Transfer platform beam erecting device crossing existing railway line

By using climbing platforms, elevators and multi-functional fastening components in the conversion platform beam mount device, the problems of operator safety and beam mount accuracy when spanning existing railway lines are solved, and a safe and efficient beam mount is achieved Erection and multifunctional applicability.

CN119059435APending Publication Date: 2024-12-03CHINA RAILWAY 24TH BUREAU GROUP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411034757.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

When crossing the existing railway line, setting up the conversion platform and performing beam body mounts will occupy the railway line space, making it difficult for operators to ensure safety during non-blocking periods, and there is a visual blind spot and accident risk.

Method used

A conversion platform beam device including counterweight base, drive turntable, operating table, vertical frame, climbing area, climbing platform and hoist is designed. The operator can be lifted and lowered safely through the climbing platform and hoist, eliminating visual blind spots. And smooth and precise beam lifting and fixing are achieved through cylinders, slide rails, electric hoists and limit frames.

Benefits of technology

It effectively avoids the risk of accidents during the non-blocking period of the railway line, ensures the safety of operators, improves the accuracy and efficiency of operations, and adapts to beam bodies of different sizes through multi-functional fastening components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119059435A_ABST
    Figure CN119059435A_ABST
Patent Text Reader

Abstract

The invention discloses a conversion platform beam erecting device stretching across an existing railway line, and relates to the technical field of railway auxiliary installation, the conversion platform beam erecting device comprises a counterweight base, a driving turntable is rotatably arranged on the counterweight base, an operation table is fixedly installed on the upper surface of the driving turntable, a vertical frame is vertically arranged on the upper surface of the operation table, and a control platform is arranged on the top of the vertical frame; a climbing area is formed among the operation table, the vertical frame and the control platform, and a climbing table and a lifting machine used for lifting the climbing table are arranged on the operation table and located in the climbing area in a lifting mode. The device has the effect of ensuring the safety of operators.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of railway auxiliary installation, and in particular to a conversion platform beam erecting device spanning an existing railway line. Background Art

[0002] The transfer platform beam erection device is an engineering equipment mainly used for erecting bridges or replacing bridge beams during railway construction and maintenance. Its main feature is that it can be constructed without interrupting the normal operation of the railway, which is particularly important for projects that require bridge replacement or new bridge construction on existing railway lines.

[0003] At present, when the beam erection operation is carried out on the existing railway line, first, during the non-blocking period of the existing railway line, continuous thin-walled bridge piers are symmetrically set up along the longitudinal sides of the existing railway line; a beam feeding platform is pre-erected outside the thin-walled bridge pier on one side of the existing railway line, and a beam body to be erected is prepared on the beam feeding platform, and the horizontal height of the beam body is more than 2m higher than the height of the contact network of the existing railway line; then during the blocking period of the existing railway line, a cantilever gantry crane that can move longitudinally is set across the direction of the existing railway line, and a front crane and a rear crane are set on the main beam of the cantilever gantry crane; and during the blocking period of the existing railway line, the front and rear double cranes on the main beam of the cantilever gantry crane are used to move the beam body to be erected on the beam feeding platform laterally, and quickly and accurately erect it on the symmetrical thin-walled bridge piers to form a beam body in place; until the number of erected beam bodies in place reaches at least 4.

[0004] However, when crossing an existing railway line, erecting a transfer platform and installing beams will occupy space on the railway line. During non-blocked hours, operators will be located on the ground of the railway line, which will result in visual blind spots and make it difficult to ensure the safety of operators. Summary of the invention

[0005] The present application provides a transition platform beam erecting device across an existing railway line, which has the function of ensuring the safety of operators.

[0006] The present application provides a transfer platform beam erection device across an existing railway line, which adopts the following technical solution: A transfer platform beam erecting device spanning an existing railway line comprises a counterweight base, a driving turntable is rotatably provided on the counterweight base, an operating platform is fixedly mounted on the upper surface of the driving turntable, a vertical frame is vertically provided on the upper surface of the operating platform, a control platform is provided on the top of the vertical frame, a climbing area is formed between the operating platform, the vertical frame and the control platform, a climbing platform and a hoist for lifting the climbing platform are provided on the operating platform and located in the climbing area.

