Cable repairing method
Through the combination of in-situ repair methods and specific materials, the complex operation and breakdown phenomenon in the repair process of cable insulation damage is solved, and efficient and rapid repair results are achieved, extending the service life of the cable and reducing maintenance costs.
Patent Information
- Application Number
- CN202411167443.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-12-03
AI Technical Summary
During the repair process of damaged insulation of existing medium and high voltage cables, the conductor needs to be cut off and an intermediate joint is set. The operation is complicated and technical requirements are high. After repair, breakdown may still occur, resulting in frequent repairs.
Using in-situ repair method, through cross-linked polyethylene insulating tape and glass fiber heating tape, through cross-linked polyethylene insulating tape, combined with semiconducting paint material Fixed with C-type copper rings to form a repair effect close to the original structure.
It reduces the complexity of the maintenance process, improves the repair efficiency and service life, reduces the subsequent maintenance needs, and the outer diameter of the cable is consistent with the original after repair, avoiding contact resistance and oxidation problems.
Abstract
Description
Technical Field
[0001] The invention relates to a cable repair method and belongs to the field of cable repair technology. Background Art
[0002] Cables are widely used in various types of electrical equipment, and are mainly used for connecting equipment. Due to the complex application environment of cables and the fact that they are subjected to external forces during use and laying, the insulation layer that bears the voltage, the alloy sheath that acts as a longitudinal water and oil barrier, the shielding layer that acts as a balanced electric field, and the sheath that acts as a moisture-proof protection may be damaged, which ultimately leads to safety problems during the operation of the cable, seriously affecting the safe operation of the equipment and ultimately having a great impact on production. In the process of repairing cables with damaged insulation in existing medium and high voltage cables, it is often necessary to saw off the cable at the fault point, and then set an intermediate joint at the sawing point. This maintenance solution has a very complicated operation process and a long operation process. It requires a high level of technical skills. Due to the difference in material between the joint and the original conductor and the difference in connection reliability, it often breaks down again after a period of safe operation, which ultimately causes the problem of frequent maintenance. How to reduce the complexity of the maintenance process without destroying the structure of the existing conductor itself, while ensuring the maintenance effect and extending the use time after maintenance, has become an important issue that needs to be solved in the current industry. Summary of the invention
[0003] The object of the present invention is to provide a cable repair method.
[0004] The technical solution to achieve the purpose of the present invention is: a cable repair method, which specifically includes the following steps:
[0005] A. Section cleaning: peel off the breakdown point, and then clean the section to make its surface smooth and bright;
[0006] B Three-layer co-extruded insulation repair: Wrap the conductor with semi-conductive tape, wrap the cross-linked polyethylene insulation tape on the section, melt the insulation tape to form an insulation layer, spray semi-conductive paint on the insulation and wrap the semi-conductive tape to form an insulation shield
[0007] C Shielding layer repair: rewind the metal shielding material around the outside of the insulating shielding layer and fix it, then wrap it with insulating tape;
[0008] D Cable wrapping repair: Wrap PVC insulation tape on the twisted cable core, and then wrap it with composite waterproof insulation self-adhesive tape;
[0009] E sheath layer repair: Put a tubular sheath with longitudinal openings on the cable wrapping tape, and then use a hot drying gun to repair the longitudinal and radial openings.
[0010] The repair method of the present invention does not need to destroy the conductor of the cable but adopts an in-situ repair method. The repair method is simple and the repair speed is fast, which reduces the technical level of on-site maintenance personnel, thereby improving the repair efficiency and reducing the repair cost. The outer diameter of the cable after repair is consistent with the outer diameter of the main body.
[0011] Further or optionally, in the cross-section cleaning step, the stripping order is to first strip the sheath and the wrapping tape, then strip the copper tape, and then cut the insulation at the breakdown point so that the cutting surface forms a 45° angle with the conductor to form a bell mouth; after completing the insulation stripping step, use sandpaper to polish the conductor surface and the bell mouth surface, and wipe the polished conductor and bell mouth insulation surface with alcohol paper to make them smooth and bright.
[0012] During the above operation, the insulation section is innovatively cut into a 45° trumpet shape, so that a smooth transition is formed between different materials, which facilitates the subsequent laying of the semi-conductive conductor shielding repair layer, the insulation repair layer and the semi-conductive insulation shielding repair layer, so that the three-layer structure has a uniform transition and the three-layer co-extrusion structure is restored to the greatest extent.
