composed of two parallel circular support plates and eight straight ribs vertically connecting the two, and the large support plate (21) is composed of an upper support plate, a lower support plate and eight inclined ribs vertically connecting the two.

5. The static load test device according to claim 3, characterized in that: A total of four displacement rods (13) are provided and are evenly connected to the small support plate (26). The four displacement rods (13) are arranged around the outside of the three load boxes (25), and four protective sleeves (14) are passed through the support platform (3) and the large support plate (21) to provide space for the displacement rods (13) to move.

6. The static load test device according to claim 1, characterized in that: It also includes a reference beam (12) arranged above the pedestal (3), the reference beam (12) being provided with displacement meters (11) matching the number of displacement rods (13), the bottom surface of the pedestal (3) being further connected with a plurality of bored cast-in-place piles (2) providing reaction force, a clamp (23) being wrapped and installed on the outer wall of the pipe mouth of the large-diameter pipe pile (1), and a fiber optic Bragg grating sensor (41) and a thermal imaging sensor (42) being evenly grooved and installed on the outer wall of the large-diameter pipe pile (1).

7. The static load test device according to claim 1, characterized in that: The steel cage (5) is composed of a plurality of horizontal annular stirrups (54) connected to a plurality of vertical U-shaped steel bars (56) to form a cage-like structure, and the vibration sensors (52) are symmetrically arranged on the horizontal annular stirrups (54).

8. The static load test device according to claim 1, characterized in that: The large-diameter pipe pile (1), the cap (3) and the load unit are connected in sequence from bottom to top, and one end of the displacement rod (13) is connected to the large-diameter pipe pile (1) and the other end is connected to the load unit.

9. The method for monitoring a static load test device according to claim 6, characterized in that: The static load test device is used as the pile foundation of a high-speed railway bridge, a vibration sensor (52) is used to monitor the dynamic characteristics of the pile head of the large-diameter pipe pile (1) during the operation of the high-speed railway, a fiber optic Bragg grating sensor (41) is used to monitor the change of the internal force of the pile body of the large-diameter pipe pile (1) during the operation of the high-speed railway, and a thermal imaging sensor (42) is used to monitor the corrosion state of the large-diameter pipe pile (1) in a corrosive environment.

10. Application of a static load test device as a pile foundation in a high-speed railway bridge, characterized in that: The static load test device is specifically the static load test device according to claim 5, wherein the application also includes injecting a polymer material into the pile head of the large diameter pipe pile (1) through a protective sleeve (14), causing the polymer material to react, expand and solidify, and the load unit surrounded by the soil layer (33) and the periphery of the large diameter pipe pile (1) respectively form a polymer material reactant layer (31) and a polymer-soil solidified body (32).