[0007] By adopting the above technical solution, operators can safely ascend and descend through the climbing platform and the hoist, avoiding the risk of accidents caused by climbing and descending when the railway line is not blocked; operators can perform various operations on the climbing platform, eliminating visual blind spots and limiting the operator's range of activities, thereby ensuring the safety of the operator.

[0008] Preferably, at least two guardrails are provided on the upper surface of the climbing platform.

[0009] By adopting the above technical solution, the guardrail can provide additional safety protection to prevent operators from accidentally falling or slipping on the climbing platform.

[0010] Preferably, a first cylinder is vertically provided on the upper surface of the operating table, an output end of the first cylinder is connected to a lifting block, a first slide rail is provided on one longitudinal side surface of the stand, and the lifting block slides on the first slide rail.

[0011] By adopting the above technical solution, a first cylinder is vertically arranged on the operating table, its output end is connected to the lifting block, and a first slide rail is arranged on one longitudinal side surface of the frame, so that the lifting block can slide on the first slide rail; the smooth lifting of the operating table is achieved, and the height adjustability and flexibility of the operating table are improved.

[0012] Preferably, a vertical rod and a second cylinder are rotatably connected to the top of the lifting block, a swing rod is rotatably provided on the top of the vertical rod, and the output end of the second cylinder is hingedly arranged at the bottom center position of the swing rod.

[0013] By adopting the above technical solution, by setting up a vertical pole on the top of the lifting block and rotatably connecting the second cylinder, and rotatably installing a swing arm on the top of the vertical pole, precise control and flexible swing of the swing arm can be achieved, thereby improving the operating accuracy and work efficiency of the equipment.

[0014] Preferably, the swing arm is provided with a third cylinder and a second slide rail, a sliding base is slidably provided on the second slide rail, and the telescopic end of the third cylinder is connected to the third cylinder.

[0015] By adopting the above technical solution, a third cylinder and a second slide rail are arranged on the rocker arm, and the sliding base is driven by the third cylinder to slide and adjust the position of the sliding base.

[0016] Preferably, an electric winch is fixedly mounted on the sliding base.

[0017] By adopting the above technical solution, an electric winch is used to realize the lifting and lowering of the beam.

[0018] Preferably, the output end of the electric winch is connected to a steel wire rope, the bottom of the steel wire rope is fixedly connected to a lock, the bottom of the lock is provided with a hanger, and the bottom of the hanger is provided with a U-shaped limiting frame for the crossbeam to pass through.

[0019] By adopting the above technical solution, the lateral movement of the heavy object can be limited by the provided limit frame, so that the heavy object is kept in a fixed position during the lifting process, which is convenient for precise operation.

[0020] Preferably, at least two limiting frames are provided, and two adjacent limiting frames are parallel to each other.

[0021] By adopting the above technical solution, two parallel limit frames are fixed at the bottom of the hanger to ensure the balance when the crossbeam is lifted.

[0022] Preferably, the bottom of the lock head is fixedly connected to the four corners of the hanger through reinforcing steel cables.

[0023] By adopting the above technical solution, the force of the lock is dispersed to the four corners of the hanger, and the reinforced steel cable can reduce the deformation of the hanger and the lock during the lifting process; it is used to extend the service life of the equipment.

[0024] Preferably, a plurality of fastening components are provided inside the limiting frame, and the fastening components are used to fix beams of different sizes inside the limiting frame.

[0025] By adopting the above technical solution, beams of different sizes are fixed inside the limit frame through the fastening components, thereby increasing the versatility and applicability of the equipment.

[0026] In summary, this application has the following beneficial effects: 1. Through the climbing platform and hoist, operators can safely ascend and descend, avoiding the risk of accidents caused by climbing and descending when the railway line is not blocked; operators can perform various operations on the climbing platform, eliminating visual blind spots and limiting the operator's range of activities, thereby ensuring the safety of operators.