[0013] Further or optionally, in the three-layer co-extruded insulation repair step, a semi-conductive tape is first wrapped around the conductor, and then a cross-linked polyethylene insulating tape is wrapped around the semi-conductive tape and the bell mouth, and the cross-linked polyethylene insulating tape extends to the junction of the bell mouth and the main body insulation shielding; then a glass fiber heating tape is wrapped around the cross-linked polyethylene insulating tape, and the glass fiber heating tape is used to heat and melt the wrapped layer of the cross-linked polyethylene insulating tape, and then cooled, polished, and dried. After drying, a semi-conductive paint is sprayed on the insulation surface, and the semi-conductive tape is wrapped while spraying.
[0014] In the above process, a wrapped cross-linked polyethylene insulating tape is innovatively used as the repaired insulating layer, and a glass fiber heating tape is innovatively used to heat and melt the cross-linked polyethylene tape to form a repaired insulating layer. The temperature of the glass fiber heating tape is transmitted to the wrapped layer of the cross-linked polyethylene insulating tape to melt the wrapped tape, and the layers are fused with each other, transforming the layered structure into an integrated structure that blends with each other. It can also be fused with the main insulation to finally form a dense insulating structure. At the same time, the good heat sealing effect of the cross-linked polyethylene insulating tape can well limit the inner layer of the semi-conductive tape material within the inner layer to ensure that the radius after repair is effectively controlled. The semi-conductive paint sprayed on the outer layer can be used as a bonding transition layer to tightly combine the insulating shielding layer with the insulation, thereby obtaining a repaired insulating structure that is closest to the original three-layer co-extrusion structure, effectively improving the service life of the repaired cable. In addition, the glass fiber heating tape occupies a small space and is easy to operate, which can realize the repair of insulation in a narrow space and can achieve rapid repair.
[0015] Further or optionally, in the shielding layer repair step, the stripped copper tape is re-wrapped on the insulated wire core. After the copper tape covering is completed, the overlap is fixed with a C-shaped copper ring, and a cross-linked polyethylene insulating tape is wrapped around the C-shaped copper ring, and then a glass fiber heating tape is used to cover and heat it.
[0016] During the above operation, a C-shaped copper ring is innovatively used as a fixing material for the overlap of the copper tape, which effectively increases the cross-sectional area of the contact point at the repair position and reduces the contact resistance. When an induced current passes through the repair position, it can effectively reduce the breakdown caused by current concentration, thereby increasing the service life of the cable and reducing the amount of subsequent maintenance.
[0017] During the above operation, cross-linked polyethylene insulating tape is innovatively used as a protective layer at the overlap of the copper tape. After the cross-linked polyethylene insulating tape is melted, a dense isolation layer is formed at the overlap, which plays a role in waterproofing and anti-oxidation. It can also fix the C-shaped copper ring, avoiding the problem of tape breakage due to large contact resistance.
[0018] Further or optionally, in the sheath layer repairing step, a tubular sheath is sleeved on the cable wrapping tape, the tubular sheath is longitudinally open, the length of the tubular sheath is longer than the cross section, and then the tubular sheath is fixed by wrapping PVC tape, and then a hot drying gun is used to heat the end to complete radial fusion with the main body sheath, and then the PVC tape is removed;
[0019] Wrap PVC tape around the interface between the tubular sheath and the body sheath, wrap PTFE film around the tubular sheath, and then use a hot drying gun to heat the longitudinal opening to perform longitudinal repair;
[0020] Use a polisher and sandpaper to grind the surface until it is flat and smooth.
[0021] During the above repair operation, a scheme of first applying a ring to fix and then melting the plastic to continue the connection was adopted. This scheme does not involve the use of large machinery to extrude the outer sheath, and the operation can be completed in a small space, which can effectively solve the problem of damage repair in a small space.
[0022] During the above-mentioned repair operation, a PTFE film is used to wrap and fix the tubular sheath. The high temperature resistance of the PTFE film can be used to control the temperature conduction during the heating process, effectively avoiding deformation of the sheath caused by excessively high heating temperature and prolonged heating time, allowing heat to be evenly transferred to the longitudinal opening. It can also ensure that the sheath does not shift during the repair process, thereby ensuring the quality and appearance of the repair.
