Evaluation method for ecological restoration effect of surface mine
The method systematically collects and analyzes biological, soil, and water quality data using a plane rectangular coordinate system to enhance the accuracy and intuitiveness of open-pit mine ecological restoration evaluations, addressing the limitations of existing methods.
Patent Information
- Application Number
- CN202411080538.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-12-03
Smart Images

Figure CN119067294A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of mine ecological restoration, and specifically relates to an open-pit mine ecological restoration effect evaluation method. Background Art
[0002] With the continuous exploitation of mineral resources, the damage caused by open-pit mines to the environment is becoming increasingly serious. Soil stripping, the accumulation of rock fragments and low-grade ore, and the formation of empty mining areas and subsidence areas have caused the ecological environment of mines to deviate seriously from the natural state. At the same time, the accumulation of tailings and the land that cannot be used and developed due to mining are also urgent issues that need to be solved. Therefore, ecological restoration of open-pit mines has become an inevitable requirement for the sustainable development of the mining industry.
[0003] Open-pit mine ecological restoration technology mainly includes various means such as physical restoration, chemical restoration and biological restoration, aiming to restore the natural form, landform and ecological environment of the mining area.
[0004] In the existing technology, data collection relies on staff to conduct on-site inspections and record in detail. Although these data will be summarized and concluded after recording, each collected data needs to be compared and analyzed with the preset table. This process makes it difficult to intuitively present the efficiency of data changes, which in turn affects the accuracy of the overall evaluation effect.
[0005] To this end, the present invention provides an open-pit mine ecological restoration effect evaluation method. Summary of the invention
[0006] In order to make up for the deficiencies of the prior art, at least one technical problem raised in the background technology is solved.
[0007] The technical solution adopted by the present invention to solve the technical problem is: an open-pit mine ecological restoration effect evaluation method described in the present invention comprises the following steps:
[0008] A1. Dispatch staff, prepare equipment, and set the collection time;
[0009] A2. Collect biological information, soil information and water quality information of the target area and establish a sample library;
[0010] A3. Establish test items, test the values of each test item of samples in the sample library, and correspond them to the collection time;
[0011] A4. Establish a plane rectangular coordinate system and draw the project curve based on the acquisition time and the numerical value of the test item;
[0012] A5. Select the time period between two adjacent acquisition time points, calculate the slope of the curve within the time period, and create a table of the curve slope and the corresponding time period;
[0013] A6. Predict the subsequent repair progress based on the data in the table, summarize the data, and fill in the repair report.
[0014] Preferably, collecting biological information of the target area in step A2 includes the following steps:
[0015] B1. Divide the target area into multiple unit areas by using the GPS system;
[0016] B2. Set up trapping devices and place them in the unit area according to categories;
[0017] B3. Retrieve the trapping device, remove and collect the captured animals, and collect and record the number of plant species in the unit area;
[0018] B4, the animal is marked without harm, then the total number of marks is recorded and released, and the trap is deployed again;
[0019] B5. Calculate the number of individual animal populations in the individual unit area based on the number of individual animals captured again, the total number of marked individuals and the number of marked individuals during recapture.
[0020] Preferably, in step B5:
[0021] The number of animal individuals captured again is n;
[0022] The total number of individual markers is M;
[0023] The number of individuals marked in the recapture is m;
[0024] The number of individual populations is N;
[0025] The formula for calculating the number of individual populations is:
[0026]
[0027] Preferably, collecting soil information of the target area in step A2 includes the following steps:
[0028] C1, obtaining soil samples in the unit area divided in step B1, and attaching labels according to the acquisition locations;
[0029] C2. Test the content of harmful substances in soil samples and record the data;
[0030] Among them, the content of harmful substances in the soil is recorded as Z.
[0031] Preferably, collecting water quality information of the target area in step A2 includes the following steps:
[0032] D1. Determine the distribution map of groundwater and surface water in the target area, and then divide it into multiple unit water areas;
[0033] D2. Obtain water samples from the unit waters and attach sample labels after collection;
[0034] D3. Test the content of harmful substances in water samples and record the data;
[0035] Among them, the content of harmful substances in water is recorded as Q.
