Disassembly evaluation model analysis method for waste and old electric power materials

By constructing a dismantling and evaluation model for power waste materials, evaluating dismantling costs and recycling value, the economic benefits assessment problem before dismantling power waste materials is solved, scientific dismantling judgment and resource recycling are realized, and the safety of the power grid is improved. and environmental protection level.

CN119047861APending Publication Date: 2024-11-29TIANJIN RICHSOFT ELECTRIC POWER INFORMATION TECH +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410912138.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-09
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

The existing technology lacks effective mathematical models and calculation methods to evaluate the economic benefits and feasibility of dismantling power waste materials before dismantling, resulting in waste of resources and environmental pollution, affecting the safety and reliability of the power grid.

Method used

Construct an evaluation model for dismantling and evaluation of electricity waste materials. By defining the dismantling cost and the recycling value of the product after dismantling, a mathematical model is established to guide the dismantling and treatment method, including assumptions, construction of evaluation index systems, dismantling costs and specific recycling value algorithm to form an objective function that maximizes the disassembly benefits.

Benefits of technology

It has achieved scientific evaluation of waste materials before dismantling, improved the rationality and efficiency of the dismantling process, reduced resource waste and environmental pollution, and improved the resource recycling level and safety guarantee capabilities of power enterprises.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119047861A_ABST
    Figure CN119047861A_ABST
Patent Text Reader

Abstract

The invention discloses a disassembly evaluation model analysis method for waste and old electric power materials, and the method comprises the steps: defining the cost generated in a disassembly process as disassembly cost M1, defining the earnings after the disassembly of the waste and old materials through bidding auction as disassembled product recovery value M2, building a model to obtain the disassembled benefit EB, and carrying out the analysis of the disassembly evaluation model of the waste and old electric power materials. The method is used for guiding a post-disassembly treatment mode of the electric power waste and old materials by the post-disassembly benefit EB, and comprises the following steps: S1, proposing an assumption: S2, in order to complete pre-disassembly evaluation of the waste and old materials, carrying out detailed analysis on the disassembly cost M1 by a project, and constructing an evaluation index system; according to the method, the economic benefits before the waste and old materials are disassembled are evaluated and analyzed, the disassembling feasibility is clear, reasonable judgment before the materials are disassembled is achieved, and a theoretical basis for disassembling the waste and old materials is provided for power enterprises.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of environmental assessment, and in particular to a disassembly assessment model analysis method for waste power materials. Background Art

[0002] State Grid Corporation of China requires all units within the system to strengthen the management of scrapped materials and strictly implement the State Grid Corporation's work regulations of "dismantling and destroying scrapped materials such as distribution transformers, electricity meters, and cables according to professional requirements to prevent them from flowing back into the power grid." In order to establish and improve a recycling system for waste power materials, prevent the backflow of scrapped materials into the power grid, improve the level of resource recycling, enhance resource security capabilities, and promote green, low-carbon, circular development, State Grid Corporation of China has formulated the "State Grid Corporation of China's Requirements for Further Strengthening the Standardized Management of the Whole Process Disposal of Idle Waste Materials" to create a physical digital resource pool for the entire network, and continuously promote the intensive, standardized, green, digital and intelligent management of idle waste resource disposal and risk prevention and control, driving the supply chain to help the company improve quality and efficiency.

[0003] With the rapid development of intelligent and smart power grids, the speed of replacement of power materials and equipment has also increased. In order to ensure the safe and reliable operation of the power grid, the quality and safety requirements of power equipment are increasing. As a result, a large number of retired and idle power materials are piled up in warehouses, causing waste of resources. The existing treatment methods are mostly based on violent and extensive disassembly, while the disassembly of precision components in intelligent power equipment requires a more refined disassembly process, making traditional extensive disassembly no longer applicable. The efficient recycling of waste materials is a sustainable and circular economic development concept that can effectively reduce energy consumption and waste emissions, and achieve the goal of energy conservation, emission reduction and green manufacturing. Faced with a large number of retired and idle power materials, how to improve the disassembly efficiency in a green and efficient manner and promote the standardization and normalization of waste material disassembly mainly involves the following problems:

[0004] (1) At present, no provincial grid company in the State Grid system has a mathematical model for pre-dismantling and process evaluation. In reality, most provincial grid companies package transformer oil and transformer bodies for disposal, making it difficult to store waste transformer oil, and it is impossible to dismantle electricity meters and transformers in a centralized and standardized manner after they are scrapped.

