Rapid construction method for factory building with ultra-large area and complex structure

Through tower crane zoning construction and mechanical resource optimization, the problem of lifting steel components in complex structures in super-large areas under traditional construction methods has been solved, and the floor load reduction and construction efficiency have been achieved, which has significantly saved construction period and cost.

CN119062166APending Publication Date: 2024-12-03SHANGHAI BAOYE GRP CORP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411384183.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-30
Publication Date
2024-12-03

AI Technical Summary

Technical Problem

Under traditional construction methods, it is difficult to lift steel components of super-large complex structure factories on one floor, resulting in excessive structural load, low mechanical resource utilization efficiency, high construction period and cost, and limited lifting range, making it difficult to cover the entire factory.

Method used

The tower crane layout is used to construct the construction, which is divided into one and two construction zones. The tower crane is used to lift and install the first layer of column, beam, and two-layer steel components. The intermittent rear casting tape and the warehousing method are used to divide the floor slabs to optimize the tower crane layout and automobiles. Replenishment of lifting to ensure the maximum utilization of mechanical resources, and the installation of flow construction and roof maintenance system.

Benefits of technology

It effectively avoids the impact of floor load, protects the finished floor products, improves construction efficiency, significantly saves construction period and labor costs, avoids quality problems such as cracking and deflection, and maximizes the utilization of mechanical resources.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119062166A_ABST
    Figure CN119062166A_ABST
Patent Text Reader

Abstract

The invention relates to a rapid building method for an ultra-large-area complex-structure factory building. The method comprises the steps that firstly, structural analysis and construction zoning are conducted; 2, component weight analysis and tower crane arrangement; step 3, constructing a first layer of column beam slab; step 4, hoisting and mounting a second-layer steel member; fifthly, tower cranes in the workshop are dismantled; sixthly, a roof and outer wall maintenance system is installed; and 7, the tower crane on the outer side of the plant is dismounted. The tower crane penetrates through all stages of construction of the foundation, the main body structure and the maintenance structure, maximized utilization of mechanical resources is achieved, the construction efficiency is remarkably improved, and the construction period cost and the labor cost are effectively saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of industrial plant construction, and in particular to a method for rapidly constructing a plant with an ultra-large area and a complex structure. Background Art

[0002] The workshop building of this project is 165,495.51 square meters long and 85 meters wide, with a total construction area of ​​approximately 165,495.51 square meters. The structure is a reinforced concrete frame + steel frame. The first floor is a reinforced concrete frame structure, and the second floor is a steel frame structure. According to the traditional construction method, during construction, a truck crane is usually used to hoist and install the second-floor steel components one span at a time on the first-floor slab. However, the thickness of the first-floor slab is only 2.0 tons, and the design load-bearing capacity is 2.0 tons, which cannot support the truck crane to directly hoist the steel components on the first-floor slab. This requires laying steel plates on the upper part of the floor slab to form an operation channel for the truck crane, and the laid steel plates will produce a large load on the structure. In addition, the weight of the truck crane and the weight of the components will produce a large force on the structure, and long-term heavy loads will have an adverse effect on the first-floor structure. At the same time, the operating range of the truck crane is small, and the laying range of the steel plates is limited. The components are spread all over the factory building, which requires the steel plates to be transported back and forth or a large number of steel plates to be laid, which will incur a large amount of transportation costs, steel plate rental costs, machine shift costs, etc. The operating surface is large and the operating radius of the truck crane is limited. It is also extremely difficult to transport a large number of steel components in the middle of the factory building. Summary of the invention

[0003] The present invention aims to overcome the defects of the prior art, provide a method for quickly constructing a large-scale complex-structure factory building, and solve the construction problem of a large-scale complex-structure factory building.

[0004] In order to solve the above-mentioned technical problems, the present invention is achieved as follows: A method for rapidly constructing a large-scale complex-structured factory building, characterized in that it comprises the following steps: Step 1: Structural analysis and construction zoning; Step 2: Component weight analysis and tower crane arrangement; Step 3: Construction of first-floor columns, beams and slabs; Step 4: Hoisting and installation of second-floor steel components; Step 5: Remove the tower crane in the internal area of ​​the factory building; Step 6: Installation of roof and exterior wall maintenance system; Step 7: Dismantle the tower crane outside the factory building.