[0036] Preferably, the method of drawing the project curve in step A4 comprises the following steps:
[0037] E1. Set the collection time interval, taking the collection time interval as the unit length, and fill the value into the horizontal axis of the plane rectangular coordinate system;
[0038] E2. Collect biological information of the target area multiple times according to the collection time interval, and fill the calculated values into the vertical axis of the plane rectangular coordinate system;
[0039] E3. Collect soil information of the target area multiple times according to the collection time interval, and fill the detected values into the vertical axis of the plane rectangular coordinate system;
[0040] E4. Collect water quality information of the target area multiple times according to the collection time interval, and fill the detected values into the vertical axis of the plane rectangular coordinate system.
[0041] Preferably, the slopes of the curves in the time period calculated in step A5 include the slope of the biological information curve, the slope of the soil information curve, and the slope of the water quality information curve;
[0042] The time interval is denoted as T, where T=rt, t is in hours, and r is a non-zero natural number.
[0043] Preferably, the calculation method of the slope of the bioinformatics curve is:
[0044] The start time of the time interval is T1, and the end time is T2;
[0045] The number of biological individual populations corresponding to the starting time T1 is N1, and the number of biological individual populations corresponding to the end time is N2. When T1 = 0, the corresponding number of biological individual populations is b, and the slope of the biological information curve in the T2-T1 time period is k s ;
[0046] in:
[0047] N1=b+k s T1;
[0048] N2=b+k s T2.
[0049] Preferably, the calculation method of the slope of the soil information curve is:
[0050] The soil harmful substance content corresponding to the start time T1 is Z1, and the soil harmful substance content corresponding to the end time is Z2. When T1 = 0, the corresponding soil harmful substance content is f, and the slope of the soil information curve in the T2-T1 time period is k t ;
[0051] in:
[0052] Z1=f+k t T1;
[0053] Z2=f+k t T2;
[0054] Preferably, the calculation method of the slope of the water quality information curve is:
[0055] The content of harmful substances in the water body corresponding to the starting time T1 is Q1, and the content of harmful substances in the water body corresponding to the end time is Q2. When T1 = 0, the corresponding content of harmful substances in the water body is h, and the slope of the water quality information curve in the T2-T1 time period is k v ;
[0056] in:
[0057] Q1=h+k v T1;
[0058] Q2=h+k v T2.
[0059] The beneficial effects of the present invention are as follows:
[0060] 1. This paper establishes a plane rectangular coordinate system and draws the project curve based on the acquisition time and the numerical value of the detection project. The plane rectangular coordinate system can intuitively represent the data in a two-dimensional space, making the data structure, relationship and trend clear at a glance. The coordinate system provides a mathematical quantitative analysis framework, which can perform accurate numerical calculations and statistical analysis. The numerical value of the mine information is brought into the plane rectangular coordinate system. By drawing trend lines or fitting curves, the trend and direction of the data can be seen, which helps predict future development trends;
[0061] 2. The present invention collects biological information, soil information and water quality information of the target area for multiple times, and fills the obtained values into the vertical axis of the plane rectangular coordinate system. By analyzing the specific coordinates of two points in a given curve, we can accurately calculate the average slope of the curve in the specific time period. This data provides us with an intuitive method to quantify the frequency of changes in the number of biological individual populations, the heavy metal content in the soil and the heavy metal content in the water body over time, which helps to more accurately grasp the changing trends of the biological population dynamics. This comprehensive evaluation method not only helps us expand the data coverage of the evaluation, but also can significantly improve the accuracy of the evaluation, thereby more accurately reflecting the actual effect of mine restoration. BRIEF DESCRIPTION OF THE DRAWINGS
[0062] The present invention will be further described below in conjunction with the accompanying drawings.
[0063] Figure 1 It is a flowchart of the whole process of the present invention;
[0064] Figure 2 It is a flowchart of collecting biological information of a target area in the present invention;
[0065] Figure 3 It is a flowchart of collecting soil information of a target area in the present invention;
[0066] Figure 4 It is a flowchart of collecting water quality information of a target area in the present invention;
[0067] Figure 5 It is a flowchart of drawing a project curve in the present invention. DETAILED DESCRIPTION
[0068] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.
[0069] like Figures 1 to 5 As shown, a method for evaluating the ecological restoration effect of an open-pit mine according to an embodiment of the present invention comprises the following steps:
[0070] A1. Dispatch staff, prepare equipment, and set the collection time.