[0005] (2) After the power materials are retired, most of them are piled up in warehouses of various power companies, causing inventory pressure and safety hazards. In the past, the disposal of scrapped materials of the power grid was done by bidding and selling by each power supply company. There were almost no dismantling centers in power grid enterprises to conduct detailed calculations on whether the economic value after dismantling was greater than the various costs consumed during the dismantling process. Some companies have established dismantling centers, but they lack appropriate mathematical models and calculation methods in the dismantling and sorting process. As long as there are recyclable materials, they are uniformly dismantled regardless of whether they have dismantling value. The phenomenon of non-compliant disposal causing environmental pollution will inevitably produce waste materials that are "refurbished" and then flow back to the power grid, which has a great impact on the safety and reliability of the power grid.

[0006] In response to the above problems, how to evaluate and analyze the economic benefits of waste materials before dismantling, clarify the feasibility of dismantling, and make reasonable judgments before dismantling materials has become a technical problem that needs to be urgently solved by people in this field. Summary of the invention

[0007] The purpose of the present invention is to overcome the shortcomings of the prior art and provide a disassembly evaluation model analysis method for power waste materials. The method evaluates and analyzes the economic benefits of waste materials before disassembly, clarifies the feasibility of disassembly, makes reasonable judgments before disassembling materials, and provides a theoretical basis for the disassembly of waste materials for power companies.

[0008] A disassembly evaluation model analysis method for power waste materials is provided. Various costs generated during the disassembly process are defined as disassembly costs M1, and the benefits after the disassembly of the waste materials through bidding and auction are defined as the post-disassembly product recovery value M2. A model is constructed to obtain the post-disassembly benefit EB, and the post-disassembly benefit EB is used to guide the post-disassembly treatment of power waste materials, including the following steps:

[0009] S1. Propose a hypothesis:

[0010] (1) The waste materials to be dismantled do not contain gases and chemical components that are harmful to the human body. If they do, dismantling is not recommended;

[0011] (2) During the disassembly operation, each disassembly operation should not affect the adjacent operation;

[0012] (3) The conversion time between disassembly tools is not counted;

[0013] (4) The value of disassembled parts and products is low when they are recycled and can be ignored;

[0014] S2. To complete the pre-dismantling assessment of waste materials, the project conducts detailed analysis of the dismantling cost M1 and constructs an evaluation index system;

[0015] S3. Build the model:

[0016] maxf(EB)=maxf(M2)-minf(M1)

[0017] Mathematical models are constructed based on the characteristics of dismantling cost M1 and post-dismantling product recovery value M2;

[0018] In the step S3,

[0019] Through the regression analysis model, the prediction model of the post-disassembly product recovery value M2 is obtained:

[0020] f(S)=G 铜 ×p 铜 +G 钢铁 ×p 钢铁

[0021] Among them, G is the total weight of the material, and p is the reference price of material recycling; by extension, assuming that the equipment contains m kinds of heavy metal materials, the valuation model is:

[0022] f(S)=G1×p1+…+Gm×pm

[0023] The meanings of the model parameters are as follows: f(S) is the price of recycled products after the dismantling of waste materials; p is the reference price of materials; G is the weight of various materials in the quota;

[0024]

[0025] Preferably, the disassembly cost M1 in step S2 is the sum of the operating cost and the energy consumption cost of the entire process from receiving the disassembly plan to completing the disassembly, expressed as: disassembly cost = disassembly operating cost + disassembly energy consumption cost.

[0026] Preferably, the specific algorithm for disassembling the operating cost is:

[0027] The total cost M1 of dismantling each piece of waste material at the dismantling station is the sum of the labor cost C1 of the waste material, the site cost C2, the loss cost of the dismantling tools C3, and the distribution cost C4;

[0028] The labor cost C1 for dismantling each piece of waste material is:

[0029]

[0030] Where T is the disassembly time required for the i-th disassembly task to be performed on the j-th device, W1 is the labor cost per hour, in RMB;

[0031] The site cost C2 for dismantling each piece of waste material is:

[0032]

[0033] Where: W2 is the monthly rental cost of the disassembly workshop; a is the number of workstations placed in the disassembly workshop;

[0034] The cost of dismantling tools for dismantling each piece of waste material is:

[0035]

[0036] The transportation cost C4 for dismantling each piece of waste material is:

[0037] C4=M0*l e

[0038] Where: M0 is the transportation cost per unit distance, l e The distance from the dismantling to the destination.