[0005] The method for rapidly constructing a super-large-area complex-structure factory building is characterized in that: step one specifically comprises: dividing the factory building into construction area one and construction area two; the factory building structure is in the form of reinforced concrete frame + steel frame, wherein the first floor is a reinforced concrete frame structure and the second floor is a steel frame structure.

[0006] The method for rapid construction of a large-scale complex structure factory building is characterized in that: Step 2 specifically comprises: the first floor of the construction area 1 is a concrete frame structure, the second floor is a steel bent structure, and three boom-length tower cranes are used; and two boom-length tower cranes are shared with the construction area 2; The first floor of Construction Area 2 is a concrete frame structure, and the second floor is a steel frame structure. It uses 2 long-boom tower cranes and 1 long-boom tower crane; the 2 long-boom tower cranes are shared with Construction Area 1.

[0007] The method for rapid construction of a super-large-area complex-structure factory building is characterized in that: Step three is specifically as follows: the construction method of the first floor slab is "setting intermittent, post-cast expansion reinforcement strips", a total of 4 post-cast strips are set in the east-west direction, and a total of 3 post-cast strips are set in the north-south direction, and disconnected deformation joints are designed, and the first floor slab is divided into 40 blocks for separate construction. During construction, the "setting post-cast strips" method or the "skip-bin method" of 40 blocks as standard modules is preferably used.

[0008] The method for rapid construction of a super-large-area complex-structure factory building is characterized in that: step four is specifically as follows: after a period of construction of the first-floor top plate, the hoisting operation of the second-floor steel structure begins after the concrete strength reaches the requirement; the hoisting construction in the first construction area is carried out in sequence from the east side to the west side, and the hoisting construction in the second construction area is carried out in sequence from the west side to the east side; the steel components within the span radius coverage of the tower crane need to wait until the tower crane is dismantled, and then a truck crane is used for partial hoisting and completion.

[0009] The method for rapid construction of a super-large-area complex-structure factory building is characterized in that: Step five is specifically as follows: after the construction of the main steel structure is completed, the tower crane is lowered to the top of the roof, a channel is reserved for the roof components, and a 50t truck crane is used to lay steel plates on the first-floor top plate near the removal of three tower cranes in the middle area. At the same time, the roof steel structure reserved for the removal of the tower crane is completed and then the truck crane is withdrawn. The seven tower cranes outside the factory building are retained until the construction of the roof and wall systems outside the factory building is completed.

[0010] The method for rapid construction of a super-large-area complex-structure factory building is characterized in that: Step six specifically includes: using the remaining 7 tower cranes to install the roof maintenance system and the outside maintenance system, paying attention to the construction arrangement to maintain flow construction during construction, reducing the hook occupation time, and improving the utilization efficiency of the tower crane machinery.

[0011] The method for rapid construction of a super-large-area complex-structure factory building is characterized in that: Step seven specifically includes: after the installation and construction of the roof and exterior wall maintenance system are completed, the remaining tower cranes are removed, and public auxiliary facilities such as greening, roads, and floors are constructed in the area where the tower cranes are located according to the requirements of the drawings.

[0012] The beneficial effects of the present invention are as follows: It can be seen from the above technical scheme that the present application provides a method for rapid construction of a factory building with a super-large area and complex structure, and adopts tower crane hoisting construction to avoid the impact on the floor load, greatly improve the protection of the finished floor, and avoid quality problems such as cracking and deflection in the later stage. At the same time, the tower crane is used throughout each stage of the construction of the foundation, main structure and maintenance structure, so as to maximize the utilization of mechanical resources, significantly improve construction efficiency, and effectively save construction period costs and labor costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments: Figure 1 It is a schematic diagram of the process of the present invention.

[0014] Figure 2 It is a schematic diagram of the overall structure.

[0015] Figure 3 This is a schematic diagram of step one.

[0016] Figure 4 This is a schematic diagram of step two.

[0017] Figure 5 This is a schematic diagram of step three.

[0018] Figure 6 This is a schematic diagram of step four.

[0019] Figure 7 This is a schematic diagram of step five.

[0020] Figure 8 This is a schematic diagram of step six.

[0021] Fig. 9 This is a schematic diagram of step seven. DETAILED DESCRIPTION

[0022] The technical solutions of the embodiments of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments in the embodiments of the present application are within the scope of protection requested by the present application.