[0071] A comprehensive review of the key stages of mine restoration effectiveness requires the proper arrangement of all staff members to ensure that they have clear responsibilities and a fine division of labor. At the same time, tools and equipment should be prepared to ensure the smooth progress of subsequent work. In addition, to ensure the accuracy and timeliness of the data, the time points for data collection should be planned, and a collection plan should be formulated accordingly to facilitate subsequent work.
[0072] A2. Collect biological information, soil information and water quality information of the target area and establish a sample library.
[0073] By systematically collecting biological, soil, water quality and other environmental data of the mine, we can directly obtain the overall picture of the mine's environmental status. As time goes by, by collecting and comparing relevant data many times, we can accurately observe the degree of change of mine environmental information, thereby intuitively reflecting the progress and effectiveness of mine restoration work.
[0074] A3. Establish test items, test the values of each test item of samples in the sample library, and correspond them to the collection time.
[0075] After the test project is successfully constructed, in order to ensure the accuracy and traceability of the data, the collected test project values will be accurately compared and the corresponding collection time will be corresponded. At the same time, in order to optimize the data management process, each project will be assigned a unique number so that the required data can be quickly and accurately obtained in the subsequent data comparison process.
[0076] A4. Establish a plane rectangular coordinate system and draw the project curve based on the acquisition time and the numerical value of the test item.
[0077] The plane rectangular coordinate system can intuitively represent data in two-dimensional space, making the data structure, relationship and trend clear at a glance. The coordinate system provides a mathematical quantitative analysis framework, which can perform precise numerical calculations and statistical analysis. It can calculate the mean, variance, correlation coefficient and other statistical quantities of data points, as well as perform regression analysis and model fitting. The coordinate system makes trend analysis intuitive and easy to understand. By drawing trend lines or fitting curves, the trend and direction of the data can be seen, helping to predict future development trends.
[0078] A5. Select the time period between two adjacent acquisition time points, calculate the slope of the curve within the time period, and establish a table of the curve slope and the corresponding time period.
[0079] The slope of a curve, as an indicator that quantitatively expresses the rate of change of the curve at each specific point, plays a core role in data analysis. It can effectively reveal the speed of data change and the steepness of the trend. Furthermore, the change points of the slope, namely the maximum, minimum and inflection points, these key nodes not only reflect the important characteristics of the data, but also directly reflect the turning points of the data change trend. Specifically, when the slope is positive, it means that the data is showing an upward trend; conversely, if the slope is negative, it means that the data is showing a downward trend.
[0080] A6. Predict the subsequent repair progress based on the data in the table, summarize the data, and fill in the repair report.
[0081] Based on detailed data analysis, this report aims to provide a rigorous and systematic summary of the mine restoration effects in order to provide strong support for subsequent review and reference.
[0082] Collecting biological information of the target area in step A2 includes the following steps:
[0083] B1. By using the GPS system, the target area is divided into multiple unit areas.
[0084] With its excellent accuracy, GPS technology can accurately provide location information, ensuring that each sampling point can be accurately located in large-scale or complex terrain sites such as mines. This is crucial to ensuring the uniformity and accuracy of the spatial distribution of sampling points. Through GPS positioning technology, sampling points can be intuitively displayed on the map, making the overall sampling layout clearly visible, providing strong support for planning sampling routes and avoiding obstacles or dangerous areas. In addition, this technology also helps to record the precise location and related information of each sampling point, laying a solid foundation for subsequent data integration, analysis and processing.
[0085] B2. Set up trapping devices and place them in the unit area in a classified manner.
[0086] Here, the trapping device is mainly responsible for trapping organisms in the target area, aiming to conveniently obtain information about the organisms in the area. Then, according to the established unit area division, the collected biological information can be effectively numbered for subsequent processing and analysis.
[0087] B3. Retrieve the trapping device, remove and collect the captured animals, and at the same time collect and record the number of plant species in the unit area.
[0088] In this example, we focus on insects in the target area as a case study and systematically obtain insect samples in the area to ensure that the data collected subsequently as the basis for individual populations are accurate and reliable.
[0089] B4, the animal is marked without harm, then the total number of marks is recorded and released, and the trap is deployed again;
[0090] B5. Calculate the number of individual animal populations in the individual unit area based on the number of individual animals captured again, the total number of marked individuals and the number of marked individuals during recapture.
