Block combination hoisting method for stage fence top of complex site stadium
Through the block combination lifting method and ground pre-assembly technology, the high-altitude operation and safety risks of traditional shank roof installation are solved, and efficient and accurate installation in closed spaces is achieved, and the stage shank roof is updated and upgraded for complex venue environments.
Patent Information
- Application Number
- CN202411539442.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-31
- Publication Date
- 2024-12-06
AI Technical Summary
Traditional shank roof installation has a large number of steel structure components, high lifting difficulty, high altitude operations and high safety risks. In a closed environment, the lifting equipment has a large lifting capacity, making it difficult to achieve precise assembly and anti-corrosion and fire treatment.
Using the block combination lifting method, the tire frame platform is temporarily assembled on the ground, calculate the lifting point, pre-assembled, reinforced support, and hoist lifting, and anti-corrosion and fire-proof treatment are carried out in the enclosed space to reduce high-altitude operations and cross-operations, and the use of lifting frames and Pullax set optimizes lifting direction and lifting requirements.
Reduce the amount of high-altitude installation operations, reduce construction risks, improve construction accuracy and quality, and is suitable for complex site environments, shorten construction time and reduce safety risks.
Smart Images

Figure CN119083742A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of theatre sill installation, in particular to a block-assembly hoisting method for a stage sill in a complex venue. Background Art
[0002] The stage grid roof is commonly known as the grape rack. It is located at the top of the stage tower. It is not only the basic space for the stage machinery and HVAC equipment on the stage, but also the hollow working layer of the stage. The grid roof of the early theater was a wooden structure, which has now been replaced by a steel structure. The steel structure of the grid roof is not only closely related to the stage machinery, but also closely related to the architectural structure of the theater. It is a transition layer connecting the stage machinery and equipment and the theater structure, and is an indispensable part. The ridge top is the carrier of the stage machinery. The use of stage machinery such as lifting railings, lifting orchestra pit lighting cages, lighting hanging pieces, electric boom lifts, and winches is realized on the ridge top. Therefore, the precise installation of the ridge top ensures the normal use of various stage machinery, the smooth realization of stage performances, and the safety of venue personnel.
[0003] There are many problems with the installation of traditional sills. 1. The sills are composed of a large number of steel structure components. The use of a single bulk method increases the number of hoisting times and time, affecting the construction progress; operators need to use climbing equipment or set up operating scaffolding for installation, and there are many installation nodes, special materials, and welding and installation are all carried out at high altitude, affecting safety. 2. If the sill is hoisted as a whole, the required hoisting equipment has a large lifting capacity. There is no large crane available in the closed environment of the upper roof, and the selection of hoisting equipment is a difficult problem. In addition, the overall plane area of the sill is large, covering the stands and stage areas. The steel beam components are numerous and short. It is difficult to be accurate after the overall family is assembled, and it is difficult to ensure that the deviation is within the allowable range; 3. Welding, bolt connection, anti-corrosion coating, fire retardant coating, etc. are all operated at high altitude, which seriously affects the safety below, and there is a risk of falling objects, and the safety risk of cross-construction is seriously increased. Summary of the invention
[0004] The present invention aims to overcome the defects of the prior art and provide a method for lifting the stage ridge top in a complex venue by combining blocks, so as to solve the problems that the overall lifting of the ridge top is difficult, there are many high-altitude operations, and there are many dangerous three-dimensional cross operations.
[0005] In order to solve the above-mentioned technical problems, the present invention is achieved as follows: A method for hoisting the stage ceiling in blocks for complex venues and stadiums, characterized in that it comprises the following steps: Step 1: Install no less than two winches on the high steel beam where the top of the ridge needs to be installed; Step 2: Process a temporary assembly tire frame platform below the installation position of the coral top; Step 3: Divide the coral top into several suitable pieces for hoisting, and calculate the hoisting points through calculation software; Step 4: Assemble and splice the top blocks on the tire frame platform, and perform pre-assembly, debugging, and deviation correction; Step 5: After assembly, set up hanging points and fixtures on the top of the block, and install temporary support and reinforcement components to enhance its rigidity and strength during hoisting; Step 6: Install and fix the ceiling column; Step 7: After the winch is threaded with the wire rope, the coral top is connected, hoisted and installed in blocks; Step 8: Connect, correct and fix the ballast blocks with the upper hanging column, set up temporary fixed reinforcement support, temporarily install and fix the first ballast block, and remove the temporary reinforcement measures and support for hoisting; Step 9: Lift the second coral top block; Step 10: Lift in sequence until all the coral top blocks are lifted.