[0023] like Figure 1 , 2 As shown: A method for quickly constructing a large-scale complex structure factory building, which includes the following steps: like Figure 3 As shown: Step 1, structural analysis and construction zoning The workshop building of this project is 165,495.51 square meters long and wide, with a total construction area of ​​about 165,495.51 square meters. The structure is a reinforced concrete frame + steel frame. The first floor is a reinforced concrete frame structure, and the second floor is a steel frame structure. According to the traditional construction method, a crane is used to hoist and install the second-floor steel components one span at a time on the first floor slab. The thickness of the first floor slab is only 1.5 tons, and the design load capacity is 2.0 tons. According to the overall construction content and the structural form of the workshop, the entire section is divided into two construction areas. The C1-C20 / CB-CW axis of the workshop is the first construction area, and the C20-C37 / CA-CW axis of the workshop is the second construction area.

[0024] like Figure 4 As shown: Step 2: Component weight analysis and tower crane arrangement According to the calculation, the maximum weight of a single component in the construction area is about 7.1t. Combined with the construction period and cost plan, 5 tower cranes are arranged in each of the construction area 1 and the construction area 2. Based on this, 9 STT983-50t and 1 STT553-18t tower cranes are selected. The STT983-50t jib tower crane has a lifting capacity of 11.0t at the maximum jib length, which is greater than 8.165t (7.1*1.15) and meets the construction requirements; the STT553-18t jib tower crane has a lifting capacity of 8.33t at the maximum jib length, which is greater than 8.165t (7.1*1.15) and meets the construction requirements.

[0025] Construction Area 1 is the plant building C1-C20 / CA-CT axis with a concrete frame structure on the first floor and a steel frame structure on the second floor. It mainly uses three STT983-50t boom tower cranes; and it shares two STT983-50t boom tower cranes with Construction Area 2.

[0026] Construction Area 2 is the plant building C20-C37 / CA-CT axis with a concrete frame structure on the first floor and a steel frame structure on the second floor. It mainly uses two STT983-50t boom tower cranes and one STT553-18t boom tower crane; it shares two STT983-50t boom tower cranes with Construction Area 1.

[0027] like Figure 5 As shown: Step 3, first floor column beam slab construction According to the construction drawings, the construction method for the first floor slab is "to set up intermittent, post-poured expansion reinforcement strips". A total of 4 post-poured strips are set up in the east-west directions of C1 axis, C6 axis, C15 axis, C25 axis and C34 axis, and a total of 3 post-poured strips are set up in the north-south directions of CG axis, CL axis and CQ axis. The positions of CT axis, C10 axis, C20 axis and C30 axis are designed as disconnected deformation joints. According to the positions of the above-mentioned post-poured strips and deformation joints, the first floor slab can be divided into 40 blocks for separate construction. During construction, the method of "setting up post-poured strips" is preferably adopted, and the "skip-bin method" with 40 blocks as standard modules can also be used for construction.

[0028] like Figure 6 As shown: Step 4: Hoisting and installation of second-floor steel components After the construction of the first floor top plate, the hoisting operation of the second floor steel structure will begin after the concrete strength reaches the requirement. When constructing the C1-C20 / CA-CT axis in the first construction area, the hoisting construction will be carried out from the C20 axis in the order from the east to the west. When constructing the C20-C37 / CA-CT axis in the second construction area, the hoisting construction will be carried out from the C20 axis in the order from the west to the east. It should be noted that the steel components within the span radius coverage of the tower crane need to wait until the tower crane is dismantled, and then use a truck crane for partial hoisting and completion.

[0029] like Figure 7 As shown: Step 5: Removal of the tower crane in the internal area of ​​the factory When the main steel structure is completed, the tower crane is lowered to the top of the roof, a channel is reserved for the roof components, and a 50t truck crane is used to lay steel plates on the first floor top plate near the removal of the three tower cranes in the middle area. At the same time, the reserved roof steel structure of the tower crane is completed and the truck crane is withdrawn. The 7 tower cranes outside the factory building are retained until the construction of the roof and wall system outside the factory building is completed.

[0030] like Figure 8 Shown: Step 6: Installation of roof and exterior wall maintenance system Use the remaining 7 tower cranes to install the roof maintenance system and the outside maintenance system. During construction, pay attention to the construction arrangement to maintain flow construction, reduce the hook occupation time, and improve the utilization efficiency of the tower crane machinery.