[0027] 2. By fastening the components, beams of different sizes are fixed inside the limit frame, which increases the versatility and applicability of the equipment. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 Schematic diagram of the overall structure of the conversion platform beam erecting device in this embodiment; Figure 2 It is a partial structural schematic diagram of the conversion platform beam erecting device in this embodiment; Figure 3 Schematic diagram of the connection structure between the electric winch and the steel wire rope in this embodiment; Figure 4 is a schematic diagram of the internal structure of the fastening assembly in this embodiment; Explanation of the accompanying drawings: 1. counterweight base; 2. track wheel; 3. driving turntable; 4. operating table; 5. frame; 6. first cylinder; 7. lifting block; 8. first slide rail; 9. control platform; 10. climbing platform; 11. hoist; 12. guardrail; 13. vertical pole; 14. second cylinder; 15. rocker arm; 16. second slide rail; 17. sliding base; 18. electric winch; 19. wire rope; 20. lock; 21. hanger; 22. limit frame; 23. reinforcement cable; 24. fastening assembly; 2401. screw; 2402. mounting plate; 2403. handle. DETAILED DESCRIPTION

[0029] The present application is further described in detail below in conjunction with the accompanying drawings. It is necessary to point out here that the following specific implementation methods are only used to further illustrate the present application and cannot be understood as limiting the scope of protection of the present application. Technical personnel in this field can make some non-essential improvements and adjustments to the present application based on the above application content. Example

[0030] The present invention discloses a beam erecting device for a switching platform across an existing railway line. Figure 1 As shown, it includes a counterweight base 1, and a track wheel 2 is fixedly installed on the side of the counterweight base 1. The track wheel 2 can provide a larger ground contact area, increase the stability and anti-overturning ability of the device, and in the process of erecting the beam body, the track wheel 2 can firmly contact the ground, provide additional support and stability, and prevent the device from tilting and shaking. The track wheel 2 on the counterweight base 1 can move freely in various terrains and environments; the device can move smoothly along a predetermined track and easily cross uneven ground, slopes and other obstacles; in this way, the device can adjust its position more flexibly to adapt to different construction needs.

[0031] like Figure 1As shown, the counterweight base 1 has an internal first driving motor, and the output end of the first driving motor is connected to a driving turntable 3, and the driving turntable 3 is located at the center of the upper surface of the counterweight base 1; the conversion platform beam erection device usually needs to be rotated to adapt to different work requirements; by placing the driving turntable 3 in the center, the rotation performance and operating efficiency of the device can be optimized while maintaining stability; an operating table 4 is fixedly installed on the upper surface of the driving turntable 3, and a stand 5 is vertically fixedly installed on the upper surface of one side of the operating table 4, and two stands 5 are provided, and a sliding area is formed between the two stands 5, and a first cylinder 6 is fixedly installed in the sliding area, and the bottom of the first cylinder 6 is fixedly connected to the operating table 4, and the first A lifting block 7 is provided at the top of the cylinder 6. By controlling the extension and retraction of the first cylinder 6, the height of the lifting block 7 can be accurately adjusted. This precise adjustment is very important for operations that require lifting at different heights, ensuring that the expected height can be reached each time the lifting is performed. A first slide rail 8 is provided on one longitudinal side surface of the stand 5, and the lifting block 7 slides on the first slide rail 8. The first slide rail 8 provides a flat surface, so that the lifting block 7 can remain stable when moving up and down, and reduce friction. This helps to improve the smoothness and accuracy of the lifting process. By arranging the first slide rail 8 on the side of the stand 5, the friction and wear between the lifting block 7 and the stand 5 can be effectively reduced. This helps to extend the service life of the first slide rail 8 and the lifting block 7 and reduce maintenance costs.

[0032] like Figure 1 and Figure 2 As shown, specifically, a control platform 9 is provided on the top of the stand 5, and a climbing area is formed between the operating platform 4, the stand 5 and the control platform 9. A climbing platform 10 and a hoist 11 are provided on the operating platform 4 and in the climbing area for lifting and lowering. The hoist 11 is used to lift the climbing platform 10, so as to adjust the operator on the climbing platform 10 to a suitable height. The climbing platform 10 and the hoist 11 allow the operator to lift and lower safely, avoiding the risk of accidents caused by climbing and descending when the railway line is not blocked; the operator can perform various operations on the climbing platform 10 without worrying about the driving safety on the railway line; the hoist 11 allows the climbing platform 10 to be lifted and lowered quickly, and the operator can quickly adjust to a suitable working height, reducing the time wasted due to climbing up and down, thereby improving work efficiency.