[0039] The disassembly operation cost is obtained from the above formula:

[0040]

[0041] Preferably, the specific algorithm for disassembling the energy consumption cost is:

[0042] The energy consumption cost of dismantling waste electrical materials includes the sum of electricity consumption C5, water resource consumption C6, and oil, diesel, and gasoline consumption C7.

[0043] The electricity consumption cost C5 for dismantling each piece of waste material is:

[0044] C5=N0T*1.025×0.8

[0045] Where: N0 is the power consumption required for disassembly per unit time;

[0046] The water resource consumption cost C6 for dismantling each piece of waste material is:

[0047] C6=Q0T*4.1

[0048] Where: Q0 is the water consumption required for dismantling per unit time;

[0049] The oil consumption cost C7 for dismantling each piece of waste material is:

[0050] C7=R0T*8.5

[0051] Where: R0 is the total consumption of engine oil, diesel and gasoline required for dismantling per unit time;

[0052] The disassembly energy consumption cost M2 is obtained from the above formula:

[0053] M2=C5+C6+C7

[0054] =N0T*1.025×0.8+Q0T*4.1+R0T*8.5

[0055] =12.6*T(N0+Q0+R0).

[0056] The advantages and technical effects of the present invention are:

[0057] (1) After analyzing and comparing the three basic methods of market method, income method and replacement cost method, the present invention conducts a detailed analysis of the dismantling cost to complete the pre-dismantling evaluation of waste materials, innovatively constructs a dismantling cost evaluation index system, and realizes a scientific evaluation of the dismantling cost of waste materials.

[0058] (2) Based on the different service life, operating conditions and damage degree of equipment, the diverse categories of power materials, the various materials involved have the characteristics of structural variability, diversity of disassembly information and complexity of component types, the present invention analyzes the relevant factors existing in the disassembly process, scientifically constructs an evaluation model that reflects the actual disassembly performance of power materials, and realizes reasonable judgment before disassembling materials.

[0059] (3) Currently, 10 provincial companies within the State Grid have built green dismantling centers, and 14 pilot green dismantling and sorting centers have been completed in the province. The remaining 17 provincial companies are in the process of investigation and planning. Most of the green dismantling centers that have been built are in the initial stage, with low levels of scientific control and refined management. There is no research on how to reasonably calculate the dismantling cost in the dismantling process. There is no available model for how to calculate and evaluate the green and low-carbon nature of the dismantling process. Based on the cost and benefit research of the entire life cycle of the dismantling process, the present invention forms a pre-dismantling evaluation model suitable for the dismantling center of power waste materials, which provides method support for the scientific evaluation and lean management of the dismantling centers of power companies in various provinces. BRIEF DESCRIPTION OF THE DRAWINGS

[0060] Figure 1 It is a schematic diagram of the disassembly process of the waste transformer in the present invention;

[0061] Figure 2 It is a schematic diagram of the framework of the disassembly cost evaluation index system in the present invention. DETAILED DESCRIPTION

[0062] In order to further understand the content, characteristics and effects of the present invention, the following embodiments are given for detailed description. It should be noted that the embodiments are illustrative, not restrictive, and the protection scope of the present invention cannot be limited thereby.

[0063] As power companies are large energy users, they have a large number of power-consuming equipment. Disassembly is a prerequisite for efficient recycling and the key to resource reuse. Due to the different service life, operating conditions and degree of damage of equipment, the variety of power materials, the various materials involved have the characteristics of structural variability, diversity of disassembly information and complexity of parts types, and there are many uncertain factors in the disassembly process. The present invention innovatively proposes a pre-disassembly evaluation model and method for power waste materials to achieve reasonable judgment before disassembling materials.