[0023] Further or optionally, during the repair process of the three-layer co-extruded insulation layer, when the cross-linked polyethylene insulation wrapping layer is heated with a glass fiber heating tape, the heating temperature of the glass fiber tape is 140-170°C, the heating time is 30-45 minutes, and the insulation is cooled with a hair dryer after heating. The temperature tolerance and cold shrinkage of the inner layer material are considered in the above repair process. The control parameters are within the above range to ensure that the wrapped cross-linked polyethylene layer can be completely melted and melted evenly, and fused with the main insulation. It can ensure that the shrinkage of the cross-linked polyethylene insulation layer after cooling is less than or equal to 0.1%, which can ensure that the mechanical properties and electrical properties of the repaired insulation layer are consistent with the main insulation, and can make the repair surface smoother after the operation is completed, reduce the workload during the subsequent grinding operation, and ensure the quality of the repair layer.
[0024] Further or optionally, in the shielding layer repairing step, the thickness of the wrapped cross-linked polyethylene insulating tape is 0.1 mm, the wrapping overlap rate is 45% to 55%, and the wrapping length exceeds the length of the C-shaped copper ring by 30 to 50 mm.
[0025] When the above-mentioned overlap ratio and overlap length on the copper ring are used, the repaired metal shield can be effectively fixed and the end points can be covered, thereby forming an effective protective layer to prevent the overlapping position from falling off and breaking, and to prevent oxidation of the contact points.
[0026] By adopting the above technical solution, the present invention has the following beneficial effects:
[0027] (1) The repair method of the present invention does not need to damage the conductor of the cable. The repair method is simple and the repair speed is fast, which reduces the technical level of on-site maintenance personnel, thereby improving the repair efficiency and reducing the repair cost. The outer diameter after repair is consistent with the main cable.
[0028] (2) The present invention controls the insulation repair cutting surface near the breakdown point to be 45° to form a bell mouth, so that a smooth transition surface is formed between different materials, which is convenient for the subsequent laying of the semi-conductive conductor shielding repair layer, the insulation repair layer, and the semi-conductive insulation shielding repair layer, and can make the repaired insulation layer better integrated with the main insulation, thereby restoring the three-layer co-extruded insulation structure to the greatest extent.
[0029] (3) The present invention wraps a cross-linked polyethylene insulating tape around the semi-conductive tape and the insulating flare, and then covers it with a glass fiber heating tape. The heat released when the glass fiber heating tape is heated is used to gradually melt the cross-linked polyethylene insulating tape from the outside to the inside, so that the layered structure is transformed into an integrated structure that is mutually blended and melted together with the main insulation to obtain an insulating layer that is closest to the original co-extruded structure. The outer diameter of the insulation does not increase after the repair, which reduces the workload of subsequent grinding and effectively improves the service life after the repair.
[0030] (4) The present invention adopts a C-shaped ring as a fixing material at the shield repair contact point, which effectively increases the cross-sectional area of the contact point at the repair position, reduces the contact resistance, and effectively reduces the breakdown phenomenon caused by current concentration; a cross-linked polyethylene insulating tape is used to wrap and fix the C-shaped copper ring. After the cross-linked polyethylene insulating tape is melted, an isolation layer is formed around the C-shaped copper ring, which reduces the occurrence of oxidation at the overlap and extends the service life.
[0031] (5) The present invention adopts a thermoplastic material ring coating scheme in the process of sheath layer repair, which does not involve the use of large-scale machinery to extrude the outer sheath. The operation can be completed in a small space, which can effectively solve the problem of damage repair in a small space.
[0032] (6) In the insulating layer and shielding layer repairing steps of the present invention, the heating temperature and heating time of the glass fiber heating belt and the cooling method of the repair layer are strictly controlled, thereby effectively controlling the uniformity of the cross-linked polyethylene wrapping layer after melting and the shrinkage of the cross-linked polyethylene after repair, so that it is fully melted and fused with the main insulation, and the shrinkage after cooling is within 0.1%, thereby ensuring the thickness of the repair layer and stable mechanical and electrical properties, and also reducing the workload during subsequent grinding operations.
[0033] (7) The present invention controls the overlap rate and length of the cross-linked polyethylene insulating tape on the copper ring, effectively fixes and covers the end points of the shielding repair layer, thereby forming an effective protective layer to avoid falling off, breaking and oxidation at the overlapping position. DETAILED DESCRIPTION
[0034] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with specific implementation methods.
[0035] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0036] All other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without creative work shall fall within the protection scope of the present invention.