[0031] like Fig. 9 As shown: Step 7: Removal of the tower crane outside the plant After the installation of the roof and exterior wall maintenance system is completed, the remaining tower cranes will be removed, and public auxiliary facilities such as greening, roads, and floors will be constructed in the area where the tower cranes are located according to the requirements of the drawings.

[0032] The present invention adopts tower crane hoisting construction, which can avoid the impact on the floor load, greatly do a good job in protecting the finished floor, and avoid quality problems such as cracking and deflection in the later stage. At the same time, the tower crane is used throughout each stage of foundation, main structure and maintenance structure construction to maximize the utilization of mechanical resources, significantly improve construction efficiency, and effectively save construction period cost and labor cost.

[0033] The above are only embodiments provided for the present application and are not intended to limit the present application. Although the present application is described in detail with reference to the embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.

Claims

1. A method for rapid construction of a large-scale complex structure factory building, characterized in that It includes the following steps: Step 1: Structural analysis and construction zoning; Step 2: Component weight analysis and tower crane arrangement; Step 3: Construction of first-floor columns, beams and slabs; Step 4: Hoisting and installation of second-floor steel components; Step 5: Remove the tower crane in the internal area of ​​the factory building; Step 6: Installation of roof and exterior wall maintenance system; Step 7: Dismantle the tower crane outside the factory building.

2. The method for rapid construction of a large-scale complex-structure factory building according to claim 1, characterized in that: Step one is as follows: the factory building is divided into construction area one and construction area two; the factory building structure is in the form of reinforced concrete frame + steel frame, where the first floor is a reinforced concrete frame structure and the second floor is a steel frame structure.

3. The method for rapid construction of a large-scale complex-structure factory building according to claim 1, characterized in that: Step 2 is as follows: The first floor of construction area 1 is a concrete frame structure, the second floor is a steel frame structure, and three long-arm tower cranes are used; two long-arm tower cranes are shared with construction area 2; The first floor of Construction Area 2 is a concrete frame structure, and the second floor is a steel frame structure. It uses 2 long-boom tower cranes and 1 long-boom tower crane; the 2 long-boom tower cranes are shared with Construction Area 1.

4. The method for rapid construction of a large-scale complex-structure factory building according to claim 1 is characterized by: Step three is as follows: for the first-floor slab, "intermittent, post-poured expansion reinforcement strips" are set, with a total of 4 post-poured strips in the east-west direction and 3 post-poured strips in the north-south direction. Disconnected deformation joints are designed, and the first-floor slab is divided into 40 blocks for separate construction. During construction, the "post-poured strips" method or the "skip-bin method" of using 40 blocks as standard modules is preferred.

5. The method for rapid construction of a large-scale complex-structure factory building according to claim 1 is characterized by: Step four is as follows: after a section of the first-floor top plate construction, wait until the concrete strength reaches the requirement before starting the hoisting operation of the second-floor steel structure; construction area one advances the hoisting construction from the east to the west, and construction area two advances the hoisting construction from the west to the east; steel components within the span radius coverage of the tower crane must wait until the tower crane is dismantled, and then use a truck crane for partial hoisting and completion.

6. The method for rapid construction of a large-scale complex-structure factory building according to claim 1 is characterized by: Step five is as follows: when the construction of the main steel structure is completed, the tower crane is lowered to the top of the roof, a channel is reserved for the roof components, and a 50t truck crane is used to lay steel plates on the first-floor top plate near the removal of three tower cranes in the middle area. At the same time, the roof steel structure reserved for the removal of the tower crane is completed and the truck crane is withdrawn. The seven tower cranes outside the factory building are retained until the construction of the roof and wall systems outside the factory building is completed.

7. The method for rapid construction of a large-scale complex-structure factory building according to claim 1 is characterized by: Step six is ​​as follows: Use the remaining seven tower cranes to install the roof maintenance system and the outside maintenance system. During construction, pay attention to the construction arrangement to maintain flow construction, reduce the hook occupation time, and improve the utilization efficiency of the tower crane machinery.

8. The method for rapid construction of a large-scale complex-structure factory building according to claim 1 is characterized by: Step seven is as follows: After the installation of the roof and exterior wall maintenance system is completed, the remaining tower cranes will be removed, and public auxiliary facilities such as greening, roads, and floors will be constructed in the area where the tower cranes are located according to the requirements of the drawings.