[0064] The present invention adopts the following technical solutions:

[0065] Step 1: Formulate a hypothesis

[0066] The general description of the waste material pre-dismantling assessment problem is as follows: After the waste materials are decommissioned and scrapped, they need to be classified first. According to the different materials that make up the materials, the materials are divided into single-component materials and multi-material materials. The most typical single-component materials are cables, and the typical multi-material materials are transformers. According to the classified materials, it is necessary to calculate the feasibility of dismantling, whether it is worth dismantling, and whether the economic value after dismantling is higher than the various costs incurred during the dismantling process. In this study, the ultimate goal to be achieved is defined as the post-dismantling benefit (EB), the various costs incurred during the dismantling process are defined as the dismantling cost (M1), and the income after the waste materials are dismantled through bidding and auction is defined as the post-dismantling product recovery value (M2). For the convenience of research, the present invention proposes the following assumptions:

[0067] (1) The waste materials to be dismantled do not contain gases and chemical components that are harmful to the human body. If they do, dismantling is not recommended;

[0068] (2) During the disassembly operation, each disassembly operation should not affect the adjacent operation;

[0069] (3) The conversion time between disassembly tools is not counted;

[0070] (4) The value of disassembled parts and components is low when they are recycled and can be ignored.

[0071] Step 2: Build an evaluation index system

[0072] In order to complete the pre-dismantling assessment of waste materials, the project conducted a detailed analysis of the dismantling cost (M1) and constructed an evaluation index system.

[0073] (1) Operating cost indicator system

[0074] Among the many influencing factors of the operating cost evaluation, four main factors are selected as input indicators and one output indicator. The input indicators include: dismantling personnel cost, machinery loss cost, equipment maintenance cost, and transportation cost. Employee cost refers to the salary cost of hiring dismantling personnel; machinery loss cost includes equipment damage, aging, consumables, etc.; equipment maintenance cost refers to the maintenance cost incurred by the damage of dismantling equipment caused by the dismantling of materials during the dismantling process; transportation cost refers to a series of transportation costs required to meet the dismantling process. The output indicator is the fixed cost, that is, the fixed cost generated by dismantling, and the smaller the value, the better.

[0075] (2) Energy consumption cost indicator system

[0076] There are many influencing factors in the energy consumption cost evaluation of the disassembly process. Through literature research on the selection of disassembly environmental value indicators, this study selected four influencing indicators as input variables, namely electricity consumption, fuel consumption, water consumption, and chemical consumables. Electricity consumption refers to the power consumption of equipment during the disassembly process; fuel consumption includes fuel oil and lubricating oil used in disassembly equipment; water consumption includes product pretreatment, parts cleaning, and water spraying and cooling in storage areas; chemical consumables include organic solvents, acids, and alkalis used to clean parts; energy consumption cost is the output variable, that is, the energy consumption used in the process of disassembling parts of the product. The smaller its value, the smaller the energy consumption cost.

[0077] Step 3: Build the model

[0078] Among them, there are two key factors involved in the present invention mentioned in step 1, namely, the dismantling cost (M1) generated during the dismantling process and the recovery value of the dismantled products after the waste materials are dismantled through bidding and auction (M2). In order to maximize the dismantling benefit (EB), that is:

[0079] max f(EB)=max f(M 2)-min f(M1)

[0080] The present invention constructs mathematical models for the disassembly cost (M1) and the post-disassembly product recovery value (M2) according to their characteristics.

[0081] (1) Product recovery value after dismantling

[0082] At present, the standardized material library has 20 major categories, more than 250 medium categories, and more than 3,000 minor categories. When it comes to materials, there are nearly 100,000 items. Whether it is a 35kV substation or a 110kV substation, cables and transformers account for a large proportion, followed by switch cabinets. Through the investigation of the dismantling centers of various power grids and provinces, the different types of dismantled materials determine the main product composition of the dismantled materials. Among them, they are mainly divided into two categories. One is the power cable materials with simple and clear raw material ratios, which are greatly affected by raw material prices and have large fluctuations in raw material prices compared to other power transmission and transformation materials. The main component is copper. The other is the waste materials of equipment such as transformers and circuit breakers with more raw material ratios. Among them, the raw materials of transformers are mainly silicon steel sheets and electromagnetic wires, and the raw materials of circuit breakers are mainly low-alloy steel plates, zinc ingots, etc.