[0037] (Example 1)
[0038] The damaged medium voltage cable of this embodiment is repaired by using a three-layer co-extrusion structure, and the specific operation is as follows:
[0039] A: Section cleaning:
[0040] With the breakdown point as the center, peel off the sheath and wrapping tape forward and backward, with a stripping length of 400-500mm, and ensure that the sheath section is flat; then peel off the copper tape, with a stripping length of 100-150mm; extend 50-100mm longitudinally along the sheath stripping position, and wipe the sheath surface with alcohol paper; use a blade to cut the insulation longitudinally in two directions to cut out a smooth transition bell mouth at an angle of 45° with the conductor, with the exposed length of the conductor being 50-100mm, and the longitudinal length of the bell mouth being 5-25mm;
[0041] First, use 400-grit sandpaper to polish the conductor for 10 minutes, and then use 800-grit sandpaper to polish the conductor for 5 minutes to polish off the black layer on the conductor surface caused by breakdown and ablation, making the conductor surface smooth and bright.
[0042] Use 800-grit sandpaper to grind the bell mouth for 5 minutes, and then use 1000-grit sandpaper to grind the bell mouth for 10 minutes. Polish the bell mouth until it is smooth, and then wipe the bell mouth with alcohol paper to make the cross-section of the bell mouth smooth and clean.
[0043] B: Three-layer co-extruded insulation repair:
[0044] Wrap a layer of black semi-conductive tape on the conductor. The thickness of the black semi-conductive tape is 0.5 mm, the width is 10 mm, the wrapping overlap rate is 45% to 55%, the wrapping direction is left, and the end is fixed with 3M thin strong double-sided tape;
[0045] Wrap XLPE insulating tape on the semi-conductive tape and the bell mouth, extending to the intersection of the bell mouth edge and the original insulation shield, the thickness of the XLPE insulating tape is 0.1mm, the width of the tape is 10-20mm, the wrapping coverage rate is 45%-50%, the number of wrapping layers is 35-90 layers, and the outer diameter after wrapping is 1-2mm larger than the original insulation outer diameter;
[0046] Wrap a glass fiber heating tape around the XLPE insulation tape, adjust the temperature of the glass fiber heating tape to 140-170°C, heat for 30-45 minutes, and fully melt the XLPE insulation tape. Use a hair dryer to cool the insulation temperature to room temperature. First, use a polisher to smooth the surface of the insulation layer, and then use 400-mesh, 800-mesh, and 1000-mesh sandpaper to polish the insulation surface in turn, so that the insulation surface is smooth and bright. The outer diameter of the insulation after grinding is consistent with the original insulation outer diameter. Wipe the insulation surface with alcohol paper to remove impurities on the insulation surface.
[0047] Use a hot drying gun to heat the insulating surface until the surface is completely dry, cool it naturally to room temperature, spray semi-conductive paint on the insulating surface with a spray thickness of 0.1mm~0.2mm, and wrap it with semi-conductive tape as an insulating shield. The thickness of the semi-conductive tape is 0.5mm, the width is 10~15mm, the number of layers is 1, the wrapping overlap rate is 45%~55%, and the wrapping end is fixed with 3M thin strong double-sided tape.
[0048] C: Shield repair:
[0049] Wrap the disconnected copper tape around the semi-conductive tape again, and fix the joint with a C-shaped copper ring. The thickness of the C-shaped copper ring is 0.2mm, the width is 30mm-45mm, and the circumference is 55mm-130mm. Restore the copper tape shielding, and the restored outer diameter is consistent with the original copper tape shielding outer diameter;
[0050] Wrap 1 to 3 layers of XLPE insulating tape on the C-shaped copper ring. The thickness of the XLPE insulating tape is 0.1 mm, the overlap rate is 45% to 55%, and the length of the wrapping exceeds the length of the C-shaped copper ring by 30 to 50 mm. Then use a glass fiber heating tape to melt the XLPE insulating tape to form a closed protective layer, and make the overlapping parts of the copper tapes in close contact to avoid the contact resistance being large and causing the tape to break again.
[0051] D: Cable wrapping repair
[0052] Wrap 2 layers of black PVC insulating tape on the twisted cable core. The thickness of the insulating tape is 0.1mm, the width is 50mm, the wrapping coverage is 45% to 55%, the wrapping direction is left, wrap to the peeling point of the cabling tape, and the overlapping length with the original cabling tape is 25-50mm. Restore the cabling wrapping. The outer diameter of the restored cabling wrapping is consistent with the original outer diameter;
[0053] Wrap 10kV cable composite waterproof insulating self-adhesive tape on the restored cabling tape, with 2 to 3 layers, tape thickness of 0.1mm, tape width of 50mm, wrapping coverage of 45% to 55%, the tape width stretched during wrapping is 75% of the original value, the wrapping direction is left, and the wrapping length is consistent with the repaired length of the cabling tape, as a waterproof and anti-oxidation isolation layer.