[0091] The mark-recapture method is a scientific method that aims to minimize the lasting impact on biological populations and promote the restoration and recovery of mining area ecology. This method captures a portion of biological individuals, marks them, and then releases them back into the natural environment. In the subsequent capture process, by counting the number of marked individuals, we can estimate the size of the overall population relatively accurately and achieve an accurate estimate of the population size. In addition, the mark-recapture method is not only suitable for short-term surveys, but also for long-term monitoring and research, providing scientists with an effective way to gain in-depth understanding of population trends, life cycles and other biological characteristics.
[0092] In step B5:
[0093] The number of animal individuals captured again is n;
[0094] The total number of individual markers is M;
[0095] The number of individuals marked in the recapture is m;
[0096] The number of individual populations is N;
[0097] The formula for calculating the number of individual populations is:
[0098]
[0099] During the mine restoration process, in order to accurately evaluate the changes in organisms in the mine area, we adopted a scientific method. This method systematically obtains the number data of individual insect populations in multiple unit areas and accurately calculates the average value of the insect population in the unit area. Then, at preset time intervals, the changes in the number of insect populations during this period are recorded and calculated multiple times. Through these detailed data records and analyses, we can clearly derive the survival status of insect populations in the target area, thereby effectively reflecting the changes in biodiversity during the mine restoration process.
[0100] Collecting soil information of the target area in step A2 includes the following steps:
[0101] C1. Obtain soil samples in the unit area divided in step B1 and attach labels according to the acquisition locations.
[0102] Soil samples from different locations, as important indicators of the geology and mineral resource distribution of the mining area, play a key role in revealing the soil pollution status of the mining area and its surrounding areas, and help us accurately assess the environmental impact of the mining area. In addition, these soil samples are also used for in-depth research on geological characteristics and geological processes. For the mining environment, collecting soil samples from different locations not only verifies the effectiveness and representativeness of the sampling method, but also provides a solid scientific basis for the planning and management of the mine. In order to ensure the accuracy of the detection information, we will also mark the corresponding samples according to the divided unit areas to facilitate the subsequent collection of information detection work.
[0103] C2. Check the content of harmful substances in soil samples and record the data, where the content of harmful substances in the soil is recorded as Z.
[0104] In this example, we focus on the heavy metal pollution problem in the soil that is closely related to minerals. As one of the common pollutants in mining activities, the detection of heavy metal content is crucial to assessing the potential impact of mines on the surrounding environment. By carefully analyzing the distribution and concentration of heavy metals in the soil, we can more accurately determine the focus and priority of environmental remediation. This analysis helps to accurately identify potential sources of pollution in mining activities and provide key guidance for remediation work.
[0105] In response to the heavy metal pollution problem, we will develop targeted soil remediation plans based on detailed content analysis results. After the mine remediation work is completed, we will regularly test the heavy metal content in the soil to evaluate the effectiveness and durability of the remediation measures. This monitoring process will not only help verify the remediation results, but also provide a scientific basis for subsequent continuous management.
[0106] By effectively reducing the heavy metal content in the soil, we are committed to promoting the restoration and reconstruction of the ecosystem and increasing vegetation coverage and biodiversity. This initiative has positive significance for achieving the mine's sustainable development goals and reflects our firm commitment to environmental protection and ecological balance.
[0107] Collecting water quality information of the target area in step A2 includes the following steps:
[0108] D1. Determine the distribution map of groundwater and surface water in the target area, and then divide it into multiple unit water areas;
[0109] D2. Obtain water samples from the unit waters and attach sample labels after collection;
[0110] D3. Test the content of harmful substances in water samples and record the data;
[0111] Among them, the content of harmful substances in water is recorded as Q.
[0112] During the mineral mining process, due to specific operations or natural infiltration, the mineral components inside the mountain may enter and mix into the water source of the mountain, causing the mountain water to have a certain degree of mineral content. During the mine restoration process, the heavy metal content in the water body is also one of the important parameters.
[0113] When assessing the degree of pollution caused by mining activities to surface water and groundwater, heavy metal content detection is a crucial task. Mining activities are often accompanied by the use and discharge of heavy metals. Therefore, through systematic detection, we can accurately understand which heavy metals have been released into the environment and determine whether their concentrations exceed the established environmental standards. The acquisition of this information is of decisive significance for the formulation of targeted environmental remediation plans. Based on the distribution and concentration data of heavy metal content, we can scientifically plan and implement corresponding remediation strategies and measures. By effectively detecting and controlling the release of heavy metals, we can significantly reduce environmental risks, thereby ensuring the stability of the surrounding ecosystem and the maintenance of biodiversity.