[0033] like Figure 2As shown, a guardrail 12 is fixedly installed on the upper surface of the climbing platform 10, and two guardrails 12 are provided. By providing two guardrails 12, the edge of the entire climbing platform 10 can be covered, effectively preventing people from accidentally falling from the side or back. This can prevent accidents and reduce potential injury risks. Moreover, the guardrail 12 can also prevent tools, equipment or other items from falling from the climbing platform 10. When working, it is often necessary to carry some tools and materials. If these items are not protected, they can easily fall down, which may cause personal injury or equipment damage. The provision of two guardrails 12 can limit the falling of items, provide a barrier layer for items, and ensure the safety and cleanliness of the work site.

[0034] like Figure 3 As shown, a vertical rod 13 is fixedly installed on the top of the lifting block 7 and is rotatably connected to a second cylinder 14. A rocker arm 15 is rotatably installed on the top of the vertical rod 13. The output end of the second cylinder 14 is hingedly arranged at the bottom center position of the rocker arm 15. The rocker arm 15 and the vertical rod 13 are rotated by the second cylinder 14. The relative angle between the rocker arm 15 and the vertical rod 13 can be flexibly adjusted by controlling the movement of the second cylinder 14; this allows the lifting block 7 to work at different angles to meet different operating requirements; the rotation of the rocker arm 15 and the vertical rod 13 can expand the working range of the lifting block 7; when it is necessary to work within a certain range, the rotation angle can be adjusted to meet different working requirements, thereby improving efficiency and flexibility.

[0035] like Figure 3 As shown, the rocker arm 15 is fixedly installed with a third cylinder and a second slide rail 16 along its length direction, a sliding base 17 is slidably provided on the second slide rail 16, the telescopic end of the third cylinder is connected to the third cylinder, an electric winch 18 is fixedly installed on the sliding base 17, and the electric winch 18 drives the winch drum based on an electric motor, and realizes the lifting and lowering of the beam through a wire rope 19 or a chain.

[0036] like Figure 3 and Figure 4 As shown, the output end of the electric winch 18 is connected to a steel wire rope 19, and a lock 20 is fixedly connected to the bottom of the steel wire rope 19. A hanger 21 is provided at the bottom of the lock 20, and a U-shaped limit frame 22 is provided at the bottom of the hanger 21 for the crossbeam to pass through. Two limit frames 22 are provided, and the two limit frames 22 are parallel to each other. The two parallel limit frames 22 are fixed at the bottom of the hanger 21 to ensure the balance when lifting the crossbeam, avoid the shaking of the crossbeam during the lifting process, and improve the safety of the operation. Furthermore, the limit frame 22 can limit the lateral movement of the heavy object, so that the heavy object remains in a fixed position during the lifting process, which is convenient for precise operation.

[0037] like Figure 4 As shown, the bottom of the lock head 20 is fixedly connected to the four corners of the hanger 21 by reinforcing steel cables 23. By dispersing the force of the lock head 20 to the four corners of the hanger 21, the reinforcing steel cables 23 can reduce the deformation of the hanger 21 and the lock head 20 during the lifting process; this not only prolongs the service life of the equipment, but also maintains the accuracy and stability of the lifting operation. This connection method can ensure the safety of the hanger 21 during the lifting and moving process; even if a certain part is subjected to greater stress, the steel cables in other parts can share the stress, thereby reducing the risk of single-point failure and preventing the hanger 21 or the lock head 20 from accidentally falling off.

[0038] like Figure 4 As shown, specifically, a plurality of fastening components 24 are provided inside the limit frame 22, and the fastening components 24 are used to fix beams of different sizes inside the limit frame 22, which can flexibly adapt to beams of different sizes and shapes; whether it is a large, medium or small beam, it can be fixed by selecting a suitable fastening component 24; this increases the versatility and applicability of the equipment.

[0039] Furthermore, the fastening assembly 24 includes a screw 2401 that passes through the interior of the limit frame 22, and a mounting plate 2402 is fixedly installed on the first end of the screw 2401 facing the beam, and a handle 2403 is fixed to the other end of the screw 2401. By rotating the handle 2403, the extension or shortening of the screw 2401 can be controlled, thereby adjusting the distance between the mounting plate 2402 and the beam; this makes it possible to adapt to beams of different sizes and ensure that the beams are firmly fixed; the threaded structure of the screw 2401 can provide a strong fixing force, so that the mounting plate 2402 can be tightly fixed on the beam to prevent it from loosening or falling off during lifting; it provides higher safety and stability; and the presence of the handle 2403 makes the extension and retraction process of the screw 2401 more convenient; by rotating the handle 2403, the length of the fixing device can be easily adjusted, saving time and labor for installation and disassembly.