[0054] E: Sheath repair
[0055] Repair the sheath on the composite waterproof insulating self-adhesive tape. The repair material is a tubular longitudinal opening sheath with a length of 405-505mm. The color, material and thickness are consistent with the original sheath. The appearance of the repair material is longitudinal opening. The cross-sections of the two ends of the repair material are flattened with a utility knife. Then, the tubular sheath is put on the composite waterproof insulating self-adhesive tape. PVC tapes are tied on the tubular sheath at equal distances. The number of ties is two to play a fixing role. The two ends of the tubular sheath are heated with a heat drying gun. The heating temperature of the heat drying gun is 155-175℃, and the heating time is 3-5min. The cross-section of the end is melted together with the original sheath, and then naturally cooled to room temperature to complete the repair of the radial opening.
[0056] Remove the PVC tape, tightly wrap the PTFE film on the tubular sheath, wrap the PTFE film with 2 layers, overlap rate of 10% to 20%, and the wrapping length extending to the main cable is 50 to 100 mm. Wrap the PVC tape on the two repaired ends to fix the repaired ends; use a heat gun to repeatedly heat the longitudinal opening at a temperature of 155 to 175°C for 10 to 15 minutes until the longitudinal opening is completely fused, and then cool naturally to room temperature;
[0057] Use a polishing machine to grind the surface of the sheath to smooth the raised parts of the joints, then use 400 mesh, 800 mesh and 1000 mesh sandpaper to grind the surface of the sheath in turn to make it smooth, wipe the surface of the sheath with alcohol paper to remove impurities on the surface of the sheath to make the surface of the sheath smooth, and then use a heat gun to heat the longitudinal and radial joints at a temperature of 155-175°C for 3-5 minutes. Cool naturally to room temperature to make the surface of the sheath beautiful. The outer diameter of the repaired sheath is consistent with the outer diameter of the original cable.
[0058] It should be understood that the present invention is described by some embodiments, and those skilled in the art will appreciate that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. In addition, under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all embodiments falling within the scope of the claims of this application belong to the scope of protection of the present invention.
Claims
1. A cable repair method, Features The following steps are involved: A. Section cleaning: peel off the breakdown point, and then clean the section to make its surface smooth and bright; B Three-layer co-extruded insulation layer repair: wrap the semi-conductive tape on the conductor, wrap the cross-linked polyethylene insulation tape on the section, melt the insulation tape to form an insulation layer, spray semi-conductive paint on the insulation and wrap the semi-conductive tape to form an outer shield; C Shielding layer repair: rewind the metal shielding material around the outside of the insulating shielding layer and fix it, then wrap it with insulating tape; D Cable wrapping repair: Wrap PVC insulation tape on the twisted cable core, and then wrap it with composite waterproof insulation self-adhesive tape; E sheath layer repair: Put a tubular sheath with longitudinal openings on the cable wrapping tape, and then use a hot drying gun to repair the longitudinal and radial openings.
2. A cable repair method according to claim 1, Features: In the cross-section cleaning step, the stripping order is to first strip the sheath and the wrapping tape, then strip the copper tape, and then cut the insulation of the breakdown point so that the cutting surface forms a 45° angle with the conductor to form a bell mouth; after completing the stripping step, sandpaper is used to polish the conductor surface and the bell mouth surface to make them smooth and bright.
3. A cable repair method according to claim 1, Features: In the three-layer co-extruded insulation layer repairing step, a semi-conductive tape is firstly wrapped around the conductor, and then a cross-linked polyethylene insulation tape is wrapped around the semi-conductive tape and the bell mouth, and the cross-linked polyethylene insulation tape extends outside the edge of the bell mouth; then a glass fiber heating tape is wrapped around the cross-linked polyethylene insulation tape, and the cross-linked polyethylene insulation tape is heated and melted by the glass fiber heating tape, and then cooled, polished, dried and cleaned. After cleaning, a semi-conductive paint is sprayed on the insulation surface, and the semi-conductive tape is wrapped at the same time to form an insulation shielding layer.
4. A cable repair method according to claim 1, Features: In the shielding layer repairing step, the disconnected copper tape is rewound on the insulating shielding, and then the overlapping part of the copper tape is fixed with a C-shaped copper ring. Then, a cross-linked polyethylene insulating tape is wrapped around the C-shaped ring, and the cross-linked polyethylene insulating tape extends outside the edge of the C-shaped ring. Then, a glass fiber heating tape is wrapped around the cross-linked polyethylene tape, and the glass fiber heating tape is used to heat and melt the cross-linked polyethylene insulating tape.