[0006] The method for combined hoisting of stage ridge blocks in complex venues is characterized in that: if the center line of the ridge block deviates greatly from the center of gravity, which will affect the flatness during lifting and installation, a fixed temporary counterweight component is added to the ridge block to achieve the purpose of balance, and the temporary counterweight component is removed after the installation and fixation are completed.
[0007] The method for combined hoisting of the ridge blocks of the stage in a complex venue is characterized in that: if the hoisting rigidity of the ridge blocks is insufficient and they are easily deformed and twisted by direct hoisting, a hoisting frame is processed; the hoisting frame is processed with steel sections according to the outer dimensions of the ridge blocks and the division of the primary and secondary beams, and the outer shape of the hoisting frame is mainly a rectangular quadrilateral, and a hook is arranged in the middle of each side of the frame, which is connected to the hoisting point of the steel beam at the bottom of the ridge block.
[0008] The method for lifting the stage ceiling in blocks in a complex venue is characterized in that: in step one, if the position of the steel beam affects the threading of the wire rope, a fixed pulley, a movable pulley or a pulley block is used to change the lifting direction and reduce the lifting requirements of the winch.
[0009] The method for assembling and lifting the block-by-block ridge of a stage in a complex venue is characterized in that: in step 2, a control reference line is set on the frame platform for deviation correction control after the pre-assembly of the ridge blocks; the frame platform is welded by suitable types of steel sections, steel pipes, etc. according to the flatness of the bottom and the depth of the building structure through force calculation; after the frame platform is installed, it is measured and adjusted to ensure that its surface is flat and horizontal, which is convenient for the assembly accuracy control of the ridge.
[0010] The method for hoisting the block-by-block combination of the stage ridge top in a complex venue is characterized in that: after the ridge top is pre-assembled on the frame and qualified, the anti-corrosion and fire-retardant coatings are applied to the ridge top, the connection nodes are wrapped with plastic sheets, and anti-corrosion and fire-retardant treatments are carried out after the installation is completed.
[0011] The method for hoisting the block-by-block combination of the stage ridge top of a complex venue is characterized in that after the ridge top is treated with anti-corrosion and fire prevention and before hoisting, some pipelines attached to the ridge top are buried and bound to the ridge top rods in advance, and label marks are left on the joints for subsequent connection.
[0012] The method for hoisting the stage ridge roof in a complex venue is characterized in that after the ridge roof is treated with anti-corrosion and fire prevention and before hoisting, auxiliary equipment that is not easily damaged, such as a horseway, a railing or a lampshade, is installed.