[0040] Working principle: Before erecting the beams, it is used to first set up continuous thin-walled bridge piers symmetrically along the longitudinal sides of the existing railway line during the non-blocked period of the existing railway line.

[0041] A beam feeding platform is pre-built outside the thin-walled bridge pier on one side of the existing railway line. The beam body to be erected is prepared on the beam feeding platform. The horizontal height of the beam body is more than 2m higher than the height of the existing railway line contact network.

[0042] During the beam erection process, during the blockade period of the existing railway line, the conversion platform beam erection device is moved to the side of the beam feeding platform by the crawler wheels 2, and the control platform 9 is aligned with the beam feeding platform. The operator stands on the climbing platform 10 and the hoist 11 is used to climb the operator to the position of the control platform 9.

[0043] Then, by lifting and lowering the lifting block 7 and the angle between the vertical rod 13 and the swing rod 15, the swing rod 15 is made to cross the direction of the existing railway line, and the hanger 21 is lowered to the beam feeding platform through the electric winch 18.

[0044] The operator frames two limit frames 22 on the outside of the beam and near the two ends respectively, and fixes the beam inside the limit frames 22 with the help of fastening components 24. By moving the sliding base 17, the beam to be erected is quickly and accurately erected on the symmetrical thin-walled piers to form a beam body in place.

[0045] Repeat the above steps until at least 4 beams are erected.

[0046] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A beam erection device for a transfer platform across an existing railway line, comprising a counterweight base (1), characterized in that: A driving turntable (3) is rotatably provided on the counterweight base (1), an operating table (4) is fixedly mounted on the upper surface of the driving turntable (3), a vertical frame (5) is vertically provided on the upper surface of the operating table (4), a control platform (9) is provided on the top of the vertical frame (5), a climbing area is formed between the operating table (4), the vertical frame (5) and the control platform (9), and a climbing platform (10) and a hoist (11) for lifting the climbing platform (10) are provided on the operating table (4) and located in the climbing area.

2. The transfer platform beam erecting device across an existing railway line according to claim 1, characterized in that: At least two guardrails (12) are provided on the upper surface of the climbing platform (10).

3. The transfer platform beam erecting device across an existing railway line according to claim 1, characterized in that: A first cylinder (6) is vertically arranged on the upper surface of the operating table (4); an output end of the first cylinder (6) is connected to a lifting block (7); a first slide rail (8) is arranged on one longitudinal side surface of the stand (5); and the lifting block (7) slides on the first slide rail (8).

4. The transfer platform beam erecting device across an existing railway line according to claim 3, characterized in that: The top of the lifting block (7) is provided with a vertical rod (13) and is rotatably connected to a second cylinder (14); the top of the vertical rod (13) is rotatably provided with a swing rod (15); the output end of the second cylinder (14) is hingedly arranged at the bottom center position of the swing rod (15).

5. The transfer platform beam erecting device across an existing railway line according to claim 4, characterized in that: The swing rod (15) is provided with a third cylinder and a second slide rail (16); a sliding base (17) is slidably provided on the second slide rail (16); and the telescopic end of the third cylinder is connected to the third cylinder.

6. The transfer platform beam erecting device across an existing railway line according to claim 5, characterized in that: An electric winch (18) is fixedly mounted on the sliding base (17).

7. The transfer platform beam erecting device across an existing railway line according to claim 6, characterized in that: The output end of the electric winch (18) is connected to a steel wire rope (19), the bottom of the steel wire rope (19) is fixedly connected to a lock (20), the bottom of the lock (20) is provided with a hanger (21), and the bottom of the hanger (21) is provided with a U-shaped limit frame (22) for the crossbeam to pass through.

8. The transfer platform beam erecting device across an existing railway line according to claim 7, characterized in that: At least two of the limiting frames (22) are provided, and two adjacent limiting frames (22) are parallel to each other.

9. The beam erecting device for a transfer platform across an existing railway line according to claim 7, characterized in that: The bottom of the lock head (20) is fixedly connected to the four corners of the hanger (21) via reinforcing steel cables (23).

10. The beam erecting device for a transfer platform across an existing railway line according to claim 7, characterized in that: A plurality of fastening components (24) are arranged inside the limiting frame (22), and the fastening components (24) are used to fix beams of different sizes inside the limiting frame (22).