[0114] The method of drawing the project curve in step A4 includes the following steps:
[0115] E1. Set the collection time interval, taking the collection time interval as the unit length, and fill the value into the horizontal axis of the plane rectangular coordinate system;
[0116] E2. Collect biological information of the target area multiple times according to the collection time interval, and fill the calculated values into the vertical axis of the plane rectangular coordinate system;
[0117] In this figure, the horizontal axis represents the time value, while the vertical axis reflects the biological information value. The curve depicted by this plane rectangular coordinate system can intuitively gain insight into the dynamic changes that biological information undergoes over time. This display method helps us more accurately grasp the trend of changes in biological information over time.
[0118] E3. Collect soil information of the target area multiple times according to the collection time interval, and fill the detected values into the vertical axis of the plane rectangular coordinate system.
[0119] In a given plane rectangular coordinate system, the horizontal axis represents the time value, while the vertical axis corresponds to the soil information value. By observing and analyzing the curve trend in this coordinate system, the law and trend of the change of soil information value over time can be clearly revealed.
[0120] E4. Collect water quality information of the target area multiple times according to the collection time interval, and fill the detected values into the vertical axis of the plane rectangular coordinate system.
[0121] In the provided plane rectangular coordinate system, the horizontal axis clearly indicates the time value, while the vertical axis represents the water quality information value. By observing the direction of the curve in this coordinate system, we can intuitively understand and analyze the changing trend of the water quality information value over time, and thus derive the correlation between the two.
[0122] The slopes of the curves in the time period calculated in step A5 include the slope of the biological information curve, the slope of the soil information curve, and the slope of the water quality information curve;
[0123] The time interval is recorded as T, where T=rt, t is in hours, and r is a non-zero natural number. In this embodiment, r=360, that is, the period for collecting information is 15 days. The collection time is refined to improve the accuracy of the collected data.
[0124] Calculation method of the slope of the bioinformatics curve:
[0125] The start time of the time interval is T1, and the end time is T2;
[0126] The number of biological individual populations corresponding to the starting time T1 is N1, and the number of biological individual populations corresponding to the end time is N2. When T1 = 0, the corresponding number of biological individual populations is b, and the slope of the biological information curve in the T2-T1 time period is k s ;
[0127] in:
[0128] N1=b+k s T1;
[0129] N2=b+k s T2.
[0130] Calculation method of soil information curve slope:
[0131] The soil harmful substance content corresponding to the start time T1 is Z1, and the soil harmful substance content corresponding to the end time is Z2. When T1 = 0, the corresponding soil harmful substance content is f, and the slope of the soil information curve in the T2-T1 time period is k t ;
[0132] in:
[0133] Z1=f+k t T1;
[0134] Z2=f+k t T2.
[0135] The calculation method of the slope of the water quality information curve is:
[0136] The content of harmful substances in the water body corresponding to the starting time T1 is Q1, and the content of harmful substances in the water body corresponding to the end time is Q2. When T1 = 0, the corresponding content of harmful substances in the water body is h, and the slope of the water quality information curve in the T2-T1 time period is k v ;
[0137] in:
[0138] Q1=h+k v T1;
[0139] Q2=h+k v T2.
[0140] By analyzing the specific coordinates of two points in a given curve, we can accurately calculate the average slope of the curve during that specific time period. This data provides us with an intuitive method to quantify the frequency of changes in the number of individual biological populations, soil heavy metal content, and water body heavy metal content over time, helping to more accurately grasp the changing trends in biological population dynamics.
[0141] In the process of evaluating the effect of mine restoration, a comprehensive method was adopted, which covers the analysis of the number of biological individual populations, the determination of heavy metal content in soil, and the detection of heavy metal content in water bodies. This comprehensive evaluation method not only helps us expand the data coverage of the evaluation, but also significantly improves the accuracy of the evaluation, thereby more accurately reflecting the actual effect of mine restoration.
[0142] The above-mentioned front, back, left, right, top and bottom are all based on the figures in the specification. Figure 1 As a benchmark, according to the person's observation perspective, the side of the device facing the observer is defined as the front, the left side of the observer is defined as the left, and so on.