[0013] The method for assembling and hoisting the ridge blocks of a stage in a complex venue is characterized by: first installing the ridge blocks at the corners, setting temporary support and reinforcement; then installing the ridge blocks at another corner, setting temporary support and reinforcement; installing the middle ridge blocks, connecting the two sides into a whole, forming a local stable space system, and removing the temporary support and reinforcement; installing the remaining ridge blocks in sequence, and finally forming an overall stable space system; The beneficial effects of the present invention are as follows: it can be seen from the above technical scheme that the present application provides a method for the block-by-block combined hoisting of the stage ridge of a complex venue, which can reduce a large amount of high-altitude installation work and reduce construction risks; the method can be constructed in a closed limited space after the roof cover is completely closed, and is suitable for various complex venue environments and has a wide range of applications. For example, it can be applied to the renewal and upgrading construction of old ridges in venue renovation and expansion projects; most components are assembled on the ground, which speeds up the construction progress; the construction accuracy on the ground is easy to control, which improves the construction quality; most of the work is completed on the ground, reducing the risk of three-dimensional cross-operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments: Figure 1 This is a schematic diagram of the stage roof division; Figure 2 Illustration of the steps for dividing the coral roof into blocks and installing it Figure 1 ; Figure 3 Illustration of the steps for dividing the coral roof into blocks and installing it Figure 2 ; Figure 4 Illustration of the steps for dividing the coral roof into blocks and installing it Figure 3 ; Figure 5 Illustration of the steps for dividing the coral roof into blocks and installing it Figure 4 ; Figure 6 It is an overall schematic diagram. DETAILED DESCRIPTION
[0015] The technical solutions of the embodiments of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. All other embodiments obtained by ordinary technicians in this field without creative work based on the embodiments in the embodiments of the present application are within the scope of protection requested by the present application. like Figure 1-6 As shown: A method for the block-by-block assembly and hoisting of the stage ceiling of a complex venue, which includes the following steps: Step 1: Install no less than two winches on the high steel beam where the top of the ridge needs to be installed; If the position of the steel beam affects the threading of the wire rope, use a fixed pulley, movable pulley or pulley block to change the lifting direction and reduce the lifting requirements of the winch; Step 2: Process a temporary assembly tire frame platform below the installation position of the coral top; The cradle platform is set with a control reference line for deviation correction after pre-assembly of the ridge top blocks; the cradle platform is welded with appropriate types of steel and steel pipes according to the flatness of the bottom and the depth of the building structure (which may be located above the foundation pit) through force calculation. After the cradle platform is installed, it is measured and adjusted to ensure that its surface is flat and level, which is convenient for the assembly accuracy control of the ridge top; Step 3: In the design plan, divide the stilt roof into several suitable hoisting blocks according to the on-site operation capacity, and calculate the hoisting points through calculation software; Step 4: Assemble and splice the top blocks on the tire frame platform, and perform pre-assembly, debugging, and deviation correction (correct processing errors, set installation margins, etc.); Step 5: After assembly, set up hanging points and fixtures on the top of the block, and install temporary support and reinforcement components to enhance its rigidity and strength during hoisting; Step 6: Install and fix the sill top hanging column at the designed sill top installation position according to the design calculation. The size, specifications and location of the hanging column are determined according to the design calculation; Step 7: After the winch is threaded with the wire rope, the coral top is connected, hoisted and installed in blocks; Step 8: Connect, correct and fix the ballast blocks with the upper hanging column, set up temporary fixed reinforcement support, temporarily install and fix the first ballast block, and remove the temporary reinforcement measures and support for hoisting; Step 9: Hoist the second coral top block; Step 10: If the center line of the ballast block deviates greatly from the center of gravity, which will affect the flatness during lifting and installation, add a temporary counterweight component to the ballast block to achieve the purpose of balance. After the installation and fixation are completed, remove the temporary counterweight component; Step 11: If the rigidity of the ballast block is insufficient and it is easy to deform and twist when lifted directly, the lifting frame should be processed; the lifting frame is processed with steel sections according to the outer dimensions of the ballast block and the division of the primary and secondary beams. The outer shape of the lifting frame is mostly a rectangular quadrilateral. A hook is set in the middle of each side of the frame and connected to the lifting point of the steel beam at the bottom of the ballast block.
[0016] like Figure 2 As shown: Install the corners first and set up temporary supports for reinforcement; like Figure 3 As shown: Install another corner and set up temporary support reinforcement; like Figure 4 As shown: install the middle corbel to connect the two sides into a whole, form a local stable space system, and remove the temporary support reinforcement; like Figure 5 As shown: install the remaining ridges in sequence to eventually form an overall stable space system; It should be noted that: When the ballast top is pre-assembled on the frame and qualified, the ballast top is applied with anti-corrosion and fire-retardant coatings, and the connection nodes are wrapped with plastic sheets. After the installation is completed, anti-corrosion and fire-retardant treatments are carried out.
[0017] After the anti-corrosion and fire-proofing treatment of the corbel top and before hoisting, some pipelines attached to the corbel top will be buried in advance and tied to the corbel top rods, and labels will be left on the joints for subsequent connection.