[0083] Through research, it is found that the market transaction price of waste materials in the country varies with different regions and time. When judging the price of materials, it is necessary to fully consider the differences in regions and time. Ignoring the differences between regions, taking the average transaction price of major waste material trading markets across the country as a reference, it is found that the price fluctuation of the waste market is smaller than the price fluctuation of the spot market and futures market in the same period, and the price of the waste market lags slightly behind the changes in the futures market and spot market. Through the regression analysis model, the prediction model of the recycling value of dismantled products is obtained:

[0084] f(S)=G 铜 ×p 铜 +G 钢铁 ×p 钢铁

[0085] Among them, G is the total weight of the material, and p is the reference price of material recycling. By extension, assuming that the equipment contains m kinds of heavy metal materials, the valuation model is:

[0086] f(S)=G1×p1+…+G m ×p m

[0087] The meanings of the model parameters are as follows: f(S) is the price of recycled products after dismantling waste materials; p is the reference price of materials; G is the weight of various materials in the quota.

[0088]

[0089] (2) Cost of dismantling waste materials

[0090] Based on the evaluation index system formed after the above analysis of the disassembly cost dimensions, the disassembly cost model is constructed according to the cost analysis method. The disassembly cost mainly includes operating cost (M1) and energy consumption cost (M2). The operating cost includes four key core factor indicators: personnel cost (C1), site cost (C2), mechanical loss cost (C3), and transportation cost (C4); the energy consumption cost includes three key core factor indicators: electricity consumption (C5), water consumption (C6), and oil consumption (C7).

[0091] The electricity consumption cost is based on the actual usage of a single dismantling plan and the unit price per kWh in the region in that year. The water consumption cost is determined by the actual usage of a single dismantling plan and the water fee per ton in the local area. The oil consumption cost is calculated based on the actual amount of oil used for different regular models and the local oil price.

[0092] The cost of the waste material dismantling process is the sum of the operating cost and energy consumption cost from receiving the dismantling plan to completing the dismantling process. That is:

[0093] Dismantling cost = dismantling operation cost + dismantling energy consumption cost

[0094] 1) Break down operating costs

[0095] The total cost M1 of disassembling each piece of waste material at the disassembly station is the sum of the labor cost C1 of the waste material, the site cost C2, the disassembly tool loss cost C3, and the distribution cost C4.

[0096] The labor cost C1 for dismantling each piece of waste material is:

[0097]

[0098] Where T is the disassembly time required for the i-th disassembly task to be performed on the j-th device, W1 is the labor cost per hour, in RMB;

[0099] The site cost C2 for dismantling each piece of waste material is:

[0100]

[0101] Where: W2 is the monthly rental cost of the disassembly workshop; a is the number of workstations placed in the disassembly workshop.

[0102] The cost of dismantling tools for dismantling each piece of waste material is:

[0103]

[0104] The transportation cost C4 for dismantling each piece of waste material is:

[0105] C4=M0*l e

[0106] Where: M0 is the transportation cost per unit distance, l e The distance that the parts and components need to be delivered to the destination after disassembly.

[0107] The disassembly operation cost is obtained from the above formula:

[0108]

[0109] 2) Breaking down energy consumption costs

[0110] The energy consumption cost of dismantling waste electrical materials includes the sum of electricity consumption (C5), water resource consumption (C6), and oil, diesel, and gasoline consumption (C7).

[0111] The electricity consumption cost C5 for dismantling each piece of waste material is:

[0112] C5=N0T*1.025×0.8

[0113] Where: N0 is the power consumption required for disassembly per unit time.

[0114] The water resource consumption cost C6 for dismantling each piece of waste material is:

[0115] C6=Q0T*4.1

[0116] Where: Q0 is the water consumption required for disassembly per unit time.

[0117] The oil consumption cost C7 for dismantling each piece of waste material is:

[0118] C7=R0T*8.5

[0119] Where: R0 is the total amount of oil, diesel and gasoline required for disassembly per unit time.

[0120] The disassembly energy consumption cost M2 is obtained from the above formula:

[0121] M2=C5+C6+C7

[0122] =N0T*1.025×0.8+Q0T*4.1+R0T*8.5 In order to more clearly illustrate the specific implementation of the present invention, the following

[0123] =12.6*T(N0+Q0+R0)

[0124] Provide an embodiment:

[0125] The present invention provides a disassembly evaluation model analysis method for waste power materials.