[0143] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the scope of protection of the present invention.
[0144] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A method for evaluating the ecological restoration effect of an open-pit mine, characterized in that: The following steps are involved: A1. Dispatch staff, prepare equipment, and set the collection time; A2. Collect biological information, soil information and water quality information of the target area and establish a sample library; A3. Establish test items, test the values of each test item of samples in the sample library, and correspond them to the collection time; A4. Establish a plane rectangular coordinate system and draw the project curve based on the acquisition time and the numerical value of the test item; A5. Select the time period between two adjacent acquisition time points, calculate the slope of the curve within the time period, and create a table of the curve slope and the corresponding time period; A6. Predict the subsequent repair progress based on the table data, summarize the data, and fill in the repair report; Collecting biological information of the target area in step A2 includes the following steps: B1. Divide the target area into multiple unit areas by using the GPS system; B2. Set up trapping devices and place them in different areas; B3. Retrieve the trapping device, remove and collect the captured animals, and collect and record the number of plant species in the unit area; B4, the animal is marked without harm, then the total number of marks is recorded and released, and the trap is deployed again; B5. Calculate the number of animal populations in the individual unit area based on the number of animals captured again, the total number of marks, and the number of marked individuals during recapture; In step B5: The number of animal individuals captured again is n; The total number of individual markers is M; The number of individuals marked in the recapture is m; The number of individual populations is N; The formula for calculating the number of individual populations is: Collecting soil information of the target area in step A2 includes the following steps: C1, obtaining soil samples in the unit area divided in step B1, and attaching labels according to the acquisition locations; C2. Test the content of harmful substances in soil samples and record the data; Among them, the content of harmful substances in soil is recorded as Z; Collecting water quality information of the target area in step A2 includes the following steps: D1. Determine the distribution map of groundwater and surface water in the target area, and then divide it into multiple unit water areas; D2. Obtain water samples from the unit waters and attach sample labels after collection; D3. Test the content of harmful substances in water samples and record the data; Among them, the content of harmful substances in water is recorded as Q; The method of drawing the project curve in step A4 includes the following steps: E1. Set the collection time interval, taking the collection time interval as the unit length, and fill the value into the horizontal axis of the plane rectangular coordinate system; E2. Collect biological information of the target area multiple times according to the collection time interval, and fill the calculated values into the vertical axis of the plane rectangular coordinate system; E3. Collect soil information of the target area multiple times according to the collection time interval, and fill the detected values into the vertical axis of the plane rectangular coordinate system; E4. Collect water quality information of the target area multiple times according to the collection time interval, and fill the detected values into the vertical axis of the plane rectangular coordinate system; The slopes of the curves in the time period calculated in step A5 include the slope of the biological information curve, the slope of the soil information curve, and the slope of the water quality information curve; The time interval is denoted as T, where T = r hours, and r is a non-zero natural number.
2. The method for evaluating the ecological restoration effect of an open-pit mine according to claim 1, characterized in that: Calculation method of the slope of the bioinformatics curve: The start time of the time interval is T1, and the end time is T2; The number of biological individual populations corresponding to the starting time T1 is N1, and the number of biological individual populations corresponding to the end time is N2. When T1 = 0, the corresponding number of biological individual populations is b, and the slope of the biological information curve in the T2-T1 time period is k s ; in: N1=b+k s T1; N2=b+k s T2。 3. The method for evaluating the ecological restoration effect of an open-pit mine according to claim 2, characterized in that: Calculation method of soil information curve slope: The soil harmful substance content corresponding to the start time T1 is Z1, and the soil harmful substance content corresponding to the end time is Z2. When T1 = 0, the corresponding soil harmful substance content is f, and the slope of the soil information curve in the T2-T1 time period is k t ; in: Z1=f+k t T1; Z2=f+k t T2。 4. The method for evaluating the ecological restoration effect of an open-pit mine according to claim 3, characterized in that: The calculation method of the slope of the water quality information curve is: The content of harmful substances in the water body corresponding to the starting time T1 is Q1, and the content of harmful substances in the water body corresponding to the end time is Q2. When T1 = 0, the corresponding content of harmful substances in the water body is h, and the slope of the water quality information curve in the T2-T1 time period is k v ; in: Q1=h+k v T1; Q2=h+k v T2。