[0018] After the coral roof is treated with anti-corrosion and fireproofing and before hoisting, install easily damaged auxiliary equipment such as horseways, railings or lampshades.
[0019] When selecting lifting equipment such as wire ropes and shackles, they should be selected through force calculations, and the weight of various additional equipment, facilities, components, etc. should be fully considered.
[0020] The above are only embodiments provided for the present application and are not intended to limit the present application. Although the present application is described in detail with reference to the embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or make equivalent substitutions for some of the technical features therein. However, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application should be included in the protection scope of the present application.
Claims
1. A method for the block-by-block assembly and hoisting of the stage ceiling in complex venues. Features It includes the following steps: Step 1: Install no less than two winches on the high steel beam where the top of the ridge needs to be installed; Step 2: Process a temporary assembly tire frame platform below the installation position of the coral top; Step 3: Divide the coral top into several suitable pieces for hoisting, and calculate the hoisting points through calculation software; Step 4: Assemble and splice the top blocks on the tire frame platform, and perform pre-assembly, debugging, and deviation correction; Step 5: After assembly, set up hanging points and fixtures on the top of the block, and install temporary support and reinforcement components to enhance its rigidity and strength during hoisting; Step 6: Install and fix the ceiling column; Step 7: After the winch is threaded with the wire rope, the coral top is connected, hoisted and installed in blocks; Step 8: Connect, correct and fix the ballast blocks with the upper hanging column, set up temporary fixed reinforcement support, temporarily install and fix the first ballast block, and remove the temporary reinforcement measures and support for hoisting; Step 9: Hoist the second coral top block; Step 10: Lift in sequence until all the coral top blocks are lifted.
2. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: If the center line of the ballast block deviates greatly from the center of gravity, which will affect the flatness during lifting and installation, a temporary counterweight component should be added to the ballast block to achieve the purpose of balance. After the installation and fixation are completed, the temporary counterweight component can be removed.
3. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: If the hoisting rigidity of the corridor blocks is insufficient and they are easily deformed and twisted when directly hoisted, a hoisting frame is processed; the hoisting frame is processed with steel sections according to the outer dimensions of the corridor blocks and the division of the primary and secondary beams. The outer shape of the hoisting frame is mostly a rectangular quadrilateral. A hook is set in the middle of each side of the frame and connected to the lifting point of the steel beam at the bottom of the corridor blocks.
4. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: In step one, if the position of the steel beam affects the threading of the wire rope, use a fixed pulley, a movable pulley or a pulley block to change the lifting direction and reduce the lifting requirements of the winch.
5. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: In step 2, a control reference line is set on the frame platform for deviation correction control after the pre-assembly of the coral top blocks; the frame platform is welded with suitable types of steel sections, steel pipes, etc. according to the flatness of the bottom and the depth of the building structure through force calculation. After the frame platform is installed, it is measured and adjusted to ensure that its surface is flat and level, which is convenient for the assembly accuracy control of the coral top.
6. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: When the ballast top is pre-assembled on the frame and qualified, the ballast top is applied with anti-corrosion and fire-retardant coatings, and the connection nodes are wrapped with plastic sheets. After the installation is completed, anti-corrosion and fire-retardant treatments are carried out.
7. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: After the anti-corrosion and fire-proofing treatment of the corbel top and before hoisting, some pipelines attached to the corbel top will be buried in advance and tied to the corbel top rods, and labels will be left on the joints for subsequent connection.
8. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: After the coral roof is treated with anti-corrosion and fireproofing and before hoisting, install easily damaged auxiliary equipment such as horseways, railings or lampshades.
9. According to the method for hoisting the stage ceiling of a complex venue according to claim 1, Features: First install the corbel blocks at the corners and set up temporary supports and reinforcements; then install the corbel blocks at another corner and set up temporary supports and reinforcements; install the middle corbel blocks to connect the two sides into a whole to form a local stable space system, and remove the temporary supports and reinforcements; install the remaining corbel blocks in sequence to finally form an overall stable space system.