[0126] (1) Taking transformer materials as an example, the mathematical model constructed above is used for verification. The principle of verification is to construct the recycling value and dismantling cost of the waste transformer after dismantling. By collecting various cost data incurred in the previous transformer dismantling process and estimating the recycling price of dismantled parts products in the future, the cost data of the dismantling process is calculated and the price trend chart of the cost model is used to match the trend chart of the recycling value after dismantling. The feasibility of dismantling is judged based on the trend matching situation.

[0127] (2) The dismantling process of waste transformers is as follows Figure 1 The specific process is as follows:

[0128] 1) Manually use a forklift to transport the transformer from the temporary storage area to the designated location; 2) When the transformer arrives at the designated location, manually use a crane to lift the transformer to the disassembly platform; 3) Drain the oil from the transformer; 4) Manually use a cantilever crane and other tools to disassemble the transformer and separate the shell; 5) Transfer the separated shell and coil winding to the oil filtering area for oil filtering; 6) Clean the shell and coil winding after oil filtering; 7) Manually disassemble and pack the cleaned winding on the disassembly platform using tools; 8) Package and compress the cleaned shell.

[0129] (3) Determine the key factors for transformer disassembly

[0130] 1) The key factors of transformer disassembly mainly include two aspects: operating cost evaluation and energy consumption cost evaluation. Among the many influencing factors of operating cost evaluation, four main factors are selected as input indicators and one output indicator. Input indicators include: disassembly personnel cost, mechanical loss cost, equipment maintenance cost, and transportation cost. Employee cost refers to the salary cost of hiring disassembly personnel; mechanical loss cost includes equipment damage, aging, consumables, etc.; equipment maintenance cost refers to the maintenance cost incurred by the damage of disassembly equipment caused by material disassembly during the disassembly process; transportation cost refers to a series of transportation costs required in the disassembly process. The output indicator is the fixed cost, that is, the fixed cost generated by disassembly, and the smaller the value, the better.

[0131] 2) There are many influencing factors in the energy cost index system. Through the study of the selection of dismantling environmental value indicators, this study selected four influencing indicators as input variables, namely electricity consumption, fuel consumption, water consumption, and chemical consumables. Electricity consumption refers to the power consumption of equipment during the dismantling process; fuel consumption includes fuel oil and lubricating oil used in dismantling equipment; water consumption includes product pretreatment, parts cleaning, and water spraying and cooling in storage areas; chemical consumables include organic solvents, acids, and alkalis used to clean parts; energy cost is used as the output variable, that is, the energy consumption used in the process of disassembling parts of the product. The smaller the value, the lower the energy cost. The specific evaluation index system is as follows: Figure 2shown.

[0132] 3) Determine the disassembly benefit function

[0133] Combined with the recycling and auction of each component product after dismantling, the evaluation of waste materials before dismantling in this project is mainly based on the comparison of dismantling process cost and recycling value, and the following assumptions are made:

[0134] Hypothesis 1: If the cost of the disassembly process is much greater than the value of the product after disassembly, then this disassembly task is not disassemblyable;

[0135] Hypothesis 2: If the cost of the disassembly process is slightly greater than the value of the product after disassembly, then it is not disassemblyable from the perspective of economic value, but further analysis can be conducted based on the properties of the disassembled equipment and the value of the assets;

[0136] Assumption 3: If the cost of the disassembly process is less than the value of the product after disassembly, then this disassembly task has disassembly value.

[0137] Based on the dismantling recycling benefits, dismantling operating costs and dismantling energy consumption cost models, this project determines whether a dismantling task is feasible. Through the analysis and research of the above various mathematical methods, the following calculation method is formulated:

[0138] Disassembly benefit = product recovery value after disassembly - disassembly cost

[0139] = Product recovery value after dismantling - (dismantling operation cost + dismantling energy consumption cost)

[0140] This will establish the deep optimization goal of dismantling waste electrical materials:

[0141] Where: f(x) is the objective function; S is the recovery income value of parts and components after dismantling materials, RMB; M1 is the operating cost of dismantling materials (personnel cost, equipment loss and maintenance fee, and transportation cost corresponding to the dismantling plan), RMB; M2 is the energy consumption cost, RMB.