5. A cable repair method according to claim 1, Features: In the cabling wrapping and repairing step: wrapping the PVC insulating tape on the twisted cabling core, and then wrapping the composite waterproof insulating self-adhesive tape, and the composite waterproof insulating self-adhesive tape needs to be longitudinally stretched.
6. A cable repair method according to claim 1, Features: In the sheath layer repairing step, a tubular sheath is sleeved on the cable wrapping tape, the tubular sheath is longitudinally open, and the length of the tubular sheath is longer than the cross section, and then the tubular sheath is fixed by wrapping PVC tape, and then a hot drying gun is used to heat the end to complete radial fusion with the main body sheath, and then the PVC tape is removed; Wrap PVC tape around the interface between the tubular sheath and the body sheath, wrap PTFE film around the tubular sheath, and then use a hot drying gun to heat the longitudinal opening to perform longitudinal repair; Use a polisher and sandpaper to grind the surface until it is flat and smooth.
7. A cable repair method according to claim 2, Features: In the cross-section cleaning step, the stripping length of the sheath and the cable wrapping tape is 400-500 mm, and the stripping length of the copper tape is 100-150 mm; the bell mouth is cut 15-25 mm on both sides with the breakdown point as the center, and the length of the exposed conductor after cutting is 30-50 mm. The insulation is beveled from the edge of the conductor to cut out the bell mouth with an inclination angle of 45°. The length of the bell mouth is 5-25 mm. The bell mouth and the surface of the conductor are polished with sandpaper with a mesh size of 400-1000 and a polishing time of 3-5 minutes until the surface of the conductor is clean and smooth and the surface of the bell mouth is smooth. The bell mouth and the surface of the conductor are wiped with alcohol paper until they are smooth.
8. A cable repair method according to claim 3, Features: When heating the cross-linked polyethylene insulating tape, a glass fiber heating tape is used for heating, the heating temperature is 140-170°C, the heating time is 30-45 minutes, and a hair dryer is used for cooling after heating. After cooling, the insulating surface is first polished with a polishing machine, and then the insulating surface is polished again with 400 mesh, 800 mesh and 1000 mesh sandpaper in sequence until the insulating surface is smooth, and then the insulating surface is wiped with alcohol paper until it is smooth; when repairing the insulating shielding layer, a semi-conductive paint is sprayed on the insulating surface, and the semi-conductive layer is wrapped while spraying, the number of wrapping layers is 1, the thickness is 0.5 mm, and the overlap rate is 50%-55%.
9. A cable repair method according to claim 4, Features: To repair the metal belt, a C-shaped ring is used to fix the contact point of the copper belt, and then 1 to 3 layers of cross-linked polyethylene insulating tape are wrapped around the C-shaped ring. The thickness of the cross-linked polyethylene tape is 0.1 mm, the wrapping overlap rate is 45% to 55%, and the wrapping length is 3 to 5 cm longer than the C-shaped copper ring. The cross-linked polyethylene insulating tape is then heated with a glass fiber heating tape at a heating temperature of 140 to 170° C. for 3 to 5 minutes, and then cooled to room temperature after heating.
10. A cable repair method according to claim 6, Features: In the sheath layer repair step, the length of the longitudinal open tubular sheath is 405-505 mm, the color, material and thickness are the same as the main sheath, and the circumference is 3-5 mm larger than the main cable; the PVC tape has two ties, and the tying distance is 130 mm-160 mm; the PTFE film has two layers, the overlap rate is 45%-55%, and the wrapping length is 500-600 mm, which plays a role in balancing heat and protecting the sheath; the heat gun is heated at a temperature of 155-175°C and a heating time of 3-5 min, the heating position is the circumference of the overlap between the tubular sheath and the main body sheath and the PTFE film covering the longitudinal opening of the tubular sheath; the sheath is polished, the polishing time of the polishing machine is 3-5min, the mesh of the sandpaper is 400 mesh and 800 mesh, and the sandpaper polishing time is 5-10min; the heating after polishing, the heating time of the longitudinal joint and the transverse joint with a hot drying gun is 1-3min, the heating temperature is 130-150℃, and it is naturally cooled after heating, so that the repaired sheath has a smooth, round, beautiful appearance and is equal to the diameter of the main cable.