[0142] Finally, all the parts not described in the present invention adopt mature products and mature technical means in the prior art.

[0143] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all these improvements and changes should fall within the scope of protection of the appended claims of the present invention.

Claims

1. A disassembly evaluation model analysis method for power waste materials, characterized by: The various costs generated during the dismantling process are defined as the dismantling cost M1, and the benefits after the dismantling of the waste materials through bidding and auction are defined as the post-dismantling product recovery value M2. A model is constructed to obtain the post-dismantling benefit EB, and the post-dismantling benefit EB is used to guide the post-dismantling treatment of power waste materials, including the following steps: S1. Propose a hypothesis: (1) The waste materials to be dismantled do not contain gases and chemical components that are harmful to the human body. If they do, dismantling is not recommended; (2) During the disassembly operation, each disassembly operation should not affect the adjacent operation; (3) The conversion time between disassembly tools is not counted; (4) The value of disassembled parts and products is low when they are recycled and can be ignored; S2. To complete the pre-dismantling assessment of waste materials, the project conducts detailed analysis of the dismantling cost M1 and constructs an evaluation index system; S3. Build the model: max f(EB)=max f(M2)-min f(M1) Mathematical models are constructed based on the characteristics of dismantling cost M1 and post-dismantling product recovery value M2; In the step S3, Through the regression analysis model, the prediction model of the post-disassembly product recovery value M2 is obtained: f(S)=G 铜 ×p 铜 +G 钢铁 ×p 钢铁 Among them, G is the total weight of the material, and p is the reference price of material recycling; by extension, assuming that the equipment contains m kinds of heavy metal materials, the valuation model is: f(S)=G1×p1+…+Gm×pm The meanings of the model parameters are as follows: f(S) is the price of recycled products after the dismantling of waste materials; p is the reference price of materials; G is the weight of various materials in the quota; 2. The method for disassembly assessment model analysis of power waste materials according to claim 1 is characterized by: The dismantling cost M1 in step S2 is the sum of the operating cost and the energy consumption cost from receiving the dismantling plan to completing the dismantling, expressed as: dismantling cost = dismantling operating cost + dismantling energy consumption cost.

3. The method for disassembly assessment model analysis of power waste materials according to claim 2 is characterized by: The specific algorithm for dismantling the operating cost is: The total cost M1 of dismantling each piece of waste material at the dismantling station is the sum of the labor cost C1 of the waste material, the site cost C2, the loss cost of the dismantling tools C3, and the distribution cost C4; The labor cost C1 for dismantling each piece of waste material is: Where T is the disassembly time required for the i-th disassembly task to be performed on the j-th device, W1 is the labor cost per hour, in RMB; The site cost C2 for dismantling each piece of waste material is: Where: W2 is the monthly rental cost of the disassembly workshop; a is the number of workstations placed in the disassembly workshop; The cost of dismantling tools for dismantling each piece of waste material is: The transportation cost C4 for dismantling each piece of waste material is: C4=M0*l e Where: M0 is the transportation cost per unit distance, l e The distance from the dismantling to the destination. The disassembly operation cost is obtained from the above formula:

4. The method for disassembly assessment model analysis of power waste materials according to claim 2 is characterized by: The specific algorithm for disassembling the energy consumption cost is: The energy consumption cost of dismantling waste electrical materials includes the sum of electricity consumption C5, water resource consumption C6, and oil, diesel, and gasoline consumption C7. The electricity consumption cost C5 for dismantling each piece of waste material is: C5=N0T*1.025×0.8 Where: N0 is the power consumption required for disassembly per unit time; The water resource consumption cost C6 for dismantling each piece of waste material is: C6=Q0T*4.1 Where: Q0 is the water consumption required for dismantling per unit time; The oil consumption cost C7 for dismantling each piece of waste material is: C7=R0T*8.5 Where: R0 is the total amount of oil, diesel and gasoline required for dismantling per unit time; the dismantling energy consumption cost M2 obtained from the above formula is: M2=C5+C6+C7 =N0T*1.025×0.8+Q0T*4.1+R0T*8.5 =12.6*T(N0+Q0+R0).

Citation Information

Cited By

  • Distribution transformer refined recovery decision-making method and system

    CN120125225A